CONTEXT AANBESTEDINGEN BETUWEROUTE EN HSL-ZUID
description
Transcript of CONTEXT AANBESTEDINGEN BETUWEROUTE EN HSL-ZUID
CONTEXT AANBESTEDINGENBETUWEROUTE EN HSL-ZUID
Ir. L.C. BOUTER
25 oktober 2005
• TIJDSBALK
• KARAKTERISTIEK
• OMGEVING
• ONTVLECHTING NEDERLANDSE SPOORWEGEN
• ONTWERP BENADERING
• CONTRACTERING HSL-ZUID
• CONTRACTEN HSL-ZUID
• CONTRACTERING BETUWEROUTE
• KALENDER CONTRACTERING
• FINANCIËN
• BUDGET ONTWIKKELING
TIJDSBALK
- HSL-ZUID
BESLUITVORMING: 70’er jaren TB 1998
BOUWPERIODE: 2000 april 2007
- BETUWEROUTE
BESLUITVORMING: 80’er jaren TB 1996BOUWPERIODE: 1998 dec. 2006
KARAKTERISTIEK
- HSL-ZUID - VERVOERSPROJECT
- INZET OP PRIVATISERING
- BETUWEROUTE- INFRA PROJECT
- TRADITIONELE AANPAK
OMGEVING
- BETUWEROUTE EN HSL-ZUID- TALRIJKE VERGUNNINGEN
- VELE BESTUURSORGANEN
- VEEL DOSSIERS GRONDVERWERVING
- WELSTANDSCOMMISSIES
- BETUWEROUTE- TIJDENS BOUW VOORTGEZETTE
DISCUSSIES OVER “NUT EN NOODZAAK”
ONTVLECHTING NEDERLANDSE SPOORWEGEN
- TOT 1995INFRASTRUCTUUR EN VERVOER EXLUSIEF BIJ NS
- NA 1995- INFRASTRUCTUUR BIJ NS RAILINFRABEHEER (NS-RIB)- VERVOER BIJ NS REIZIGERS (NIET MEER EXCLUSIEF)
- 2003UITPLAATSING NS-RIB (PRORAIL) UIT NS HOLDING NAAR HET RIJK (MINISTERIE V&W)
ONTWERP BENADERING
- HSL-ZUIDSPOORLIJN IN DOORGAANDE “GEÏNTEGREERDE”
BAK MET MOOI PROFIEL
- BETUWEROUTEVANUIT TRADITIONELE SPOORBOUW
CONTRACTERING HSL-ZUID
- ZWAAR STEMPEL PRIVATISERING
- EMBRYONAAL IDEE: ÉÉN CONTRACT MET VERVOERDER
- GEKOZEN VOORD&C VOOR DE ONDERBOUWDBFM VOOR DE BOVENBOUWCONCESSIE VOOR HET VERVOER
- NAAST AANLEG OOK ONDERHOUD EN VERVOERSDIENSTEN GECONTRACTEERD
CONTRACTEN HSL-ZUID
- ONDERHANDELING CONTRACTEN ONDERBOUW
prijs aanbieding risico’s opdrachtgever
- CONTRACT INFRASPEED VOLGENS ANGELSAKSICHS MODEL NAAR NEDERLANDS RECHT (SIC!)
CONTRACTERING BETUWEROUTE
• TRADITIONELE BENADERING
• ALLEEN AANLEG
• DEELS NIEUWE CONTRACTEN (E&C; ALLIANTIE)
• “STAP VOOR STAP” WERKEND VANUIT ONDERBOUW NAAR BOVENBOUW
• DE ZIN VAN EEN DBFM-CONTRACT VOOR BOVENBOUW ONDERZOCHT LOPENDE DE UITVOERING V/D ONDERBOUW(DBFM DBM D&C E&C RAW)
KALENDER CONTRACTERING
- HSL-ZUID- GECONCENTREERD IN PERIODE VANAF 1998 TOT BEGIN 2001
- GEPLANDE OPLEVERING IN APRIL 2007 HARD
- BETUWEROUTE- VANAF 1996 “STAP VOOR STAP” TOT IN 2004
- GEPLANDE OPLEVERING IN DECEMBER 2006 (AANVANKE-LIJK IN JULI 2005)
FINANCIËN
- SPANNING: GERESERVEERD BUDGET VS WERKELIJKE KOSTEN
- BUDGET IN RIJKSBEGROTING TEN TIJDE VAN TB OP BASIS VAN 50% VERWACHTINGSWAARDE
- 20% ONZEKERHEIDSMARGE IVM TEGENVALLERS EN RISICO’S IN DE UITVOERING NIET GEBUDGETTEERD
BUDGET ONTWIKKELING
- BUDGET ONTWIKKELING IN DE BELEIDSFASE VEEL GROTER DAN IN DE UITVOERINGSFASE (WIJZIGING SCOPE PROJECTOPDRACHT)
- SCOPE WIJZIGINGEN TIJDENS DE UITVOERING ZIJN RELATIEF DUUR
- BOVENDIEN: OVERGROTE DEEL BUDGETSTIJGING IS HET GEVOLG VAN SCOPE WIJZIGINGEN
- FORS DEEL KOSTENSTIJGING IS GEVOLG VAN INFLATIE (INDEX)
- KOSTENSTIJGING DOOR TEGENVALLERS EN RISICO’S IN DE UITVOERING BLEVEN BINNEN 20% ONZEKERHEIDSMARGE