BUILDING TECHNOLOGY 2: Project 2- Working Drawing- Construction Drawing
Construction technology 2
-
Upload
foong-mei-yap -
Category
Education
-
view
161 -
download
0
Transcript of Construction technology 2
What is Secant Piles?
• Formed by constructing overlapping piles to produce a continuous wall.
• They are constructed by either drilling under mud called augering.
• The depth depends on the final design, the soil and appropriate equipment to be used.
• Secant piles are great for permeable grounds with watery conditions.
HOW SECANT PILES
CONSTRUCTED?
• The primary piles (laggings) are installed
first & filled with lean concrete.
• Then, the secondary piles is constructed in
between primary piles formed in structural
concrete.
• Pile overlap is usually 8 cm & the diameter
of each pile typically range from 760mm,
880mm, 1000mm or 1180mm.
PRIMARY SECONDARY
REINFORCEMENT
WITHIN THE PILES
• Secondary piles are usually reinforced with
either steel rebar or steel beams. Its less
common to have both piles reinforced.
• Steel beams are used when it involves the
use of weaker than normal concrete.
Primary/ Lagging piles installation
• Not reinforced
• Uses lean concrete
depending on the
final design.
Secondary/ Closing piles installation
• Secondary piles are reinforced with rebar.
• High strength structural concrete is typically used
• Process is repeated with the secondary piles. Driving
the casing into the ground and augering it .
SUMMARY OF THE PROCESS
1. GUIDE WALL
INSTALLATION
2. CASE
INSTALLATION3. AUGERING &
REINFORCEMENT
4. CONCRETE
SECANT PILES
ADVANTAGES • Increased alignment flexibility in
construction.
• Increased wall stiffness compared to sheet piles.
• Can be installed in difficult ground (cobbles/boulders).
• Produce less noise during construction.
DISADVANTAGES
• Vertical tolerance may be hard to achieve for deep piles.
• Total waterproofing is very difficult to obtain in joints.
• High cost compared to sheet pile walls.