Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work...
Transcript of Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work...
![Page 1: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/1.jpg)
Contract Schedule of Values (SOV)Agency/Higher-Ed
1
![Page 2: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/2.jpg)
Purpose & Procedure
2
‣ Provides for the submission, review, and approval of the Contractor’s Schedule of Values.
‣ Submitted and approved SOV in this business process becomes the basis for all future Contractor Pay Requests.
‣ WorkflowCreated by: Contractor Submitted to: Associate (A/E) Approval Sent to: Contractor Update (if necessary) Sent to: PC Review Sent to: PM Approval
![Page 3: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/3.jpg)
Roles & Responsibilities
3
‣ Contractor‣ Creates the Schedule of Values (SOV)‣ Identifies work items that are provided by Subcontractors and Material
Suppliers‣ Negotiates details of the SOV with the Associate (A/E)
‣ Associate (A/E)‣ Reviews the SOV submission
‣ Negotiates details of the SOV with the Contractor
‣ Recommends Approval
‣ Project Manager (PM)
‣ Reviews the SOV record
‣ Requests clarifications and updates
‣ Approves the SOV record
‣ Project Coordinator
‣ Reviews the SOV record
‣ Determines that EDGE participation is accurate
![Page 4: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/4.jpg)
Getting Started
4
‣ Prior to submitting any request for payment, the Contractor must prepare and have approved a detailed Schedule of Values (SOV) that clearly and accurately reflects the costs of labor and materials including profit and overhead for each item of work.
![Page 5: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/5.jpg)
Create New Contract SOV Record
‣ In OAKS CI navigate to:‣ Logs -> Contract
Schedule of Values
‣ Click Create
5
![Page 6: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/6.jpg)
Enter Information into the Record‣ Complete the General tab
‣ Everything with a Red * is required
6
![Page 7: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/7.jpg)
Spreadsheet Method
7
‣ Utilizes an externally produced excel spreadsheet that is imported into the SOV record
‣ Recommended for larger projects with numerous work requirements and SOV line items
![Page 8: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/8.jpg)
Navigate to Spreadsheet
8
‣ Step 1: Open Excel spreadsheet from website: http://ofcc.ohio.gov‣ Click- Documents Tab
‣ Click- Standard Forms
‣ Click- Procurement Tab
‣ Click- Oaks CI Contract SOV Import Template- Contractor (Cloud)(Excel)
![Page 9: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/9.jpg)
Enter Contract SOV Line Items‣ Step 2:
‣ Include ONLY EDGE Subcontractors/Suppliers
‣ Note: If the Subcontractor/Supplier is EDGE, type (EDGE) next to your short description
‣ Make sure to spell the name of the Subcontractor/Supplier EXACTLY the way you spelled it on the Subcontractor/Supplier Declaration
9
![Page 10: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/10.jpg)
Adding Additional Lines‣ Step 3: If necessary, add additional lines to the SOV spreadsheet
‣ Left click on the number of the line to highlight it
‣ Right click and choose copy
10
![Page 11: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/11.jpg)
Adding Additional Lines‣ Step 3 (cont.):
‣ Right click on the line you want to be below the line you are inserting
‣ Choose insert copied cells
‣ Your line will show up above the selected line. You can edit the text in the line as necessary
11
New line
will appear
above here
![Page 12: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/12.jpg)
Save the Spreadsheet
‣ Step 4: ‣ Name and Save the Spreadsheet- Very Important!
12
![Page 13: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/13.jpg)
Enter Contract SOV Line Items
13
‣ Step 5: ‣ Make sure you have reviewed your spreadsheet with the A/E
and PM
‣ Click “Prepare Interface File”
This box will appear indicating the
file preparation is complete.
![Page 14: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/14.jpg)
Import Spreadsheet‣ Open the Contract SOV Record
‣ Click on the Contract SOV Details Tab
‣ Click Import
14
![Page 15: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/15.jpg)
Import Spreadsheet‣ Click the 3 dots next to the “Select File” field
‣ Navigate to the “Comma Separated Values (CSV File)” of your spreadsheet and select it
‣ Click Open
15
![Page 16: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/16.jpg)
Import Spreadsheet‣ File name should appear in “Select File” field
‣ Click Next
16
![Page 17: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/17.jpg)
Import Spreadsheet‣ Add any additional attachments if necessary
‣ Click Upload
17
![Page 18: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/18.jpg)
Important Note: Error Message
‣ If you receive the following message, please say Yes and email the downloaded excel sheet to the OAKS CI Support Desk: [email protected]
‣ We will be able to diagnose your error and assist you with your import
18
![Page 19: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/19.jpg)
Review Imported Line Items‣ When all SOV Line Item entries are imported:
‣ Review the SOV information summary in the Contracts SOV Detail Pane
‣ Verify that the total value in the Contract Amount Detail Block and the total amount in the WBS Detail pane are equal and the Difference($) value is zero (0.00)
19
![Page 20: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/20.jpg)
Complete Contract SOV
20
‣ Verify Workflow Action
‣ The (To) field will auto populate once the Workflow Action is selected
‣ Click Send
![Page 21: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/21.jpg)
Associate Approval Step
21
‣ Associate‣ Reviews the record and performs one of the
following Workflow Actions:‣ Recommend Approval: Approves the SOV
submittal from the Contractor
‣ Return for Clarification: Returns the SOV to the Contractor for revisions or corrections
![Page 22: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/22.jpg)
If Returned for Update:
22
‣ Contractor: Provides clarifications or revisions to the SOV record and resubmits it for another review‣ Review the Contract SOV information
‣ Make corrections or Add Attachments as necessary
‣ Individual Line Items cannot be modified
‣ First copy the line item (along with attachments)
‣ Make changes to the copied line item
‣ Click Remove to delete the original line item
![Page 23: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/23.jpg)
Resubmit the Contracts SOV Record
23
‣ Verify Workflow Action
‣ The record will go back to the Associate (A/E) for review
![Page 24: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/24.jpg)
PC Review Step
24
‣ Project Coordinator‣ Reviews the SOV and annotates receipt of the
record‣ Performs one of the following Workflow Actions:
‣ Recommend Approval: Forwards the SOV to the PM for Approval
‣ Return for Clarification: Returns the SOV to the Contractor for revisions or corrections
![Page 25: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/25.jpg)
PM Approval Step
25
‣ Project Manager‣ Performs one of the following Workflow
Actions:‣ Approve: Approves the record
‣ Return for Clarification: Returns the record for clarification, the submittal review and approval process is repeated
![Page 26: Contract Schedule of Values (SOV) · ‣Creates the Schedule of Values (SOV) ‣Identifies work items that are provided by Subcontractors and Material Suppliers ‣Negotiates details](https://reader036.fdocuments.net/reader036/viewer/2022071016/5fcf074803ffca0e1259ff99/html5/thumbnails/26.jpg)
SOV Approval Completion
26
‣ Upon SOV approval, the Contract Record will be opened by the Project Coordinator and marked “Final_Approved”
‣ Once the SOV is “Approved” pay requests can be created.