Contract Procurement Management Report

download Contract Procurement Management Report

of 60

Transcript of Contract Procurement Management Report

  • 7/29/2019 Contract Procurement Management Report

    1/60

    CONTRACT &

    PROCUREMENT

    MANAGEMENT AT NTPC

    SUBMITTED BY:

    ****************

    INDUSTRY GUIDE FACULTY GUIDE

    **************** ****************

  • 7/29/2019 Contract Procurement Management Report

    2/60

    ii

    TABLE OF CONTENTS

    Chapter No. Subject Page No.

    Ch.-1.0 Executive Summary.

    Ch.-2.0 Research Methodology

    1.1 Primary Objective(s).

    1.2 Hypothesis

    1.3 Research Design

    1.4 Sample Design..

    1.5 Scope of the Study.

    1.6 Limitations.

    Ch.-3.0 Critical Review of Literature..

    Ch.-4.0 Company Profile .

    4.1 Industry Profile..

    4.2 Swot Analysis.

    Ch.-5.0 Data..

    5.1 Collection

    5.2 Primary Data

    5.3 Secondary Data...

    Ch.-6.0 Findings & Analysis.

    Ch.-7.0 Recommendations

    Ch.-8.0 Bibliography.

    Ch.-9.0 Annexure..

    9.1 Tables.

    9.2 Graphs

    Ch-10.0 Case Study .......

    Ch-11.0 Synopsis of the project..

  • 7/29/2019 Contract Procurement Management Report

    3/60

    iii

    EXECUTIVE SUMMARY

    The report entitled BIDDING AND FINANCIAL ANALYASIS OF N.T.P.C. is about the

    purchase practices followed at NTPC. These practices are followed during all procurement by

    NTPC. The purchase procedure starts at Indenting by the department that requires the material and

    goes to the cost department and finance department for required approval. In between various

    activities like Liquidated Damages calculation, Spare Parts procurement terms, Guarantee in

    Liability Defect period etc are undertaken. Once all the terms and conditions are formulated and

    approved, the tender document preparation starts. The tender documents are issued to the

    prospective bidder for a cost that starts from Rs 200 to Rs 3000. The content of the tender

    document is prepared in such a manner that the prospective bidder comes to know about all the

    important details about the contract. The issuance of tender document is followed by the receipt ofBids from various vendors in the specified format. Once all the bids are received, they are opened

    in presence of some nominated officials from Finance, Contracts and Materials department. The

    representatives from the bidders may also be present. Then a comparative statement of the quoted

    bids is prepared and the contract is awarded to the lowest quoting bidder.

    During the document preparation phase, payments terms are also decided and documented in the

    General Condition of Contract, which is issued to the bidder with the tender documents. Apart

    from payments, there are various other issues like Arbitration, which are dealt in the tenderdocuments. Liquidated Damages is one of the very important clauses. Liquidated damage is a

    payment to be made by the contractor in case he fails to complete the project in the stipulated

    time. In case of equipment, it is related to the performance of the equipment. The purchase is

    followed by the evaluation, which is done for two things, the vendors performance and the

    purchase performance. The Vendor evaluation comes in handy for placing future orders where as

    the Purchase Performance evaluation provides detailed insight into the procedures being followed

    to procure the required material.

  • 7/29/2019 Contract Procurement Management Report

    4/60

    1

    RESEARCH METHODOLOGY

    Primary Objective :- The objective is to study the BIDDING AND FINANCIAL ANALYASIS

    OF N.T.P.C. procedures followed at NTPC .

    The observations were carefully analyzed and some constructive facts and figures were revealed.

    On the basis of those observations some recommendations and suggestions for NTPC have been

    drafted.

    The research methodology comprised of secondary data collected from various NTPC records

    and through NTPC website and India Infoline.com.

    Sample Design:-for the research activity to turnout into a success, a careful selection of various

    Project was made. All possible effort was made to choose the unbiased data to get the fruitful

    result.

    Scope of the Study :- This effort is to understand the procurement practices followed at NTPC and

    understand what they keep in mind before awarding a particular bid contract to the specific

    bidder. It will also recommend the points to NTPC to improve upon to get the maximum chunk in

    the power industry.

    Limitations :-

    Time factor.

  • 7/29/2019 Contract Procurement Management Report

    5/60

    2

    Industry Profile

    The electricity services in India were generally provided by the State Electricity Boards (SEBs),

    as it was believed that being under the control of the State governments, they could protect the

    consumer interests against exploitation. Over a period of time, it however, came to be realized that

    because of their monolithic nature, the State Electricity Boards suffered from operational

    inefficiencies on account of which they had incurred heavy losses. The services rendered by them

    were also of poor quality. These factors forced the governments to think in terms of

    commercialization of the services so that the additional investments necessary for infrastructure

    development become available through private sector involvement and the services rendered

    become globally competitive.

    Central Government issued a policy resolution dated 22-10-1991 on private sector participation in

    power sector. It was followed by necessary changes in the legal framework. Despite the policy of

    liberalization, the entry of new players continued to be regulated by the government who

    remained the final arbiter in all matters, including tariff fixation. It became necessary, therefore, to

    provide a level playing field to new players and to provide for competition. It was decided to

    encourage private sector participation in the generation, transmission and distribution since future

    expansion could not be achieved through public resources alone. Thus, the phenomenon of privatesector involvement in power sector is a relatively modern reaction to the revealed concerns and

    issues associated with complete reliance on the public sector provision of infrastructure. It should

    also be decided to set up independent Central and State Regulatory Commissions.

    Promotion of competition, efficiency and economy in electricity industry can be conveniently

    achieved through the process of competitive bidding. The Central Government issued detailed

    guidelines for competitive bidding of power projects in January 1995 whereby the competitiveprocurement of power sector projects was made mandatory. These guidelines laid emphasis on

    project identification, justification and development before taking up competitive bidding.

    Growth of economy calls for a watching rate of growth in infrastructure facilities. Power sector is

    one of the major aspects of this infrastructure building. Some prominent people like the Ex

    Chairman of GE Jack Welch have gone to the extent of saying, you dont have a chance to stand

    in the 21st

    century without lots of powerWithout this you miss the next revolution.

  • 7/29/2019 Contract Procurement Management Report

    6/60

    3

    Moreover, the growth rate of demand for power in developing countries is generally higher than

    that of GDP. In India, the elasticity ratio was 3.06 in 1st plan, and peaked at 5.11 during 3rd plan

    and came down to 1.65 in 80s. For 90s a ratio of around 1.5 was projected. Hence, in order to

    support a growth of GDP of around 7% the rate of growth of power supply of 10%is required.

    If we look at current scenario, electricity consumption in India has more than doubled in the last

    decade, outpacing the economic growth. If we analyze the various statistics of Indian power

    sector, we will find that the generating capacity has gone up tremendously from a meager

    1712MW in 1950 to a whooping 112000MW today.

    GROWTH OVER YEARS:

    INSTALLED CAPACITY AROUND THE END OF PERIOD:

    13000

    28000

    66000

    112000

    212000

    2012200019901980197019601950

    460017000

    50000

    100000

    150000

    200000

    250000

    1 2 3 4 5 6 7 8 9

    YEARS

    CAPACITIES

    At the same as a result of growing installed capacity, the power produced has also gone up. In

    1950, the total power produced by Indian power sector was a meager 50BU and that is now587.3BU.

    Now a days when world is transforming into a global village and economies are opening up, a

    substantial and reliable infrastructure is a must for any economy to develop. Electricity is one of

    the most vital parts of any economic structure. The govt. of India had realized it way back in 60s

    that to develop the economy and be economically independent, one must be independent in ones

    power generation. And hence the Indian govt. emphasized the need of independence in power

    generation and in all subsequent five-year plans the allocated budget for power sector

    development was increased. But despite all these efforts by our govt., there is an acute power

    shortage in the country. Despite all efforts, a no.of states particularly the northern and western

    region are faced with severe power shortage. The projected power consumption for next 10 years

    is not very comforting either. Capacity expansion in power sector is outpaced by economic

  • 7/29/2019 Contract Procurement Management Report

    7/60

    4

    development and hence widening the gap between the demand and supply of electricity. We can

    see the projected figures for the coming years in the diagram below:

    POWER DEVELOPMENT- 16TH

    EPS PROJECTIONS:

    PEAK REQUIRMENT IN BILLION UNITS:

    78037 85132 115705

    1574107

    507 529 719 9760

    200000

    400000

    600000

    800000

    1000000

    1200000

    1400000

    1600000

    1800000

    MAR'01 MAR'02 MAR'07 MAR'12

    YEARS

    PEAK

    AND

    ENERGYREQUIRM

    EN

    The growth rate of power sector is shown in the diagram below:

    3.4

    5.1 5.2

    0

    1

    2

    3

    4

    5

    6

    02-'03 03-'04 04-'05

    years

    billionunits

    Generation during the years has been as follows:

    513533 552

    587

    202 213226 240

    0

    100

    200

    300

    400

    500

    600

    700

    01-'02 02-'03 03-'04 04-'05

    years

    billionunits

    Series1

    Series2

  • 7/29/2019 Contract Procurement Management Report

    8/60

    5

    Power availability has been as follows:

    While energy shortage during the same period has been as follows:

    7.2

    7.25

    7.3

    7.35

    7.4

    7.45

    7.5

    7.55

    01-'02 04-'05

    years

    Shortage(%)

    And peak deficit during the same period has been as follows:

    11.2

    11.4

    11.6

    11.8

    12

    12.2

    12.4

    12.6

    12.8

    01-'02 04-'05

    years

    deficit(%

    450000

    460000

    470000

    480000

    490000500000

    510000

    520000

    530000

    540000

    550000

    01-'02 04-'05

    years

    availability(MU)

  • 7/29/2019 Contract Procurement Management Report

    9/60

    6

    There has been an improvement in last three years with 13% increased power availability.

    However, we could reduce energy shortage by a meager 0.2% while peak deficit by a meager

    0.9%. We could have generated 18b units more had we not suffered gas and coal shortages.

    However, we are now set to achieve 10 th plan target of about 41000 MW as the projects worth

    10959 MW have already been commissioned and project worth 24152 MW are under execution.

    In accordance with electricity policy a substantial portion of under utilized capacity plants are

    targeted to be brought under the grid.

    PROFILE OF NATIONAL THERMAL POWER CORPORATION

    LTD. (NTPC)

    National Thermal Power Corporation Ltd. (NTPC) a global giant in the power sector was set up

    on 7th November 1975, with an objective to accelerate the electricity generation by planning,

    promoting and organizing integrated development of thermal power in India.

    Today; NTPC is the largest power generating company in India and contributes one-fourth of the

    thermal energy generated in the country. It has 463 rank in the World Top Class 2000 Companies

    which is improve from the last year rank i.e. 486.Over all these years NTPC has been an

    organization which has delivered expected performance in all the spheres of its business activities

    and meeting all the challenges for growth and operation through adoption of excellent

    management system and practices.

    The success of NTPC is the result of a modest but systematic beginning.

    NTPC known as the NAVRATANS of PSUS have central govt. and the finding agencies as one

    of their major stakeholder. Railways are the major supplier of NTPC.

    If anything which is manufactured is to be sold out. In the same manner NTPC also has some of

    its buyers. The main buyers who purchase electricity from NTPC are the state electricity board

    (SEBS) and the state govt.

    It will be much more clearly from the following diagram below:

  • 7/29/2019 Contract Procurement Management Report

    10/60

    7

    NTPC- BACKGROUND

    NTPCa global giant in power sector

    Source:www.ntpc.co.in

    National Thermal Power Corporation Limited (NTPC) is the largest thermal power generating

    company of India. A public sector company incorporated in the year 1975 to accelerate power

    development in the country as a wholly owned company of the Government of India. At present,

    Government of India holds 89.5% of the total equity shares of the company and the balance

    10.5% is held by FIIs, Domestic Banks, Public and others.

    Based on 1998 data, carried out by Data monitor UK, NTPC is the 6th largest in terms of thermal

    power generation and the second most efficient in terms of capacity utilization amongst the

    thermal utilities in the world.

    NTPC's core business is engineering, construction and operation of power generating plants and

    also providing consultancy to power utilities in India and abroad. As on date the installed capacity

    of NTPC is 23,749 MW through its 13 coal based (19,480 MW), 7 gas based (3,955 MW) and 3

    Joint Venture Projects (314 MW). NTPC acquired 50% equity of the SAIL Power Supply

  • 7/29/2019 Contract Procurement Management Report

    11/60

    8

    Corporation Ltd. (SPSCL). This JV Company operates the captive power plants of Durgapur (120

    MW), Rourkela (120 MW) and Bhilai (74 MW). NTPC is also managing Badarpur thermal power

    station (705 MW) of Government of India.

    Source- www.indiainfoline.com

    NTPCs share on 31 Mar 2004 in the total installed capacity of the country was 19.4% and it

    contributed 27.1% of the total power generation of the country during 2003-04.

    NTPC has set new benchmarks for the power industry both in the area of power plant construction

    and operations. It is providing power at the cheapest average tariff in the country. With its

    experience and expertise in the power sector, NTPC is extending consultancy services to various

    organizations in the power business. NTPC has entered into a joint venture with Alstom, Germany

    for renovation and modernizations of power plants in India.

    NTPC has taken proactive steps for ash utilization. In 1991, it set up Ash Utilization Division to

    manage efficient use of the ash produced at its coal stations. This quality of ash produced is ideal

    for use in cement, concrete, cellular concrete, and building material.

  • 7/29/2019 Contract Procurement Management Report

    12/60

    9

    NTPCs share on 31 Mar 2004 in the total installed capacity of the country was 19.4% and

    it contributed 27.1% of the total power generation of the country during 2003-04.

    NTPC

    OIL

    SUPPLY

    CENTRAL

    GOVT

    COALSUPPLY

    RAILWAYS

    EQUIPMEN

    T

    SUPPLY

    FUNDING

    AGENCIES

    STATE

    GOVT

    SEBS

    S

    UP

    P

    L

    I

    E

    R

    S

    B

    U

    Y

    E

    R

    S

    STAKE HOLDERS

  • 7/29/2019 Contract Procurement Management Report

    13/60

    10

    CORPORATE PLAN

    The company has formulated a long term Corporate Plan for 15 years upto 2017. The

    Corporate Plan seeks to integrate the Companys vision, mission and strategies for growth

    with the national plans and to provide the company the cutting edge in the emerging

    competitive environment. NTPC is targeting to become a 46 000 MW Plus company by 2012.

    (A) Projects under construction Total Capacity - 10990 MW

    Project(State)

    Capacity(MW)

    Fuel Commission Schedule

    Vindhayachal - III

    (Madhya Pradesh)

    1000

    (2x500)

    Coal Unit IX Feb 2007

    Unit X Aug 2007

    Unchahar III(Uttar Pradesh)

    210(1x210)

    Coal Unit I Sep 2006

    Kahalgaon Phase IIStage I (Bihar)

    1000(2x500)

    Coal Unit V Nov 2006Unit VI May 2007

    Kahalgaon Phase IIStage II (Bihar)

    500(1x500)

    Coal Unit VII Mar 2007

    Sipat - I(Chhattisgarh)

    1980(3x660)

    Coal Unit I Apr 2008Unit II Feb 2009Unit III Dec 2009

    Sipat - II(Chhattisgarh)

    1000(2x500)

    Coal Unit I Jun 2007Unit II Dec 2007

    Koldam(Himachal Pradesh)

    800(2x400)

    Hydro Unit I Nov 2008Unit II Jan 2008Unit III Mar 2009Unit IV Apr 2009

    Barh(Bihar)

    1980(3x660)

    Coal Unit I Mar 2009Unit II Jan 2110Unit III Nov 2010

    Bhilai Exp. PowerProject,

    JV with SAIL

    (Chhattisgarh)

    500(2x250)

    Coal Unit I July 2007Unit II Oct 2007

    Total 8970MW

    (B) New projects being pursued for capacity addition for Eleventh Plan and Beyond

    In addition to the above, a host of new power projects as given below are being pursued forfurther capacity addition in the 11th plan and beyond:

    S. No. Project / State Capacity (MW)

    1. Kawas - II, Gujarat 1,300

    2. Jhanor Gandhar - II, Gujarat 1,300

    3. Nabinagar - JV with Railways, Bihar 1,000

    http://www.ntpc.co.in/powerplants/ntpc_pw_vindhyachal.shtmlhttp://www.ntpc.co.in/powerplants/ntpc_pw_vindhyachal.shtmlhttp://www.ntpc.co.in/powerplants/ntpc_pw_vindhyachal.shtmlhttp://www.ntpc.co.in/powerplants/ntpc_pw_kahalgaon.shtmlhttp://www.ntpc.co.in/powerplants/ntpc_pw_kahalgaon.shtmlhttp://www.ntpc.co.in/powerplants/ntpc_pw_kahalgaon.shtmlhttp://www.ntpc.co.in/powerplants/ntpc_pw_kahalgaon.shtmlhttp://www.ntpc.co.in/powerplants/ntpc_pw_kahalgaon.shtmlhttp://www.ntpc.co.in/powerplants/ntpc_pw_kahalgaon.shtmlhttp://www.ntpc.co.in/powerplants/ntpc_pw_vindhyachal.shtmlhttp://www.ntpc.co.in/powerplants/ntpc_pw_vindhyachal.shtmlhttp://www.ntpc.co.in/powerplants/ntpc_pw_vindhyachal.shtmlhttp://www.ntpc.co.in/powerplants/ntpc_pw_vindhyachal.shtmlhttp://www.ntpc.co.in/powerplants/ntpc_pw_vindhyachal.shtmlhttp://www.ntpc.co.in/powerplants/ntpc_pw_vindhyachal.shtmlhttp://www.ntpc.co.in/powerplants/ntpc_pw_kahalgaon.shtmlhttp://www.ntpc.co.in/powerplants/ntpc_pw_kahalgaon.shtmlhttp://www.ntpc.co.in/powerplants/ntpc_pw_kahalgaon.shtmlhttp://www.ntpc.co.in/powerplants/ntpc_pw_kahalgaon.shtmlhttp://www.ntpc.co.in/powerplants/ntpc_pw_vindhyachal.shtmlhttp://www.ntpc.co.in/powerplants/ntpc_pw_vindhyachal.shtml
  • 7/29/2019 Contract Procurement Management Report

    14/60

    11

    4. Loharinag Pala, HEP Uttaranchal 600

    5. Tapovan Vishnugad, HEP Uttaranchal 520

    6. Lata Tapovan, HEP Uttaranchal * 171

    7. North Karanpura, Jharkhand 1,980

    8. Rajiv Gandhi CCPP-II, Kerala 1,950

    9. Ennore (JV with TNEB ), Tamil Nadu 1,000

    10. Farakka III, West Bengal 500

    11. Lara, Integrated Power ChhattisgarhGeneration project,

    4,000

    12. Darlipalli, Integrated PowerOrissaGeneration Project,

    3,200

    13. Rammam III HEP, West Bengal * 120

    14. Hutong II HEP, Arunachal Pradesh 1,250

    15. Kalai II HEP, Arunachal Pradesh 1,200

    *(To be implemented by NTPC Hydro Ltd, a wholly owned subsidiary of NTPC Ltd.)

    AN OVERVIEW

    Projects No. of ProjectsCommissioned

    Capacity(MW)

    NTPC OWNED

    COAL 14 20, 685

    GAS/LIQ. FUEL 07 3,955

    TOTAL 21 24,640

    OWNED BY JVCs

    Coal 3 314*

    GRAND TOTAL 24 24,954

    * Captive Power Plant under JV with SAIL

    @Additional capacity under implementation

    Vindhyachal Stage III 1000 MW Unchahar Stage III 210 MW Kahalgaon Stage II

    - Phase I 1000 MW- Phase II 500 MW

    Korba Stage III 500 MW

  • 7/29/2019 Contract Procurement Management Report

    15/60

    12

    VISION OF NTPC:

    "To be one of the world's largest and best power utilities, powering India's growth".

    To realize this vision, NTPC has drawn up a detailed Corporate Plan for the period 1997-2012

    which represents the company's collective optimism and enthusiasm, inspired by a glorious past, a

    vibrant present and a brilliant future. The Plan has been prepared in-house in consultation the

    committed, competent and confident members of the NTPC family. The road map that has been

    charted out was after a thorough scan of the strengths and weaknesses within the organization as

    well as opportunities and threats in the environment.

    Considering multidimensional opportunities in the energy sector, NTPC will adopt a multi-pronged growth strategy for capacity addition through Greenfield sites, expansion of existing

    stations, takeovers and joint ventures.

    The capacity addition plans that we have drawn up for the fifteen-year period using all the above

    strategies to enable the corporation to become a 40,000 MW company by 2012 A.D.

    In addition to the above, NTPC also has plans to venture into the following areas:

    Renovation & Modernization of old power stations through a separate joint venture

    company;

    Investment in LNG terminal;

    Investment in coal mining and washeries;

    Setting up of power plants abroad;

    Joint ventures for ash-based industries;

    Setting up of small pilot plants using renewable energy sources;

    Setting up of hydel power plants to facilitate techno-economic operation of thermal-hydro

    mix of NTPC stations;

    Setting up of associated extra high voltage transmission lines / inter-regional EHV transmission

    lines so as to ensure evacuation of power from NTPC stations.

  • 7/29/2019 Contract Procurement Management Report

    16/60

    13

    NTPC CORE VALUES: -

    Known as one of the NAVRATANS of the PSUS NTPC has its following core values. They are:

    CUSTOMER FOCUS

    ORGANISATIONAL PRIDE

    MUTUAL RESPECT & TRUST

    INITIATIVE & SPEED

    TOTAL QUALITY

    Every firm, be it a manufacturing concern or a trading concern has to buy something either to

    trade it as it is or add some value to it. In both the cases the firm is buying and selling the goods

    or services generated. The value generated between two points in the value chain is the profit

    generated by that particular chain partner. These values. Be in terms of place, time, quantity of

    form etc. in the case of NTPC. NTPC buys coal, diesel, and other capital goods and converts it

    into electricity. Since the raw material is changing form during the value addition process henceNTPC is a manufacturing firm. For every manufacturing concern, the raw material is the cost

    center after the initial expenditure relating to the capital goods. It is also the most important factoraffecting the quality of the product and in case of NTPC the performance. A low-grade coal may

    not only reduce the efficiency of the plant but may also make it malfunction or might even lead to

    a sudden breakdown. Hence the plant but may make it malfunction or might even lead to a

    sudden breakdown. Hence the right quality of fuel is not only desired but is required.

    Similarly the plants and equipment required to generate the electricity is also to be procured andhence one more purchasing comes into picture. Once the plant is erected and commissioned,

    during its normal operations the plant may require some spare parts as well as some replacement

    and maintenance parts. Hence for that also the firm has to maintain a constant supply. So for all

    this purchase system is another big question. To get an appropriate purchase system structure we

    must identify the actual requirement NTPC has some plants as old as 25 years old, which are

    using a very aged or aging technology; on the other hand some of its required for these two plants

    will obviously be different. Similarly some of the plants are located in a well-connected city likeDelhi, others are located in very distant places where even the transport is a big problem. So these

    two types of plant may require different amount of the same material for the same time period.

    The purchasing procedures at NTPC should be such that it can take care of such extremedifferences and provide both the locations with the required material at the right time,. If NTPC

    procure all the material through a centralized purchasing division which will club all therequirements of various projects together and order on the basis of his clubbed requirement, of

    various projects together and order on the basis of the clubbed requirement, then NTPC canachieve economies of scale as the quantity bought will be significantly high considering that it has

    more than 20 projects running in its fold this trade of between the economic efficiency and

    response is very important as all the plants of NTPC run on 365x24 basis.

  • 7/29/2019 Contract Procurement Management Report

    17/60

    14

    FINANCIAL

    STATEMENT

    ANALYSIS

  • 7/29/2019 Contract Procurement Management Report

    18/60

    15

    A financial statement analysis consists of application of analytical tools and techniques to the data

    in financial statement in order to derive from these measurement and relationships that are

    significant and useful for decision making.

    Financial analysis can be used as the preliminary screening tool in selection of stock in secondary

    market .It can be used as a forecasting tool of future financial condition and results. It may be

    used as a process of evaluation and diagnosis of managerial, operating, or other problem areas.

    The principal tool for the analysis of financial statement is RATIO ANALYSIS.

    ANALYSIS OF FINANCIAL STATEMENTS :-

    A ratio gives the mathematical relationship between one variable and another. Ratio analysis

    mainly helps in valuing the firm in quantitative terms.

    Financial tool can be grouped as

    1) Profitability or efficiency ratio

    2) Ownership ratio

    Earning ratio

    Leverage ratio

    Capital structure ratio

    Coverage ratio

    Dividend ratio

    LIQUIDITY RATIO

    Liquidity is firms ability to pay its debt in short term. Short-term liquidity involves the

    relationship between the current asset and current liability. If the firm has sufficient net working

    capital (excess current asset over the current liability) the firm is said to be highly liquid.

    Current Ratio

    Current AssetIt is define as

  • 7/29/2019 Contract Procurement Management Report

    19/60

    16

    Current liability

    Current asset includes cash; marketable securities, debtors, inventories, loan and advances, and

    pre-paid expenses, current liability includes loan and advances taken, creditors, accrued expenses,

    and provisions.

    In operating cycle the current assets are converted into cash to provide the payment for current

    liabilities. So higher the current asset higher the short term liquidity.

    Quick Ratio

    Quick test is also defined as the acid-test ratio

    Quick AssetIt is define as

    Current liability

    Current asset inventories=

    Current liability

    The quick ratio is more stringent measure of liquidity, because the inventory which are liquid of

    current asset, and exclude from the ratio.

    Inventory Turnover Ratio

    The liquidity of firms inventory may be calculated by dividing the cost of good sold, by the

    firms inventory The inventory turnover measure that how fast the inventory is moving through

    the firm and generating sales,

    Inventory turnover ratio

    Cost of good sold=

    Average inventory

    Higher the ratio the greater the efficiency of inventory management.

    Presence of inventory involves two risks:

    1 Running out the inventory due to low inventory (high turnover), which may indicate

    future shortage.

  • 7/29/2019 Contract Procurement Management Report

    20/60

    17

    2 Excess inventory causes the blockage of capital.

    PROFITABILITY RATIO

    These ratios measure the firms ability to generate profits. These are of two types. These are:-

    1) Profit in relation to sales:

    It is important from the profit standpoint the how much the firm is able to generate the profit

    with the sales of each unit. Two popular ratios in this category is operating profit margin, net

    profit margin.

    2) Profit in relation to asset

    It is important that the profit be compared to the capital invested by the owners and creditors,

    if the firm cannot produce a satisfactory profit on its asset base, it might be misusing its assets.

    They are also referred to as rate of return. Ratio like asset turnover ratio, earning power, and

    return on equity fall in this category.

    Operating Profit Margin

    Operating profit is basically earning before interest and taxes, it profit generated by operation.

    Operating profit margin

    EBIT=

    Net sales

    Net sales = sales - excise duty

    Net Profit Margin

    It is defined as Net profit

    Net sales

  • 7/29/2019 Contract Procurement Management Report

    21/60

    18

    This ratio shows the earning left for the shareholders as a percentage of net sales .It measures the

    overall efficiency of production , administration , selling , financing, pricing, and tax

    management,

    Asset Turnover Ratio

    Asset turnover ratio defined as

    Sales

    Average asset

    It highlights the amount of assets the firm used to generate its total sales. The ability to generate a

    large volume of sales on a small asset base is an important part of the firms profit picture .Idle or

    improperly used asset increase the firms need for costly financing and the expense formaintenance and upkeep.

    Return on Equity

    The return on equity (ROE) is an important indicator to shareholders of the firm. It is calculatedby the formula:

    Net Income

    Average Equity

    The return on equity measure the profitability of equity fund invested in the firm. It reflects the

    productivity of capital employed in the firm. It is influenced by several factors: earning power,

    debt-equity ratio, average cost of debt fund, and tax rate.

    EARNING RATIO

    The earning ratios are earning per share (EPS), Price-earning ratio (P/E) and capitalization rate.

    From the earning ratios we can get information on the firm and their effect on price of common

    stock.

    Earning Per Share

    Shareholders are concerned with the earnings of the firm in two ways, one the availability of

    dividends and other to expand their interest in the firm with the retained earning. EPS can be

    defined as

  • 7/29/2019 Contract Procurement Management Report

    22/60

    19

    Net Income (PAT)

    Number of outstanding share

    PriceEarning Ratio

    The priceearning ratio is also called P/E multiple.

    Market price of sharePrice-earning multiple =

    Earning per share

    This ratio gives the relationship between the market price of the stock and its earnings by

    revealing how the earning of a firm affects the price of its stock. If a P/E ratio of the stock is verysmall say 3/1 it may be considered as undervalued stock .If the P/E value of firm is 80/1 it may be

    considered as overvalued firm .

    The Capitalization Rate

    Earning per shareCapitalization rate =

    Market price of share

    The reciprocal of P/E ratio gives the return the investors generally expect before buying shares.

    For example if a stock has Rs. 12 EPS and sell for Rs. 100, the market place expect a return of

    12/100, i.e. 12% .this is called stocks capitalization rate. A 12% capitalization rate implies that

    the firm is required to earn 12 % on the common stock value. If the investor expects less than 12%

    they will be ready to pay more than current value and the capitalization rate of stock drops.

    LEVERAGE RATIO

    Debt-Equity

    The debt-equity ratio indicates the relative contribution of creditors and owners, it can be defined

    as

    Debt

    Equity

    Depending on the type of business and the pattern of cash flow the component of debt-equity ratio

    will vary .Normally the debt component consists of all liability including current. The equity

    component consists of net worth and preference capital. It is the screening device in the financial

  • 7/29/2019 Contract Procurement Management Report

    23/60

    20

    analysis .If the D/E ratio is relatively high, the owner is putting less money and that is the danger

    signal for the creditors .If the project of such firm fails the loss is major shared by the creditors

    and the owner may act irresponsibly .high portion of debt can affect the operation of firm because

    the creditors can interfere in the operational as well as managerial decision.

    Debt-Asset Ratio

    The debt-asset ratio measures the extent to which borrowed fund support the firms asset . It is

    defined as

    Debt

    Asset

    The asset here indicates total of all asset in balance sheet.It is usually held that fixed asset and long term asset should not be financed by short term loans.

    The most appropriate kind of fund for financing of this kind of assets is equity capital.

    Interest Coverage Ratio

    One measure of a firms ability to handle financial burden is the interest coverage ratio, also

    referred to as the times interest coverage ratio. This ratio tells us how many times the firm can

    cover or meet the interest payments associated with debt.

    EBIT

    Interest coverage ratio =Interest expenses

    The greater the interest coverage ratio, the higher the ability of the firm to pay its interest expense.

    Degree of Operating Leverage (DOL)

    Operating leverage examine the effect of the change in the quantity produced on the EBIT

    of company.

    Percentage change in EBITDOL =

    Percentage change in output

    Greater the DOL, the more sensitive is EBIT to a given change in unit sales, DOL is therefore

    indicates the business risk.

  • 7/29/2019 Contract Procurement Management Report

    24/60

    21

    Degree of financial leverage (DFL)

    Financial leverage results from the presence of fixed financial charges in firms income stream

    .These fixed charges do not vary with the EBIT. It is defined as the ability of a firm to use fixed

    financial charges to magnify the effect of change in EBIT on firms EPS.

    Percentage change in EPSDFL =

    Percentage change in EBIT

    There will be no financial leverage if there is no fixed-charged financing.

    Degree of total leverage (DTL)

    It is combination of operating leverage and financial leverage .The degree of total leverage is the

    measure of the output and EPS of company .DTL is product of DOL and DFL and can be

    calculated as follows:

    Percentage change in EPSDTL =

    Percentage change in output

    OrDTL= DOL*DFL.At the break-even point of output the DTL is undefined.

    At the output less than output DTL is negative.

    At the output more than output DTL is positive.

    DIVIDEND RATIO

    Dividend Payout Ratio

    This is the ratio of dividend per share and earning per share (EPS).It indicates how much of the

    earnings of company is being disbursed as dividend .If the company believes in high pay-out ratio

    then it can be said that firm is retaining less that may hamper future growth of company .If the

    firm need money for financing any project it can retain more and pay less dividend.

    Dividend Yield

    This is the ratio of dividend per share and market price of share.

  • 7/29/2019 Contract Procurement Management Report

    25/60

    22

    DPSDividend yield =

    Market price of share

    The ratio gives the current return on ones investment .this is mainly interest of investor.

    GROWTH

    Growth of firm = retention ratio * ROE.

    This value gives the annual growth of company taking assumption that whatever

    firm is retaining is investing and getting the rate of return equals to ROE.

    COST OF CAPITALIt is the cost of acquiring the fund required to finance the project .i.e. cost of capital is the

    borrowing rate of the firm, alternatively cost of capital in terms of lending rates may refer to the

    opportunity cost of the funds to the firm .i.e. what the firm could be earned by investing funds

    elsewhere.

    NTPC (Rs. Millions)

    Years 2005 2004 2003 2002 2001

    LIQUIDITY RATIO

    Current Assets,

    Loans & Advances 129073 135468 194132 177771.98 160751.7Current Liabilities &Provisions 67467 80942 45851 58153.09 67324.34

    Secured Loans 44407 45844 41226 16455 19655

    Current ratio( incl.ST loans) 1.15 1.07 2.23 2.38 1.85

    Current ratio 1.91 1.67 4.23 3.06 2.39

    Quick ratio 1.65 1.46 3.85 2.71 2.12

    inventory 17777 17380 17712 20142 18356Operating Income(turnover ) 225402 188491 190475 177697 189449

    Inventory TurnoverRatio 12.68 10.85 10.75 8.82 10.32

    Fixed asset (afterdepreciation ) 223148 212545 198650 176781 184657FIXED ASSETTURNOVER RATIO 1.010 0.890 0.960 1.010 1.030

    INVESTORSRATIO

    Retained Earnings 35600 40398 28600 28317 29106

    Reported Net Profit 58070 52608 36075 35396 37338

  • 7/29/2019 Contract Procurement Management Report

    26/60

    23

    RETENTIONRATIO(RE/PAT) 0.613 0.768 0.793 0.8 0.78

    ROE (%) 14.16 15.02 11.59 12.44 14.59GROWTHg=RETENTIONRATIO*ROE 8.68 11.535 9.191 9.952 11.38

    Equity Dividend 19790 10823 7080 7079 7470Number of Equityshares outstanding 8245464400 7812549400 7812549400 78125494 78125494

    DPS(DIV./OUT.SHARES) 2.4 1.385 0.906 90.611 95.615EPS (PROFIT/OUT.SHARES) 7.043 6.734 4.618 453.066 477.923DIV.PAYOUTRATIO (%) 34.08 20.57 19.62 20 20.01

    D+E 515404 447555 402336.61 356255.12 329877.86TOTAL EQUITY (E) 410077 350167 311306 284621 255933

    TOTAL DEBT (D) 170878 154528 132157 115812 98048

    INTERST PAID (I) 16955 33697 9916 10414 12485COST OF DEBT(Kd=I/D*100)%(1-t) 6.59 14.48 4.98 5.97 8.46COST OF EQUITYCAPITAL(Ke)%=ROE 14.16 15.02 11.59 12.44 14.59OVERALL COST OF CAPITAL =Kd*(D/D+E)+Ke*(E/D+E)OVEALL COST OFCAPITAL(Ko) % 11.93 14.85 9.62 10.57 12.89

    MARKET VALUEOF FIRM=EBIT/Ko 713185.25 639643.1 595072.77 530832.5 490768

    WEIGHTED AVERAGE COST OF CAPITAL

    WEIGHTED AVERAGE COST OF CAPITAL

    WACC (FOR 2005)

    average price of stock 2005(P) 86.32

    dividend paid (D) 2.4ygrowth (g) 8.68

    expected dividend next year D1=D*(1+g) 2.60832

    REQUIRED RATE OF RETURN =D1/P+g

    REQUIRED RATE OF RETURN (%) 8.71

    CAPITAL PROPORTION(P CAPITAL

    Equity Share Capital 82455 0.14193 Ke=14.16

    Reserves & Surplus 327622 0.56394 Ke=14.16

    Unsecured & Secured Loans 170878 0.29413 Kd=6.59

    TOTAL 580955

  • 7/29/2019 Contract Procurement Management Report

    27/60

    24

    WACC=P1*Ke+P2*Ke+P3*Kd

    PROPORTION (P) COST OF CAPITAL

    P*COSTOFCAPITAL

    P1 0.142 14.16 2.01

    P2 0.564 14.16 7.99

    P3 0.294 6.59 1.94

    WEIGHTED AVERAGE COST OF CAPITAL 11.94

  • 7/29/2019 Contract Procurement Management Report

    28/60

    25

    PROCUREMENT MANAGEMENT AT

    NTPC LIMITED

    INTRODUCTION

    Procurement activities to be taken by NATIONAL THERMAL POWER CORPORATION

    (NTPC) are to satisfy varying project requirement of equipment, materials and services. Any

    procurement-requiring adherence to the IDA procurement procedure, long equipment delivery

    periods, intense engineering co-ordination or specialized engineering knowledge during

    procurement etc. would be classified as category A contracts. All other procurement contracts

    pertaining to a project will be classified as category B contracts.

    Procurement at NTPC is initiated on the basis of approved indents/requisitions and indicating

    budget and project estimate provisions. The contract services/materials management services

    receive the requisition/indent for the procurement of materials/equipment/services duly approved

    by the competent authority and then plan and organize the procurement action.

    OBJECTIVE

    The basic objective of procurement management at NTPC is to make available, the neededequipment, material, works and services in the right quality and quantity, at the right time and at

  • 7/29/2019 Contract Procurement Management Report

    29/60

    26

    the right price after giving fair and equal chance to tenderers, so as to obtain the optimum value

    for each unit of expenditure.

    PROCEDURE

    DOP (DELEGATION OF POWER)All the activities undertaken at NTPC are regulated by a guideline called DELEGATION OF

    POWERS or DOP in short. The guideline lays down the responsibility and authority of various

    level executives in the PSE (Public Sector Enterprises). Based on this guideline the following

    major procedures have been identified.

    However, procurement of any material for any plant or the office of NTPC is done by two

    processes. These processes are:-

    Procurement through tenders.

    Emergent Procurement

    Though in case of urgency the respective department is allowed to make procurement through

    cash up to the limit of Rs. 10,000 only. But in case of the normal procurement that is done by

    tendering, a standard procedure is followed where the intender sends the procurement list to the

    finance department for the goods valued over Rs. 10,000 for vetting.

    Once the finance department clears the cost aspect of the tender it is send for the required

    approval from the competent authority as described in the DOP. After getting the required

    authorization the indent is forwarded to materials, contracts or HR services as is suitable. From

    there a tender notice is issued and the procurement process starts.

    TENDERING PROCEDURE FOLLOWED

    AT NATIONAL THERMAL POWER

  • 7/29/2019 Contract Procurement Management Report

    30/60

    27

    CORPORATION LTD.

    (NTPC)

    PROCEDURE FOR INDENTING:

  • 7/29/2019 Contract Procurement Management Report

    31/60

    28

    INDENT

    COST ESTIMATION

    FINANCE

    CONTRACT MATERIAL HR

    For the purpose of indenting, material planning is required. It is nothing but classifying the

    materials into various categories to facilitate a speedy and efficient procurement. In this process

    all the materials which may be required at any of the NTPC projects or offices are classified in to

    five major categories and their procurement is to be done on the basis predefined for them.

    1.Stock item (Automatic Recoupment items/AR)

    2.Insurance Items (I)

    3. Unit Replacement item (UR)4. Capital Item (P)

    5 Other non-stock items (Not falling under any of the above category)

    But since this classification is very vague and unspecific, a further classification is done to

    exercise selective control over all Material Management activities. This classification is known

    as the ABC analysis.

    A- Class items: Items having Annual Consumption over Rs 1 lakhs are classified as class A

    Items.

    There are few points worth noting about the indenting process. The estimated value of the indent

    should be as far as practicable. Basis of estimates should be either on the last purchase price with

    escalation if any or market trend or on the basis of technical specification e.g. size weight etc. In

    case of new items detailed justification & working sheet of estimated cost shall be furnished,

    wherever possible. Similarly in case of proprietary items, PAC/OEM/DES or standardization

    certificate must be furnished by the competent authority that should be DGM or above. After these

    details are checked and satisfied, the indent may be registered and further procurement process

    may be started.

    B- Class items: Items having Annual Consumption over Rs. 10000/- but less than Rs. 1 lakhs are

  • 7/29/2019 Contract Procurement Management Report

    32/60

    29

    classified as B class item.

    C- Class items: Items having annual consumption of less than Rs. 10000/- fall

    underthis category.

    Cost estimation: Cost estimation process is the most important financial activity in the process ofbudgeting and procurement. Whenever NTPC procures some material, it is either financed from

    the budget allocated to the particular department requesting for the material or it will be financed

    from the central fund. The procurement of the second kind requires financial clearance from the

    Finance Concurrence department. For the purpose, cost estimate is made before forwarding the

    indent document to the Finance department. There are various methods of cost estimation, which

    are used at NTPC. Some of the methods use very technical details and procedures whereas others

    are simple to implement and uses market rate to prepare a cost estimate.

    a) Historical Cost Method: In this method of cost estimation. The cost engineering

    department at NTPC uses the latest cost incurred for a similar kind of project. For

    example, if a cost estimate has to be prepared for a new Thermal Power Plant, the latest

    executed Thermal Power Plant rates will be used not any other. Hence the rates thus

    obtained are very near to the actual that might be prevalent in the market at present. But to

    smoothen the effect of inflation and various other financial components in the price at the

    time of the execution of that project, an escalation factor is used. All the prices of previous

    projects are multiplied by this factor and a very close estimation of market rate is thus

    obtained. The escalation factor calculation is discussed separately in the report.

    b)Market Rate Method: Market rate method is used for the procurements that are not in

    very large numbers and value. In this method once an indent is prepared, some of the

    vendors registered at NTPC or listed in trade journals are sent a request for quoting the

    prices of a particular good. This enquiry is not a tender and the rates provided by the

    vendors are not part of the bid. After the information is received, the rates quoted by

    various vendors are compared and the lowest quoted price is taken as base rate forcalculation. However if the difference in the price quoted by two vendors are reasonably

    high an average of the two may be taken as the base. However for civil works component

    of the contract, the wages rates are taken from the government gazettes and similarly for

    some homogeneous products like cement, steel etc a standard market prevailing rate is

    used.

    TENDERING PROCEDURES

  • 7/29/2019 Contract Procurement Management Report

    33/60

    30

    Purchasing at NTPC is not a very simple process. As we have discussed earlier, the purchasing

    process is not same for all kind ofmaterials andequipments. The urgently required materials are

    procured through cash purchase and single tendering, the routine purchase are routed through

    MaterialManagement Services and are procured by bidding. As we had seen the classification or

    the materials, the value frequency of purchase decides the mode of procurement. But as a policy,

    all the items worth more than Rs. I lakhs must be procured through tenders. The materials

    department or the HR Services department usually initiates the tender process .In case of

    construction and civil works; the tender is initiated by Contracts Services. Tendering process is the

    most important activity during the entire acquisition process and hence this is the main focus

    during the project. Close monitoring of tendering process is required because there are lots of

    chances or fraud, Mis-representation of facts and various other legal and procedural

    misrepresentations. To simplify the study of tendering process we have divided the topic in sub-

    parts, which will he discussed subsequently. But before we go any further we wi1I see a graphical

    representation of the tendering process.

    I) TYPE OF TENDERS: Based on the materials classification and DOP, there are three types of tenders

    l. Open tender: Procurements or value Rs I lakh and above must be done through open

    tendering. All the plant packages are procured through Open Tender. Open tender is

    Tender Notification

    Issuance of Tender

    Document

    Received Quotation

    Has TenderEvoked

    Res onse?

    No

    Yes

    Award of contract

  • 7/29/2019 Contract Procurement Management Report

    34/60

    31

    accessible to all known, reliable and proven sources ofparticular equipment/material. For

    the purpose, a notice inviting tenders must appear in two or more newspapers of all India

    repute in addition to one or more local newspaper where the material/equipment is to be

    delivered. However to avoid frivolous tenders, a pre-qualification procedure may be

    adopted. this process will take place once in every three years by advertising in two or

    more newspapers of all India repute in addition to one or more local newspaper where the

    material/equipment is to be delivered. The criteria for pre-qualification will inter-alia

    consist of past performance, financial soundness, technical competence, organizational

    capability etc. But for the items valued less than Rs 1 lakh the pre-qualification can be done

    on the basis of data available in Trade Journals, Manufacturer's Directory, or approved

    vendors list of State Government/Central Government/DGS&D vendors to whom enquiries

    were floated in past.

    2. Limited Tender: Limited tender is a type of tender where instead of sending bid enquiry to

    all the possible vendors through newspapers, a limited number of vendors arc intimated

    through post or fax. But a Limited Tender may be invited only for the procurements worth

    less than Rs. 50000/-. In limited tender, a minimum of four bidders are invited to quote the

    prices for the required equipment/material /services and these four bidders must be from the

    approved list of vendors mentioned in the open tender. However a Limited Tender is a

    special case and cannot be issued without proper explanation and requirement. In case of

    urgency, items worth more than Rs. 50000/- may also be procured with authorization of

    competent authority and the reason must be recorded in the indent documents. However the

    next higher authority of the procurement department will decide the number and names of

    supplier.

    3. Single Tender: This type of tendering is the easiest and fastest to acquire a good but

    requires lot of paper work and authorization before the acquisition can be initiated. These

    acquisitions take place on the ground of proprietary items or standardization. To initiate a

    single tender, a Proprietary Article Certificate must be issued by a competent authority and

    the purchase will not be made without authorization of a Genial Manager or to whom the

    power is delegated. This type of tendering is monopolistic in nature and is avoided to theextent possible. However Single Tendering is done in many other cases which are not

    mentioned anywhere in the DOP.

    4. E-Procurement at NTPC : E-Procurement is very important to achieve e-governance and for

    applicability of uniform procurement process to all units. It has ability to reduce procurement cost

    by reduction in the lead time, reduction in transaction cost and cycle time etc. E-Procurement also

    help in building collaborative relationship with suppliers. E-Procurement enables greater

    transparency, it also enables best practices and increase vendor base. E-Procurement also reduce

  • 7/29/2019 Contract Procurement Management Report

    35/60

    32

    the possibility of cartel formation and generate responsible competition. It also achieves saving in

    administrative and process cost. E-Procurement enhance the security and it is also a step towards

    ERP systems for the organization.

    E-Procurement further promises the following gains to the supplier/ vendor community,

    No geographical barriers: Sales/Marketing time reduction , which otherwise is spent on

    price negotiations, follow up etc., as this will lead to the quicker order finalisation at our

    end.

    Reduction in venders cost as they need not to travel our offices and there is not need to

    make those umpteen calls (communication cost).

    Complete transparency in the process/ the operating community, leading to sound

    decisions.

    In pursuance to achieve e-governance, in the recent past Government of India has issuednecessary guidelines for implementation of e-business and Government is keen for

    implementation of e-business in all the areas. It has been informed that many of public sector

    Organisations as well as Government Department have been benefited with E-Procurement.

    Central Vigilance Commission (CVC) vide office order no 46/9/03 dated 11/09/03 has issued the

    guidelines for procurement through E-Procurement /Reverse Auction.

    CONCEPT AND SCOPE: E-Procurement is purchase and sales of supplies and services and

    management of procurement process over internet. E-Procurement website allow qualified andregistered users to look for buyers or sellers for goods and services.

    E-Procurement is an integrated system and can be adopted uniformly at all the units of NTPC, to

    help reduce the procurement cost, procurement lead time and shall enhance the increased

    transparency.

    POLICY: NTPC is spread over all parts of the country and therefore a uniform system is

    envisaged which shall be efficient, economic and transparent. The E-Procurement shall be

    applicable to all the NTPC stations/ Projects / Regions and at Corporate Center. Procurementprocess shall gradually be taken electronically so that we achieve all possible procurement

    through electronic media.

    The present policy is for adaptation of procurement process through electronic media, therefore

    the existing DOP shall remain same. THIS POLICY IS EFFCTIVE FROM 1-04-2006.

    TARGETS: Implementation of e-procurement at all stations/regions have been targeted as

    detailed below:

    60% of e-procurable items by Dec 2006.

    100% of e-procurable items by Dec 2007.

  • 7/29/2019 Contract Procurement Management Report

    36/60

    33

    E-TENDERING: The concerned executive C&M department shall examine the indent with

    reference to type of items, complexity, technical specifications and other aspects and may decide

    for e-tendering. Depending upon the type of items and value etc. It will be decided as single part

    bidding or double part bidding.

    SECURITY CONCERN: In order to assure confidentiality, security and authenticity and non-

    repudiation, following techniques shall be used. Security is not restricted to these but if felt

    appropriate, at any time, additional features shall be applied.

    Public key Infrastructure

    Digital Signature

    SSL/Passwords

    Digital Certificate

    Tender preparation & Release.Work flow based

    Bid preparation-data resides on server only bidder is able to view

    Bid submission-with HASH and Encryption

    Bid opening- can be viewed only upon Un-encryption

    PROCESS: The process of e-procurement shall be taken up at Contracts & Materials department

    after receipt of the requisition or the indent from the user department. The indent duly approved

    by the competent authority as per DOP, is a pre-requisite to initiate e-procurement actions. The

    indent complete in all respect along with the all required information, documents, specifications,

    quality plan shall be forwarded by indentor to Materials department.

    The main steps involved are:

    Mode of tendering

    Nomination of tender committee

    Defining tender documents

    Defining auction rules

    Obtaining digital certificates for each T.C member Generation of passwords

    Defining of Server timing of clock

    Hosting of tender documents

    Release and Uploading of documents

    Defining tender schedule

    Allowing download of tender documents

    Clarification on tender documents on line

    On line price bid clarification / Amendments

  • 7/29/2019 Contract Procurement Management Report

    37/60

    34

    Preparation of bids on line

    Submission of bids online

    Up-loading of bids

    Submission of EMD-off-line(online possible where e-payment facility is available)

    Opening of bids- online (upon applying individual digital certificate and passwords by

    Tender committee)

    Opening of envelope1..EMD

    Opening of envelope2 ..QR (in case of open tender)

    Opening of envelope3 ..Technical details & data sheets

    Opening of envelope4 Technical deviation details

    Online evaluation of technical bids and QR

    Online technical & QR clarifications

    Arriving at technical loading off line

    In corporation of loading logic

    Assessment of NEW vendor

    Opening of envelope5 Price bid schedule

    Online generation of comparative statement

    Defining Auction Strategy/ date/ Time/Rules

    Intimation of Reverse Auction date & time to vendors Conducting reverse auction

    Providing of item wise break up by L1 bidder in the event of composite tender

    DETAILS OF PILOT PROJECTS ,UNDERTAKEN BY VARIOUS PROJECT:

    1.Badarpur Forged steel balls Completed

    2. Dadri Laptops & PCs Completed

    3.Simhadri Conveyor Belts Under completions

    4. Farraka Conveyor Belts Work in ProgessVALIDITY OF THE POLICY:

    This policy document is valid for the period of one year w.e.f 1-04-2006. In the mean time any

    suggestions / recommendation may be forwarded to corporate materials for review.

    II) TenderDocuments: Every time when an open tender is invited, the bidders are provided with

    a set of documents, which provides various required information and terms and condition of the

    contract The documents also contains the various contract forms which the bidder is expected to

    sign and return to NTPC to acknowledge the acceptance of the terms and condition of the contract.

    The document also contains the guidelines for bidders for bank guarantee. Earnest

  • 7/29/2019 Contract Procurement Management Report

    38/60

    35

    money and the like, this document is issued for a cost that is decided on the basis of

    the total estimated value of the indent the costs of the documents are as follows:

    ESTIMATED VALUE OF INDENT

    COST OF TENDER

    DOCUMENT

    1 Up to Rs. 10 lakhs 2002 Above Rs 10 lakhs and up to 25 lakhs 300

    3 Above Rs 25 lakhs and up to Rs 50 lakhs 500

    4 Above Rs 50 lakhs and up to Rs 100 lakhs 750

    5 Above Rs 100 lakhs and up to Rs 500 lakhs 1500

    6 Above Rs 500 lakhs 3000

    Every time a new tender is notified, a set of tender documents is issued against a payment of

    stipulated fee according to the price list given above. This set of tender document consists of many

    different documents meant for different purposes. The documents may vary from project to

    project. Here we will see what the documents that are generally issued to bidders are.

    A) Instruction to Bidder (1TB): This document is meant to provide the bidders the vital

    information required to understand and evaluate the tender offer. The document contains

    the general instructions like the Terms of Payment, Bid Security, Contract Performance

    Security, Liquidated Damages, Currencies conversion, Defects Liability and Work

    Schedule. The document also specifics the Qualifying/Eligibility requirements of thebidder and the goods/services supplied. The ITB also contains information for the foreign

    bidders. Additionally the ITB contains various references to clauses of GCC (General

    Condition of Contract) and SCC (Special Condition of Contract). Finally the document

    specify about the language and interpretation and implied terms and condition of all the

    documents provided with the bid. ITB also contains information about how to modify and

    withdraw the bids already submitted to NTPC. Hence in short we can identify this

    document as the guidelines and information brochure to bidders before they submit their

    quotation for the notified work.

    B) Bid Proposal Sheet or Bid Data Sheet: Bid proposal sheet is a set of documents, which

    contains the formats for bidding, Summary price proposal, Break up of Bid. Price,

    Equipment wise price break-up, civil works price break-up, commercial deviation,

    Technical deviations, Guarantee declaration, Price Adjustment data, Price break up of

    recommended spares, Construction Equipments, Special Maintenance Tools, QR Data and

    capacity data, Work completion Schedule, Declaration of Import content, Check list,

    Information regarding value addition and Type test charges. This document is nothing but

    a standard format providing the bidder to -Furnish the details required by the NTPC in a

    standard format used at NTPC.

  • 7/29/2019 Contract Procurement Management Report

    39/60

    36

    c) General condition of Contract: The document titled General Condition of Contract of

    GCC is a document that takes care of the legal aspect of the contract between the

    bidder and NTPC. This document also is an integral part of all the bid

    documents with some minor changes or no changes at all. The document

    starts with the definition for The terms used in various tender documents. This is

    worth noting that all the terms used in the bid document are predefined and have one and

    only meaning which is defined in the GCC. The document also contains different

    formulae that are to be used on some future dates to calculate the LD or the Price

    Escalation. Finally the document also refers to the unforeseen events like Out Break of a

    War, Bankruptcy of the contractor or any otherForce Majeure. The GCC also has a

    clause called RESOLUTION OF DISPUTES that specifies the procedures to be followed

    ifany dispute occurs, arising out of or in connection with the Contract.

    D) Special Conditions of Contract: Special Condition of Contract or SCC is not a standarddocument that is issued with all the tender documents. The document takes care of the

    special issues that have come up or may come up in the course of the execution of that

    particular contract and has not been covered in the General Condition of Contract. The

    very first clause of the document is TIME-THE ESSENCE OF CONTRACT. The

    document also talks about the detailed Manufacturing plan and Master Schedule of the

    execution of the contract. It is the SCC where we mention the issues related to

    Liquidated Damage Clause. This is mentioned in the document itself that "The following

    Special Condition (if Contract shall supplement the General Condition of Contract.

    Wherever there is a conflict. The provisions herein shall prevail over those in the

    General Conditions of contract. Hence the document may also be considered as the

    amendments to the GCC.

    E) Erection Condition of Contract: This document again is specific document which may

    not be issued with all the tenders. As the name itself suggests. The document deals with

    the erection component of the contract (if any). In the document some particular issues

    pertaining to the erection component of the contract is dealt with. Typically, an Erect ionCondition of Contract deals with the civil construction works undertaken at the site

    where the equipment is to be installed and commissioned. This also takes into

    consideration the statutory and local authority who may be in charge of monitoring the

    work in progress and whose permission may be required. Hence this document is a must

    for all the work where there is an erection component.

    F) Technical Specification: The document is the thickest document or any bid document.

    This document contains all the specification required for that particular project. The

    document is prepared by the Project Engineering department and contains the technical

    specifications of the equipments and spares to be procured. It may also contain the

  • 7/29/2019 Contract Procurement Management Report

    40/60

    37

    drawings of the equipment or layout of the project. Similarly the document will also enlist

    all other possible alternatives to the already mentioned specifications (if any). Since there

    are no financial aspects associated with this document, a detailed study of this document is

    out of the scope of this report.

    III) Tender Committee: As we have mentioned earlier, Delegation of Power has a very

    important role to play in purchasing process At NTPC. For every purchase value of

    exceeding Rs 50000/-.

    The committee consists of three members, one representative each from the Indenting

    department, Materials Department and Finance (Concurrence). The representatives are

    nominated by competent authority varying from Senior Manager to DGM depending upon the

    value of the contract. This committee will take into consideration every possible aspect of the

    terms and conditions, prices, inspection procedures, phasing delivery if required etc. This

    committee also formulates the QR (Qualifying Requirements) for the bidders of that particular

    tender.

    .

    IV) Tenderopening: Tender opening is the penultimate step in the purchasing process. Tenders

    are opened on the due date and time mentioned in the tender notification without fail. Ifthe datamentioned is declared holiday, the next working day will be considered as the opening date but

    the time will remain the same. The sealed envelopes containing the bid will be opened by thepurchase and finance executives nominated by their Head of the Department. The representatives

    of the bidders may also present themselves if they wish so however their absence will not hinderthe process. The name and rates quoted by all the present bidders will be read out and any

    omission or irregularity will be pointed out on the spot.

    Alterations or erasures (if any) will be initiated by the officers present at the time or the opening

    of the tenders. All the quoted figures should also be encircled and will be written in words if the

    bidder have not done so already and will be attested. Total number of erasures and correction will

    also be written and attested. These all activities are done to ensure proper and transparent

    procurement process.

    V) Late and Delayed Tender: Though the last dates for receipt of tender and tender opening dates

    are mentioned in the bid invitation notice and all the bidders are expected to adhere to them, some

    times some tender documents posted by the bidders get delayed in the post and reach the NTPC

    office later than the date specified in the tender invitation notice. It can be caused by several

    reasons within bidder's control or out of one's control. All such tenders are classified into two

    categories, Late Tenders and Delayed Tenders.

  • 7/29/2019 Contract Procurement Management Report

    41/60

    38

    a) Late tender: The tenders that have been posted on or after the due date and received

    subsequently are considered to be Late Tenders. Similarly all the tenders posted through courier

    before the due date but received after the due date is also considered to be Late Tenders. As a

    policy All the Late Tenders are rejected out right.

    b) Delayed tender: When a tender document is posted before the due date but is received after the

    due date. For such tenders which are posted through Registered Post/Speed Post before the due

    date and is received within 6 working days of bids due date may be opened and considered with

    the approval of competent authority. But this consideration has a condition that the date of

    posting of the bids documents must be clearly visible On the postal stamp on the

    envelope containing the documents. Tender those is posted by ordinary post and

    are received after the due date and time will not be opened and will be returned to the party after

    finalization of bid except in case where:- .

    1) The number of acceptance offers is less than three

    2) Lowest and acceptable tender is unreasonably high when compared with Lowest Purchase

    Price.

    3) Artificial manipulation of rates by forming a ring is suspected.

    4) All the tenderers are providing the make of only one manufacturer.

    5) If a substantial savings in foreign exchange is possible.

    VI)Negotiation: When adequate competition exists, the negotiation should and must be avoided.

    This competition may be in form of many manufacturers making the same good or a single

    manufacturer providing the goods through many retailers/suppliers and all the retailers/suppliers

    are free to quote individually. However if it's found that the price quoted by allindividual bidders

    are unreasonably high in comparison to the last purchase price/estimate or in case of some

    ambiguous technical/commercial terms and conditions, negotiations can be done with the

    approval of competent authority as per DOP. In normal circumstances, the negotiation should take

    place with the technically and commercially evaluated lowest (Lt) vendor only. However,

    depending upon the situation the negotiation may be carried out with more than one party at atime. Normally the negotiation is carried out by the TC (Tender Committee). But in case a tender

    committee is absent i.e. no committee was formed to monitor the procurement, representatives

    from finance and purchase may complete the task of negotiation. However, negotiation process is

    not always for negotiating the prices of equipment/material/services supplied but it may also

    involve terms and conditions of supply, future commitments for supply of spare parts and

    consumables and many other aspect of the contract. For example a lowest price bidder may not

    get the contract if its found that another bidder who is quoting higher than him but is offering

    lower priced spares. Hence in this case a negotiation may be conducted with the L 1 to make him

    offer the spares at the same rate as being offered by his competitor. Once the negotiation process

    is finished and the two parties involved in the negotiation reach a consensus, the committee's

  • 7/29/2019 Contract Procurement Management Report

    42/60

    39

    purchase proposal/recommendation will be put up to the competent authority for approval and

    subsequently the letter of intent may be faxed to the party.

    6) Security Deposits: A refundable security deposit may be asked at the time of submission of the

    bid. This deposit is taken to ensure that the vendor who is awarded the contract will not refuse toundertake the contract. If the bidder after successful bid refuses to undertake the contract, the

    earnest money deposited by him will be forfeited. However there arc various instances where this

    deposit may be waived off. For example for all the purchases valued less than Rs 50000/- the

    EMD may be waived off. Similarly for the PSUs, NSICs and SSI parties, the EMD can be waived

    also. On successful completion of bidding the earnest money may either be returned to the bidder

    or may be adjusted towards the security deposit to be provided by the bidder. Another

    major deposit is in form of performance guarantee or Liquidity damage (LD) the

    equipments provided by the vendor fail to perform as per the specification, the cost

    for this shortfall may be recovered from the vendor. This guarantee is generally 10% of the

    awarded value and is generally in form of bank guarantee. However in cases of procurement from

    OEM/OES or proprietary vendor the same may be waived depending upon the merit of case.

    However in case of procurement of equipment/material/services there is a contract for

    providing spares for the next three years. In case the prices of these spare parts goes up in the

    future and the vendor refuses to supply the spares at the same rate this guarantee deposit will

    be forfeited. As a matter of fact, this guarantee is taken just to make sure that the contractor

    does not refuse to honor the contract in future after he realizes that the prices have gone up or

    for some similar reasons.

    Post Purchase Activities:

    Vendor Evaluation:

    Once a vendor has supplied some material to NTPC, the vendor is registered with the NTPC

    and it is given a performance rating which may be used in future to award of contracts in case of

    limited tender and single tender. This rating system is not very complex but some formulae are

    used:

    Parameter Measure Weightage

    A) Quality Performance Rejection 4

    B) Delivery Performance

    1. Time schedule Delivery

    Ratio of contracted

    delivery to actual delivery 2

  • 7/29/2019 Contract Procurement Management Report

    43/60

    40

    in weeks

    2. Quantity schedule delivery Deviation in qty. 2

    C) Commercial and contractual

    Pre-post award

    performance 2

    Per formance

    Calculation of vendor ratings will be done as follows:

    Rejected Quantity

    a) Quality performance = 1 - * weightage

    Supplied Quantity

    Contract delivery in weekb) 1. Time Schedule = 1 - * Weightage

    Actual delivery in week

    QTY received (acceptable)

    2. Quantity Schedule = * weightage

    QTY. ordered

    Parameter Min % Score

    Quality 70%

    Delivery 50%

    Commercial Contractual Terms 50%

    On the basis of points scored against each parameter categorization of vendor shall be done as

    follows:

  • 7/29/2019 Contract Procurement Management Report

    44/60

    41

    Vendor Rating Point Score

    a) Outstanding 8 and above

    b) Very Good/Good 6-8

    c) Unacceptable less than 6

    Indices of performance

    A)Adherence to lead-time: Against each purchase order the supplies arc to be affected as per the

    declared lead-time with a cushion+I0%. In case the actual lead-time differs by more than +10%

    from the declared lead-time then the total lead time slippage shall be taken into account for rating

    calculation.

    Declared Lead Time Slippage

    RATING =

    Declared Lead -Time

    B)Extent of Rejection: Supplier as per specification and without rejection should be the

    aim of all the purchase executives. But at times the rejection is possible due to non

    conformance of the specification or performance slippage. Hence a rating system is

    developed to take care of that

    Value of Material SuppliedValue of Material Rejected

    RATING =

    Value of Material Supplied

    B) Budget Compliance: The responsibility of each purchase personnel is to keep the procurement

    within the allocated budget. The additional responsibility is in form of maintaining the quality also

    at the same time. The rating for budget compliance will be done as follows:

  • 7/29/2019 Contract Procurement Management Report

    45/60

    42

    Budget allocatedExcess over budget

    RATING =

    Budget Allocation

    And the overall rating will be done on following basis:

    Sum of above rating X 100

    OVERALL RATING =

    3

  • 7/29/2019 Contract Procurement Management Report

    46/60

    43

    A. INTRODUCTION

    Source of Funds

    National Thermal Power Corporation Ltd. (herein after called 'NTPC' or 'Employer)

    intends to finance the Package named in the Bid Data Sheet (BDS), through external

    commercial borrowings, internal and other sources.

    NTPC intends to make financing arrangements for the subject package by means of Buyers

    Credit from International Banks through the Export Credit Agencies of the country

    concerned to the extent the goods and services covered in the package are imported from

    OECO countries. For the above purpose the Export Credit Agencies require certain. Procedure

    formalities to be completed by the equipment supplier of their country. The bidder shall, in case of

    award of contract, facilitate completion of such formalities as may be required by the respectiveexport credit agency to enable NTPC to avail Buyers Credit for funding eligible goods and

    services covered in the package. The aforesaid option of funding is also intended to be availed by

    NTPC for supply of goods and services from OECD countries by the sub-vendors/sub-contractor

    of the bidder. The bidder shall make similar compliance in respect of its sub-vendors/ sub-

    contractors to the extent the goods are imported from concerned OECD country

    ELIGIBLE PLANT, EQUIPMENT AND SERVICES

    For the purposes of these bidding documents, the word "facilities" means the plant and equipment

    to be supplied and installed, together with the services to be carried out by the contractor under

  • 7/29/2019 Contract Procurement Management Report

    47/60

    44

    the contract. The words "plant and equipment, "installation services," etc., shall be construed in

    accordance with the respective definitions given to them in the General Conditions of Contract.

    All countries and areas are the eligible source countries for goods and services to be supplied

    under this contract and accordingly goods and services to be supplied under this contract may

    have their origin in any country and area

    For purposes of this clause, "origin" means the place where the plant and equipment or component

    parts thereof are mined, grown, or produced. Plant and equipment are produced when, through

    manufacturing, processing or substantial and major assembling of components, a commercially

    recognized product results that is substantially different in basic characteristics or in purpose or

    utility from its components.

    The origin of the plant, equipment and services is distinct from the nationality of the Bidder.

    BID PRICES

    Unless otherwise specified in the Technical Specifications. Bidders shall quote for the entire

    facilities on a "single responsibility" basis such that the total bid price covers all the Contractor's

    obligations mentioned in or to be reasonably inferred from the bidding documents in respect of the

    design, manufacture, including procurement and subcontracting (if any), delivery, construction,

    installation and Completion of the facilities including supply of mandatory spares (if any). This

    includes all requirements under the Contractor's responsibilities for testing, pre-commissioning

    and commissioning of the facilities and, where so required by the bidding documents, the

    acquisition of all permits, approvals and licenses, etc.; the operation, maintenance and training

    services and such other items and services as may be specified in the bidding documents, all in

    accordance with the requirements of the General Conditions of Contract and Technical

    Specification.

    Bidders are required to quote the price for the commercial, contractual and technical obligationsoutlined in the bidding documents. If a Bidder wishes to make a deviation to the provisions of the

    bidding documents save those listed, such deviations shall be listed in Attachment 6 of its bid.

    Bidders shall give a breakdown of the prices in the manner and detail called for in the Price

    Schedules. The Bidders shall present their prices in the following manner:

    Separate numbered Schedules shall be used for each of the following elements. The total amount

    from each Schedule (1 to 4) shall be summarized in a Grand Summary (Schedule 5) giving the

    total bid price (s} to be entered in the Bid Form.

  • 7/29/2019 Contract Procurement Management Report

    48/60

    45

    Schedule No. 1

    Plant and Equipment including Type Tests charges and Mandatory Spare Parts supplied from

    Abroad

    Schedule No. 2

    Plant and Equipment including Type Tests charges and Mandatory Spare Parts to be manufactured

    within Employer's Country

    Schedule No. 3

    Local Transportation including port handling, port clearance, port charges, Inland transit

    Insurance and other local cost incidental to delivery of Plant & Equipment and Mandatory Spares

    Schedule No. 4

    Installation Services including Erection Works, insurance covers other than inland transit

    insurance and other services as specified in the bidding document

    Schedule No. 5 Grand Summary (Schedules Nos. 1 to 4)

    Schedule No. 6 Recommended Spare Parts

    Schedule No. 7 Taxes and Duties not included in Bid Price

    Schedule No. 8A Break up of type test charges quoted in Schedule -1

    Schedule No. 8B Break up of type test charges quoted in Schedule -2.

    BID SECURITY

    The bidder shall furnish, as part of its bid, a bid security in a separate sea/ed envelope in the

    amount and currency as stipulated in the Bid Data Sheet

    The bid security shall, at the Bidder's option, be in the form of a Banker's cheque irrevocable letter

    of credit or a bank guarantee. , In case of domestic bidders the Bank Guarantee shall be from- a

  • 7/29/2019 Contract Procurement Management Report

    49/60

    46

    Bank as specified in the Bid Data Sheets. In case of foreign bidders, the Bank Guarantee can be

    from any other bank also in addition to the banks specified in Bid Data Sheet and if the Bank

    Guarantee is from a Bank not specified in the Bid Data Sheet, then the Bank Guarantee shall be

    confined by any such Bank as specified in the Bid Data Sheet. The format of the bank guarantee

    or letter of credit shall be in accordance with the' form of bid security included in the bidding

    documents. Bid security shall remain valid for a period of forty five (45) days.

    The bid security shall be furnished in a separate sealed envelope. Any bid not accompanied by an

    acceptable bid security, in a separate sealed envelope, shall be rejected by the Employer as being

    non-responsive and returned to the Bidder without being opened. The bid security of a joint

    venture must be in the name of all the partners in the joint venture submitting the bid.

    The bid securities of unsuccessful bidders will be returned as promptly as possible, but not later

    than twenty-eight (28) days after the expiration of the bid Validity period.

    THE BID SECURITY MAY BE FORFEITED

    (a) If the Bidder withdraws its bid during the period of bid validity specified by the Bidder in the

    Bid Form

    (b) If the Bidder does not accept the correction of its Bid Price pursuant

    (c) If the Bidder does not withdraw any deviations listed in Anachment-6 at the cost of withdrawal

    indicated by him

    (d) If the Bidder refuses to withdraw, without any cost to the Employer,

    Any deviation not listed in Attachment 6 but found else...where in the bid.

    In case of successful bidder, if the bidder fails within the specified time limit

    To sign the contract agreement, in accordance with ITB.To furnish the required performance security in accordance with ITB.

    CONVERSION TO SINGLE CURRENCY

    To facilitate evaluation and comparison, the Employer will convert all bid prices expressed in the

    amounts in various currencies in which the bid price is payable to a single currency. The currency

    selected for converting bid prices to a common base for the purpose of evaluation, along with the

    source and date of the exchange rate.

  • 7/29/2019 Contract Procurement Management Report

    50/60

    47

    TECHNICAL EVALUATION

    The Employer will carry out a detailed evaluation of the bids previously determined to be

    substantially responsive in order to determine whether the technical aspects are in accordance with

    the requirements set forth in the bidding documents. In order to reach such a determination, the

    Employer will examine and compare the technical aspects of the bids on the basis of the

    information supplied by the bidders, taking into account the following factors:

    a) Overall completeness and compliance with the Technical Specifications

    And Drawings; deviations from the Technical Specifications as identified in Attachment 6 to the

    bid; suitability of the facilities offered in relation to the environmental and climatic conditions

    prevailing at the site; and quality, function and operation of any process control concept included

    in the bid. The bid that does not meet minimum acceptable standards of completeness, consistency

    and detail will be rejected for non-responsiveness.

    Achievement of specified performance criteria by the facilities

    (c) Type, quantity and long-term availability of mandatory and recommended Spare parts and

    maintenance services.

    (d) Any other relevant factors, if any, listed in the Bid Data Sheet, or that

    the Employer deems necessary or prudent to take into consideration.

    COMMERCIAL EVALUATION

    The comparison shall be of the EXW price of domestically manufactured plant and equipment

    including Type Test charges and mandatory spares (within the Employer's country), such price to

    include all costs as well as duties and taxes paid or payable on components and raw materials

    incorporated or to be incorporated in the plant and equipment including mandatory spares plus the

    CIF (Indian port-of-entry) price of the plant and equipment including Type Test charges and

    mandatory spares named port of destination offered from outside the Employer's country, plus thecost of local transportation, insurance covers, installation and other services required under the

    contract. The Employer's comparison will also include the costs resulting from application of the

    evalua