Contents...Contents: Previous Co-operation with the Japanese Companies Recent available Co-operation...
Transcript of Contents...Contents: Previous Co-operation with the Japanese Companies Recent available Co-operation...
Contents:
Previous Co-operation with the Japanese Companies
Recent available Co-operation Opportunities in energy
Sector Power Projects.
1
3
2
Introduction & Egyptian Power sector key parameters.
4
Recent Energy Challenges for the Egyptian Power sector.
5
Initiatives of the Egyptian Power sector to meet energy
challenges
The electricity and energy sectors plays a vital role in
the economical growth to secure adequate electricity
supplies at minimum cost to all consumers with the
international standards. During the last decade, a
rapid increase of electricity demand occurred, the
electricity sector has grown rapidly trying to meet
this increase.
Introduction & Egyptian Power sector
key parameters.
% MW Type
33 11830.5 Combined Cycle
45 13843.5 Steam Cycle
11 3504 Gas turbine
9 2842.5 Hydro
2 547 Renewables
100 32708 Total
Installed Capacity (MW)
Introduction & Egyptian Power sector
key parameters.
Recent Challenges for the Egyptian Power sector
From the year 2012, The electricity sector has faced
the following challenges:
1) High increase in the electrical loads in an unmatched
way, where the maximum load growth rate in 2012 rate
of 10.3% compared to the average past growth rate,
which ranged from 4.3% to 8%.
2) Significant shortage in the natural gas supplies by the
year 2012.
Recent Challenges for the Egyptian Power sector
3) Necessity of Restructuring electricity tariff as the selling
price was less than 50% of the production cost.
4) Significant shortage in the natural gas supplies by the
year 2012.
5) Lack of funds needed for new power projects.
6) The low efficiency in some power plants due to:
a- Ongoing initiative for Existing assets & power sector regulations.
b- Private Sector Partnership.
c- Changing the energy generation mix.
The Egyptian Electricity sector seeks to face the previous
stated challenges through the following:
Initiatives
Initiatives
Ongoing initiative for Existing assets & power sector
regulations.
•Existing Generation assets:
Launching a program to optimize operation and
maintenance of GTs & CCGT and steam turbine.
•Power sector regulations:
Review tariff system.
Assess potential impact from DSM measures.
a- Ongoing initiative for Existing assets & power sector regulations.
b- Private Sector Partnership.
c- Changing the energy generation mix.
The Egyptian Electricity sector seeks to face the previous
stated challenges through the following:
Initiatives
The Egyptian government and the electricity sector recognized the
importance of private sector partnership to improve all production
processes and to minimize the investment cost burden.
Gradual subsidies removal over the next five years by designing a
new electricity tariff structure.
Issuing a Feed-In-Tariff for renewable energy trading.
Repairing the new low of electricity (expected to be issued soon).
Initiating the gradual liberalization of the electricity market.
Initiatives for Private sector
b- Private sector Partnership
An area of about 7845 km2 on the Gulf of Suez region and
the Nile Banks has been allocated for NREA for
implementing wind energy projects, Permitted lands are
provided to Investors through Land Use agreement
against 2% of annual generated Energy from the project
or its value.
One window (dealing with one central services unit in the
ministry of electricity and renewable energy).
Bankable PPA (Power Purchase agreement)
Government sovereign Guarantees.
Initiatives for Private sector for
Renewable Energy
(2%) Custom duties for all renewable system
components.
Lower interest rates for Solar project less than 500 KW &
roof top units.
Assessment of environmental impact, including bird
migration.
Investors will benefit from selling Certified Emission
Reductions, CERs, resulted from the implemented
project.
Initiatives for Private sector for
Renewable Energy
Feed In Tariff for PV Power Plant
Residential 84.8 PT / KWh
Other than residential and up to 200 KW 90.1 PT / KWh
From 200 Kw up to 500 KW 97.3 PT / KWh
Installation connected to the low voltage:
from 500 Kw up to 20 MW 97.3 PT/ KWh
Installation connected to the medium voltage
Installation connected to the medium voltage
From 20 Mw up to 50 Mw 102.5 PT/ KWh
Incentives for Renewable Energy
Wind Energy Feed in Tariff Operational Hours Second Stage FiT First Stage FiT
pt / kwhr $ cent / kwhr pt / kwhr $ cent / kwhr
82.08 11.48
82.08 11.48
2500
75.053 10.56 2600
69.46 9.71 2700
63.83 8.93 2800
58.58 8.19 2900
53.68 7.51 3000
63.82 8.93
68.4 9.57
3100
59.53 8.33 3200
55.49 7.76 3300
51.7 7.23 3400
48.12 6.73 3500
44.73 6.26 3600
41.54 5.81 3700
38.51 5.39 3800
35.58 4.98 3900
32.9 4.6 4000
Incentives for Renewable Energy
The Private Sector Investors have taken part in
implementing Generation Power Plants in the
Egyptian power sector through three basic contract
Scheme:
•(BOO or BOOT) schemes
•IPP scheme
Recently, the Egyptian electricity sector encourages
the private sector partnership through the (EPC +
Finance) scheme.
b- Private sector Partnership
b- Private Sector partnership
Initiatives
Already signed agreements with private investors in power
plants Projects
Already signed agreements with private investors in power plants Projects:
Frame Work Agreement
Power Purchase Agreements
Memorandum of Understanding
Accessibility Land Agreements - FIT
b- Private sector Partnership
Framework
Agreements MOU
Power Purchase
Agreements
Agreement Parities
Constructing (3200 Mw) Coal Power Plant
(in El-Hamrawain) Site
Party (1): EEHC
Party(2): Orascom/IPIC Consortium
Constructing (6 × 660 Mw) Coal Power
Plant
Party (1): EEHC
Party(2): Dong Fang (DEC)
Smart Meters Party (1): EEHC
Party(2): Huawei
Constructing (2100 Mw) Pump storage
power plant in (Ataqqa) site
Party (1): HPPEA
Party(2): Sinohydro Corporation Ltd.
Accessibility Land
Agreements
Already signed agreements with private investors in power plants Projects:
b- Private sector Partnership
Agreement Parities
Constructing (4640 Mw) Coal Fired
Power Plant
Party (1): EEHC
Party(2): Shanghai Electric
Transmission System Development Party (1): EEHC
Party(2): State Grid
Framework
Agreements MOU
Power Purchase
Agreements Accessibility Land
Agreements
Already signed agreements with private investors in power plants Projects:
b- Private sector Partnership
Agreement Parities
Power Purchase Agreement from
(2640 Mw) Coal Power Plant in
(Eyoun Mousa) site
Party (1): EEHC
Party(2): Nowise
Power Purchase Agreement from
(2300 Mw) Metoubas Power Plant in
(Kafr El-Shiehk) site
Party (1): EEHC
Party(2): Benchmark
Framework
Agreements MOU
Power Purchase
Agreements Accessibility Land
Agreements
Already signed agreements with private investors in power plants Projects:
b- Private sector Partnership
Agreement Parities
Conversion of (Assuit) & (West Dumyat) to be
worked as (750 Mw) CCGT
Party (1): EEHC
Party(2): General Electric/Orascom
consortium
Implementing (5 Billion) Projects: • (3000 Mw) Solar power plant as (600 Mw)
each 5 yrs. • Providing a part of project profits for
development & training on solar power projects (519 M$)
Party (1): EETC Party(2): Sky power/Gulf development consortium
Constructing (2000 Mw) solar power plant
Party (1): EETC
Party(2): Sky power/Gulf development
consortium
Framework
Agreements MOU
Power Purchase
Agreements Accessibility Land
Agreements
Already signed agreements with private investors in power plants Projects:
b- Private sector Partnership
Agreement Parities
Constructing (2000 Mw) Projects based on
(BOO) or (EPC+Finance) in addition to
implementing a human development
programs for training, learning& qualifying.
Party (1): EETC
Party(2): Tera Nex/Tera Sola Consortium
•Constructing (2200 Mw) CCGT in (West Dumyat) site.
•Constructing (1500 Mw) solar power plant •Constructing (200 Mw) Wind power plant
Party (1): EEHC
Party(2): Acwa power/Masder Consortium
Framework
Agreements MOU
Power Purchase
Agreements Accessibility Land
Agreements
Already signed agreements with private investors in power plants Projects:
b- Private sector Partnership
Agreement Parities
Constructing (6000 Mw) Coal power
plant
Party (1): EEHC
Party(2): Tharwa investment
company
Constructing (2000 Mw to 4000 Mw) Coal power plant in (Safaga) Site
Party (1): EEHC
Party(2): Acwa power
Framework
agreements MOU
Power Purchase
agreements Accessibility Land
Agreements
Already signed agreements with private investors in power plants Projects:
b- Private sector Partnership
List of Chinese companies signed MOUs with the ministry of electricity
Harbin Electric Group
AVIC International Holding Company
China Gezhouba Group Corporation CGGC
China Machinery Engineering Corporation
Dong Fang Electric Group
Huawei North Africa Region
Huawei Technologies Co.Ltd
Shanghai Electric Company
Sinohydro Corporation Ltd
State Grid Corp of China
Framework
agreements MOU
Power Purchase
agreements Accessibility Land
Agreements
Already signed agreements with private investors in power plants Projects:
b- Private sector Partnership
Agreement Parities
4 Entry permit
MOUs to some pieces of NREA land
owned in Aswan for executing the
required necessary studies and
measurements for constructing (200
Mw) solar power plants according to
(FIT) contracting model
Part (1): NREA
Parties:
(50 MW) O-capital Company
(50 Mw) FAS Company
(50 Mw) Philadelphia Company
(50 Mw) Static Company
Framework
agreements MOU
Power Purchase
agreements Accessibility Land
Agreements
Already signed agreements with private investors in power plants Projects:
b- Private sector Partnership
a- Ongoing initiative for Existing assets & power sector regulations.
b- Private Sector Partnership.
c- Changing the energy generation mix.
The Egyptian Electricity sector seeks to face the previous
stated challenges through the following:
Initiatives
Meeting the future electricity demand requires
diversification of the energy mix by including the new
generation technologies (such as clean coal, nuclear and
renewable energy), with taking into consideration choosing
the best generation mix taking into consideration the
optimum:
Technological aspects.
Environmental aspects.
Economical and social dimensions.
The current and expected situation of electricity demand
and peak load and generated energy.
c- Changing the energy Generation mix
In that framework, The importance of coal utilization in
power generation appears as an alternative to natural gas
power plants due to the following:
• The Prediction of resuming the insufficient local
quantities of natural gas to cover the future load
demand.
• The economic competitiveness of coal with comparing
the recent and future predicted exportation prices of
coal and natural gas.
Recent Situation Of Coal utilization in Egyptian power sector:
c- Changing the energy Generation mix
NO Project Name Contractor/
Consortium Task
Contract
date
contract
(Million
US$)
1 Cairo West Steam
Units “5 & 6”
(2 × 320 MW)
Maroubiny Company Steam Boilers 1999 77.8
2 Cairo North (1)
CCGT (750 MW)
Mitsubishi for heavy
industries/Toyota Tosusho Gas Turbines 2002 115.1
Hitachi /Somotomo Transformers 2002 6.7
Hitachi /Somotomo Steam Turbines 2009 34.8
3
Noubaria
(1 & 2) – CCGT
(1500MW)
Mitsubishi for heavy
industries/Toyota Tosusho Steam Turbines 2003 61
AE for energy systems/
Somotomo/ the Egyptian
Company ” Consis”
Switch yard
(500KV) 2003 52.5
Previous Co-operation with Japanese Companies
41
NO Project Name Contractor/
Consortium Task
Contract
date
contract
(Million
US$)
4
Kurimat (2) –
CCGT
(750 MW)
Hitachi /Somotomo Steam Turbines 2005 20.35
5
Cairo North (1)
CCGT
(750 MW)
Mitsubishi for heavy
industries/Toyota Tosusho Gas Turbines 2007 103.4
Toyota Tosusho/Toshiba Mechanical
works 2008 37.4
Ibara Koryorition/Ibara
yusheKora Hydrotech
Pumps and their
accessories 2008 13.5
Toyota Tosusho/Toshiba Electrical works 2008 16
Previous Co-operation with Japanese Companies
NO Project Name Contractor/
Consortium Task
Contract
date
contract
(Million
US$)
6 El Atf– CCGT
(750 MW)
Mitsubishi for heavy
industries/Toyota
Tosusho
Gas Turbines 2007 104
Toyota Tosusho/Toshiba Mechanical
works 2008 43.5
Ibara Koryorition/Ibara
yusheKora Hydrotech
Pumps and
their
accessories
2008 12.4
Toyota Tosusho/Toshiba Electrical
works 2008 16.5
Previous Co-operation with Japanese Companies
NO Project Name Contractor/
Consortium Task
Contract
date
contract
(Million
US$)
7
Cairo West
Steam Units
“7 & 8”
(2 × 350 MW)
Mitsubishi for heavy
industries/Toyota Tosusho
Steam
Turbines 2007 99.9
Hitachi /Somotomo Steam Boilers 2007 174.4
8 Abo Qir Steam
(2× 650 MW)
Mitsubishi for heavy
industries/Toyota Tosusho
Steam
Turbines 2009 318.1
9
Ain Sokhna
Steam
(2× 650 MW)
Hitachi /Somotomo Steam
Turbines 2009 301.3
Hitachi Pumps 2010 40
10 Banha CCGT
(750MW) Hitachi / Toyota Tosusho
Mechanical
works 2012 27.2
Previous Co-operation with Japanese Companies
NO Project Name Contractor/
Consortium Task
Contract
date
contract
(Million
US$)
11 Suez steam
(650MW) Hitachi Pumps 2013 20.8
12
South Helwan
steam
(3× 650 MW)
Mitsubishi for heavy
industries/Toyota
Tosusho
Steam
Turbines 2014 289.1
Previous Co-operation with Japanese Companies
Recent Co-operation Opportunities in Power Projects
a- Conventional Thermal power plants
b- Coal Fired thermal Power plants
Power Plant Installed
Capacity (MW)
Process
number Expected Tendering date
Cairo West Steam 1 × 650 Mw 18 Start: 1st half 2015
Closing: June 2016
Assuit Steam P.P 1 × 650 Mw 17 Start: 1st half 2015
Closing: June 2016
Damanhur CCGT 1 × 900 Mw 19 Start : last quarter of 2015
Closing: end of 2016
MHI participate in the (Suif) site tender among 14 other investor
a- Conventional Thermal power plants
EEHC Multi-Packages Tenders
EPC + Finance
Gas Units Conversion to CCGT to face Summer 2015 loads
Power Plant Installed Capacity
(MW)
Commissioning date of gas
units
Assuit 8 × 125 Mw
Units (1,2,3) in 31/5/2015
Units (4,5,6) in 30/6/2015
Units (7,8) in 31/8/2015
West Damietta 4 × 125 Mw Units (1,2) in 30/6/2015
Units (4,3) in 31/7/2015
El-Mahmoudia 2 × 160 Mw Unit (1) in 31/7/2015
Unit (2) in 8/8/2015
a- Conventional Thermal power plants
Power Plant Installed Capacity
(MW)
Commissioning date of
gas units
Ataqa 4 × 160 Mw
Unit (1) in 31/5/2015
Unit (2) in 8/6/2015
Unit (3) in 16/6/2015
Unit (4) in 1/7/2015
Sharm El-sheikh 6 × 48 Mw
5 /2015 Hurghada 6 × 48 Mw
a- Conventional Thermal power plants
Gas Units Conversion to CCGT to face Summer 2015 loads
b- Coal fired Thermal Power Plants
Recent MOU signed with Chinese companies for Coal power plants implementation
Coal power plants to be financed by EXIM- Bank
Coal power plants to built through BOO or Boot Model
b- Coal fired Thermal Power Plants
Company Name Project
Capacity Budget
(Billion USD)
AVIC 1320 MW 2
Shanghai Electric
Corporation & Shanghai
Electric Power
2640 Mw 4
Dong Fang 1320 Mw 2
NWPC 1320 Mw 2
Coal power plants to built through Chinese private sector investors under (EPC + Finance) scheme.
b- Coal fired Thermal Power Plants
Coal power plants to built through Chinese private sector investors under (EPC + Finance) scheme.
Company Name Project
Capacity Budget
(Billion USD)
CGGC 1320 MW 2
CMEC 1320 Mw 2
Harbin 1320 Mw 2
AVIC 1320 Mw 2
Sino-Hydro 1320 Mw 2
b- Coal fired Thermal Power Plants
Recent Candidate sites for Coal power plants implementation
Coal power plants to be financed by EXIM- Bank
Coal power plants to built through BOO or Boot Model
Company Name Project
Capacity
Budget
(Billion USD)
AVIC 1320 MW 2
Shanghai Electric
Corporation & Shanghai
Electric Power
2640 Mw 4
Dong Fang 1320 Mw 2
NWPC 1320 Mw 2
b- Coal fired Thermal Power Plants
Coal power plants to be financed by EXIM- Bank
b- Coal fired Thermal Power Plants
Recent Candidate sites for Coal power plants implementation
Coal power plants to be financed by EXIM- Bank
Coal power plants to built through BOO or Boot Model
Company Name Project
Capacity
Budget
(Billion USD)
CGGC 1320 MW 2
Shanghai Electric Corporation & Shanghai
Electric Power 2000 Mw 3.5
CMEC 1320 Mw 2
Harbin 1320 Mw 2
AVIC 1320 Mw 2
Sino-Hydro 1320 Mw 2
b- Coal fired Thermal Power Plants
Coal power plants to built through BOO or Boot Model
In the Light of the previous, the Japanese Side is invited to
co-operate with the Egyptian side in the field of
implementing coal power plants according to the following
suggested steps:
1) Sign MOU between the two parties includes providing the
Egyptian side with a preliminary technical and
economical feasibility study carried out by the Japanese
side as EPC + finance.
2) Signing an (EPC + Finance) contract between parties in
the light of preliminary feasibility study results.
Fruitful expected Egyptian – Japanese co-
operation framework
In the frame work of the continuous co-operation between the
Japanese and the Egyptian sides specially in the energy sector
with the most advanced and efficient technologies, And with
taking into consideration that the coal power plants are one of
the most essential promoted projects decided to be established
in Egypt. It is expected that the Japanese side continue its
effective support to the Egyptian side in different energy
projects specially the coal fired thermal power plants.
Fruitful expected Egyptian – Japanese co-
operation framework
a- Conventional Thermal power plants
Attaqa
Sharm Elsheik
Hurghada
West Domiaata El Mahmoudia
Assuit