Construction Update 07-28-2010
-
Upload
kansas-city-wizards -
Category
Documents
-
view
1.030 -
download
0
Transcript of Construction Update 07-28-2010
Building the Future
Current Activities this Week:
Mass Excavation:
Backfilling of on-grade seating is ongoing in Area 2
and Area 3.
Site Utilities:
Storm Sewer Installation (Line 6000) is ongoing
on the east side of France Family Drive.
Foundations:
Area 3 Field Level – Foundation installation continues on
the east side of the site.
Concrete Flatwork:
Area 1 – Slab-on-grade is placed at field level from
Column line 25-23. Slab-on grade for player’s field
Entrance is placed. “Ribbon” slab is placed over precast
Seating tubs on Suite Level.
Structural Steel Erection:
Area 1 – Main Canopy Truss Erection is ongoing (Seq 1-8)
Area 2 – Decking is being installed Sequence 2-1 is
ongoing. Area 3 – Structural Steel Erection Sequence
3-1 is nearly complete.
Underground MEP:
Electrical Secondary Distribution is ongoing in Areas 2.
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 7.28.2010
Re: Wizards Stadium Project
Update – Week of
7.26.2010
Area 3 – Installation of Storm Line 6000 is
ongoing on the east side of France Family
Drive.
Suite Level Area 1 – Concrete “Ribbon” Slab
is placed over the precast seating tubs.
Field Level Area 1 – Cast-in-place concrete
riser installation is ongoing at west
elevation. Forming of intermediate stairs
has also started.
Building the Future
MEP Rough-in:
Area 1 – Shallow electrical and plumbing rough-in is
ongoing. Ductwork installation on Suite Level is ongoing.
Plumbing installation is ongoing on Suite Level.
Metal Stud Framing:
Area 1 – Metal stud framing for Suite and Press
Levels are ongoing. Metal stud framing has started on
Main Concourse West Building.
Projected Activities occurring next Week:
Mass Excavation:
Backfilling of on-grade seating areas will continue in Area
3. Grading in Area 3 (east of A-Line) will continue.
Site Utilities:
Installation of the Storm Line 6000 on the East Side (France
Family Drive) of the site will be complete. Sanitary Sewer
installation will begin at locations where Storm Line 6000
is complete.
Deep Underground MEP:
Deep Electrical Distribution installation will start again
in Area 3.
Foundations:
Area 3 Field Level – Foundation installation will continue.
Concrete Flatwork:
Area 2 Field Level – Concrete placement for Slab-on-Grade
will be completed to Column Line 14.
Area 1 Field Level – Installation of on-grade seating risers
will continue.
Structural Steel Erection:
Erection of Structural Steel in Sequence 3-2 will
begin. Decking installation will begin in Steel Sequence
3-1.
Area 1 – Shot of the West Building from the
North East corner of the Project Site.
Press Level Area 1 – Metal stud framing is
ongoing.
Field Level Area 3 – Steel Erection is nearly
complete. Rakers are currently being set.
Building the Future
Erection of the Canopy Trusses will continue in
Sequence 1-8.
Underground MEP:
Electrical Secondary will continue in Area 3.
MEP Rough-in:
Plumbing and Electrical rough-in for Area 1/2 Field Level slab
on grade will continue. MEP Rough-in at Suite Level will
continue.
Metal Stud Framing:
Area 1 – Metal stud framing for Concourse, Suite and Press
Levels will continue.
Area 1 – Shot of “Wing” at Roof Canopy
being installed.
Suite Level Area 1 – Metal Stud Framing and
Ductwork installation is ongoing.
Building the Future
Additional Photos:
Area 1 – Installation of formwork for
intermediate stairs.
Suite Level Area 1 – In wall plumbing rough-
in has started.
Field Level Area 1 – Player Field Entrance
Vomitory slab prepped for concrete.
Field Level Area 1 – Slab-on-Grade placed
and being finished from Column Lines 25-23.
Area 3 – Backfill of east side on-grade
seating is ongoing.
Area 1 – Caulking of precast risers is
ongoing.