CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams...

51
CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION AND REHABILITATION OF FOUR I-90 DECK ARCH BRIDGES IN SILVER CREEK, NY Statewide Conference on Local Bridges November 6, 2014 Joshua T Rodems EIT Joshua T . Rodems, EIT

Transcript of CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams...

Page 1: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION AND

REHABILITATION OF FOUR I-90 DECK ARCH BRIDGES IN SILVER CREEK, NY

Statewide Conference on Local BridgesNovember 6, 2014

Joshua T Rodems EITJoshua T. Rodems, EIT

Page 2: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Project Background

• 2 Twin span thruway bridges: Silver Creek, NY (Region 5)

• Feature Carried: I-90

• Feature Crossed: Silver Creek and Walnut Creek• Feature Crossed: Silver Creek and Walnut Creek

• Structure Type: Reinforced concrete deck arch with transverse floorbeams, 3 spans: center arch span with 2 approach spans

• Length: 133’-0” clear span (arch), 285’-8” (total)

• Width: 56’-7” out-to-out, 51’-0” curb-to-curb

1

Page 3: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Project Background

• Year Built: 1954

• 1988: Replaced bridge rail with concrete barrier

• 1993: Concrete repairs scupper removal joint• 1993: Concrete repairs, scupper removal, joint

replacement

• Traffic: 2 lanes

O i i l D i Li L d HS 20• Original Design Live Load: HS 20

2

Page 4: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Project Location

3

Page 5: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Project Location

Silver Creek StructuresStructures

Walnut Creek Structures

4

Page 6: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Project Team

• Owner: New York State Thruway Authority (NYSTA)New York State Thruway Authority (NYSTA)

• Engineer:• Engineer: HNTB

• General Contractor: Cold Spring Construction CoCold Spring Construction Co.

• Construction Support Engineer:• Construction Support Engineer: Erdman Anthony

5

Page 7: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Floorbeam Removal

6

Page 8: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Project Background• Last inspected in July 2011

Rating performed by HNTB in April 2012• Rating performed by HNTB in April 2012

• Existing concrete deck rated poorly (HS 13 - 24.7 tons). g p y ( )Replace concrete deck.

• Existing floorbeams act as true T beams Removing deck• Existing floorbeams act as true T-beams. Removing deck slab would compromise compression flange. Replace transverse floorbeams (with precast).transverse floorbeams (with precast).

• Existing spandrel columns and arch satisfactory. Class D t i R l t 4 h tconcrete repairs as necessary. Replace center 4 short

spandrel columns.

7

Page 9: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Damaged Deck Slab

8

Page 10: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Erdman Anthony Scope

• Demolition Calculations

• Erection Procedure with drawings for floorbeams

• Calculations supporting Erection Procedure• Calculations supporting Erection Procedure

• General construction support

• Ensure overall structural integrity

9

Page 11: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Plan

PHASE 2I 90 WB PHASE 2I-90 WB

PHASE 1 I-90 EB

10

Page 12: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Elevation

STAGE 1ARCH SPAN

STAGE 2APPROACH

STAGE 2APPROACH Deck slab andARCH SPAN

SPAN SPANDeck slab and floorbeams to be replaced

Existing arch and spandrel columnsspandrel columns to remain

11

Page 13: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Section – Arch Span

Typical Spandrel

12

yp pColumns

Page 14: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Section – Approach Span

13

Page 15: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Construction Equipment

• Walk-behind diamond blade wet saw

• Caterpillar 304C Excavator

• Caterpillar 328D Excavator• Caterpillar 328D Excavator

• Link-Belt HSL 238 150-ton Crawler Crane (2)

• Liebherr LTM 1200 250-ton Hydraulic Crane

• Grove GMK5275 275-ton Hydraulic Crane

14

Page 16: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Demolition Procedure• Transition all traffic onto single bridge

R b id l• Remove bridge overlay

• Remove concrete barriers

• Deck slab demolition – arch span (symmetrical)

• Floorbeam demolition – arch span

• Erect 12 new arch span floorbeams• Erect 12 new arch span floorbeams

• Approach span demo similar

15

Page 17: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Restrictions• No construction live load on overhangs

• Transverse sawcuts in deck 2” in from edge of floorbeam• Transverse sawcuts in deck 2 in from edge of floorbeam

• No longitudinal sawcuts over floorbeams

• Reactions based on excavator at maximum lift capacity

• Excavator will be located precisely to minimize bending in deck

• Crane mats for crawler cranes, excavator as needed

• Exterior lanes on existing bridge are adequate for 4 lanes of traffic, post-tension floorbeams as required (HNTB)

16

Page 18: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Existing Floorbeam PT

17

Page 19: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Tasks• Determine max pick weight for excavator

D t i li it ti f t iti• Determine limitations for excavator position

• Determine crane locations

• Design crane mats and outrigger pads

• Design rigging for floorbeams

• Perform surcharge analysis (crane on approaches)• Perform surcharge analysis (crane on approaches)

18

Page 20: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Saw Cut & Slab Demo

2”2”

19

Page 21: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Photos – Slab Demo

20

Page 22: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Photos – Slab Demo

Transverse

Edge of

sawcut

21

Edge of floorbeam

Page 23: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Excavator Load

MAXMAX

22

Page 24: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Excavator Location

MAXMAX

23

Page 25: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Excavator Location

MAX

CL Floorbeam8’-0”

CG Excavator

24

Page 26: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

DemolitionBarrier and Slab – Arch Span

2 Lanes West Bound

2 Lanes East Bound

25

Page 27: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

DemolitionFloorbeams – Arch Span

2 Lanes West Bound

2 Lanes East Bound

26

Page 28: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Floorbeam Removal

27

Page 29: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Floorbeam Removal

28

Page 30: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

29

Page 31: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Erection Procedure

Arch Span:

• Deliver precast floorbeams on adjacent bridge.

• Lift floorbeams:• Lift floorbeams:– Center 4 Arch span floorbeams: 2 Hydraulic Cranes in

tandemtandem– Floorbeams 5 and 6: Single pick with Hydraulic Crane– Remaining 6 arch span floorbeams: Single pick withRemaining 6 arch span floorbeams: Single pick with

Crawler Crane

30

Page 32: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

ErectionFloorbeams – Arch Span: Dual Crane Picks

2 Lanes West Bound

EB Lane 2 - Fully closed for deliveryEB Lane 1 - Temp. closure during erection (1-2 min)EB Lane 2 Fully closed for delivery

250-ton Hydraulic Crane 275-ton Hydraulic Crane

31

250 ton Hydraulic Crane 275-ton Hydraulic Crane

Page 33: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Floorbeam Erection

32

Page 34: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Floorbeam Erection

33

Page 35: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

ErectionFloorbeams – Arch Span: Single Crane Picks

EB Lane 1 - Temp. closure during erection (1-2 min)2 Lanes West Bound

EB Lane 2 - Fully closed for delivery

250-ton Hydraulic Crane 275-ton Hydraulic Crane

34

250 ton Hydraulic Crane 275-ton Hydraulic Crane

Page 36: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Floorbeam Erection

35

Page 37: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Floorbeam Erection

36

Page 38: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

ErectionFloorbeams – Arch Span: Single Crane Picks

EB Lane 1 - Temp. closure during erection (1-2 min)2 Lanes West Bound

EB Lane 2 - Fully closed for delivery

150-ton Crawler Crane 150-ton Crawler Crane

37

150 ton Crawler Crane 150-ton Crawler Crane

Page 39: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Floorbeam Erection

38

Page 40: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Floorbeam Erection

Grout Closure Pour

39

Page 41: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Floorbeam Removal

40

Page 42: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

DemolitionSlab and Floorbeams – Approach Spans

2 Lanes West Bound

2 Lanes East Bound

Crane mats on column lines

41

Page 43: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Demolition & ErectionSlab and Floorbeams – Approach Spans

2 Lanes West Bound

2 Lanes East Bound

Crane mats on column lines

42

Page 44: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Floorbeam Removal

43

Page 45: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

PDH Question 1Q: Why was special attention

paid to the method of d liti f th d k ddemolition for the deck and transverse floorbeams?

Existing Spandrel Columns

A: A majority of the spandrel columns and the entire arch were to remain in place and were required to be undamaged

Existing Arch

undamaged.

44

Page 46: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

PDH Question 2Q: Why were the slab sections

that were being removed li it d t t i i ?

A1: Tipping capacity of the excavator.

limited to a certain size?

(2 parts)

A2: Reaction under excavator tracks cannot

(2 parts) cause a failure in the deck slab or floorbeams.

45

Page 47: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

PDH Question 3Q: Why were the floorbeams

and slab analyzed for the i lift l d f th

A: To be conservative in the analysis and to avoid

t i th d kmaximum lift load for the excavator and not just the weight of the slab section

overstressing the deck floorbeams.

weight of the slab section being removed?

46

Page 48: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

PDH Question 4Q: Why was the Crawler

Crane placed on the column li f th h

A: To reduce bending forces in the floorbeams. (T f ti i ht tlines for the approach span

work?(Transfers reaction right to columns)

47

Page 49: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

PDH Question 5Q: Why were crane mats used

under the tracks of the l ?

A: To span between the floorbeams and avoid

t i th d k l bcrawler cranes? overstressing the deck slab.

48

Page 50: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

“You don’t wanna know.”

- Cold Spring PM Jeff Younger when asked exactly how they plan to remove the deck slab sections from the bridge.plan to remove the deck slab sections from the bridge.

49

Page 51: CONSTRUCTION SUPPORT FOR SUPERSTRUCTURE DEMOLITION … · Arch Span: • Deliver precast floorbeams on adjacent bridge. • Lift floorbeams: – Center 4 Arch span floorbeams: 2 Hydraulic

Thank You

Joshua T. Rodems, EITStructural EngineerStructural Engineer

Erdman [email protected]

50