Construction Update 07-28-2010

4
Building the Future Current Activities this Week : Mass Excavation : Backfilling of on-grade seating is ongoing in Area 2 and Area 3. Site Utilities : Storm Sewer Installation (Line 6000) is ongoing on the east side of France Family Drive. Foundations : Area 3 Field Level – Foundation installation continues on the east side of the site. Concrete Flatwork : Area 1 – Slab-on-grade is placed at field level from Column line 25-23. Slab-on grade for player’s field Entrance is placed. “Ribbon” slab is placed over precast Seating tubs on Suite Level. Structural Steel Erection : Area 1 – Main Canopy Truss Erection is ongoing (Seq 1-8) Area 2 – Decking is being installed Sequence 2-1 is ongoing. Area 3 – Structural Steel Erection Sequence 3-1 is nearly complete. Underground MEP : Electrical Secondary Distribution is ongoing in Areas 2. To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner From: Brandon Valdez Office: Kansas City Date: 7.28.2010 Re: Wizards Stadium Project Update – Week of 7.26.2010 Area 3 – Installation of Storm Line 6000 is ongoing on the east side of France Family Drive. Suite Level Area 1 – Concrete “Ribbon” Slab is placed over the precast seating tubs. Field Level Area 1 – Cast-in-place concrete riser installation is ongoing at west elevation. Forming of intermediate stairs has also started.

Transcript of Construction Update 07-28-2010

Page 1: Construction Update 07-28-2010

Building the Future

Current Activities this Week:

Mass Excavation:

Backfilling of on-grade seating is ongoing in Area 2

and Area 3.

Site Utilities:

Storm Sewer Installation (Line 6000) is ongoing

on the east side of France Family Drive.

Foundations:

Area 3 Field Level – Foundation installation continues on

the east side of the site.

Concrete Flatwork:

Area 1 – Slab-on-grade is placed at field level from

Column line 25-23. Slab-on grade for player’s field

Entrance is placed. “Ribbon” slab is placed over precast

Seating tubs on Suite Level.

Structural Steel Erection:

Area 1 – Main Canopy Truss Erection is ongoing (Seq 1-8)

Area 2 – Decking is being installed Sequence 2-1 is

ongoing. Area 3 – Structural Steel Erection Sequence

3-1 is nearly complete.

Underground MEP:

Electrical Secondary Distribution is ongoing in Areas 2.

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

From: Brandon Valdez

Office: Kansas City

Date: 7.28.2010

Re: Wizards Stadium Project

Update – Week of

7.26.2010

Area 3 – Installation of Storm Line 6000 is

ongoing on the east side of France Family

Drive.

Suite Level Area 1 – Concrete “Ribbon” Slab

is placed over the precast seating tubs.

Field Level Area 1 – Cast-in-place concrete

riser installation is ongoing at west

elevation. Forming of intermediate stairs

has also started.

Page 2: Construction Update 07-28-2010

Building the Future

MEP Rough-in:

Area 1 – Shallow electrical and plumbing rough-in is

ongoing. Ductwork installation on Suite Level is ongoing.

Plumbing installation is ongoing on Suite Level.

Metal Stud Framing:

Area 1 – Metal stud framing for Suite and Press

Levels are ongoing. Metal stud framing has started on

Main Concourse West Building.

Projected Activities occurring next Week:

Mass Excavation:

Backfilling of on-grade seating areas will continue in Area

3. Grading in Area 3 (east of A-Line) will continue.

Site Utilities:

Installation of the Storm Line 6000 on the East Side (France

Family Drive) of the site will be complete. Sanitary Sewer

installation will begin at locations where Storm Line 6000

is complete.

Deep Underground MEP:

Deep Electrical Distribution installation will start again

in Area 3.

Foundations:

Area 3 Field Level – Foundation installation will continue.

Concrete Flatwork:

Area 2 Field Level – Concrete placement for Slab-on-Grade

will be completed to Column Line 14.

Area 1 Field Level – Installation of on-grade seating risers

will continue.

Structural Steel Erection:

Erection of Structural Steel in Sequence 3-2 will

begin. Decking installation will begin in Steel Sequence

3-1.

Area 1 – Shot of the West Building from the

North East corner of the Project Site.

Press Level Area 1 – Metal stud framing is

ongoing.

Field Level Area 3 – Steel Erection is nearly

complete. Rakers are currently being set.

Page 3: Construction Update 07-28-2010

Building the Future

Erection of the Canopy Trusses will continue in

Sequence 1-8.

Underground MEP:

Electrical Secondary will continue in Area 3.

MEP Rough-in:

Plumbing and Electrical rough-in for Area 1/2 Field Level slab

on grade will continue. MEP Rough-in at Suite Level will

continue.

Metal Stud Framing:

Area 1 – Metal stud framing for Concourse, Suite and Press

Levels will continue.

Area 1 – Shot of “Wing” at Roof Canopy

being installed.

Suite Level Area 1 – Metal Stud Framing and

Ductwork installation is ongoing.

Page 4: Construction Update 07-28-2010

Building the Future

Additional Photos:

Area 1 – Installation of formwork for

intermediate stairs.

Suite Level Area 1 – In wall plumbing rough-

in has started.

Field Level Area 1 – Player Field Entrance

Vomitory slab prepped for concrete.

Field Level Area 1 – Slab-on-Grade placed

and being finished from Column Lines 25-23.

Area 3 – Backfill of east side on-grade

seating is ongoing.

Area 1 – Caulking of precast risers is

ongoing.