Contract Types and Appropriate Incentives. 1 Jo Cunningham Distinguished Member of Laboratory Staff...
-
Upload
kristian-ramsey -
Category
Documents
-
view
217 -
download
1
Transcript of Contract Types and Appropriate Incentives. 1 Jo Cunningham Distinguished Member of Laboratory Staff...
2
Jo CunninghamDistinguished Member of Laboratory Staff
Sandia National Laboratories
Session #3, 1:00pm - 1:30pm ET
NCMA’s 1st Performance-Based Service Acquisition Community of Practice - Virtual Conference
Wednesday, March 31, 2010 12:00pm - 4:00pm ET
Contract Types & Appropriate Incentives
3
Basic Decisions:
• Selecting the contract pricing arrangement is THE most important decision you will ever make!
• The Second most important decision is how to motivate the contractor.
5
Contract Types
• Two Basic Contract Types:
– Fixed Price• FFP, FFP/EPA, FP+AF, FP+I, FF Rate, Cost-
Share
– Cost Reimbursement• CNF, CPFF, CPIF, CPAW, Cost-Share• T&M, LH
6
Contractor Performance Considerations
• Firm Fixed Price: Failure is not an option
• Time & Materials: We can’t fail as long as we show up for work.
• Cost Reimbursable: We will give it our best try, but failure may be an option
7
Cost Risk & Contract Type
Cost Risk:High >>>>>>>>>>>>>>>>>>>>>>>> Low
Requirement
Definition Vague >>>>>>>>>>>>>>>>>>>>>>>>> Well Defined
Production Concept Exploratory Test/ Full scale Full
Stages Studies, & Development Demo DevelopmentProduction
Basic Research
Contract Varied CPFF CPIF, CPIF, FPIF, FFP, FPIF,
Type FPIF or FFP or FPEPA
8
Firm Fixed Price
Principal Risks: None, Contractor assumes all cost risk
Use When: The requirement is well-defined.
Contractors are experienced in meeting the fixed price.
Market conditions are stable.
Financial risks are otherwise insignificant
Typical Application: Commercial supplies and services, Generally NOT appropriate for R&D.
Contractor is required to: Provide acceptable deliverable at the time, place and price specified in the contract
Contractor Incentive: Generally realizes an additional dollar of profit for every dollar that costs are reduced
9
Fixed Price Economic Price Adjustment
Principal Risks: Unstable market prices for labor or material over life of contract.
Use When: Market prices at risk are severable and significant. Risks stem from industry-wide contingencies beyond contractor's control. Dollars at risk outweigh administrative burdens of an FPEPA.
Typical Application: Long-term contracts for commercial supplies during a period of high inflation.
Contractor is required to: Provide acceptable deliverable at the time and place specified in the contract at the adjusted price.
Contractor Incentive: Generally realizes an additional dollar of profit for every dollar that costs are reduced
10
Fixed Price Incentive Fee
Principal Risks: Moderately uncertain contract labor or material requirements
Use When: Ceiling price can be established that covers most probable risks inherent in nature of work. Proposed profit sharing formula would motivate contractor to control costs to & meet other objectives
Typical Application: Production of a major system based on a prototype.
Contractor is required to: Provide acceptable deliverable at time & place specified in contract, at or below ceiling price.
Contractor Incentive: Realizes a higher profit by completing work below ceiling price and/or by meeting objective performance targets
11
Fixed Price Award Fee
Principal Risks: Risk that the user will not be fully satisfied because of judgmental acceptance criteria.
Use When: Judgmental standards can be fairly applied by Award-fee panel. The potential fee is large enough to both: (1) Provide meaningful incentive; (2) Justify related administrative burdens.
Typical Application: Performance-based service contracts.
Contractor is required to: Perform at time, place, and price fixed in contract.
Contractor Incentive: Generally realizes an additional dollar of profit for every dollar that costs are reduced; earns an additional fee for satisfying performance standards
12
Fixed Price Prospective Redetermination
Principal Risks: Costs of performance after the first year because they cannot be estimated with confidence.
Use When: Buyer needs a firm commitment from contractor to deliver supplies /services during subsequent years. Dollars at risk outweigh administrative burdens of FPRP.
Typical Application: Long-term production of spare parts for a
major system.
Contractor is required to: Provide acceptable deliverables at time & place specified in contract at price established for each period.
Contractor Incentive: For the period of performance, realizes an additional dollar of profit for every dollar that costs are reduced.
13
Cost Plus Incentive Fee
Principal Risks: Highly uncertain & speculative labor hours, labor mix, material requirements (and other) necessary to perform contract. Buyer assumes risks; benefiting if actual cost is lower than expected cost; losing if work can’t be completed within expected cost of performance.
Use When: Objective relationship can be established between fee & such measures of performance as actual costs, delivery dates, performance benchmarks, etc.
Typical Application: Research and development of prototype for major system.
Contractor is required to: Make good faith effort to meet Buyer's needs within estimated cost in the Schedule.
Contractor Incentive: Realizes a higher fee by completing work at lower cost and/or by meeting other objective performance targets
14
Cost Plus Award Fee
Principal Risks: Highly uncertain & speculative labor hours, labor mix, material requirements (and other things) necessary to perform contract. Buyer assumes risks inherent in contract; benefiting if actual cost is lower than expected cost; losing if work cannot be completed within expected cost of performance.
Use When: Objective incentive targets are not feasible for critical aspects of performance. Judgmental standards can be fairly applied. Potential fee would provide a meaningful incentive.
Typical Application: Large scale research study.
Contractor is required to: Make good faith effort to meet Buyer's needs within estimated cost in the Schedule.
Contractor Incentive: Realizes a higher fee by meeting judgmental performance standards.
15
Cost Plus Fixed Fee
Principal Risks: Highly uncertain & speculative labor hours, labor mix, material requirements (and other things) necessary to perform contract. Buyer assumes risks inherent in contract; benefiting if actual cost is lower than expected cost; losing if work cannot be completed within expected cost of performance.
Use When: Relating fee to performance (e.g., to actual costs) would be unworkable or of marginal utility.
Typical Application: Research studies.
Contractor is required to: Make good faith effort to meet Buyer's needs within estimated cost in the Schedule.
Contractor Incentive: Realizes a higher rate of return (i.e., fee divided by total cost) as total cost decreases.
16
Cost Sharing
Principal Risks: Highly uncertain & speculative labor hours, labor mix, material requirements (and other things) necessary to perform contract. Buyer assumes risks inherent in contract; benefiting if actual cost is lower than expected cost; losing if work cannot be completed within expected cost of performance.
Use When: The contractor expects substantial compensating benefits for absorbing part of the costs and/or foregoing fee.
Typical Application: Joint research where Contractor expects to derive long term benefits to his company.
Contractor is required to: Make good faith effort to meet Buyer's needs within estimated cost in the Schedule.
Contractor Incentive: Shares in the cost of providing a deliverable of mutual benefit..
17
Cost No Fee
Principal Risks: Highly uncertain & speculative labor hours, labor mix, material requirements (and other things) necessary to perform contract. Buyer assumes risks inherent in contract; benefiting if actual cost is lower than expected cost; losing if work cannot be completed within expected cost of performance.
Use When: The supplier is a not-for-profit entity.
Typical Application: Joint research with an educational institutions or other not-for-profit entities.
Contractor is required to: Make good faith effort to meet Buyer's needs within estimated cost in the Schedule.
Contractor Incentive: Providing a deliverable with benefits to both parties; Contractor expects to derive long term benefits to his firm; Enhanced reputation.
18
Time and Materials
Principal Risks: Highly uncertain & speculative labor hours, labor mix, material requirements (and other things) necessary to perform contract. Buyer assumes risks inherent in contract; benefiting if actual cost is lower than expected cost; losing if work cannot be completed within expected cost of performance.
Use When: No other type of contract is suitable (e.g., labor & materials can’t be reliably estimated due to inherent uncertainties, and contractor does not have accounting system to support a job cost accounting system).
Typical Application: Emergency repairs to heating plants and aircraft engines; hazardous waste removal; Contractor support for field exercises.
Contractor is required to: Make good faith effort to meet Buyer's needs within ceiling price.
Contractor Incentive: None, other than enhanced reputation.
19
Firm Fixed Rate
Principal Risks: Highly uncertain & speculative labor hours, labor mix, material requirements (and other things) necessary to perform contract. Buyer assumes risks inherent in contract; benefiting if actual cost is lower than expected cost; losing if work cannot be completed within expected cost of performance. Limit risk by ceiling price of $100,000 or less.
Use When: No other type of contract is suitable (e.g., because costs are too low to justify an audit of the contractor's indirect expenses).
Typical Application: Emergency repairs to facilities and equipment; Contractor support for small efforts <$100,000.
Contractor is required to: Make good faith effort to meet Buyer's needs within ceiling price.
Contractor Incentive: None, other than enhanced reputation.
20
Summary
• Initial steps to remember:• Discuss requirements with the customer & compare to the SOW,
revising as necessary• Review the pricing types, and consider the pros & cons of each.
• Pitfalls:• Avoid cost-type and T&M/LH if contractor has unsophisticated
accounting system.• Avoid setting up Contractor for failure (e.g. using FFP when not
appropriate)• Award / Incentive Fees = High Admin costs
• Remember: Choosing Wisely Reduces Risks and may save you potentially significant costs!