Contractor Pre-qualification
description
Transcript of Contractor Pre-qualification
-
Contractor Pre-qualification
-
What Is Contractors PQ? Screening construction contractors according to a pre determined set of criteria in order to determine their competence or ability to participate in the project bid.
-
Awarding Authorities Should Verify That the Bidder Has:Adequate financial resources, experience, personnel resources, and equipment to perform the task.
The ability to comply with the required performance and time schedule.
-
Benefits of PQAvoiding overburdened of the contractor.Elimination limited financial sources contractors.Only the qualify will stay.Protecting the contactor.Speeding devaluation & awarding process.Moving from subjectivity to objectivity.
-
Tenders PQ
Employer/ Engineer
Contractor
Place PQ Advertisement In Press, Etc. As Appropriate Stating:
Employer & Engineer
Outline Of Project (Scope, Location, Etc.)
Enquiry Issue & Tender Submission Date.
Instruction For Applying PQ.
Submission Date For Contractor.
PQ Data.
Invitation to Contractors to Pre-qualify.
Issue and Submission of PQ Documents.
Issue PQ instruction & Questionnaire requesting from each company/ Joint venture:
Organization and Structure.
Experience in Same Type of work.
Resources (Managerial, Technical, labor, etc).
Financial Statement
Request PQ Documents
Respond to Questionnaires on Company/Joint venture
Acknowledge Receipt
Analysis of PQ Data selection & Notification of List of selection
Analyze PQ data:
Company/Joint venture structure
Experience & Resources.
Financial & General stability
Acknowledge Receipt
Select Company/Joint venture for inclusion in list of Tenderers.
Confirm Intention to Submit Valid Tender
Notify all Contractors/Joint venture of the list of selected Tenderers.
-
Contractor Data Sources:Internal:Reports,documents, ..Etc.External:Questionnaire filled by the contractor. Additional sources (banks, suppliers,..Etc).Site visits to currently projects done by the contractor.
-
Typical Questionnaire Includes: Introduction: a brief description of the project.Organization: classification and companys organizational chart.Financial resources: financial capability of the contractor.Physical resources: contractor manpower, equipment, etc.Experience: contractor experience on similar projects.
-
Contractor PQ Process
Development of Criteria (Questionnaire)
Contractor Submits a Proposal
Contractor Informed to Collect Bidding Documents
Inform Rejected Contractors
Qualify Contractor
Reject Contractor
Decision
Apply Contractor Data to criteria (Systematic Model)
Gather More Data
Available Data not Sufficient to make a Decision
Available Data Sufficient to make a Decision
Check Sufficiency & Correctness of Data
Gather Contractor Data (PQ Questionnaire)
-
PQ Elements 1)LITTER TO CONTRACTORS (invitation) 2)PRE-QUALIFICATION FORM:A) Information for the contractor: i)Objective and scope of workii)General information1)Degree of eligibility2)Formation of partnership or joint venture3)Bonding capacity4)Official language5)Supply materials
-
PQ Elements Cont..6)Questionnaire submission7)Beginning and duration of construction B) PQ questionnaire:i)Identification of the contractor ii)Contractor performanceiii)Contractors equipmentiv)Construction ability v)Completion ability vi)Client relationship C)Certification and waves
-
Contractor Rating Strategies: A) dimensional weighting strategy:
-
Contractor Rating Strategies Cont.. B)two-step pre-qualification: Allow to eliminate unwanted contractors.Contractor to satisfy selected screening dimensions.If passes, use DWS with more specific criteria.
-
Paired Comparison Criteria Weighting:
-
Evaluation Matrix:
Contractor Name: ---------------------- Grade: ---------
Address: ---------------------------------
CRITERIA
Weight
5 Exce
4 V. G
3 Good
2 Fair
1 Poor
A
Experience
10
x
40
B
Equipment
3.3
x
16.5
C
Financial Resources
1.7
x
5.3
D
Reputation
3.3
x
6.6
TOTAL SCORE
68.4
-
Model Philosophy:Uses DWS based on multiple-criterion decision-making.Approach assumptions:Impact for each criterion ( 1unsatisfactory to 10 excellent).Obtain numerical value from PQ questionnaires.Addition or deletion of decision parameters have no dependency of models parameters.
-
Model Philosophy Cont..
CDF (Experience)
DF (Size of Completed Projects)
DF (Type of Completed Projects)
Example of Decision Parameters
-
Model Calculation: a. Calculate the mean impact for each DF included in each CDF. b. Calculate the DF weight to each DF from equation: Where: wij = the weight of the DFj associated with the CDFi . DFMIij = the mean impact of the DFj associated with CDFi, zero (no impact) to four (very high impact).
-
Model Calculation Cont..
c. Calculate the mean impact for the CDF from equation:
Where: CDFMIi= mean value of CDF.
mi = the number of DFs in the CDF.
d. Calculate the weight of the CDF using the equation:
_1065530322.unknown
_1065685545.unknown
-
Model Calculation Cont..
c. Find the aggregate score of the candidate contractor K
using the following equation:
Where: AWSK: aggregate weighted rating for the contractor K.
n = number of CDFs ; m = number of DFs in the CDF.
RijK: score of the DFj in the CDFi for the contractor K on scale
of 1(unsatisfactory) to 10(excellent for specific project).
_1065695819.unknown
-
Example:
Sheet1
Contactor A:
CDF(1)DFDFMIWijCDFMIiWiRijkWij*RijkAWSK1
Financial StabilityBanking Arrangement20.22230.37530.6671.9166666667
Bonding Capacity40.44441.778
Financial Statement30.33382.667
95.111
CDF(2)DFDFMIWijCDFMIiWiRijkWij*RijkAWSK2
ExperienceSuccess of Completing Projects30.37520.2541.5001.09375
Size of Completing Projects20.25030.750
No of Similar Comletdd Projects20.25061.500
Types of Completing Projects10.12550.625
84.375
CDF(3)DFDFMIWijCDFMIiWiRijkWij*RijkAWSK3
Current Work loadCurrent Work load3130.375772.625
37
AWSK (A)Total = AWSK1+AWSK2+AWSK3 =5.635
MBD00590FD7.unknown
MBD005E65B2.unknown
MBD005FFCC2.unknown
MBD00603E5E.unknown
MBD00604023.unknown
MBD00604075.unknown
MBD00603EB6.unknown
MBD006007C2.unknown
MBD0060082A.unknown
MBD005FFD27.unknown
MBD005E682C.unknown
MBD005E6897.unknown
MBD005E6612.unknown
MBD005DB1E6.unknown
MBD005DC2EC.unknown
MBD005DCCDE.unknown
MBD005DBCBF.unknown
MBD005A54DE.unknown
MBD005A5844.unknown
MBD00590FD8.unknown
MBD0013D417.unknown
MBD00163BF3.unknown
-
Example Cont..
Sheet1
Contactor B:
CDF(1)DFDFMIWijCDFMIiWiRijkWij*RijkAWSK1
Financial StabilityBanking Arrangement20.22230.37551.1111.7916666667
Bonding Capacity40.44431.333
Financial Statement30.33372.333
94.778
CDF(2)DFDFMIWijCDFMIiWiRijkWij*RijkAWSK2
ExperienceSuccess of Completing Projects30.37520.2531.1251.09375
Size of Completing Projects20.25051.250
No of Similar Comletdd Projects20.25041.000
Types of Completing Projects10.12581.000
84.375
CDF(3)DFDFMIWijCDFMIiWiRijkWij*RijkAWSK3
Current Work loadCurrent Work load3130.375662.25
36
AWSK (B)Total = AWSK1+AWSK2+AWSK3 =5.135
MBD00603E5E.unknown
MBD00604023.unknown
MBD00604075.unknown
MBD00603EB6.unknown
MBD00163BF3.unknown
MBD005DB1E6.unknown
-
Example Cont..Result: Contractor A has the highest score followed by Contractor C then contractor B.
Sheet1
Contactor C:
CDF(1)DFDFMIWijCDFMIiWiRijkWij*RijkAWSK1
Financial StabilityBanking Arrangement20.22230.37540.8892.4166666667
Bonding Capacity40.44483.556
Financial Statement30.33362.000
96.444
CDF(2)DFDFMIWijCDFMIiWiRijkWij*RijkAWSK2
ExperienceSuccess of Completing Projects30.37520.2541.5001.15625
Size of Completing Projects20.25061.500
No of Similar Comletdd Projects20.25030.750
Types of Completing Projects10.12570.875
84.625
CDF(3)DFDFMIWijCDFMIiWiRijkWij*RijkAWSK3
Current Work loadCurrent Work load3130.375883
38
AWSK (C)Total = AWSK1+AWSK2+AWSK3 =6.573
MBD00603E5E.unknown
MBD00604023.unknown
MBD00604075.unknown
MBD00603EB6.unknown
MBD00163BF3.unknown
MBD005DB1E6.unknown
-
Model Advantages:
Simple and understandable.Provides a systematic approach for all candidate evaluation.The calculated aggregate weighted score for each contractor provides a basis for comparison.