Construction Technology 3 D39 TA

Dr Mohamed Abdel-WahabEdwin Chadwick Building, Room 1.16

[email protected]

Lecture 3: Types of offsite production

Page 2: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.

What are the drivers for offsite production?

Page 3: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.

Lecture Outline

1. Volumetric

2. Panellised construction systems

3. Hybrid construction

4. Sub-assemblies and components

Page 4: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.

Volumetric

Page 5: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.

Can you think of a type of project where it would be crucial to use volumetric construction?

Page 6: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.

Would you live here?!

Page 7: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.

How long did it take to construct Container City 1 and how long it would have taken if constructed the traditional way?

Container City 1

Page 8: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.

What could be the practical considerations for volumetric construction?

Page 9: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.

Volumetric construction: bathroom and kitchen pods

Bathroom in a box

Page 10: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.
Page 11: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.

Practical considerations for volumetric construction (Pods)

Page 12: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.

Summary of Pod cost data

Page 13: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.

Panellised construction systems

Page 14: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.

Types of panels

Open panels

Closed panels

Concrete panels

Page 15: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.

Composite panels

SIPS

Page 17: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.

Can you identify the 11-step process for the manufacturing of OSBs?

Page 18: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.

Advantages of using SIPs

• Pre-assembled from the factory• Three times stronger than conventional stud walls • Allowing for design flexibility• Protection of the insulation material• Using recycled wood chips instead of newly-cut lumber

Page 19: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.

Unitised curtain walling

Page 20: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.

Practical considerations for panellised construction system

Page 21: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.

Hybrid construction

Page 22: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.

Practical considerations for hybrid construction

Page 23: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.

Sub-assemblies and components

Pre-fabricated foundations (e.g. ground beams)

Floor cassettes

Page 24: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.

Roof cassettes

Pre-assembled roof structure

Pre-cast stairs

Page 25: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.

Practical considerations for sub-assembly

Page 26: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.

Summary

1. Volumetric2. Panellised construction systems3. Hybrid construction4. Sub-assemblies and components

Page 27: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.

Suggested resources

Steel framing walls assembly video

Page 28: Construction Technology 3 D39 TA Dr Mohamed Abdel-Wahab Edwin Chadwick Building, Room 1.16 m.abdel-wahab@hw.ac.uk  Lecture.

Go to m.socrative.com

G02

G02