Contract Administration

55
1.Responsibilities/Liabilities Principal, contractor 2. Settlement of claims - claims for advance - claims for payment of bills - claims for extras/ variations - claims for cost escalations - claims for time extensions 3. Statutory Requirements and social responsibilities / obligations 4. Files and records Contract Administration

description

c2

Transcript of Contract Administration

  • 1.Responsibilities/Liabilities

    Principal, contractor

    2. Settlement of claims

    - claims for advance

    - claims for payment of bills

    - claims for extras/ variations

    - claims for cost escalations

    - claims for time extensions

    3. Statutory Requirements and

    social responsibilities /

    obligations

    4. Files and records

    Contract Administration

  • Contract

    Administration

  • Performance, cost and time depends on three conditions:

    1. The parties to the contract must have a clear understanding of and

    commitment to their obligations.

    2. Employer should select a project team with adequate experience good

    exposure to project problems, ability to give prompt decisions, make

    timely payments and to settle extra items/ claims judiciously.

    3. The contractor should select a competent project manager and other

    members of the team, make a correct assessment and deploy required

    resources, by proper forward planning, keeping in view time, cost and

    quality control.

  • To nominate Engineer in charge/ Project Manager and his

    team.

    Giving possession of site, obtaining necessary sanctions,

    permissions.

    Supplying Instructions to carry out the work.

    Furnishing necessary plans, designs, drawings, specifications,

    etc., sufficiently in advance.

    Timely supply of materials to the contractor in required

    quantities and quality as specified in schedule of Materials.

    1 a] Responsibilities / liabilities of Principal

  • Nominating / approving the Sub-Contractors.

    Supervision of the work

    - Ensuring that execution works is as per drawings, design and

    specifications.

    - Monitoring progress, quality of work.

    - Giving necessary instructions, guidance.

    - Giving clearances without undue delay.

    - Issuing necessary certificates.

    - Ensuring coordination among the contractors.

    Contd

  • Maintaining good relationship, working condition.

    Ensuring smooth progress of work.

    Noninterference in contractors work.

    Settlement of the claims.

    Claims for payment of bills, extras/variations, cost escalations,

    time extension.

    Compliance with statutory requirements and social

    responsibility / obligations.

    Preparing and submitting reports to the owner, maintenance of

    files, records, documents.

    Contd

  • i) Execution of works in compliance with plans, drawings, design

    and specifications.

    ii) Execution of works to meet performance criteria of Quality,

    Time and Cost.

    iii) Ensuring safety and security of the staff, laborers.

    iv) Selection of resourceful sub-contractors, coordinating and

    monitoring their work.

    v) Setting up and running the site organization

    1 b] Responsibilities / Liabilities of Contractor

  • Procurement of materials, labor at reasonable cost, ensuring

    their proper usage and storage.

    Controlling the wastage

    vii) Planning and organizing the execution of work. Providing

    designs of those minor works for which the Principal has not

    provided the designs.

    viii) Maintenance of construction equipment and machinery.

    ix) Labor safety and welfare.

    contd

  • x) Providing assistance to the Principal for supervision,

    monitoring, quality checking, measurements, etc..

    xi) Submitting all claims in time.

    xii) Site clearance and handing over possession of works after

    completion.

    Contd

  • a) Claims for advances:-

    Contractors will have a need for large amount of money before

    commencement of the execution of works for

    Mobilization and preparations for commencement of the

    execution of works.

    Purchase of plant, machinery, Equipment, tools etc.,

    Payment of advances for materials, sub contracts

    Working capital, contingency, etc.

    SETTLEMENT OF CLAIMS

  • Following is a list of various advances that can be

    made available to contractor in major contracts:

    Mobilization advance

    Advance against machinery and equipment's

    Advance against materials

    Advance for work done but not measured.

  • [purpose, conditions, guarantee to be provided, recovery of advances]

    Mobilization advance:-

    Purpose:- to facilitate mobilization of construction resources to the site and

    make arrangements for commencement of the execution of works.

    Conditions:-

    This advance may be granted to the extent of about 5% to 10% of the

    contract value.

    Where the work is of specialized nature and mobilization expenses are likely

    to exceed 10% of the contract value, additional advance may be made

    available through a specific enabling clause in the contract conditions.

    Mobilization advance may not be necessary for minor contracts ( contract

    value, say, < 10 to 25 lakhs)

  • In contracts of very large value, mobilization advance may be

    given in installments in accordance with an agreed schedule

    specified in contract conditions, as and when the contractor

    incurs the expenses.

    [NOTE: - in many international contracts under FIDIC conditions

    and world bank aided projects, mobilization will be treated as a

    separate item of work and payments are done on quoted rate

    basis.]

    Mobilization advance

  • Guarantee to be provided:-

    This advance will be given against a bank guarantee to be

    furnished by the contractor.

    The principal will be entitled to make sure that the mobilization

    advance released to the contractor is utilized for the particular

    contract for which it has been given. The bank guarantee can be

    encashed if the contractor fails to properly account for the

    advances received against the expenses incurred towards

    mobilization.

    Mobilization Advance

  • ii) Advance against machinery and equipment:-

    Purpose:- to remunerate the contractor for his investments on

    plant, machinery, equipment, tools etc..

    Conditions:-

    Advance against plant, machinery, equipment, tools, etc., bought

    to the site for use in the execution of works under the contract

    can be given for both new purchases for the contract as well as

    the existing, deployed at the site.

    The advance in case of new purchases can be up to 75% to

    90% of the cost , subject to furnishing of satisfactory evidence

    of purchase and cost by the contractor.

  • In case of existing, plant, machinery, equipments, tools,

    etc., deployed at the site up to 50% of their estimated present

    value may be given as advance. In this case, a certificate from

    an approved valuer about their present value estimated

    according to accepted norms of valuation, must be provided

    by the contractor.

    These advances are normally limited to about 10% of the

    contract value. In special cases it may be 20% or even higher.

    Contd.

  • Guarantee to be provided:-

    These advances are provided against the security of

    the plant , machinery, Equipment, tools, etc., deployed

    at the site on their hypothecation to the owner/

    Principal by executing a deed of hypothecation.

    A bank guarantee may be accepted in lieu of

    hypothecation.

    Contd

  • Advance against materials:-

    Secured advances can be granted to the contractor

    against non-perishable materials brought to the site for

    consumption in the works under the contract.

    In civil construction contracts these materials include

    coarse and fine aggregates, boulders, bricks, size stones,

    tiles, wood etc., [steel and cement if not supplied by the

    Principal].

  • Conditions:- these advances are provided under the following terms-

    i) Advance is granted up to 75% of actual cost of materials purchased

    and brought to the site.

    ii) The advance has to be recovered within a period of three months

    from the month in which advance is paid.

    iii) The contractor must provide adequate storage and protection for

    these materials against damage by weather/ other causes and

    pilferage.

    iv) The contractor must provide an Indenture Bond or Surity Bond by

    executing a suitable deed.

    Contd.

  • Advance for work done but not measured:-

    Sometimes the contractor makes a request for payment against

    a part of work that is completed but its detailed measurement and

    / or quality assurance checks has not yet been done. In such cases

    the contractor can be paid up to 80% of the value of such work as

    advance payments.

    The advance so provided must be recovered in the subsequent

    monthly running bill based on detailed measurement and quality

    assurance checks of all works completed till then, including the

    work against which advance payment has been done.

  • RECOVERY OF ADVANCES:-

    The recovery of advances should be so regulated that it does not hinder the

    availability of funds to the contractor.

    Therefore recovery of funds can commence after at least work of the value

    equal to 10% of the contract value is completed and paid to the contractor.

    The recoveries are made in such a phased manner that the total

    principal amount against all types of advance granted to the contractor

    together with interest ( if any ) there on is fully recovered by the time

    80% of the value of the work under the contract is completed and within a

    suitable timeframe that is not exceeding 90% of the originally scheduled

    completion time in the contract.

  • If there is an exceptional delay due to some

    genuine reasons and the contract period has

    been extended, then, the advance recovery period

    may also be rescheduled, if deemed necessary.

    Contd

  • SETTLEMENT OF CLAIMS FOR PAYMENT OF BILLS:-

    This is the most sensitive and vital issue in contract

    management. Timely payment of bills is a basic obligation of the

    Owner / Principal.

    Its delay / denial will be a cause for frustration to contractors

    resulting in disputes.

    A smooth and assured cash flow to the contractor fetches a

    better rate and will serve as an incentive, motivation for better

    performance by the contractor.

  • Normal expected Time Schedule for payment of Bills are:-

    - Interim or running bills: with in a fortnight or a month

    - Final bill :- within three to six months.

    If final bill is held up due to any reason advance to the extent of

    90% of the bill amount may be paid pending settlement of the final

    bill.

    Contd

  • MEASUREMENT OFWORKS:-

    IS 1200 standard mode of measurements of Buildings

    - Unless otherwise specified measurement of civil construction

    works are done as per the guidelines provided in this standard.

    - A measurement book (M B) to be maintained in which

    measurements are recorded.

    - Measurements are to be recorded by the Principals authorized

    engineer in the presence of the authorized representative of the

    contractor. His signature should be obtained on M.B. as a token of

    acceptance of the measurement.

  • Each set of measurements should include the following:-

    i) name of the work / contract , its reference code number

    ii) name of the contractor

    iii) date of agreement and date of commencement of work

    iv) date of recording the measurement

    v) reference of the previous measurement.

    Contd..

  • RECOVERIES TO BE MADE FROM THE BILLS:-

    1) security deposit

    2) recoveries from the advances paid

    3) retention money (if any)

    4) liquidated damages for delay in construction time

    5) income tax deductions and any other statutory deductions

  • ISSUES IN SETTLEMENT OF CONTRACTORS BILLS

    - Payment at reduced rates

    - Payments to the sub- contractor

    - Suspension of works

    - Defects liability period

    NOTE:- interim / partial payments, Entire/partial

    occupancy of the works by owner/ principal will not be

    deemed as acceptance of work or its materials which are not

    in accordance with the specifications.

    .

  • (C) CLAIMS FOR TIME EXTENSIONS

    The time period for completion of contract work may be specified

    by giving :

    a specified date for completion

    number of calendar months

    number of weeks from the date of commencement within which the

    works should be completed.

    The reasons for delay in completion of the works are categorized

    as delays attributable to i) Principal ii) Contractor iii) Neither

  • i) DELAYS ATTRIBUTABLE TO THE PRINCIPAL

    These include the following:-

    1. Not able to give the possession of whole or part of the site.

    2. Not able to secure mandatory clearances from the relevant

    government authorities.

    3. Delay in supplying drawings, designs, specifications, etc,

    4. Delay in issuing materials agreed to be supplied by principal

    as per schedule A of the contract.

  • 5. Delays due to extra items of work or variations in quantities of

    the items of work, beyond specified limits.

    6. Delay in checking contractors work and giving the clearance

    to proceed with the work.

    7. Temporary suspension of the work by the principal.

    8. Delay due to other contractors work.

    Contd..

  • Most contracts presume that such delays will be within

    reasonable and tolerable limits. Hence, do not provide for any

    compensation to be payable to the contactor for delays that are

    attributable to the Principal. Only time extensions as required

    will be granted.

    However, if there is a delay beyond reasonable tolerable limits

    then it constitutes a fundamental breach by the principal and at

    the option of the contractor, the contract can be terminated. He

    can then, even, file a claim for a suitable compensation also.

    Contd

  • A few contracts do provide for compensation to be payable to

    the contractor for delays attributable to the Principal which are

    beyond the specified limit. The compensation payable will be

    based on the estimate of contractors loss due to idle men and

    equipment.

    Contd

  • ii) DELAYS ATTRIBUTABLE TO CONTRACTOR

    These include in addition to contractors own defaults, labour

    strikes / disputes, bad weather, delays due to transportation, non-

    availability of materials, laborers, etc.

    In order that the contractor makes sincere efforts to minimize

    such delays all contracts usually provide for the compensation to

    be paid to the owner for delay in completion of the works due to the

    reasons attributable to the contractor. Such a compensation which

    is deductible from contractors bill is termed as Liquidated

    Damages.( L.D.)

  • A maximum limit for L.D. is specified in the contracts

    usually 10% to 15% of the total contract value and if

    L.D. reaches this limit, it constitutes a fundamental

    breach by the contractor and at the option of the

    principal, the contract can be terminated (termination is

    not mandatory or automatic)

    Contd

  • iii) DELAYS ATTRIBUTABLE TO NEITHER

    these include natural calamities, earthquake, massive landslides,

    Acts of Government, Acts of Terrorism, wars, prolonged General

    Strikes.

    In all three cases, where delay is within acceptable limits, a

    reasonable extension of time for completion as assessed by the

    Engineer In-Charge will be provided and then time extension has

    to be got approved by the Engineer-in-charge from the competent

    authority of the Principal.

  • Delays beyond acceptable limits attributable to the Principal/

    Contractor constitute a fundamental breach of the contract.

    Delays beyond acceptable limits attributable to neither

    constitute a Force Majeure / Frustration.

    Contd

  • CLAIMS FOR EXTRAS/ VARIATIONS

    Settlement of claims for extras / variations

    Engineer-in-charge has the power to make additions, deletions,

    alterations to the original B.O.Q such changes would not invalidate the

    contract. However , this power usually has the following limitations:-

    i) the variation in quantities of individual items of the work are

    permitted up to a limit specified in the contract. ( generally, 25% to

    30% of the quantity included in the B.O.Q)

    ii) if variations in quantities of individual items of work exceed above

    defined limits then it will be treated like an extra item of work.

  • iii) the total variation in the contract value due to variations in

    quantities or extra items/ deletions shall be limited to 15% to

    20% of the original contract value, as awarded.

    If variations, extra items and deletions exceed the limits specified

    as above then the contractor can refuse to execute such

    variations, extra items or deletions.

    Contd

  • PROCEDURES FOR FIXING RATES OF EXTRA ITEMS OF WORK

    1st preference:- the rate is derived from any similar or allied

    item in the contract document with suitable modifications for

    rates of materials and (or) labour as decided by the Engineer-

    in-charge.

    2nd preference:- where no such similar/allied item of work

    exists in the contract document the rate shall be derived from

    the latest available CPWD schedule of rates ( to be specified in

    the contract document) with suitable modifications for

    escalations and contractors overheads profits.

  • 3rd preference:- if the rates are not available in CPWD

    schedule also, then , the rates should be derived from

    accepted norms of rate analysis based on the market

    rates for materials and labour with a provision of about

    15% to 25% towards contractors overheads profit.

    The rates as fixed from any of the above methods shall

    be agreed upon between Engineer-in-charge and the

    contractor before the commencement of such items of

    work.

  • The rates and quantity of such items of work shall be got approved

    from competent authority of the Principal.

    If there is disagreement over the rates between the Engineer-in-

    charge and the contractor then the matter will have to be settled

    through the dispute settlement process specified in the contract.

    Pending the approval of rates by the competent authority of the

    Principal / settlement of the rates by the dispute settlement process ,

    payment can be made to the contractor as an advance , by taking a rate

    equivalent to 75% to 90% of the proposed rate.

    In order to avoid disagreements over the rates, sometimes, the

    tenderers are asked to quote their rates, at the time of tendering

    itself for anticipated extra items of work and for those items of work

    where quantities are likely to vary beyond specified limits.

  • SETTLEMENT OF CLAIMS FOR COST ESCALATIONS

    The price adjustments for escalations in costs, when provided for

    in contracts, will be governed by the following conditions:-

    i) the materials covered in schedule A, which are issued by the

    principal, shall be excluded from the scope of price adjustments for

    escalations as these would be issued at a fixed price.

    ii) the price adjustment shall be done from the date indicated in the

    contract document.(usually date of submission of bid or date of

    award of contract)

  • iii) the price adjustments will be provided up to date of

    completion, initially specified in the contract or such

    extended period of time as sanctioned for reasons not

    attributable to the contractor.

    iv) price adjustments shall be determined for each quarterly

    or monthly running bill as per, the procedure and based on

    indices, specified in the contract documents.

    v) price adjustments shall be given to the extent of 75% to

    85% of the escalation in costs.

  • PRICE ADJUSTMENT PROCEDURE:-

    Price adjustment shall be calculated separately for the cost of

    labour, cement, POL(petroleum, oil and lubricants) and other

    materials. They are then added up to arrive at the escalations in

    costs which have to be paid.

  • ADJUSTMENTS FOR LABOUR COMPONENT:-

    VL= { K *( PLR/100)} * { (L1 L0)/L0}

    K= Allowable escalation factor (0.75 to 0.85 usually)

    PL = Percentage of cost due to labour

    R = quantity of work done in the billing period.

    L1 = labour index on 28 days prior to billing date

    L0 = labour index on base date/ reference date.

    VL = variation cost due to labour.

    CPI Consumer price index

    MLW Minimum labour wage.

  • Files and Records:

    The following is a list of some of the typical files and records that many

    become necessary for a major civil engg, construction contract .

    A. Contract Document with all its amendments/ modifications.

    Amendments/ modifications to drawing, designs, specifications, BOQ.

    Construction progress

    Minutes of meeting between the principal and contractor

    Record of staff, labor, equipment, etc., deployed at the site by the contractor.

    Record of instructions given to the contractor.

  • B. Field office files and records:

    Correspondence with consultants, H.O, supplies,

    statutory bodies, govt. authorities etc.

    Samples of approved materials, suppliers warranties.

    Manufacturers certificates for pre-fabricated items,

    equipment's etc.

    Reports at operation tests, field investigations.

    Documentation of measure of safety, hazard warnings.

    Inspection reports of statutory authorities.

  • C. Construction files and records:

    Work progress reports

    Reports of quality check/ measurements

    Concrete batch plant reports (for critical works)

    Contractors submission for claims, records of its processing

    D. Miscellaneous files and records:

    Labour welfare standards review records

    Job conferences

    Construction photographs/ video-graphs

    Records of dignitaries and other visitors to the site, their

    impressions

  • Social Responsibilities/ obligations Statutory requirements

    Social responsibilities/ obligationgs

    Joint responsibility

    Some of the commonly required facilities/ measures for a large project in a remote area

    are listed below, and the responsibilities of the Principal, Contractors for their provision

    are discussed.

    1. Approach Roads:

    The main approach road to the site and the major roads within the site which are

    likely to be used by many contractors are constructed and maintained by the

    Principal.

    The subsidiary(or internal) roads within the contractors work area and from the

    colonies of the contractors personal, his stores, offices etc., are constructed and

    maintained by the contractor.

  • 2. Housing and Sanitation:

    These include houses for staff, labour, colonies, site offices, stores etc.,

    These facilities are to be provided by the contractor for his staff and

    labour and by the principal for his personnel.

    A few houses and office's constructed by the principal may be made

    available temporarily to the contractor in the initial period on agreed

    charges.

    Provision may be made in the contract to take back a specific number

    of houses, officies, stores etc., built and used by the contractor at

    depreciated cost at the end of the contract period.

    Such aspects should be considered in the planning of infrastructural

    facilities for the project and they have to be clearly specified in the

    special conditions of the contract (SCC)

  • 3. Power and water Supply:

    Arrangements must be made by the principal for taking off power and water by the contractor from within a reasonable distance (usually 1 or 2km ) from his work place.

    From the designated taken points further distribution and it maintenance is the responsibility of the contractor.

    The contractor should also make arrangements for maintaining proper voltage, standby generator, water storage and its pumping to take care of disruption in supplies. The contractor cannot claim any compensation or extension of time for disruption of time for disruption in power or water supplies.

    The designated points of take off of power and water should be clearly identified and specified in the SCC.

  • 4. POL supply, Banking and communication facilities:

    The communication facilities include post, telegraph, wireless, telephone etc.,

    POL supply, banking, and communication facilities must be ensured at the

    project site by the principal.

    Contractor can avail these facilities by paying the applicable user charges.

    5. Medical, Educational shopping facilities and entertainment:

    The basic minimum facilities in respect to these have to be made available at

    the project area by the principal.

    Tender documents should clearly indicate the provision made with regard to

    these facilities and its applicable usage charges, their location, transport

    arrangements that are made available.

  • 6. Law and order, security arrangements:

    It is the general obligation of the state and central government to

    provide general security, maintain law and order.

    The principal has to interact with the government authorities to

    ensure the law and order and security arrangements are set up at

    the site. The costs involved in providing the required facilities in

    respect of these have to be taken care by the principal.

    However, the security and maintainance of works under the

    contract, materials, plant and equipments etc., is the

    responsibility of the contractor.