Contractor Pre-qualification

download Contractor  Pre-qualification

If you can't read please download the document

description

Contractor Pre-qualification. What Is Contractors PQ?. Screening construction contractors according to a pre determined set of criteria in order to determine their competence or ability to participate in the project bid. Awarding Authorities Should Verify That the Bidder Has:. - PowerPoint PPT Presentation

Transcript of Contractor Pre-qualification

  • Contractor Pre-qualification

  • What Is Contractors PQ? Screening construction contractors according to a pre determined set of criteria in order to determine their competence or ability to participate in the project bid.

  • Awarding Authorities Should Verify That the Bidder Has:Adequate financial resources, experience, personnel resources, and equipment to perform the task.

    The ability to comply with the required performance and time schedule.

  • Benefits of PQAvoiding overburdened of the contractor.Elimination limited financial sources contractors.Only the qualify will stay.Protecting the contactor.Speeding devaluation & awarding process.Moving from subjectivity to objectivity.

  • Tenders PQ

    Employer/ Engineer

    Contractor

    Place PQ Advertisement In Press, Etc. As Appropriate Stating:

    Employer & Engineer

    Outline Of Project (Scope, Location, Etc.)

    Enquiry Issue & Tender Submission Date.

    Instruction For Applying PQ.

    Submission Date For Contractor.

    PQ Data.

    Invitation to Contractors to Pre-qualify.

    Issue and Submission of PQ Documents.

    Issue PQ instruction & Questionnaire requesting from each company/ Joint venture:

    Organization and Structure.

    Experience in Same Type of work.

    Resources (Managerial, Technical, labor, etc).

    Financial Statement

    Request PQ Documents

    Respond to Questionnaires on Company/Joint venture

    Acknowledge Receipt

    Analysis of PQ Data selection & Notification of List of selection

    Analyze PQ data:

    Company/Joint venture structure

    Experience & Resources.

    Financial & General stability

    Acknowledge Receipt

    Select Company/Joint venture for inclusion in list of Tenderers.

    Confirm Intention to Submit Valid Tender

    Notify all Contractors/Joint venture of the list of selected Tenderers.

  • Contractor Data Sources:Internal:Reports,documents, ..Etc.External:Questionnaire filled by the contractor. Additional sources (banks, suppliers,..Etc).Site visits to currently projects done by the contractor.

  • Typical Questionnaire Includes: Introduction: a brief description of the project.Organization: classification and companys organizational chart.Financial resources: financial capability of the contractor.Physical resources: contractor manpower, equipment, etc.Experience: contractor experience on similar projects.

  • Contractor PQ Process

    Development of Criteria (Questionnaire)

    Contractor Submits a Proposal

    Contractor Informed to Collect Bidding Documents

    Inform Rejected Contractors

    Qualify Contractor

    Reject Contractor

    Decision

    Apply Contractor Data to criteria (Systematic Model)

    Gather More Data

    Available Data not Sufficient to make a Decision

    Available Data Sufficient to make a Decision

    Check Sufficiency & Correctness of Data

    Gather Contractor Data (PQ Questionnaire)

  • PQ Elements 1)LITTER TO CONTRACTORS (invitation) 2)PRE-QUALIFICATION FORM:A) Information for the contractor: i)Objective and scope of workii)General information1)Degree of eligibility2)Formation of partnership or joint venture3)Bonding capacity4)Official language5)Supply materials

  • PQ Elements Cont..6)Questionnaire submission7)Beginning and duration of construction B) PQ questionnaire:i)Identification of the contractor ii)Contractor performanceiii)Contractors equipmentiv)Construction ability v)Completion ability vi)Client relationship C)Certification and waves

  • Contractor Rating Strategies: A) dimensional weighting strategy:

  • Contractor Rating Strategies Cont.. B)two-step pre-qualification: Allow to eliminate unwanted contractors.Contractor to satisfy selected screening dimensions.If passes, use DWS with more specific criteria.

  • Paired Comparison Criteria Weighting:

  • Evaluation Matrix:

    Contractor Name: ---------------------- Grade: ---------

    Address: ---------------------------------

    CRITERIA

    Weight

    5 Exce

    4 V. G

    3 Good

    2 Fair

    1 Poor

    A

    Experience

    10

    x

    40

    B

    Equipment

    3.3

    x

    16.5

    C

    Financial Resources

    1.7

    x

    5.3

    D

    Reputation

    3.3

    x

    6.6

    TOTAL SCORE

    68.4

  • Model Philosophy:Uses DWS based on multiple-criterion decision-making.Approach assumptions:Impact for each criterion ( 1unsatisfactory to 10 excellent).Obtain numerical value from PQ questionnaires.Addition or deletion of decision parameters have no dependency of models parameters.

  • Model Philosophy Cont..

    CDF (Experience)

    DF (Size of Completed Projects)

    DF (Type of Completed Projects)

    Example of Decision Parameters

  • Model Calculation: a. Calculate the mean impact for each DF included in each CDF. b. Calculate the DF weight to each DF from equation: Where: wij = the weight of the DFj associated with the CDFi . DFMIij = the mean impact of the DFj associated with CDFi, zero (no impact) to four (very high impact).

  • Model Calculation Cont..

    c. Calculate the mean impact for the CDF from equation:

    Where: CDFMIi= mean value of CDF.

    mi = the number of DFs in the CDF.

    d. Calculate the weight of the CDF using the equation:

    _1065530322.unknown

    _1065685545.unknown

  • Model Calculation Cont..

    c. Find the aggregate score of the candidate contractor K

    using the following equation:

    Where: AWSK: aggregate weighted rating for the contractor K.

    n = number of CDFs ; m = number of DFs in the CDF.

    RijK: score of the DFj in the CDFi for the contractor K on scale

    of 1(unsatisfactory) to 10(excellent for specific project).

    _1065695819.unknown

  • Example:

    Sheet1

    Contactor A:

    CDF(1)DFDFMIWijCDFMIiWiRijkWij*RijkAWSK1

    Financial StabilityBanking Arrangement20.22230.37530.6671.9166666667

    Bonding Capacity40.44441.778

    Financial Statement30.33382.667

    95.111

    CDF(2)DFDFMIWijCDFMIiWiRijkWij*RijkAWSK2

    ExperienceSuccess of Completing Projects30.37520.2541.5001.09375

    Size of Completing Projects20.25030.750

    No of Similar Comletdd Projects20.25061.500

    Types of Completing Projects10.12550.625

    84.375

    CDF(3)DFDFMIWijCDFMIiWiRijkWij*RijkAWSK3

    Current Work loadCurrent Work load3130.375772.625

    37

    AWSK (A)Total = AWSK1+AWSK2+AWSK3 =5.635

    MBD00590FD7.unknown

    MBD005E65B2.unknown

    MBD005FFCC2.unknown

    MBD00603E5E.unknown

    MBD00604023.unknown

    MBD00604075.unknown

    MBD00603EB6.unknown

    MBD006007C2.unknown

    MBD0060082A.unknown

    MBD005FFD27.unknown

    MBD005E682C.unknown

    MBD005E6897.unknown

    MBD005E6612.unknown

    MBD005DB1E6.unknown

    MBD005DC2EC.unknown

    MBD005DCCDE.unknown

    MBD005DBCBF.unknown

    MBD005A54DE.unknown

    MBD005A5844.unknown

    MBD00590FD8.unknown

    MBD0013D417.unknown

    MBD00163BF3.unknown

  • Example Cont..

    Sheet1

    Contactor B:

    CDF(1)DFDFMIWijCDFMIiWiRijkWij*RijkAWSK1

    Financial StabilityBanking Arrangement20.22230.37551.1111.7916666667

    Bonding Capacity40.44431.333

    Financial Statement30.33372.333

    94.778

    CDF(2)DFDFMIWijCDFMIiWiRijkWij*RijkAWSK2

    ExperienceSuccess of Completing Projects30.37520.2531.1251.09375

    Size of Completing Projects20.25051.250

    No of Similar Comletdd Projects20.25041.000

    Types of Completing Projects10.12581.000

    84.375

    CDF(3)DFDFMIWijCDFMIiWiRijkWij*RijkAWSK3

    Current Work loadCurrent Work load3130.375662.25

    36

    AWSK (B)Total = AWSK1+AWSK2+AWSK3 =5.135

    MBD00603E5E.unknown

    MBD00604023.unknown

    MBD00604075.unknown

    MBD00603EB6.unknown

    MBD00163BF3.unknown

    MBD005DB1E6.unknown

  • Example Cont..Result: Contractor A has the highest score followed by Contractor C then contractor B.

    Sheet1

    Contactor C:

    CDF(1)DFDFMIWijCDFMIiWiRijkWij*RijkAWSK1

    Financial StabilityBanking Arrangement20.22230.37540.8892.4166666667

    Bonding Capacity40.44483.556

    Financial Statement30.33362.000

    96.444

    CDF(2)DFDFMIWijCDFMIiWiRijkWij*RijkAWSK2

    ExperienceSuccess of Completing Projects30.37520.2541.5001.15625

    Size of Completing Projects20.25061.500

    No of Similar Comletdd Projects20.25030.750

    Types of Completing Projects10.12570.875

    84.625

    CDF(3)DFDFMIWijCDFMIiWiRijkWij*RijkAWSK3

    Current Work loadCurrent Work load3130.375883

    38

    AWSK (C)Total = AWSK1+AWSK2+AWSK3 =6.573

    MBD00603E5E.unknown

    MBD00604023.unknown

    MBD00604075.unknown

    MBD00603EB6.unknown

    MBD00163BF3.unknown

    MBD005DB1E6.unknown

  • Model Advantages:

    Simple and understandable.Provides a systematic approach for all candidate evaluation.The calculated aggregate weighted score for each contractor provides a basis for comparison.