Contract Change Order No. 2 Redacted

download Contract Change Order No. 2 Redacted

of 5

Transcript of Contract Change Order No. 2 Redacted

  • 8/20/2019 Contract Change Order No. 2 Redacted

    1/8

    City of

    Carmel-by-the-Sea

    PUBLIC WORKS DEPARTMENT

    POST OFFICE BOX CC CARMEL-BY-THE-SEA, CA 93921

    (831) 620-2070

    CONTRACT CHANGE ORDER NO. 2

    CONTRACT

    AWARDED

    BY: City Council

    DATE OF AWARD Apr

    7,

    2015

    ~ R ~ O ~ J ~ E ~ C ~ ~ ~ ~ T ~ h ~ e ~ a ~ t e ~ r ~ ~ e ~ n ~ o ~ v ~ a ~ t i ~ o ~ n ________________________________________

    SHEET

    ____ ~ ~ __

    PROJECT ID#: 13-70903

    TO: Otto

    Construction

    Company; 2150 Garden Road, Suite A-1, Monterey, CA 94940 ,CONTRACTOR

    You

    are

    hereby requested to

    make

    the herein

    described chang

    es

    from

    the plans and specifications

    or

    do the

    following described work not included

    in

    the plans

    and

    specifications on this contract.

    NOTE: THIS UNTIL

    Description:

    1 CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.

    Addition

    : Supply all labor and materials necessary to complete the following: Reference

    Request for Information #25 by the City

    of

    Carmel-By-The-Sea and Otto's PCO #13 (their

    tracking number, not City's). Work includes demolition of existing concrete curbs, excavation of

    soil to 5 below existing finished concrete floor,

    com

    paction of subgrade, concrete, rebar,

    dowels, relocation of existing water lines (per RFI #25) and wood box curb. Excludes

    inspections, engineering and testing fees .

    Agreed Lump Sum....... .. .

    ..

    ..... . ...

    ..

    . ............... .

    ..

    ... ........ ....

    ..

    .. ...

    .................

    .... .

    2 CONTRACT PRICE

    Total Increase in contract price

    3 CONTRACT TIME

    No additional days

    Net change in Contract Price is

    of

    the original Con

    tr

    act Price

    4,

    638

    .

    00 Increase

    1,

    462,236.00

    4,898.00

    0.7%

    We the undersigned contractor have given careful consideration to the change proposed and hereby agree  if his proposal is

    approved that we will provide all equipment  furnish all materials  except as may otherwisebe noted above and perform all services

    necessary for the work above specified and will accept as full payment therefore the price shown above.

    Submitted

    By

    : Andy

    Vanderford

    Proj

    ec:t

    Manager

    Contractor: Otto Construction Company

    Title: ?r '

    .e

    c

    .A--1 A -'

    c

    c

    Z

    his attention is directed to the requiremenfs of t

    he

    4,638.00

    4,638.00

    0

    Approved:

    Is

    Publ

    ic Works

    Direct

    or

    Rob Mullane

    Date /0-/f-/L

    Authorized: 0 City Administrator

    Doug Schmitz

    Authorized:

    El

    City Council

    Attachments: Contractor Proposal (2 pages total)

    Request for Information #25

    Date

    Is

    /s

  • 8/20/2019 Contract Change Order No. 2 Redacted

    2/8

    Potential Change Order (PCO) Cost Breakdown & Summary

    Project

    Forest Theater Renovat ion

    De

    scription

    of

    Change

    Project#

    15-3141-00

    Below costs are associated with required

    work

    per "RFI #261ndoor

    Theater Exposed Soil

      .

    Work includes

    demolition of existing

    concrete

    curbs, excavation

    of soil

    to

    5

    below

    existing finished

    concrete

    floor

    ,

    compaction of subg

    rad

    e,

    concrete, rebar, dowels, relocation

    of

    existing

    water lines (per RFI #25) and

    wood box curb

    . Excludes i

    nspections

    ,

    engineering and testing fees.

    CHANGE ESTIMATE ITEM COST M/U% M/UTOTAL

    GC DIRECT COSTS

    GC DIRECT LABOR

    52,736

    GC

    DIRECT

    MATER

    IALS $850

    GC

    DI

    RECT EQUIPMENT

    5387

    GC OTHERIINDIRECTS

    $200

    GC MARKUP ON DIRECT COST

    GC MAR KUP ON DIRECT LABOR

    $2

    ,736 10.0%

    $274

    GC MARKUP ON DIRECT MATERIAL $850 10.0% $

    85

    GC \1ARKuP ON DIRECT EQUIPMENT S387 10.0%

    5 9

    GC MARKUP ON DIRECT OTHERrlNDIRECTS

    $200 10.0%

    520

    GC SUBCONTRACT(S)

    OR

    'OTHERS'

    GC FEE ON SUBCONTRACT(S)

    $0 5.0%

    s

    ADDITIONAL TIME REQUIRED 0 DAY(S)

    FOR

    CONTRACT

    COMPLETION  _ ......

    COMPLETED BY: John Garayalde

    PCOII:

    Re lated ASI II:

    Related BU L II:

    Re

    lated

    RFJ

    DATE:

    TOTAL L, M, & E DIRECT COST

    TOTAL MARKUP ON DIRECT COST

    TOTAL SUBCONTRACT COST

    TOTAL GC FEE ON SUBCONTRACT(Si

    TOTAL UNAVO IDABLE DELAY COSTS

    TOTAL CONSTRUCTION COSTS

    BOND AND INSURANCE 1

    TOTAL COST OF CHANGE ORDER

    13

    N/

    A

    N/A

    25

    08 05/15

    $4,173

    $417

    0

    s

    0

    4,590

    $48

    $4,638

  • 8/20/2019 Contract Change Order No. 2 Redacted

    3/8

    OI'ISTIWCHON

    Otto Construction

    2150 Garden Road, Sui1e A 1

    Monterey, CA 93940

    TEL

    83

    1.657.9805 FAX 831.657.9820

    License #178809

    OTTO ESTI  TE SUMM RY SHEET

    ID

    Below costs are associated with required work per RFI #26

    Indoor

    Theater Exposed

    Soil  .

    Work

    includes

    demolition

    of

    existing

    conc rete curbs, excavation of so i l

    to

    below existing

    finished concrete floor, compaction of subgrade, concrete, rebar,

    dowels, relocation of

    exist

    i

    ng

    water lines {per RFI #25)

    and

    wood

    box curb. Excludes inspections, engineering and testing fees.

    Description Hrs Rate Labor

    1 Labor

    er

    36.0 76 2,736

    2 Demo, excavate, off-haul & concrete 0

    4 0

    5 Shortload (potential credit back) 0

    6 0

    7 0

    8 0

    9 0

    10 0

    11

    0

    12

    0

    13 0

    14

    0

    15 0

    16 0

    17

    0

    18 0

    19

    0

    20 0

    21

    0

    22 0

    23 0

    24 0

    25 0

    26 0

    27 0

    28

    0

    29

    0

    30 0

    31 0

    32 0

    33 0

    34 0

    Totals

    36.0 2,736

    CHECK

    L

    M,E,S : 4,173

    Notes:

    Job No

    .:

    15-31

    41

    ·00

    Project : Forest Theater Renovation

    PCO# 13

    Date: 8/5/2015

    Matt Equip

    Sub

    /Mise

    TOTAL

    850 387

    50

    4,023

    150

    150

    -

     

    850

    387 200

    4,173

  • 8/20/2019 Contract Change Order No. 2 Redacted

    4/8

    OTTO

    ONSTRU TION

    2150 GARDEN ROAD, SUITE A-1

    MONTEREY, CA 93940

    Ph:

    831 657-9805

    To :

    Andrew Vanderford

    CITY OF CARMEL BY THE SEA

    P.O.

    Bo

    x CC

    Carmel By the Sea, CA 93921

    Ph:

    831-620-2078

    R I

    I

    RFI : 25

    Date: 7f7/2015

    Job

    : 15-3141-00 FOREST THEATER RENOVATIONS

    Phone: 831 )620-2078

    CC: Jilian Cadouri (Cody Anderson Wasney), Monique Wood (Cody Anderson Wasney), Oscar Cisneros (Otto Construction),

    John Garayalde (Otto Construction)

    Subject: Indoor Theater Exposed Soil

    Drawing: A2.4

    Spec Section:

    Cost Impact: TBD Schedule Impact: TBD

    Request: Date Required: 7/17/2015

    The

    re

    is existing soil that was exposed during the removal

    of

    the existing indoor stage. There is a drain line and water lines located

    where the new stage ledger is

    to

    be installed for the new indoor stage. Location of existing lines is between grid lines 1 and 2 on the

    back side

    of

    the dressing room wall (see photos).

    Please advise.

    Requested by : Matt Wetmore

    OTIO CONSTRUCTION

    Response:

    Demo (e) concrete curbs at gridline G and

    just

    south of gridline 2 to

    be

    level with adjacent concrete floor. Reroute

    pipe south of gridline 2

    to

    run along gridline G

    Where soil occurs, excavate, and pour new 5

    th1ck

    slab with rebar per 1/A6.5 Install 4 epoxy dowels at edges at

    18 o.c. wi

    th

    4 min. embed depth New slab to be level with (e) concrete slab.

    For new landing, Install ledger on either side

    of

    pipes and notch new plywood landing where (e) drain and water

    lines extend above landing level. Construct wood box curb to enclose pipes above landing level.

    See also comments on photos.

    ~ ~

    REVIEWE

    By Andy Vanderford at 11:10 am  Ju 21  2015

    J.Cadouri

    Answered by

    C W Architects

    07/21/15

    Company Date

    Page 1

    of

    1

  • 8/20/2019 Contract Change Order No. 2 Redacted

    5/8

    s - --- --- -

    ...

    ..:..03

    s

     ==

    .

    :;R Z.SS·

     

    G F l O '

    . . . .  

    S F

    _

    r \

    -rl  G X S T ~ G R ~ I N

    J - WATE L I N E ( ~ ) I

    ~ r ___T __ __ __ _

    PROPOSED INDOOR

    THE TER PL N

    -----  8

    --  ----8

  • 8/20/2019 Contract Change Order No. 2 Redacted

    6/8

  • 8/20/2019 Contract Change Order No. 2 Redacted

    7/8

  • 8/20/2019 Contract Change Order No. 2 Redacted

    8/8

    lines to remain in place New

    crete slab to run below. Install

    ledger on either side notch new

    lywood landing t pipes constru ct

    u rb to enclose lines at landing