Construction - Sector Update (1)

download Construction - Sector Update (1)

of 38

Transcript of Construction - Sector Update (1)

  • 8/4/2019 Construction - Sector Update (1)

    1/38

    1 Edelweiss Securities Limited

    Executive Summary

    Edelweiss Securities LimitedParvez Akhtar Qazi+91 22 4063 [email protected]

    Rohit Patni+91 22 6623 [email protected]

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    2/38

    2 Edelweiss Securities Limited

    Construction

    Executive Summary

    We travelled more than 8,500 km by road, air, and railway and visited various road projects

    across North, South, East, and West India. We met developers, contractors and sub-

    contractors executing projects at a cumulative cost of ~INR 65 bn. Our mission was to findanswers to the following pertinent questions:

    What are the ground level issues in road project execution?

    Do land acquisition issues continue to hamper the pace of project development?

    What are the impediments in the land acquisition process?

    How smooth is the process of getting regulatory approvals in forest / environment /

    utility shifting?

    What is the likelihood of reducing cost/time overrun in future projects?

    Are there constraints in manpower/equipment/raw material availability?

    Our key conclusions are as follows

    Regulatory approvals a big dampener

    Land acquisition continues to remain the single biggest road block hampering

    developers. Lack of clear land titles, protests over land compensation and

    lackadaisical attitude of state government authorities are major causes for delays.

    Most developers indicated that execution time of projects could be cut by up to six

    months by timely land acquisition. Similarly, getting timely approvals from railway

    and forest departments is very difficult due to the cumbersome process involved.

    Developer involvement in regulatory approvals ensures timely execution

    Many projects commissioned in the past had been delayed due to the above

    mentioned issues. However, developers have learnt from past mistakes and have

    started facilitating coordination within various government departments by hiring

    retired officials. As a result, many projects that we visited were running ahead of

    schedule; also, cost/time overruns, if any, in future projects may not be substantial

    and are likely to be less than in past projects.

    Resource availability not an issue

    We were positively surprised by the fact that resources (manpower, equipment, raw

    materials, financing or sub-contractors) were easily available. Even if there is any

    temporary resource crunch, the entrepreneurial spirit of contractors ensures that

    these issues are taken care of. Also, with multiple resource providers (in terms of

    equipment manufacturers, banks and other financial institutions), timeliness and

    cost efficacy of the supply is also reasonably ensured.

    Outlook on execution of road projects: Bright

    Over FY09-10, the government has initiated many steps to ensure that the pace of

    project award has picked up. This leaves execution issues as the principal irritant in

    improving the pace of road project development. While enhanced developer

    involvement, good resource availability and increased government efforts have

    emerged as a positive, some more action is required to speed up the approvals

    process. We believe if the regulatory side of approvals is taken care of, ramping up

    execution will not be too challenging.

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    3/38

    Edelweiss Securities Limited 3

    Construction

    Contents

    Our modus operandi .................................................................................................... 3

    Why focus on execution? .............................................................................................. 4

    Land acquisition .......................................................................................................... 6

    Utility shifting and other local clearances ...................................................................... 13

    Railways, forest & environmental approvals .................................................................. 16

    Resource availability issues ........................................................................................ 18

    Cash contracts continue to get delayed ........................................................................ 22

    Outlook on road projects execution.............................................................................. 23

    Major project details .................................................................................................. 24

    Dhule-Palasner Project ............................................................................................ 24

    Hyderabad outer ring road project ............................................................................ 26

    Pimpalgaon-Nashik-Gonde project ............................................................................ 29

    Ranchi ring road project .......................................................................................... 31

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    4/38

    4 Edelweiss Securities Limited

    Construction

    Our modus operandi

    We travelled more than 8,500 km by road, air and railway and visited various road projects

    across North, South, East, and West India. We met developers, contractors and sub-

    contractors executing projects with a cumulative cost of ~ INR 65 bn. Apart from interacting

    with project managers and engineers, we also met some bankers financing these road

    builders.

    What was the scope of projects covered?

    We have tried to cover the widest possible array of road projects in terms of geography,

    project cost, mandate of project (toll/annuity/EPC) and mode of execution (developer /

    sub contractor). This was to ensure that we do not restrict ourself to any one particular

    kind of project and interact with a wide spectrum of industry participants. To better

    understand execution issues across the industry, we tried to diversify the type of

    projects visited.

    Fig. 1: Projects visited across I ndia

    Source: Google Maps, Edelweiss research

    Table 1: Covering entire spectrum of road projects

    Source: Edelweiss research

    Scope of projects visited Mode of projects visited

    2 lane BOT toll project

    4 lane BOT annuity project

    6 lane State govt EPC project

    8 lane access controlled expressway District road project

    Regions visited Cost of projects visited

    North India < INR 1 bn

    West India INR 1 - 5 bn

    South India INR 5 - 10 bn

    East India INR 10+ bn

    Visited road projects

    across the country to

    understand ground level

    execution issues

    We covered every type

    of road project possible

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    5/38

    Edelweiss Securities Limited 5

    Construction

    Why focus on execution?

    Between 1951 and 2006, while Indias vehicle population posted a CAGR of close to 11% and

    freight and passenger traffic carried by road posted 10% CAGR, the total road length

    registered a mere 3.9% CAGR with the National Highway (NH) segment increasing at a

    minuscule 2.2% CAGR.

    Also, the quality of roads is abysmal. The Global Competitiveness Report 2010-11 ranks

    India at a dismal 90th spot as far as quality of roads is concerned, way below

    neighbours China (53 rd), Sri Lanka (55 th) and Pakistan (72nd).

    This shows that the pace as well as quality of road length addition in the country has

    remained tardy over the years. While things have definitely improved, particularly in the NH

    segment, since the start of the National Highway Development Programme (NHDP), we have

    still fallen short of targets. This can be attributed to: (i) slowdown in the pace of project

    awards in 2006-08 due to regulatory issues and recession; and (ii) execution issues on road

    projects as manifested in cost and time overruns.

    Table 2: Physical targets and achievements for NHDP

    Source: Govt documents, Edelweiss research

    Over FY09-10, the government has initiated many steps which have enhanced the

    attractiveness of road projects for developers and ensured pick up in the pace of project

    awards. With most regulatory issues being sorted out and ~ 26,000 km of projects to be

    awarded over the next 4-5 years under NHDP, we believe project award is unlikely to be

    a major dampener going forward (even if pace of project award may not be uniform).

    This leaves execution issues on road projects as the principal irritant in improving the

    pace of road development.

    How big an issue is execution and what are the costs involved?

    As per the government, ~68% of projects undertaken by the National Highway Authority

    of India (NHAI) so far have been delayed (includes both completed and under

    implementation projects).

    The World Bank had carried out a time and cost overrun analysis on on-going and

    completed national highway and state highway contracts a couple of years ago. The

    results of the study are given below:

    Table 3: Time and cost over-run details

    Source: World Bank, Edelweiss research

    Category Target Achievement Target Achievement Target Achievement

    Widening to 4-lanes and strengthening (kms.) 2,885 1,683 3,520 2,203 3,165 2,693

    2007-08 2008-09 2009-10

    Time Cost Time Cost

    100% 7.6 0.0 12.3 0.0

    NHAI and

    state govt

    contracts

    % Overrun [overoriginal estimates of

    time and costs]

    Completed contracts(%)

    Completed + ongoingContracts (%)

    Pace as well as quality ofroad length addition inthe country has beendisappointing

    Most road projectswitness time/costoverruns

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    6/38

    6 Edelweiss Securities Limited

    Construction

    The study indicates that 90% of all contracts had a time overrun of more than 25%;

    46% had a cost-overrun of more than 25%. The cost overrun figures for completed

    contracts do not include a large portion of pending claims and arbitration orders. As per

    estimates, ~ INR 100 bn is locked in disputes between the government and contractors.

    Thus, execution remains a major issue in road development; the final costs of road

    project implementation are much higher than initially envisaged.

    What are the major execution issues?

    Major issues in road project execution can be broadly categorised into:

    1. Regulatory issues Land acquisition

    Utility shifting and other local clearances

    Other approvals like forest, railways etc.

    2. Resource availability issues Manpower availability

    Raw material availability

    Availability of financing

    Equipment availability

    Sub-contractors availability

    Our trip was aimed at getting to the root of the execution issues listed above.

    Execution is a bigconcern in roaddevelopment

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    7/38

    Edelweiss Securities Limited 7

    Construction

    Land acquisition

    How big is this problem?

    As per World Bank, on an average, it takes 50% more time than scheduled to hand over

    encumbrance-free land to contractors for national highway projects. Also, according to a

    survey of 190 infrastructure projects facing delays, 70% were delayed due to land

    acquisition problems. This indicates that land acquisition is arguably the biggest hurdle

    afflicting road development.

    Fig. 2: Delayed due to reluctance of farmers to hand Fig. 3: Problems due to protest over demolition of

    over land structure

    Source:Edelweiss research What are the relevant regulations?

    Land acquisition for development projects in India happens through the Land Acquisition

    Act (LAA), 1894. However, land acquisition for national highways is carried out under a

    separate law known as the National Highway Act (NHA), 1956.

    State governments sometimes constitute a specific law for land acquisition (land

    acquisition in India is a Concurrent subject as per the Indian Constitution which gives

    state governments the right to legislate on the matter).

    Land acquisition is the

    biggest issue in roaddevelopment

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    8/38

    8 Edelweiss Securities Limited

    Construction

    What is the process for land acquisition?

    The various steps involved in the process of land acquisition for National Highways are

    given below:

    Fig. 4: Land acquisition process for national highw ays

    Source: Govt documents, Edelweiss research

    What are the reasons behind difficulties in land acquisition?

    We learnt from our visit that there are multiple reasons behind difficulties in land

    acquisition. Prominent amongst them are:

    Institutional framework and dependence on local authorities: When land is to

    be acquired under the NHA, 1956, the NHAI generally relies on the district

    administration since the relevant land records are with the revenue department. The

    district administration appoints an Additional District Magistrate or Sub-Divisional

    Magistrate as the competent authority for this purpose. Sometimes, there is delay in

    the appointment of a competent authority by the state government which further

    delays the process.

    Also, this means that NHAI is dependent on the district administration for the land

    acquisition process. Since NHAI has no control on district administration (for

    which land acquisition is not a priority issue due to other responsibilities),

    the entire process becomes dependent on the proactiveness of district

    officials. Sometimes, local officials are transferred, which again hampers the

    process.

    Special land acquisition cells enhancing coordination but local authorities

    still the key: Over the past year, NHAI has set up local cells to enhance

    coordination in land acquisition with local authorities. These units carry out the

    following functions:

    Prepare the notification under section 3A (Intention to acquire land).

    Prepare the notification under section 3D (1).

    Disburse the compensation to land owners.

    These units coordinate with local officials to ensure that the process of land

    Govt expresses its intention toacquire the land (3A

    notification)

    Carry ing out of surveys, inspection etc.,setting out of boundaries and intended

    lines of work

    Hearing objections fromconcerned persons

    Decleration of acquisition afterdisposing off objections (3D

    notification)

    Determination of amount payable ascompensation

    Award finalisation at the SpecialLand Acquisition Officer (SLAO)

    level

    Approval at the NHAI Projectimplementation unit / NHAI

    hedaquarter

    Disbursement of compensation amount Physical possession

    NHAI depends on localauthorities for landacquisition

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    9/38

    Edelweiss Securities Limited 9

    Construction

    acquisition is smooth. Our interaction with developers reveals that there definitely

    has been improvement on the ground level with the setting up of such cells.

    However, in case district administration officials are not dynamic and cannot handle

    various problems which emerge from time to time with regards to land acquisition,

    the entire process is still delayed. Indeed, developers raised serious concerns

    regarding the motivation levels of local authorities.

    Fragmented land holdings: The fragmented nature of land holdings in rural areas

    means that a large number of landowners need to be compensated for their land.

    According to data from the Ministry of Agriculture, 62% of farmers have land

    holdings of less than one hectare. This creates problems in land acquisition.

    Fig. 5: Land acquisition delayed due to nearby farm Fig. 6: Land acquisition stuck due to dispute over

    land compensation amount

    Source:Edelweiss research Lack of clear land titles: Unclear land titles and absent/incomplete revenue

    records in villages are the biggest constraints in timely land acquisition. The process

    gets bogged down due to the problem in finding the rightful owner of the land. This

    is because land records are generally outdated, inaccurate and/or incomprehensive.

    This gives rise to frequent disputes, which result in litigation. This is a problem

    which no amount of NHAI/developer involvement can solve. For e.g., news reports

    suggest that land acquisition progress in Jharkhand had been hit due to inadequate

    land revenue records reflecting ownership; the maps were as old as 1912 and the

    state government is now developing land records by way of physical verification.

    Similarly, in case there has been an informal division of land amongst family

    members, it is not reflected in records of the revenue department. Also, in case the

    land belongs to tribals, the acquisition process further suffers since there isrestriction on sale of land from tribals to non-tribals.

    Inadequate land acquisition plans: Many a times, land acquisition plans as

    formulated according to the detailed project report (DPR) are inadequate; this is

    because the professionals involved in preparing DPRs do not have sufficient

    knowledge of land acquisition. The design consultants do not have sufficient

    expertise in preparing proper land acquisition plans; also, land acquisition plans are

    unrealistic due to deficiencies in on-the-ground verification of the design/alignment.

    Lack of clear land titlesand inadequate DPRscreate hurdles

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    10/38

    10 Edelweiss Securities Limited

    Construction

    Lack of uniformity in state governmentregulations: There is lack of uniformity

    across state governments in terms of statutes. For e.g., the Uttar Pradesh

    government had earlier imposed a condition that NHAI will have to guarantee

    development of a 10 m wide strip of plantation along either side of highways if the

    project involves felling of existing trees. This affects land acquisition progress.

    Lack of adequate compensation and methodology of computation: Weunderstand that compensation for land acquired is also a big issue impeding land

    acquisition. The bone of contention here is both the eventual quantum of

    compensation and the methodology used to arrive at the figure.

    The NHA, 1956, provides for compensation based on: (a) market value of the land

    on the date of publication of 3A notification; (b) extra payments for trees, crops,

    houses, or other immovable properties; and (c) payments for damage due to

    severing of land, residence, or place of business.

    A lot of discretion is vested with state authorities during the entire process and,

    many a times, there is lack of clear cut procedures for the same. This results in

    grievances against authorities which delays actual possession of land by the

    government.

    V ar ious p r ob lems r e la ted to c omp ens at i on a r e de ta i l ed be low :

    Sometimes, valuation of land, as determined by authorities, is based on sale

    deeds recorded with revenue offices; this is way below prevailing market prices

    and is a cause of heartburn for the landowner.

    Over the past couple of years, land prices in some parts of rural India have

    increased sharply due to expansion of rural roads and improvement in

    accessibility. This has resulted in many landowners demanding higher

    compensation than the official acquisition rate.

    Also, sometimes, there is a dispute between state and central governments over

    the manner of compensating affected land owners. This is also because manystates have their own land acquisition and rehabilitation laws, which differ from

    NHA, 1956.

    This means that even after publication of 3D notification signifying the acquisition of land

    by the government, the valuation of the land, approval of the same, disbursement and

    physical possession of the land by the developer takes a long time. In theory, the land

    acquisition is complete as soon as the relevant government notification is issued;

    however, in practice, developers have to wait for a long time in getting unencumbered

    access to the land.

    What is developers viewpoint?

    Our interaction with various developers threw some interesting takeaways:

    Developers have become involved in land acquisition p rocess: A large number

    of projects which have been commissioned over the past couple of years had been

    delayed due to land acquisition problems . However, developers have also learnt

    from past mistakes and have realized that they need to be proactive to facilitate

    coordination between various government departments to ensure that land

    acquisition is completed on time in order to save time and cost (for BOT projects).

    To this extent, developers have become involved in the land acquisition process.

    This includes hiring retired officials (earlier involved in land acquisition) to ensure

    smooth running of the process. In fact, we came to know of instances where

    Developers lending ahelping hand in landacquisition process

    Institutional framework

    for land acquisition isinadequate

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    11/38

    Edelweiss Securities Limited 11

    Construction

    developers have themselves acquired certain stretches of land which were proving to

    be problematic so as to ensure speedy completion of the land acquisition process.

    Developers indicate more efforts from state government could help: While

    most developers indicated that NHAI emphasis on land acquisition has improved,

    they also highlighted that developer involvement is not the panacea of all problems;

    beyond a particular level, land acquisition progress ultimately depends on the levelof state government involvement. They highlighted that states where authorities are

    proactive (Gujarat, Rajasthan) are the best places to work. On the other hand,

    projects in certain states like West Bengal, Kerala, Uttar Pradesh, Orissa etc.,

    continue to face problems. Thus, overall while there has been some progress on the

    land acquisition front, it is sporadic in nature and still depends on developer

    involvement.

    Land acquired is not continuous but piecemeal: Developers indicated that many

    a times, land parcels acquired are not continuous , i.e., they are piecemeal and at

    quite a distance from each other. This creates problems in execution since it leads to

    increase in inefficiencies due to less than optimal utilisation of equipments.

    Unencumbered access to land still a problem: As highlighted above, even after

    acquisition of land, various encumbrances mean that developers ability to undertakework in a continuous uninterrupted manner is constrained. Unencumbered access to

    land thus still remains a problem.

    Land acquisition process needs to be initiated earlier in project lifecycle:

    Currently, the land acquisition process continues well into the execution period,

    thereby affecting the construction schedule. Developers suggested the process

    needs to be initiated at the design stage itself, well before the beginning of civil work.

    To this end, a comprehensive land survey should be completed before land

    acquisition schedules are prepared and included in DPRs.

    Our view

    We believe that while the land acquisition process has improved, many issues remain to

    be tackled before pace of road development picks up. Our key learning from the visit isas follows:

    Land acquisition continues to remain the single biggest issue faced by

    developers

    Our interaction with developers/contractors indicated that land acquisition continues

    to remain the single biggest issue troubling developers. This was the unanimous

    feedback received across all projects that we visited. Most developers indicated that

    execution time of projects could be reduced by up to six months in case land

    acquisition is completed in the scheduled time. However, this is hardly the case with

    developers having to contend with numerous delays due to non-availability of land.

    Cost/time overruns in future projects may not be substantial and likely to

    be lesser than past projects

    With developers lending a helping hand to the government, project execution was

    on the right track for most BOT projects we visited. This leads us to believe that

    cost/time overruns in future BOT projects may not be substantial and is likely to be

    lesser than in past projects.

    Calculation methodology o f land acquisition needs closer scrutiny

    The revised guidelines for road project awards announced last year state that a LoA

    will be issued only when 80% of the land required is under possession. However, the

    calculation of this figure needs a closer look. The Right of Way (RoW) or the land

    Developers want more

    efforts from stategovernments

    Project execution couldreduce by up to sixmonths, if landacquisition is completedwithin schedule

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    12/38

    12 Edelweiss Securities Limited

    Construction

    required for any project includes the portion of the land for existing road as well, i.e.,

    for a four laning project, the RoW includes the land of the existing 2 lane project.

    As a result, a substantial quantity of land required is available upfront. For e.g., the

    RoW of ~40-45 m required for a 4 lane road includes the existing 2 lane road

    (usually 10 m wide). Thus, any figure with respect to land acquisition progress

    needs to be considered in the proper perspective.

    Recent news flow suggest that governments efforts bearing fruit

    Recent news articles suggest that governments efforts on the land acquisition front

    have resulted in improvement. News articles point that:

    NHAI took possession of 3,022 hectares in Q1FY11.This is almost half the size

    of the total land possessed (6,244 hectares) by NHAI in 2009-10 which itself

    was a huge improvement over the 3,120 hectares acquired in 2008-09 and

    3,684 hectares acquired in 2007-08. The total land acquired by NHAI was at a

    relatively higher level at 5,513 hectares in 2006-07.

    Under section 3G of the NHAI Act, which makes the government liable to pay

    compensation to the land owner, NHAI has issued notification for 2,204 hectares

    in Apr-Jul 2010, compared with 3,605 hectares in the previous fiscal.

    Out of the total 60,500 hectares land required for various stages under the

    NHDP, the government has managed to acquire around 25,000 hectares.

    Enhanced support from state government the key

    While NHAI and the roads ministry are doing all they can to improve the land

    acquisition process, the big kicker can come only if the respective state

    governments pull up their socks and improve coordination at the ground level. In

    this context, the signing of state support agreements (SSAs) by 24 states and Union

    Territories with the roads ministry is a step in the right direction. The agreement

    empowers the concessionaire with access to the site and right of way in accordance

    with the provisions of the respective concession agreements without hindrance from

    any government agency or person claiming it.

    Proposed National Highway Amendment Bill will be a key monitorable

    The proposed National Highway Amendment Bill is being keenly watched with

    regards to changes in the regulation regarding national highways. News reports

    suggest a couple of important recommendations as per the draft bill.

    If a planned road is abandoned, the original owner will reserve the right to buy

    back the land by returning the money paid by the government for purchase.

    Further, the owner will not have to pay the appreciation price but only that

    received when he or she sold the land.

    It has been proposed that a two-step mechanism be introduced for calculating

    cost of land at the time of acquisition by NHAI. In the first step, price of the

    land will be calculated on the basis of the average land price of top 50% sales

    (in terms of value) in the past three years. The land cost will also be estimated

    according to the price guidelines for the area maintained by the collector in

    charge. After arriving at the two values, the higher of the two will prevail as the

    price that the NHAI will pay to the land owner.

    Currently, the land price is calculated based on the average price of all land

    sales in the area in the past three years. The new mechanism proposed,

    however, takes into account the top 50% values of land sale in three years.

    Enhanced support fromstate governments is keyto speedier roadexecutionISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    13/38

    Edelweiss Securities Limited 13

    Construction

    It is also proposed that the person who sells the land to NHAI should get

    solatium for better rehabilitation and resettlement. It is proposed that the land

    owner gets 60% of the agreed sale price of the land as compensation for

    displacement in addition to the land price.

    It is proposed that a time limit of three months be imposed for the aggrieved to

    approach an arbitrator in the case of land sale. The current form of bill placesno such time limit, leaving it open ended. The arbitrator will also be required to

    give a decision within six months.

    Achieving 20 km/day hinges on land acquisition success

    Land acquisition will be an important parameter in determining the success of the 20

    km/day initiative. As the recent protests by farmers in Uttar Pradesh over land

    acquisition for an expressway demonstrated, land acquisition remains a contentious topic

    in the Indian infra scene. The sooner the outstanding issues are resolved, the better it

    will be for progress of road development.

    Land acquisition will bean important parameter

    in determining thesuccess of the 20km/day initiative

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    14/38

    14 Edelweiss Securities Limited

    Construction

    Utility shifting and other local clearances

    How big is this problem?

    Utility shifting and other local clearances is another problem facing road projects. Many

    times, while land acquisition is complete, unencumbered access to the land and initiation

    of execution is not possible due to delays in shifting of utilities and other approvals.

    Sometimes design and layout of the project have to be changed due to problems in

    utility shifting.

    A World Bank study highlighted had indicated that on an average, shifting of electrical

    utilities took about 33 months, telephone utilities about 31 months and water utilities

    about 29 months, against the planned target of about 18 months for all these utilities

    more than a year of delay.

    Fig. 7: Problems in shifting of power lines Fig. 8: While tree cutting has been completed, power

    lines still needs to be shifted

    Source: Edelweiss research

    Utility shifting and otherlocal clearances delayproject execution

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    15/38

    Edelweiss Securities Limited 15

    Construction

    Various clearances involved

    Utility shifting: When it comes to utility shifting, major problems are shifting of

    transmission towers, electric wires, telephone cables, water pipes, etc.

    Local clearances: Various local clearances required are given below:

    Table 4: Various local level clearances required

    Source: Edelweiss research

    Agencies involved

    For utility shifting, developers need to coordinate with various government departments

    like the telecom department, the local municipal board and local bodies for water and

    power maintenance.

    For other local clearances, entities involved are the village panchayats/municipal board,

    District Collector, Pollution Control Board and other government bodies.

    Reasons behind delays in utility shifting/other clearances

    We learnt from our visit that there are multiple reasons behind difficulties in utilityshifting/other clearances. Prominent amongst them are: Lack of proper coordination between the implementing agency and respective utility

    departments

    Inadequate investigations during DPR preparation and lack of proper utility

    mapping; sometimes contractors come to know of utilities (underground ones)

    during the project implementation stage.

    The road implementing agency has no leverage on utility relocation departments.

    Developer viewpoint on utility shifting/other local clearances

    Our interaction with various developers threw some interesting takeaways:

    Better coordination between different government departmentsrequired -

    Developers highlighted the need of better coordination between various government

    departments. Like land acquisition, utility shifting stretches late into the execution

    period, thereby preventing developers from optimal use of resources.

    Presence of a dedicated agency helps - Our interaction with developers indicated

    that the presence of a dedicated agency (like Hyderabad Growth Corridor for

    Hyderabad outer ring road project) helps in better coordination amongst

    government departments.

    Sl. No. Description of permits/licenses required

    1 Labour license

    2 Registration under building and other construction workers' act

    3 Blasting permissions

    4 Approvals from village panchayat for installation of crusher, batching plant,

    asphat plant etc

    5 Approval from Pollution Control Board for installation of crusher, batching

    plant, asphat plant etc

    6 Blasting permission from District Collector

    7 License for use of explosive from Chief Controller of explosive

    8 Permission for installation and operation of HSD consumer pump

    Lack of propercoordination betweengovt departments delaysutility shiftingISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    16/38

    16 Edelweiss Securities Limited

    Construction

    Developers giving a helping hand to government - Like land acquisition,

    developers have also become involved in utility shifting/other clearances. They have

    themselves approached the concerned authorities to ensure smooth coordination

    between various entities.

    Our viewWe believe the challenges in utility shifting are far lower than those in land acquisition as

    the factors involved are less complex. Also, with a little improvement in coordination

    between various agencies, there can be a marked upturn in the pace of road project

    development.

    Better coordinationbetween variousagencies can enhanceroad development

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    17/38

    Edelweiss Securities Limited 17

    Construction

    Railways, forest & environmental approvals

    In every NHAI or state highway project that we visited, there was an issue with a railway

    over bridge (ROB) or with regards to area under the forest department. Getting approval

    from railways or the Ministry of Environment and Forests (MoEF) is a tough task for

    developers. An approval for cutting trees can take up to 30 months. Similarly, approval for a

    railway over bridge (ROB) from railways can take 15-18 months.

    Reasons behind delays in getting railways, forest and environmental approvals

    The reason for delays in getting these approvals is primarily the cumbersome process

    involved. For e.g., in case of a forest clearance, the developer first receives an in

    principle approval which stipulates certain specific conditions. Only when all the

    conditions are fulfilled is the final clearance issued. Project implementation cannot

    begin until the final clearance has been achieved.

    Road projects which pass through a national park or sanctuary require the approval of

    the National Board of Wildlife (NBW) even for the very first step like undertaking asurvey.

    News reports suggest that there is a lack of a standard procedure for clearance of such

    projects and the matter has been raised before an Empowered Group of Ministers

    (EGoM), which is expected to meet shortly to prepare the required norms for such

    projects.

    Apart from the central government represented by the MoEF, developers have to face

    additional conditions imposed by the forest department in the state government.

    For environmental clearance, the proposal needs to be submitted at the feasibility stage

    itself. A complete assessment of the environmental impact is done and the project is

    examined by an expert committee. The whole process can easily take up to an year.

    In the recent past, many projects have been stuck due to delay in approvals in one of

    the above parameters. For e.g., news reports suggest that only recently, the standing

    committee of NBW, rejected NHAIs proposal to divert 85 hectares of forest land for four-

    laning in an 85 km stretch on national highway No. 6.

    Our view

    After interacting with project managers, we believe that railways and forest approvals

    are emerging as major choke points. Even the proactive efforts of NHAI or developers

    usually fail in front of these departments since they follow their own procedures which

    usually take time.

    Getting approval from

    railways or MoEF is atough task fordevelopers

    The process forenvironmental clearancecan take up to a year

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    18/38

    18 Edelweiss Securities Limited

    Construction

    Fig. 9: Project delayed due to construction of an ROB for w hich permission w as

    pending for long

    Source: Edelweiss research

    We had a chance to examine delays due to ROBs firsthand. In a project, which has been

    under implementation for the past four years, the entire road widening part of the

    project has been complete for some time now. The only portion where work was still

    pending were a couple of ROBs.

    Fig. 10: Project stalled due to delays in approval for Fig. 11: Project delayed due to delays in approvalscutting trees from forest department

    Source: Edelweiss research

    Similarly, the process for environmental clearances involves a number of NGOs; a single

    objection from them can cause a major delay. Sometimes, project alignment itself has to

    be changed to accommodate demands of the forest department.

    I S I E m e r g i n g M a r k e t s P D F i n

    D o w n l o a d e d b y i n - u n i v e r s a

  • 8/4/2019 Construction - Sector Update (1)

    19/38

    Edelweiss Securities Limited 19

    Construction

    Resource availability issues

    After looking at the regulatory approval scenario, we now focus our attention on resource

    availability issues i.e., the ease of building asset base in terms of manpower, equipments,

    raw materials, financing and execution multipliers (sub-contractor). Our interaction with

    project execution personnel pointed out a few positives which we have listed below:

    Quality manpower resources at middle management level are scarce

    We observed that there is a scarcity of experienced and good quality manpower

    resources at the middle management level (civil engineers with 10-15 years of

    experience). Contractors attributed this to the migration of civil engineers to IT

    companies (starting from the mid 1990s). As a result, there is a shortage of skilled

    professionals at the middle management level. Also, most contractors believed that the

    shortage is likely to emerge as a big issue going ahead with the large scale up in

    infrastructure spending planned in the coming years. However, unskilled or semi skilled

    manpower is not an issue.

    We believe contractors have also realized the benefit of developing their own talent base

    to cope with the anticipated increase in human resource crunch going ahead. Recent

    news flow suggests that Gammon India has started its own training center in Mysore

    with a view to create a pool of skilled workforce trained in various skilled disciplines

    including masonry, plastering, scaffolding, carpentry, electrical work, painting and

    plumbing.

    Availability of plant/equipment and raw material is not a constraint

    Our interaction with project personnel indicated that there were no major issues with the

    availability of either plant/machinery or with raw materials. Funding is easily available for

    enhancing the fixed asset base. In fact, many contractors opined that it is easier to get

    funding for equipment finance than getting their non-fund based banking facilities

    enhanced. They attributed this to the presence of NBFCs in the equipment finance space.

    Fig. 12: Fixed asset base is easy to expand Fig. 13: Equipment availabi lity is not a concern

    Source: Edelweiss research

    Scarcity of qualitymanpower resources atmiddle managementlevel

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    20/38

    20 Edelweiss Securities Limited

    Construction

    Also, raw material constraints are few; in fact, resources mobilisation was in full swing in

    practically all locations that we visited even before the work at the site was

    started/scheduled to start. Even in areas where there were some issues with raw

    material availability, contractors had the foresight of planning for this beforehand.

    Fig. 14: Raw material is easily available Fig. 15: No problems in raw material supply

    Source: Edelweiss research

    For e.g., in Haryana where the state government has imposed a ban on mining of major

    minerals in Faridabad, Gurgaon and Mewat districts for 10 years, alternate supply

    arrangements from Rajasthan were already in place. This ensured that project

    implementation was not affected.

    No shortage of quality subcontractors

    Most developers that we interacted with indicated that there is no dearth of sub-

    contractors in the industry. There are enough small contractors willing to work for

    developers. We visited a few projects being executed by these sub-contractors and foundthat the asset base, both in terms of equipment and manpower, with these sub-

    contractors was substantial. These sub-contractors also had easy access to funding

    which is crucial to their growth prospects.

    Responsibilities clearly outlined: In projects where the execution is being carried

    out by a sub-contractor, the role of developers veers more towards project

    monitoring and supervising the implementation schedule. Developers have their own

    set of technical personnel engaged at the site who oversee the project execution.

    There are weekly review meetings with sub-contractors to keep a tab on progress of

    the project.

    Sub-contractors have adequate asset base: We also met a few sub-contractors

    and visited projects being executed by them. Here again, the fact that these sub-

    contractors had their own asset base and qualified manpower came through. Ourinteraction with these sub-contractors revealed that they had scaled up their

    execution capabilities over the years which was reflected in the average size of

    projects being undertaken by them.

    There are enough smallcontractors willing towork for developers

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    21/38

    Edelweiss Securities Limited 21

    Construction

    Fig. 16: Sub-contractors have good quality asset base Fig. 17: Sub-contractors have adequate technical

    acumen

    Source: Edelweiss research

    These sub-contractors also had their own laboratories for ensuring the quality of

    work being undertaken.

    Fig. 18: Quality check at a sub-contractors si te

    Source: Edelweiss research

    When it comes to the selection process undertaken by developers for choosing sub-

    contractors for any project, the asset base and past work are crucial parameters.

    Traditional developer-sub-contractor relationships changing: Also, some sub-

    contractors indicated that developers had started giving them incentives for

    upgrading execution capabilities in terms of asset base and manpower resources.

    This was being done by developers in the form of assuring the sub-contractor of a

    minimum volume of work every year for a fixed period of time. We believe this is a

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    22/38

    22 Edelweiss Securities Limited

    Construction

    win-win situation for both parties involved as sub-contractors get to enhance their

    execution capabilities and also learn from project management skills of experienced

    developers; for developers, the benefit is in the multiplier effect brought in by sub-

    contractors.

    Fig. 19: Sub-contractors have built up execution capabilities and asset base

    over the years

    Source: Edelweiss research

    Funding not an issue: We enquired about the ease of availing financing for

    purchasing equipments etc. Here again, sub-contractors indicated that they were

    not facing any shortage. They had relationships with multiple banks and fund

    availability was not an issue.

    Interaction with financial institutions corroborates findings: We also

    interacted with a couple of financial institutions who fund sub-contractors. They

    corroborated sub-contractors feedback and were optimistic about future growth

    prospects of these sub-contractors. These institutions had witnessed growth

    trajectories of these sub-contractors for the past many years and sounded confident

    in their ability to scale up their business.

    Our view

    We believe there is no shortage of resource availability, be it manpower, equipments,raw materials, financing or sub-contractors. Even if there is any temporary resource

    crunch, the entrepreneurial spirit of contractors ensures that these are taken care of

    adequately. Also, with multiple providers of these resources (in terms of equipment

    manufacturers, banks and other financial institutions etc.), the timeliness and cost

    efficacy of supply is also reasonably ensures. One more positive thing is that even the

    small sized entities have access to these resources; also, these resources are not

    geographically concentrated. What this means is that if the regulatory side of approvals

    is taken care of, ramping up execution will not be too challenging.

    There is no shortage ofresource availability, beit manpower, equipment,raw materials, financingor sub-contractors

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    23/38

    Edelweiss Securities Limited 23

    Construction

    Cash contracts continue to get delayed

    We visited a number of projects being implemented on cash contract basis. The primary

    difference between these projects and BOT projects lies in the mode of funding; while cash

    contracts are funded by the government, in BOT projects, the developer has to tie up the

    financing i.e., in BOT projects, developers own money is at stake. As is natural, the

    commitment towards avoiding cost/time overrun is higher in BOT projects.

    It was not surprising to find that almost every cash contracting project that we visited was

    running behind schedule. Since there is no incentive for contractors to get involved in the

    process of land acquisition and other regulatory approvals, most contractors adopt a laidback

    attitude with regards to cash contracts. They were content with religiously documenting their

    machine/labour idle time for the purpose of claims adjustment at a later stage. The entire

    responsibility for getting regulatory approvals in this case lies with the client (NHAI/State

    PWD etc). The process is rarely completed in time due to bureaucratic hurdles. Thus, cash

    contracts continue to get delayed. As is natural, the chances of legal disputes at a later stage

    in such projects are also much higher.

    Fig. 20: Project stalled due to delays in land acquisition Fig. 21: Project stuck due to delays in utility shifting

    Source: Edelweiss research

    The delay in cash contracts is also due to the fact that the incentive payment for an early

    completion of a cash contract project is minuscule as compared to those for BOT projects

    (bonus annuities or early toll collection). Hence, contractors are also not proactive in

    completion of cash contracts on time.

    Data from NHAI corroborates our hypothesis. Of the 136 projects which were running late

    w.r.t. their original implementation schedule at Sep 2010 end, only 28 were on BOT basis

    (toll or annuity), balance were all cash contracts.

    It needs to be kept in mind that only ~ 9% of projects in the NHDP work plan for future

    (approved last year) are proposed to be completed under the EPC mode. This means that

    future delays in NHAI projects may be lesser than the past due to smaller share of cash

    contracts. However, for state government roads and district roads which continue to be

    implemented on EPC basis, there is no such ray of hope.

    Most cash contractscontinue to get delayed

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    24/38

    24 Edelweiss Securities Limited

    Construction

    Outlook on road projects execution

    Over FY09-10, the government has initiated many steps to ensure that there is a pick-up in

    the pace of project award. We believe project award is unlikely to be a major

    dampener going forward; this leaves execution issues as the principal irritant in

    improving the pace of road project development.

    Our interaction with developers and other project execution personnel has convinced us that

    there are quite a few positives when it comes to road project execution. Enhanced developer

    involvement, good resource availability and increased government efforts are likely to ensure

    that the execution on road projects is likely to improve going ahead. However, regulatory

    constraints continue to stifle efforts to build 20 km/day of roads. We believe if the regulatory

    side of approvals is taken care of, ramping up execution will not be too challenging.

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    25/38

    Edelweiss Securities Limited 25

    Construction

    Major project details

    We highlight the key learnings from some major projects we visited:

    Dhule-Palasner project

    Key project specific details:

    Developer: Hindustan Construction / Sadbhav Engg / John Laing consortium

    Project scope: Design, engineering, finance, procurement, construction, operation

    and maintenance of 4/6 laning of Madhya Pradesh/ Maharashtra border-Dhule

    Section of NH-3 from km 168.500 to km 265.000 in Maharashtra under NHDP Phase

    III A on BOT (Toll) basis. The concession period is 18 years including construction

    period of 30 months.

    Client: NHAI

    Project award date: Jan 2009

    Scheduled completion date: June 2012

    Total project cost: INR 14.2 bn

    Significance of the project: The project involves expansion of an existing 2 lane

    stretch on NH-3 into 4 lane. National Highway 3 (NH-3), which is commonly referred

    to as the Mumbai-Agra Highway, is a major Indian national highway that runs

    through the states of Uttar Pradesh, Rajasthan, Madhya Pradesh and Maharashtra.

    The highway originates in Agra in Uttar Pradesh, travels South-West through

    Dhaulpur in Rajasthan, Gwalior, Shivpuri, Guna, and Indore in Madhya Pradesh, and

    Dhule, Nashik, Thane and terminates at Mumbai in Maharashtra. NH 3 runs for a

    distance of 1,161 km.

    The project starts from the city of Dhule. At Dhule, NH-3 crosses National Highway 6

    (NH-6) which is a busy national highway that runs through Gujarat, Maharashtra,

    Chhattisgarh, Orissa, Jharkhand and West Bengal. NH-6 passes through the cities of

    Surat, Dhule, Nagpur, Raipur, Sambalpur, Kolkata, running over 1,949 km from

    Hazira to Kolkata.

    Fig. 22: Location of the project Fig. 23: Project stretch

    Source: Maps of India, Google map, Edelweiss research

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    26/38

    26 Edelweiss Securities Limited

    Construction

    Key observations from site visit:

    Land acquisition problems and forest clearance big challenges: We learnt

    that the project faced land acquisition problems in the beginning. This was primarily

    due to resistance from land owners who were demanding a higher compensation for

    their land. There was some opposition amongst people due to compensation rates

    being different from village to village. Also, land acquisition was not lateral in nature.

    Moreover, since the project passes through a stretch which has forests, clearance

    from MoEF was required. This took some time.

    Local resistance led to design changes: Since the project passes through an

    urban area, there was a demand from the local population to include certain

    underpasses which were earlier not part of the original scope of the project. This

    issue has been sorted out now. The changes have been incorporated and the

    additional cost to be incurred has also been approved by the client.

    Project designed keeping future needs in mind: The project has been designed

    keeping in mind the expected traffic growth in the future. As a result, even though

    the project will be a 4 lane road after completion, various structures such as flyovers,

    bridges etc., which are being built will have 6 lanes. We believe this is a step in the

    right direction to ensure that the project can handle the increase in traffic ahead and

    that future capacity expansion will not be difficult.

    Fig. 24: Execution underway on a major bridge Fig. 25: Construction in full swing on a bridge across

    a river

    Source: Edelweiss research

    Despite challenges, project running ahead of schedule: Despite the challenges

    mentioned above, the project has been running ahead of schedule. This is primarily due

    to the developers proactive attitude, aided by the NHAI. The developer mobilisedresources as soon as the project was awarded. Also, a major effort was put in identifying

    the challenges in land acquisition, forest clearance etc., in the initial part of the project

    itself. Close coordination with various government departments has ensured that all local

    clearances have been achieved; design changes have also been incorporated. Significant

    progress on the land acquisition front has also been achieved. As a result, currently the

    project is ahead of schedule.

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    27/38

    Edelweiss Securities Limited 27

    Construction

    Fig. 26: Execution on track after resolution of land Fig. 27: In spite of heavy traffic, construction is ahead

    acquisition issues of schedule

    Source: Edelweiss research

    The progress on the project is commendable considering that the stretch lies on a busy

    route. There was heavy traffic on the road; despite this, construction was in full swing.

    Crushers, wet mix plants, batching and asphalt plants were in operation; similarly,

    machines like excavators, pavers, graders etc., were also working.

    Hyderabad outer ring road project

    Key project specific details are:

    Road stretch: Cyberabad Expressway

    Developer: Gayatri Projects consortium

    Project scope: Design, construction, development, finance, operation and

    maintenance of an eight lane access controlled expressway from Kollur to

    Patancheru (km. 12 to km 23.70). The project is on BOT-annuity basis under Phase

    II programme of Hyderabad outer ring road (ORR).

    Client: Hyderabad Growth Corridor (HGCL), an SPV formed for development for the

    Hyderabad outer ring road by the state government.

    Date of commencement: Dec 2007

    Total project cost: INR 5.01 bn

    Significance of the project: The Hyderabad ORR is aimed at the development of

    well planned and well connected urban settlements around the Hyderabad

    Metropolitan area. The 159 km long ring road provides connectivity to various state

    and national highways to bypass the city of Hyderabad. The proposed corridor is

    expected to relieve congestion in the metropolitan area and inner ring road, provide

    orbital linkage to radial arterial roads, provide link to the proposed MRTS and bussystem and provide quick access to the international airport from strategic parts of

    the city.

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    28/38

    28 Edelweiss Securities Limited

    Construction

    Fig. 28: Outer ring road project in Hyderabad city Fig. 29: Project stretch (Cyberabad expressway)

    Source: HUDA, Edelweiss research

    Key observations from site visit:

    Major portion of project completed: Work on majority of the project stretch has

    been completed. Construction is still going on a small stretch of the road.

    Fig. 30: Completed portion of the expressway Fig. 31: Work going on a small stretch of road

    Source: Edelweiss research

    Land acquisition problems delays project: The project has been delayed due to

    land acquisition problems. Our interaction with project personnel indicated that

    majority of the work has been completed. However, land acquisition problem for a

    small stretch of land has meant that the work is incomplete on that portion of the

    project.

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    29/38

    Edelweiss Securities Limited 29

    Construction

    Fig. 32: Project stalled due to land acquisition issues Fig. 33: Progress hampered by delays in land

    acquisition

    Source: Edelweiss research

    A look at the website of Hyderabad Metropolitan Development Authority indicates

    that this indeed is the case. Of the RoW of 11.7 km required for the project, only

    11.2 km has been handed over.

    Utility shifting: Apart from land acquisition, the project progress was also

    hampered by delays in utility shifting. This happened due to delay in getting

    approval for shifting power transmission lines.

    Fig. 34: Shifting of power transmission lines delayed Fig. 35: Utility shifting hampers project completion

    project execution schedule

    Source: Edelweiss research

    The developer has been coordinating with HGCL for getting the approval for this purpose.

    Timely land acquisition could have avoided the delay: The project has been

    delayed by more than three months due to delay in land acquisition/utility shifting.

    To put things in perspective, an identical project on the same road by the

    same developer has been completed six months ahead of schedule i.e.

    Hyderabad Expressway is a 13 km stretch of Hyderabad ORR from Bongulur to

    Tukkuguda. This project (again an access controlled 8 lane expressway) being

    undertaken by a consortium headed by Gayatri Projects has been completed 6

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    30/38

    30 Edelweiss Securities Limited

    Construction

    months ahead of schedule. This was possible due to timely handover of land

    required for the project.

    Key learning: Despite being close to an urban area which raises its own set of

    execution challenges, the developer has been able to build a good quality road

    ahead of schedule when RoW was available; however, when land acquisition/utility

    shifting is delayed, the project is delayed too despite the best efforts of thedeveloper.

    Pimpalgaon-Nashik-Gonde project

    Key project specific details:

    Developer: L&T / Ashoka Buildcon consortium

    Project scope: Design, engineering, finance, procurement, construction, operation

    and maintenance of 6 laning of Pimpalgaon-Nashik-Gonde Section of NH3 from 380

    kms to 440 kms in Maharashtra under NHDP Phase III A on BOT (toll) basis. The

    project involves construction of 452 lane kms of roads. The concession period will

    expire in January 2029.

    Client: NHAI

    Project award date: Jan 2009. Construction began in January 2010.

    Scheduled completion date: July 2012

    Total project cost: ~ INR 17 bn

    Significance of the project: The project involves expansion of an existing 2 lane

    stretch on NH-3 into 6 lane.

    The project runs from Pimpalgaon to Gonde via Nashik with Gonde lying on the busy

    Mumbai-Nashik highway. Nashik today is one of the fastest growing cities in India

    and has been identified as a tier-2 metro. The city's economy is driven chiefly by the

    engineering and manufacturing industry; many auto majors and original equipment

    manufacturers have their plants here and have spawned a huge network of auto

    component suppliers and engineering ancillary services.

    Fig. 36: Location of the project Fig. 37: Project stretch

    Source: Maps of India, Google Maps, Edelweiss research

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    31/38

    Edelweiss Securities Limited 31

    Construction

    Key observations from site visit

    Land acquisition and utility shifting a key test: Since the project passes

    through the city of Nashik, land acquisition and utility shifting have emerged as a

    key test for the developer. We surmise that many small commercial establishments

    will have to be shifted to get the land required for road widening.

    Management of existing traffic will be the key: Since the project passes

    through a heavy traffic density area, developers have to undertake the construction

    work along with managing existing traffic. The project also contains an elevated

    corridor for traffic to bypass the underlying city congestion.

    Execution happening on both sides of the road: The existing road is 2 lane. Due

    to heavy growth in traffic, it is being directly widened to 6 lanes (instead of the

    more usual 2-to-4 laning in the first part and 4-to-6 laning thereafter). As a result,

    construction is being carried out on both sides of the road. Despite the challenging

    task, we believe the developer was carrying out work admirably. We did not see any

    disruption in traffic; work was going on smoothly.

    Fig. 38: Land acquired for widening on both sides of road Fig. 39: Construction in full swing

    Source: Edelweiss research

    Raw material availability enhances efficiencies: The project benefits from easy

    and cost effective raw material availability as the sources of raw material are close

    to the project site. This has in turn led to smooth resource mobilization. Ashoka

    Buildcon has two captive RMC plants with a capacity of 60 and 120 cubic meters per

    hour which are being used in execution of the project (Source: IPO prospectus).

    I S I E m e r g i n g M a r k e t s P D F i n

    D o w n l o a d e d b y i n - u n i v e r s a

  • 8/4/2019 Construction - Sector Update (1)

    32/38

    32 Edelweiss Securities Limited

    Construction

    Fig. 40: Adequate asset base helps in resource Fig. 41: Convenient raw material availability near

    mobilisation project site

    Source: Edelweiss research

    Project progress on track: In spite of the project lying on a busy route which brings

    traffic management into the picture, execution was on track. Construction was going

    ahead at full speed, aided by easy raw material availability and adequate resource

    mobilisation. Land acquisition challenges have been adequately met with good progress

    on land parcels located within the city. As a result, construction on the project is

    progressing satisfactorily.

    Ranchi ring road project

    Key project specific details:

    Developer: IL & FS Transportation Networks

    Project scope: The project is concerned with improvement of the Ranchi ring road

    (Sec III, IV, V and VI). It involves design, engineering, finance, procurement,

    construction, operation and maintenance of 6 lane divided carriageway on BOT

    (annuity) basis. The length of the project is 36.2 km. The concession period is 17.5

    years (including construction period of 30 months).

    Ranchi ring road is part of the Jharkhand Accelerated Road Development Programme

    (JARDP) which involves development of select road stretches in the state of

    Jharkhand. The total length covered under the programme is 1002 lane km; of this,

    phase I involves 3 projects (Ranchi ring road, Ranchi to Patratu road and Patratu to

    Ramgarh road) spread over 466 lane km while the balance comes under phase II.

    The Jharkhand government is a stakeholder in JARDP with it holding 26% equity in

    the SPV for the project.

    Client: Road construction department, Govt of Jharkhand

    Date of commencement: March 2010

    EPC cost: INR 4.77 bn

    EPC contractor: Sadbhav Engg

    Significance of the project: The project aims to ease traffic congestion in and

    around the city of Ranchi, the capital of the mineral rich state of Jharkhand. Ranchi

    boasts of a number of industrial facilities which are located in and around the city.

    With rapid growth in trade, commerce, and industry in the city, the traffic has

    jumped sharply.

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    33/38

    Edelweiss Securities Limited 33

    Construction

    Fig. 42: Location of the project Fig. 43: Ranchi ring road

    Source: Maps of India, Company, Edelweiss research

    Key observations from site visit

    Involvement of state govt helped in land acquisition: Since the state

    government holds a stake in the project SPV, there was a high degree of

    involvement from state officials in the project. This has helped in regulatory

    approvals like land acquisition, utility shifting, etc.

    Intensive project monitoring on the part of developers: The developer has

    given the EPC contract to a third party contractor. Developers involvement is in

    terms of design and value engineering, project development, consultancy and

    management as well as operations and maintenance management. To this end, the

    developer is intensely involved in all the facets of the project including review of theproject construction also. There are regular review meetings to take stock of

    progress as well as to assess and to plan for future milestones.

    Well qualified EPC contractor(s): The EPC contractor(s) engaged in the project

    are well qualifiedboth in terms of having a substantial equipment base and

    technical/human resources. This has helped in the smooth implementation of the

    project. The plant/machinery deployed at the site included batching plants,

    excavators, graders, compactors, tippers, pavers, rollers, transit mixers, crushers

    etc.

    I S I E m e r g i n g M a r k e t s P D F i n

    D o w n l o a d e d b y i n - u n i v e r s a

  • 8/4/2019 Construction - Sector Update (1)

    34/38

    34 Edelweiss Securities Limited

    Construction

    Fig. 44: Excellent asset base with EPC contractors Fig. 45: Equipment strength not lacking in case of

    contractors

    Source: Edelweiss research

    Construction in full swing: The project involves construction of various structures

    like flyovers, RoBs/RuBs and major/minor bridges. At certain points, it intersects

    existing national highways as well. Regulatory approvals for various structures were

    in place and execution was in full swing. Overall, the project is progressing as per

    schedule.

    Fig. 46: Work on structures is going on Fig. 47: Execution is progressing as per schedule

    Source: Edelweiss research

    Key learning: In case the state government is actively involved, getting regulatory

    approvals becomes easy. Also, regular project monitoring and review along withintensive developer involvement is the key for a project being on the right track.

    This, when supported by well qualified contractors, leads to smooth project

    execution.

    I S I E m e r g i n g M a r k e t s P D F i n

    D o w n l o a d e d b y i n - u n i v e r s a

  • 8/4/2019 Construction - Sector Update (1)

    35/38

    Edelweiss Securities Limited 35

    Construction

    NOTES:

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. Down

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unau

  • 8/4/2019 Construction - Sector Update (1)

    36/38

    36 Edelweiss Securities Limited

    Construction

    NOTES:

    I S I E m e r g i n g M a r k e t s P D F i n

    D o w n l o a d e d b y i n - u n i v e r s a

  • 8/4/2019 Construction - Sector Update (1)

    37/38

    Edelweiss Securities Limited 37

    Construction

    Edelweiss Research is also available on www.edelresearch.com ,Bloomberg EDEL , Thomson First Call, Reuters and Factset. Edelweiss Securities Limited

    Edelweiss Securities Limited, 14th Floor, Express Towers, Nariman Point, Mumbai 400 021,Board: 91-22 2286 4400, Email: research@edelca .com

    Vikas Khemani Head Institutional Equities [email protected] +91 22 2286 4206

    Nischal Maheshwari Head Research [email protected] +91 22 6623 3411

    Cove r age g r oup ( s ) o f s t ocks by p r im a r y ana lys t ( s ) : Cons t ruc t ion

    Consolidated Construction Co., C and C Construction, Gammon India, Hindustan Construction Co., IRB Infrastructure, IVRCL Infra,Jaiprakash Associates, BL Kashyap & Sons Ltd, Man Infraconstruction, Nagarjuna Construction Co, Patel Engineering Ltd, SimplexInfrastructures Ltd

    EW Indices Recent Research

    This document has been prepared by Edelweiss Securities Limited (Edelweiss). Edelweiss, its holding company and associate companies are a full service, integrated

    investment banking, portfolio management and brokerage group. Our research analysts and sales persons provide important input into our investment banking

    activities. This document does not constitute an offer or solicitation for the purchase or sale of any financial instrument or as an official confirmation of any

    transaction. The information contained herein is from publicly available data or other sources believed to be reliable, but we do not represent that it is accurate orcomplete and it should not be relied on as such. Edelweiss or any of its affiliates/ group companies shall not be in any way responsible for any loss or damage that

    may arise to any person from any inadvertent error in the information contained in this report. This document is provided for assistance only and is not intended to

    be and must not alone be taken as the basis for an investment decision. The user assumes the entire risk of any use made of this information. Each recipient of this

    document should make such investigation as it deems necessary to arrive at an independent evaluation of an investment in the securities of companies referred to inthis document (including the merits and risks involved), and should consult his own advisors to determine the merits and risks of such investment. The investment

    discussed or views expressed may not be suitable for all investors. We and our affiliates, group companies, officers, directors, and employees may: (a) from time to

    time, have long or short positions in, and buy or sell the securities thereof, of company (ies) mentioned herein or (b) be engaged in any other transaction involving

    such securities and earn brokerage or other compensation or act as advisor or lender/borrower to such company (ies) or have other potential conflict of interest withrespect to any recommendation and related information and opinions. This information is strictly confidential and is being furnished to you solely for your

    information. This information should not be reproduced or redistributed or passed on directly or indirectly in any form to any other person or published, copied, inwhole or in part, for any purpose. This report is not directed or intended for distribution to, or use by, any person or entity who is a citizen or resident of or located inany locality, state, country or other jurisdiction, where such distribution, publication, availability or use would be contrary to law, regulation or which would subject

    Edelweiss and affiliates/ group companies to any registration or licensing requirements within such jurisdiction. The distribution of this document in certain

    jurisdictions may be restricted by law, and persons in whose possession this document comes, should inform themselves about and observe, any such restrictions.

    The information given in this document is as of the date of this report and there can be no assurance that future results or events will be consistent with thisinformation. This information is subject to change without any prior notice. Edelweiss reserves the right to make modifications and alterations to this statement as

    may be required from time to time. However, Edelweiss is under no obligation to update or keep the information current. Nevertheless, Edelweiss is committed to

    providing independent and transparent recommendation to its client and would be happy to provide any information in response to specific client queries. Neither

    Edelweiss nor any of its affiliates, group companies, directors, employees, agents or representatives shall be liable for any damages whether direct, indirect, specialor consequential including lost revenue or lost profits that may arise from or in connection with the use of the information. Past performance is not necessarily a

    guide to future performance. The disclosures of interest statements incorporated in this document are provided solely to enhance the transparency and should not be

    treated as endorsement of the views expressed in the report. Edelweiss Securities Limited generally prohibits its analysts, persons reporting to analysts and their

    family members from maintaining a financial interest in the securities or derivatives of any companies that the analysts cover. The analyst for this report certifiesthat all of the views expressed in this report accurately reflect his or her personal views about the subject company or companies and its or their securities, and no

    part of his or her compensation was, is or will be, directly or indirectly related to specific recommendations or views expressed in this report.

    Copyright 2009 Edelweiss Research (Edelweiss Securities Ltd). All rights reserved

    Access the entire repository of Edelweiss Research on w ww .edelresearch.com

    Distribution of Ratings / Market Cap

    Edelweiss Research Coverage Universe

    Rating Distribution* 116 45 12 176

    * 3 stocks under review

    Market Cap (INR) 110 53 13

    > 50bn Between 10bn and 50 bn < 10bn

    Buy Hold Reduce Total

    Rating Interpretation

    Buy appreciate more than 15% over a 12-month period

    Hold appreciate up to 15% over a 12-month period

    Reduce depreciate more than 5% over a 12-month period

    Rating Expected to

    16-Nov-10 IVRCLInfra

    Weak quarter; strongorder book the only silverlining; Result Update

    133 Buy

    15-Nov-10 PatelEngineering Stable performance;progress on assetownership ventures;Result Update

    372 Buy

    12-Nov-10 ManInfraconst.

    Steady revenue growth;margins decline;Result Update

    339 Hold

    Date Company Title Price (INR) Recos

    800

    950

    1,100

    1,250

    1,400

    20-Nov-09 20-May-10 20-Nov-10

    EW Construction Index Nifty

    ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

    Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

  • 8/4/2019 Construction - Sector Update (1)

    38/38