Contract CloseoutNCMA Workshop

October 27, 2014

Hycentha Hodge Instructor

UCLARetired Deputy Commander, DCMA Western Regional Command

Page 2: Contract Closeout NCMA Workshop October 27, 2014 Hycentha Hodge Instructor UCLA Retired Deputy Commander, DCMA Western Regional Command.

2

Disclaimer

The information in this presentation was prepared and accomplished by me in my own personal capacity. Although I am a formal employee of the Defense Contract Management Agency (DCMA), the comments and opinions expressed herein are my own and does not reflect the official views of DCMA, the Department of Defense, or the United States Government

Page 3: Contract Closeout NCMA Workshop October 27, 2014 Hycentha Hodge Instructor UCLA Retired Deputy Commander, DCMA Western Regional Command.

3

Outline

• Contract Physical Completion

• FAR-Mandated Time Standards• DCMA Performance Metric

• DCMA Closeout Footprint• West Region Closeout Footprint

• Closeout Overage Reason Codes• What About Quick Closeout Procedures?

Page 4: Contract Closeout NCMA Workshop October 27, 2014 Hycentha Hodge Instructor UCLA Retired Deputy Commander, DCMA Western Regional Command.

4

• Contractor has completed the required deliveries or the contractor has performed all services

• Government has inspected and accepted the supplies

• Government has accepted these services

• All option provisions, if any, have expired

• Government has given the contractor a notice of complete contract termination, if applicable.

Contract Physical Completion

No job is complete until the paperwork is done! No job is complete until the paperwork is done!

Page 5: Contract Closeout NCMA Workshop October 27, 2014 Hycentha Hodge Instructor UCLA Retired Deputy Commander, DCMA Western Regional Command.

5

• Contracts Using Simplified Acquisition Procedures – upon evidence of receipt of property and final payment

• Fixed Price Contracts - 6 months after physical completion (Exception for fixed price unilateral purchases orders – MOCAS sets the overage date as 3 months after physical completion)

• Cost Reimbursement Contracts – 36 months after physical completion

• All Other Contracts – 20 months after physical completion

FAR-Mandated Time StandardsFAR 4.804-1

Do not close contracts in litigation or under appeal and in case of terminated contracts until all termination actions are complete!

Page 6: Contract Closeout NCMA Workshop October 27, 2014 Hycentha Hodge Instructor UCLA Retired Deputy Commander, DCMA Western Regional Command.

6

 CONTRACT CLOSEOUT CHECK-LIST(Use a separate page to attach any comments.)

1.  CONTRACT NUMBER

2.  CONTRACT MODIFICATION NUMBERS (If applicable)

3.  NAME OF CONTRACTOR

4.  DATE OF PHYSICAL COMPLETION (YYYYMMDD) 6.MILESTONES/CALENDAR 

MONTHS AFTER PHYSICAL COMPLETION (FAR 4.804-1)

7.FORECAST COMPLETION 

DATE (YYYYMMDD)

8.    DATE ACTION COMPLETED (YYYYMMDD)

(NA if not applicable) 5.                                    ACTION ITEMS

Category 2 Category 3 Category 4 a.  DISPOSITION OF CLASSIFIED MATERIAL COMPLETED

         

b.  FINAL PATENT REPORT SUBMITTED(Inventions Disclosures)                                                     DD 882

         

 c.  FINAL ROYALTY REPORT SUBMITTED

         

 d.  FINAL PATENT REPORT CLEARED (Inventions Disclosures)

         

 e.  FINAL ROYALTY REPORT CLEARED

         

f.   ISSUANCE OF REPORT OF CONTRACT COMPLETION          

g.  NO OUTSTANDING VALUE ENGINEERING CHANGE PROPOSAL (VECP)          

 h.  PLANT CLEARANCE  REPORT RECEIVED                        DD 1593

         

 i.   PROPERTY CLEARANCE RECEIVED                                DD 1593

         

j.   SETTLEMENT OF ALL INTERIM OR DISALLOWED COSTS(DCAA Form 1)

         

 k.  PRICE REVISION COMPLETED

         

l.   SETTLEMENT OF SUBCONTRACTS BY THE PRIME CONTRACTOR          

 m. PRIOR YEAR OVERHEAD RATES COMPLETED

         

 n.  CONTRACTOR'S CLOSING STATEMENT RECEIVED

         

 o.  FINAL SUBCONTRACTING PLAN REPORT SUBMITTED

         

 p.  TERMINATION DOCKET COMPLETED                             DD 1593

         

 q.  CONTRACT AUDIT COMPLETED

         

 r.  CONTRACTOR'S CLOSING STATEMENT COMPLETED

         

 s.  FINAL VOUCHER SUBMITTED                                          SF 1034

         

 t.  FINAL PAID VOUCHER RECEIVED                                    SF 1034

         

 u.  FINAL REMOVAL OF EXCESS FUNDS RECOMMENDED

         

v.  ISSUANCE OF CONTRACT COMPLETION STATEMENT(Or MILSCAP Format Identifier PK9)

 6

 36

 20

   

w. OTHER REQUIREMENTS COMPLETED (Specify)          

9.  RESPONSIBLE OFFICIALa.  TYPED NAME (Last, First, Middle Initial) b.  TITLE

c.  SIGNATURE (Sign only upon completion of all actions) d.  DATE SIGNED (YYYYMMDD)

DD Form 1597 Contract Check List

Page 7: Contract Closeout NCMA Workshop October 27, 2014 Hycentha Hodge Instructor UCLA Retired Deputy Commander, DCMA Western Regional Command.

Deliver Work

Dissecting Closeout Process

Final Voucher

Accept Work

Reconcile Funding

Close Contract

Mods Definitized

SubKs Closed

Price Revision

Final Rates

Deoblig Funds

Review Final Voucher

Patent /Royalties

Litigation

Termination

Property Clearance

Interim ContractCompletion Record

Warranties

Dispose of Classified

36 months

ContractPhysically Complete

ContractCompletion Statement

Line Item Recon

l Work solutions-- tools, workarounds, relief

l Identify show stoppers

l Start the closeout process early

Example of Cost Type 

Contract

Page 8: Contract Closeout NCMA Workshop October 27, 2014 Hycentha Hodge Instructor UCLA Retired Deputy Commander, DCMA Western Regional Command.

8

If the administrative contracting officer (ACO) cannot close out a contract within the specified time period (see FAR 4.804-1), the ACO shall notify the procuring contracting officer (PCO) within 45 days after the expiration of the time period of—

(i) The reasons for the delay; and

(ii) The new target date for closeout.

DFARS PGI 204.804-2(2)

The reason for the  

delay in closing your 

contract is  among the 

many reasons  at our 

disposal.   Let me tell you about our 

performance indicators. 

Page 9: Contract Closeout NCMA Workshop October 27, 2014 Hycentha Hodge Instructor UCLA Retired Deputy Commander, DCMA Western Regional Command.

9

Performance Indicators

Contract Closeout TimelinessIndicator Title: AQ--Contract Closeout: TimelinessIndicator: Percent of Contracts closed on time per FAR 4.804-1 requirementsIndicator Rationale:  Provide status of timely closeout of contracts that are administered by DCMA.  Performance Standard: Close 90% of contracts within the FAR 4.804-1 time standards.  Date Performance Standard is to be Achieved: End of Fiscal Year (FY)

Contract Closeout: Number of Overage ContractsIndicator Title: AQ--Contract Closeout: Number of Overage ContractsIndicator: Percent of contracts past overage date  Indicator Rational:  To provide status of the overage contracts to the Administrative Contracting Officers and Contract Administrators so they are able to track their respective contracts which will help them reduce their numbers. Performance Standard: Reduce number of contracts past overage date at a 10% annual rate.  Date Performance Standard is to be Achieved: End of Fiscal Year (FY)

The DCMA performance usually looks pretty good!!

This is the reality

Data obtained from DCMA West Region

Page 10: Contract Closeout NCMA Workshop October 27, 2014 Hycentha Hodge Instructor UCLA Retired Deputy Commander, DCMA Western Regional Command.

10

West Region Overage Footprint

Contract Count 2012/Jan 2012/Feb

DCMA Western Regional Command 4,324 4,666

The trend is moving in the wrong direction….

February 2012 – 4,666September 2015 – 8,736

Data obtained from DCMA West Region

Page 11: Contract Closeout NCMA Workshop October 27, 2014 Hycentha Hodge Instructor UCLA Retired Deputy Commander, DCMA Western Regional Command.

11

West RegionR2 Codes Definition Total as of 09/30/2015

 A - Contractor has not submitted final invoice/voucher 1429

 B  - Final acceptance not received 30

 C - Contractor has no submitted patent/royalty report 321

 D  - Patent/royalty clearance required 220

 E - Contractor has not submitted proposal for final price 8

 F - Supplement Agreement covering Final price redetermination required 2

 G  - Settlement of subcontracts pending 78 H  - Final Audit in Process 655 J  - Disallowed cost pending 2 K  - Final audit of Govt property pending 1

 L - Independent research & development rates pending 0

 M  -  Neg of O/H Rates Pending 5119

 N - Additional funds requested, but not yet received 45

 P  - Recon w/Pay Off & Ktr Being Accomplished 236

 Q - Armed Serviced Board of Contract Appeals case 35

Data obtained from DCMA West Region

Page 12: Contract Closeout NCMA Workshop October 27, 2014 Hycentha Hodge Instructor UCLA Retired Deputy Commander, DCMA Western Regional Command.

12

 R  - Public Law 85-804 case 0 S  - Litigation/investigation pending 44 T  - Termination in process 2 U  - Warranty clause action pending 1 V  - Disposal of Gov't Prop Pending 74 W   - Contract Mod Pending 111

 X - Awaiting contractor's submission of the release and assignment 41

 Y - Proper final invoice/voucher forwarded to dFAS for payment, awaiting payment 179

 Z

 - Awaiting disposition instructions on classified materials from the Buying Activity.  The ACO is responsible for notifying DIS that the contract is complete and classified material should be dispositioned 3

1

 - Canceled funds (Do Not Use - Use "Y" when Final voucher/invoice has been forwarded to DFAS 8

2  - Appropriations in Red (Do Not Use) 03  - Pre-validation Action Pending 06  - Fee Withheld 07  - Awaiting Removal from Excess Funds 26

Blanks 66Total OA Reason Codes* 8670Total OA Ks in Section 2 8736       *OA reason codes filtered by R2 code in the first position onlySection 2 On-Time** 11620Section 2 Approaching OA ** 896  * * - These numbers are as of 10/3/2015Total Ks in Section 2 - On Time/Approaching OA/OA 21252

West Region

Data obtained from DCMA West Region

Page 13: Contract Closeout NCMA Workshop October 27, 2014 Hycentha Hodge Instructor UCLA Retired Deputy Commander, DCMA Western Regional Command.

13

Quick Closeout Class Deviation

Page 14: Contract Closeout NCMA Workshop October 27, 2014 Hycentha Hodge Instructor UCLA Retired Deputy Commander, DCMA Western Regional Command.

14

 

Uncle Sam Wants You!

To do your part to assure contracts are delivered on time, on cost, on quality, and then close ON TIME!!