Construction Sector - EMIS Insight - MENA... · Construction Sector in MENA ... Yemen is the only...
Transcript of Construction Sector - EMIS Insight - MENA... · Construction Sector in MENA ... Yemen is the only...
- 1 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Produced by:
Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Construction SectorMENAJuly 2015
- 2 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Table of Contents
I. Regional Sector Overview
1. Definition of MENA Region
2. Construction Sector in MENA
3. MENA Region: Share of Construction Sector in GDP
4. MENA Region: Share of Construction Sector in GDP (cont'd)
5. MENA Region: Share of Construction Sector in GDP (cont'd)
6. MENA Region: Share of Construction Sector in GDP (cont'd)
7. MENA Region: Construction Sector Growth, 2011-2014 CAGR
8. MENA Region: Ease of Dealing with Construction Permits
9. MENA Region: Ease of Dealing with Construction Permits (cont'd)
10. MENA Region: Ease of Dealing with Construction Permits (cont'd)
11. MENA Region: Ease of Dealing with Construction Permits in 2015, Ranking
II. Qatar
1. Sector Highlights
2. Economic Indicators
3. Construction Industry Data
4. Construction Industry Data (cont’d)
5. Construction Industry Forecast
6. Residential Building Data
7. Non-residential Building Data
8. Segmentation of the Non-residential and Infrastructure Subsectors, 2014
9. Major Construction Projects
10. Major Construction Projects (cont'd)
11. Major Construction Projects (cont'd)
12. Major Construction Projects (cont'd)
13. Major Construction Projects (cont'd)
14. Investment Climate
15. Investment Climate (cont'd)
III. Saudi Arabia
1. Sector Highlights
2. Economic Indicators
3. Construction Industry Forecast
4. Construction Industry Data
5. Major Construction Projects
6. Major Construction Projects (cont’d)
7. Major Construction Projects (cont’d)
8. Major Construction Projects (cont’d)
9. Major Construction Projects (cont'd)
10. Major Construction Projects (cont'd)
11. Major Construction Projects (cont'd)
12. Investment Climate
13. Investment Climate (cont’d)
- 3 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Table of Contents
IV. United Arab Emirates
1. Sector Highlights
2. Economic Indicators
3. Construction Industry Forecast
4. Construction Regional Data
5. Construction Regional Data (cont'd)
6. Construction Regional Data (cont'd)
7. Construction Regional Data (cont'd)
8. Major Construction Projects
9. Major Construction Projects (cont'd)
10. Major Construction Projects (cont'd)
11. Major Construction Projects (cont'd)
12. Investment Climate
13. Investment Climate (cont'd)
V. Main Players
1. Top M&A Deals
2. M&A Activity, 2013-2014
3. Arabtec Holding PJSC
4. Arabtec Holding PJSC (cont’d)
5. Drake & Scull International PJSC
6. Drake & Scull International PJSC (cont’d)
7. Combined Group Contracting Co.
8. Combined Group Contracting Co. (cont’d)
9. Galfar Engineering And Contracting SAOG PLC
10. Galfar Engineering And Contracting SAOG PLC (cont’d)
11. National Marine Dredging Company PSC
12. National Marine Dredging Company PSC (cont’d)
- 4 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
I. Regional Sector Overview
- 5 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Comments
Definition of MENA Region
The current report outlines the development of the construction sector in the Middle East and North Africa (MENA) region, which is composed
of 17 countries: Algeria, Bahrain, Egypt, Iran, Iraq, Jordan, Kuwait, Lebanon, Libya, Morocco, Oman, Qatar, Saudi Arabia, Syria, Tunisia,
United Arab Emirates (UAE) and Yemen. The report focuses on three main countries, namely Qatar, Saudi Arabia, and the United Arab
Emirates. They were selected because of the huge project pipeline of each country related to ambitions to diversify the economy and also to
large scale international events like the World Expo 2020 in Dubai and the FIFA World Cup 2022 that will take place in Qatar.
Middle East and North Africa Region
EMIS
- 6 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Construction Sector in MENA
High-income
Countries
Bahrain, Kuwait, Oman, Qatar, Saudi Arabia, United Arab Emirates
The economies of these oil-rich countries are highly dependent on the production and export of hydrocarbons. Over the
2011-2014 period, the construction sector accounted for around 5% of their national GDPs, with the exception of Kuwait,
where construction accounts for about 2% of GDP. It is worth noting that with a CAGR of 15.2% the Qatari construction
sector was the third fastest growing within MENA between 2011 and 2014.
In addition, four of countries in this group are in MENA’s Top 5 regarding the ease of dealing with construction permits in
2015. These are UAE, Bahrain, Saudi Arabia and Qatar.
Upper-
middle-
income
Countries
Algeria, Iran, Iraq, Jordan, Lebanon, Libya, Tunisia
The contribution of the construction sector to GDP within this group is highly variable. While the sector accounted for
around 9.7% of Algerian GDP between 2010 and 2013 and for 8.6% of Iranian GDP between 2011 and 2014, it stood at
4% to 5% of the economies of Jordan, Lebanon, and Tunisia in 2011 – 2014.
Remarkably, between 2011 and 2014 the construction sector in Iran and Lebanon saw a double-digit increase and grew
fastest within MENA at impressive CAGRs of 39% and 26%, respectively. However, due to high costs and extensive
waiting time, the two countries are also among those in the region, where it is hardest to deal with construction permits.
Lower-
middle-
income
Countries
Egypt, Morocco, Syria, Yemen
Yemen is the only economy in the region where the construction industry registered an average annual decline of 5.7% in 2010-2013. The downturn was driven by the 2011 recession, coupled with extensive corruption in the country. However, Yemen’s construction sector appears to be on its way to recovery, registering an average growth of 11.2% in 2012 and 2013.
During the 2011 – 2014 period, the construction sector contributed around 4.6% to the Egyptian economy and increased by a CAGR of 14%, ranking the 4th fastest growing in the region. However, the country is among the laggards in MENA as far as dealing with construction permits is concerned, mainly because of long waiting time to obtain all needed documentation.
EMIS, World Bank, National Statistics
- 7 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
MENA: Share of the Construction Sector in GDP*
Algeria
Egypt
Bahrain, GDP Value Added
Iran, GDP Basic Prices
CEIC, National Statistics, - * Unless specified otherwise, data present GDP and sector shares at current prices.
10.5% 9.2% 9.3% 9.8%
89.5% 90.8% 90.7% 90.2%
14.9%
6.0%
11.8%8.7%
2010 2011 2012 2013
Other sectors
Constructionsector
Constructionsector, YoYchange
6.1% 6.0% 5.9% 6.3%
93.9% 94.0% 94.1% 93.7%
-7.1% 3.6% 5.0% 9.8%
2011 2012 2013 2014
Other sectors
Constructionsector
Constructionsector, YoYchange
4.6% 4.5% 4.6% 4.7%
95.4% 95.5% 95.4% 95.3%
14.2%12.2%
13.9%15.9%
2011 2012 2013 2014
Other sectors
Constructionsector
Constructionsector, YoYchange
7.6%
7.9% 9.8% 9.2%
92.4% 92.1% 90.2% 90.8%
3.0%
36.4% 40.7%
24.9%
2011 2012 2013 2014
Other sectors
Constructionsector
Constructionsector, YoYchange
- 8 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
MENA: Share of the Construction Sector in GDP* (cont’d)
Jordan
Lebanon, GDP Gross Value Added
Kuwait
Morocco, GDP Value Added
4.3% 4.4% 4.4% 4.5%
95.7% 95.6% 95.6% 95.5%
-0.9%8.3% 10.3% 7.5%
2011 2012 2013 2014
Other sectors
Constructionsector
Constructionsector, YoYchange
2.3% 1.7% 1.8% 2.1%
97.7% 98.3% 98.2% 97.9%
32.7%
-14.1%
7.8% 8.0%
2011 2012 2013 2014
Other sectors
Constructionsector
Constructionsector, YoYchange
4.3%
4.8% 5.6% 6.7%
95.7% 95.2% 94.4% 93.3%
-16.6%
20.5% 27.7% 29.2%
2011 2012 2013 2014
Other sectors
Constructionsector
Constructionsector, YoYchange 6.0% 6.2% 6.1% 6.3%
94.0% 93.8% 93.9% 93.7%
10.1% 6.7% 3.8% 4.0%
2011 2012 2013 2014
Other sectors
Constructionsector
Constructionsector, YoYchange
CEIC, National Statistics, - * Unless specified otherwise, data present GDP and sector shares at current prices.
- 9 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
MENA: Share of the Construction Sector in GDP* (cont’d)
Oman, GDP Basic Prices
Saudi Arabia
Qatar
Tunisia GDP Factor Cost
5.2% 5.7% 5.2% 6.2%
94.8% 94.3% 94.8% 93.8%
14.5% 20.8%-5.8% 24.9%
2011 2012 2013 2014
Other sectors
Constructionsector
Constructionsector, YoYchange 4.6% 4.4% 5.2% 5.7%
95.4% 95.6% 94.8% 94.3%
3.0% 8.7% 24.7% 12.9%
2011 2012 2013 2014
Other sectors
Constructionsector
Constructionsector, YoYchange
4.3% 4.3% 4.8% 5.5%
95.7% 95.7% 95.2% 94.5%
17.9% 10.7% 13.6% 13.7%
2011 2012 2013 2014
Other sectors
Constructionsector
Constructionsector, YoYchange 4.7% 4.6% 4.6% 4.6%
95.3% 95.4% 95.4% 95.4%
-1.3% 1.8% 1.5% 1.9%
2011 2012 2013 2014
Other sectors
Constructionsector
Constructionsector, YoYchange
CEIC, National Statistics, - * Unless specified otherwise, data present GDP and sector shares in current prices.
- 10 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Comments
Source:
MENA: Share of the Construction Sector in GDP* (cont’d)
Note: Data concerning the 2010-2013/14 period are not available for Iraq, Libya, and Syria.
United Arab Emirates Yemen
5.4% 3.7% 3.9% 4.1%
94.6% 96.3% 96.1% 95.9%
10.0% -32.1% 6.9% 15.4%
2010 2011 2012 2013
Other sectors
Constructionsector
Constructionsector, YoYchange9.5% 8.8% 8.8% 9.0%
90.5% 91.2% 91.2% 91.0%
-0.1% -1.4% 3.4% 6.2%
2011 2012 2013 2014
Other sectors
Constructionsector
Constructionsector, YoYchange
CEIC, National Statistics, - * Unless specified otherwise, data present GDP and sector shares in current prices.
- 11 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
MENA: Construction Sector Growth, 2011-2014 CAGR
Country Ranking*
CEIC, National Statistics, - * CAGR of Algeria and Yemen is calculated over the 2010-2013 period due to unavailable data for 2014.
33.8%
25.7%
15.2%
14.0%
12.6%
12.4%
8.8%
8.7%
7.8%
6.1%
4.9%
2.6%
1.7%
-5.7%
Iran Lebanon Qatar Egypt Saudi Arabia
Oman Algeria Jordan Kuwait Bahrain
Morocco United Arab Emirates Tunisia Yemen
- 12 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
MENA: Ease of Dealing with Construction Permits
Procedures to legally build a warehouse, number Comments
The procedures to legally build a warehouse are fewest in
Iraq, UAE, Bahrain, Saudi Arabia, and Oman.
On the contrary, construction developers need to pass
through the most complex procedures if they are building
in Syria, Kuwait, Egypt, and Lebanon.
However, the number of procedures is not completely
relevant to the ease of dealing with construction permits
as it remains unknown how much time they take. For
instance, Iran has about the average number of
procedures in the region but they take the longest among
all MENA economies. In Morocco there is one procedure
less than in Iran, but the time needed to complete the
bureaucratic work is three times less than that in Iran.
Note: Procedures to legally build a warehouse include
submitting all relevant documents and obtaining all
necessary clearances, licences, permits and certificates;
completing all required notifications and receiving all
necessary inspections; obtaining utility connections for
water, sewerage and a land telephone line, registering the
warehouse after its completion (if required for use as a
collateral or for transfer of the warehouse).
Doing Business 2010 -2014 Reports, - * MENA Average is calculated for the 17 countries under analysis and excludes economies, that might be part of the region in other classifications
2010 2011 2012 2013 2014
MENA Average* 19 19 16 17 16
Algeria 22 22 19 19 19
Bahrain 13 13 12 12 12
Egypt 25 25 22 22 21
Iran 17 17 16 16 16
Iraq 14 14 13 12 10
Jordan 19 19 17 17 17
Kuwait 25 25 24 24 24
Lebanon 20 21 19 19 20
Libya n/a n/a n/a n/a n/a
Morocco 19 19 15 15 15
Oman 16 15 14 13 13
Qatar 19 19 17 16 17
Saudi Arabia 17 12 9 14 12
Syria 26 26 23 23 n/a
Tunisia 20 20 17 17 19
United Arab Emirates 17 17 14 14 12
Yemen 15 12 12 12 14
- 13 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
MENA: Ease of Dealing with Construction Permits (cont’d)
Time required to complete each procedure, calendar days Comments
Economies in MENA vary sharply in terms of
calendar days needed to obtain all permits related to
the legal construction of a warehouse.
UAE, Bahrain, Qatar, and Jordan are the countries
where the procedures are the most streamlined and
facilitated, and thus take the shortest time.
On the other hand, the time required to complete
each procedure is the longest in Iran, where it takes
almost a year. Legally building a warehouse is a
lengthy process in Algeria, Lebanon, and Yemen as
well, where it takes considerably longer than the
average time needed in the region.
Note: Time required to complete each procedure does not
include time spent gathering information. Each procedure
starts on a separate day. Procedures that can be fully
completed online are an exception to this rule. The
procedure is considered completed once the final
document is received. No prior contact with officials is
assumed.
Doing Business 2010 -2014 Reports, - * MENA Average is calculated for the 17 countries under analysis and excludes economies, that might be part of the region in other classifications.
2010 2011 2012 2013 2014
MENA Average* 150 148 140 146 143
Algeria 240 240 281 281 241
Bahrain 43 43 43 43 60
Egypt 218 218 218 218 179
Iran 322 322 320 320 320
Iraq 215 215 187 187 139
Jordan 87 87 70 70 70
Kuwait 104 104 130 130 130
Lebanon 211 218 219 219 246
Libya n/a n/a n/a n/a n/a
Morocco 163 163 97 97 97
Oman 242 186 174 174 174
Qatar 76 76 70 62 63
Saudi Arabia 94 89 75 103 102
Syria 128 128 104 104 n/a
Tunisia 84 97 88 88 94
United Arab Emirates 64 64 46 46 44
Yemen 107 116 116 191 186
- 14 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
MENA: Ease of Dealing with Construction Permits (cont’d)
Cost required to complete each procedure, % of income per capita Comments
The cost required to complete each procedure is a
function of the income per capita within the
respective country. Therefore, income levels should
be carefully examined and taken into account as they
vary widely within MENA.
Based on World Bank data on GDP per capita in
current USD for 2014, Kuwait (USD 50,108),
Lebanon (USD 35,791), Jordan (USD 27,113) and
Saudi Arabia (USD 12,705) were the economies
where it was the most expensive to obtain all permits
to legally construct a warehouse in 2014.
The countries where it was the least expensive
during the last year were Yemen (USD 766), Qatar
(USD 934), Bahrain (USD 2,268), and Algeria (USD
3,217).
Note: The indicator measures official costs only and
excludes bribes.
Doing Business 2010 -2014 Reports, - * MENA Average is calculated for the 17 countries under analysis and excludes economies, that might be part of the region in other classifications
2010 2011 2012 2013 2014
MENA Average* 290 270 190 162 131
Algeria 40 44 23 55 60
Bahrain 55 78 11 10 9
Egypt 332 294 155 135 108
Iran 366 382 356 262 225
Iraq 398 507 470 110 17
Jordan 697 634 534 530 500
Kuwait 124 173 122 96 99
Lebanon 195 285 235 302 353
Libya n/a n/a n/a n/a n/a
Morocco 264 252 235 220 218
Oman 428 106 46 38 35
Qatar 1 1 1 1 1
Saudi Arabia 33 44 19 25 25
Syria 540 568 504 484 n/a
Tunisia 998 859 261 256 256
United Arab Emirates 31 36 5 9 12
Yemen 144 61 61 52 48
- 15 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
MENA: Ease of Dealing with Construction Permits in 2015
Country Ranking
Doing Business 2015 Report
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
16
United Arab Emirates Bahrain Iraq Saudi Arabia QatarOman Morocco Yemen Tunisia KuwaitJordan Algeria Egypt Lebanon IranSyria Libya
- 16 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
II. Selected Economies
Qatar
- 18 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Qatar: Sector Highlights
The Qatari construction sector, including infrastructure, residential and non-residential buildings, is the fastest growing sector in the country. In an effort to diversify
its oil-dominated economy and to prepare for the upcoming 2022 FIFA World Cup, Qatar has entered a phase of massive spending on all subsectors. The country
has pledged USD 140bn of investment between 2015 and 2020, as told by Qatar’s minister of transport, Jassim Saif Ahmed Al Sulaiti in September, 2014.
However, the rapid growth comes with its numerous challenges - late payments, inflation, recurrent project delays, and bottlenecks in the supply of labour and
materials. Notably, bad labour conditions on the construction sites, in particular stadiums, have come under considerable international scrutiny.
Overview
Non-residential Construction
The residential construction in Qatar is fueled by a growing population and a growing economy. The Qatari population is expected to grow by 4%
y/y between 2014 and 2019. This demographic outlook, coupled with increased purchasing power will put pressure on housing. Technavio
Research experts project healthy demand for both luxury and affordable homes. The latter are mainly needed for the migrant manpower that is
working on the construction projects. For instance, a workers’ city in Barwa Al-Baraha, that will have capacity to house around 55,000 people, is
about to be completed.
Currently, the non-residential segment is fueled mainly by long-term complete city developments. Among them, Lusail and Barwa Al Khor cities are
standing out with respective values of USD 45bn and USD 9.9 bn. Naturally, some of the other major projects in the subsector are related to the
FIFA World Cup 2022. They include the USD 4bn expansion and construction of 12 stadiums which will host the games. Stadium construction is
coupled with extensive USD 20bn investments in hotel infrastructure by the Qatar Tourism Authority. BMI states that approx. 90,000 additional
hotel rooms are required to cater for the projected influx of 400,000 supporters.
Infrastructure is particularly influenced by the preparations for the World Cup 2022 as the country is building transport infrastructure to connect the
numerous World Cup sites to each other and to accommodate the huge tourist influx that is expected. The government is currently building its USD 28.8bn
national railway network and is implementing a USD 4.4bn expressway programme which provisions the construction of 900 km of first-class roads
throughout the country. The state has also allocated a huge investment of USD 36bn to build the Doha Metro. Already having serious traffic congestion
problems, the capital will need a working public transport system in order to cope with the tourist inflow coupled with the dense local population.
Infrastructure
Residential Construction
- 19 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Comments
Qatar: Economic Indicators
Qatari economy grew at an impressive CAGR of 9.7% in 2009-2014. BMI Research experts maintain a positive forecast for 2015 with a real GDP y/y growth at 6.6%. Growth is
mainly attributed to investment spending, especially in transport projects, expansionary fiscal stance, and population growth, as explained by the Qatari ministry of development
planning and statistics. The falling oil prices are a key risk to the economic outlook of Qatar, the country being a major oil and gas exporter. However, the ministry considers state
finances as a sufficiently strong to shield the wider economy in 2015 with a fiscal surplus of 8.7% of GDP. According to BMI Research, inflation rate is expected to rise at 3.8% y/y
in 2015.
In 2011 to 2014, the construction sector increased by a CAGR of 15.2% - more than double the real growth rate of the economy which was 5.8% a year. The booming activity in the
sector has been coupled with a growing number of people employed in it. Last year, construction workers in Qatar made up 37.7% of the total active labour force in the country.
Selected Economic Indicators
CEIC, World Bank, Ministry of Development Planning and Statistics – Qatar, IMF, Reuters
2009 2010 2011 2012 2013 2014
GDP, constant prices 2005 (USD bn) 87 102 116 122 130 138
GDP, constant prices 2004 (QAR bn) 243 284 321 341 362 384
GDP, current prices (USD bn) 98 125 170 190 203 212
GDP, current prices (QAR bn) 356 455 618 693 735 765
GDP Real Growth Rate (%) 12.0 16.7 14.1 5.1 6.2 6.2
GDP, Non Oil: Construction (QAR bn) 26 28 28 31 38 43
GDP, Non Oil: Construction, Growth Rate (%) -6.2 7.8 3.0 8.7 24.7 12.9
People Employed in Construction, thou persons 545 559 498 499 569 636
Foreign Direct Investment, net inflows (USD bn, current) 8.1 4.7 -0.1 0.3 -0.8 n/a
Consumer Price Index (%) -4.9 -2.4 1.9 1.9 3.1 3.0
- 20 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Comments
Qatar: Construction Industry Data
Over the 2015-2018 period, BMI Research experts project 11.2% annual average real growth rate in the sector. Thanks to robust private consumption and
rapidly growing population, residential and non-residential building will perform better than infrastructure as it will both create more value and grow faster.
Residential and non-residential building is expected to account for an average 58% of the sector’s activity in 2015-2018. It is also projected to grow by an
impressive 15% annual average real growth rate, while infrastructure will increase tangibly slower by 6.5% over the 2015-2018 horizon.
Construction Industry Data
BMI Research, EMIS Insight
2013 2014e 2015f 2016f 2017f 2018f
Construction Industry Value, USD bn 9.7 11.6 13.6 15.9 18.3 20.7
Construction Industry Value Real Growth, % y-o-y 13.60 15.40 13.07 12.35 10.30 9.04
Construction Industry Value, % of GDP 4.80 5.50 6.20 6.60 6.80 7.10
Residential and Non-Residential Building Industry Value, % of total construction 49.92 52.77 55.56 57.64 58.90 59.94
Residential and Non-Residential Building Industry Value, USD bn 4.86 6.11 7.57 9.17 10.76 12.43
Residential and Non-Residential Building Industry Value Real Growth, % 16.57 22.20 19.30 16.71 12.81 11.05
Residential and Non-Residential Building Industry Value, % of GDP 2.40 2.88 3.44 3.80 4.03 4.24
Infrastructure Industry Value, % of total construction 50.10 47.20 44.40 42.40 41.10 40.10
Infrastructure Industry Value, USD bn 4.87 5.47 6.05 6.74 7.51 8.31
Infrastructure Industry Value Real Growth, % y-o-y 7.70 8.60 6.10 6.90 6.90 6.20
Infrastructure Industry Value, % of GDP 2.40 2.60 2.80 2.80 2.80 2.80
- 21 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Qatar: Construction Industry Data (cont’d)
Construction Industry Real Growth, % y-o-y
Construction Industry Value
BMI Research, EMIS Insight
13.615.4
13.1 12.4
10.39.0
16.6
22.2
19.3
16.7
12.811.1
7.78.6
6.16.9 6.9
6.2
2013 2014e 2015f 2016f 2017f 2018f
Construction industry real growth, % y-o-y Residential and non-residential building real growth, % y-o-y Infrastructure industry real growth, % y-o-y
4.86 6.117.57
9.1710.76
12.434.87
5.476.05
6.74
7.51
8.31
9.73
11.58
13.62
15.91
18.27
20.74
2013 2014e 2015f 2016f 2017f 2018f
Infrastructure, USD bn
Residential and non-residential building, USDbn
Total, USD bn
- 22 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Comments
Qatar: Construction Industry Forecast
Qatar is set for a steep growth of its construction industry. Experts from Oxford Economics expect an almost twofold increase of the
construction output value-added index in 2030 compared to 2015, surpassing by far the projected values for Middle East and Africa. The
positive outlook is associated with huge government investments, a stable business environment and growing consumer demand. Residential
and non-residential construction, the major growth driver in the industry, is leveraged by the massive infrastructure improvements throughout
the country and by the World Cup 2022 preparations. Indeed, developers are building major residential projects and the adjacent social
infrastructure, coupled with numerous hotels and stadiums.
Construction, Output (value-added index, 2015=100)
CEIC, Oxford Economics, BMI Research
100
122
175
224
268
100
113
138
168
202
100107
120
148
182
2015 2017 2020 2025 2030
Qatar Middle East Africa
- 23 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Qatar: Residential Building
Number of New Building Permits Issued
Area of Completed Residential Buildings
Completed Residential Buildings
Actual Cost of Completed Residential Buildings
CEIC, Ministry of Development Planning and Statistics - Qatar
4,09
3
4,94
5
4,43
0
4,73
3
3,96
2
-25.6%
20.8%
-10.4%
6.8%
-16.3%
2009 2010 2011 2012 2013
Permits issued YoY change, %
7,77
7
6,06
6
4,41
2
4,58
5
-22.8% -22.0%-27.3%
3.9%
2010 2011 2012 2013
Completed residential buildings, units YoY change, %
4,53
8
3,71
8
3,96
9
3,60
9
-18.1%
6.8%-9.1%
2010 2011 2012 2013
Completed residential buildings, thou sq.m. YoY change, %
11,2
96
10,2
64
11,8
66
5,42
0
-1.2%-9.1%
15.6%
-54.3%
2010 2011 2012 2013
Actual cost of completed residential buildings, QAR mn
YoY change, %
- 24 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Qatar: Non-Residential Building
Number of New Building Permits Issued
Area of Completed Non-Residential Buildings
Completed Non-Residential Buildings
Actual Cost of Completed Non-Residential Buildings
441
298
476 52
8
296
-25.0%-32.4%
59.7%
10.9%
-43.9%
2009 2010 2011 2012 2013
Permits issued YoY change, %
339
239 26
6
152-6.4%
-29.5%
11.3%
-42.9%
2010 2011 2012 2013
Completed non-residential buildings, units YoY change, %
2,26
9
1,80
8
1,85
5
1,71
7-20.3%
2.6%-7.4%
2010 2011 2012 2013
Completed non-residential buildings, thou sq.m.
YoY change, %
9,08
2
9,34
4
8,37
3
3,24
2
46.5%
-9.1%
15.6%
-54.3%
2010 2011 2012 2013
Actual cost of completed non-residential buildings, QAR mn
YoY change, %
CEIC, Ministry of Development Planning and Statistics - Qatar
- 25 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Qatar: Non-Residential Building and Infrastructure Segmentation
Non-Residential Building, 2014
Infrastructure, 2014
Technavio Research, EMIS
Industrial 59.3%
Commercial29.6%
Retail 5.8%
Cultural 5.4%
Oil & gas 36.9%
Power 19.5%
Transport 13.7%
Water 9.6%
Marine 7.0%
Mixed use 5.3%
Hospitality 2.6%
Education 2.3%Healthcare 2.3%Public 0.7%
Telecom 0.2%
- 26 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Qatar: Major Construction Projects
Major Ongoing Projects
BMI, Lusail, Festival City Doha, Msheireb, Doha News, Construction Week Online, Qatar Construction News, Mazaya Holding, The Peninsula Qatar, Qatar Tenders, Barwa, MEED
Project Name Value, USD mn Capacity/Length Overview Timeframe
Commercial ConstructionLusail City, Al
Daayen
45,000 38,000,000 sq m Lusail City is located approx. 15 km north of Doha. Once completed, the city will include 4 exclusive islands
and 19 multi-purpose residential, mixed use, entertainment and commercial districts. The city is expected
to accommodate 450,000 people in total, including residents, employees, and visitors. Among the
numerous residential and commercial units, 22 hotels with different international star ratings will be built.
2011 - 2020
Barwa Al Khor City 9,900 5,500,000 sq m This is a complete city development, including more than 17,000 housing units, as well as shopping malls,
leisure facilities, luxury hotels and a golf course.
After three-year
delay, works have
started in H1 2013.
Estimated end in
2018.
Lusail Golf
Residential
Development
Project
4,900 3,659,736 sq m Upon completion, the development will feature an 18-hole golf course, a tennis centre, as well as a 6-hole
Academy Golf Course, a retail village, and a boutique hotel offering 80 rooms. Residential components will
account for 31% of the development, and sports facilities and green areas - for the remaining 69%.
2018
Education City:
Research Institute
(QEERI) Sidra
Medical and
Research Center
2,500 The project includes the construction of a 9-storey hospital (512 beds), 7-storey clinic and research
building, as well as accomodation building for 350 nurses with additional service buildings, parking space
and associated facilities.
2008 - Fall of 2015
Doha Festival City
project
1,600 433,847 sq m When completed, the Doha Festival City will have some 250,000 sq m of gross leasable area, offering
shopping, entertainment, leisure, and hospitality services to its visitors. A 5-star hotel will also be featured
within the city along with one of the largest conference centres in Qatar.
2011 - 2016
Six-phase
Redevelopment of
Doha's Old
Industrial Area
1,100 The first stage will focus on infrastructure modernisation and will cost approx. USD 357mn. At planning stage
- 27 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Qatar: Major Construction Projects (cont’d)
Major Ongoing Projects
BMI, Lusail, Festival City Doha, Msheireb, Doha News, Construction Week Online, Qatar Construction News, Mazaya Holding, The Peninsula Qatar, Qatar Tenders, Barwa, MEED
Project Name Value, USD mn Capacity/Length Overview Timeframe
Commercial Construction (cont’d)Phase II(B) of the
Doha Convention
Centre and Tower
657 DCCT is a 551 m tall skyscraper with over 100 storeys located in the West Bay area. It was scheduled for
completion in 2012 but construction works have been suspended following the discovery that the building
would impact flight paths to and from Doha International Airport. However, work has restarted after the New
Doha Hamad International Airport was completed in 2014. The tower, shaped like a tapering obelisk, will
offer both residential and office space. At the very top, a private club will occupy a 60 m high glass-only
cylinder surrounded by extensions of the tower’s facade and supported by a structural helix. DCCT will also
comprise a 100,000 sq m convention centre and a 175,000 sq m car parking facility.
To be completed by
end-2015
Msheireb
Downtown Doha
project-Phase III
PPP, Doha
686
Msheireb is a sustainable downtown regeneration project that aims to revive the old commercial district of
Doha. The project will adhere to high standards in green building in order to reverse the energy-intensive
pattern of construction in Qatar. Upon completion, it will offer office space, retail, leisure facilities,
townhouses, upscale apartments, hotels, museums, civic services, as well as cultural and entertainment
venues. Interestingly, cars and traditional services will be strategically placed underground in several
basement levels, ensuring a pedestrian - friendly atmosphere. The total cost of the project amounts to USD
5.5 bn and it should be completed in 2016.
Started in 2013
Doha Msheireb
Downtown, Phase 2
632 Started in 2012
Msheireb
Downtown Doha
Project (Phase 1C)
411.9 To be completed by
end-2015
Marina Mall 275 Marina Mall, to be built in Lusail City, will offer 57,605 sq m of gross leasable area, with an additional
10,000 sq m hypermarket at basement level. The building will consist of five interconnected retail ‘islands’
that link the mall to a body of water that runs through the centre of the scheme. It should be completed in
2018.
In tender/tender
launched
Residential ConstructionMsheireb
Development
(formerly Heart of
Doha), Qatar
5,500 370,000 sq m Msheireb is a sustainable downtown regeneration project that aims to revive the old commercial district of
Doha. The project will adhere to high standards in green building in order to reverse the energy-intensive
pattern of construction in Qatar. Upon completion, it will offer office space, retail, leisure facilities,
townhouses, upscale apartments, hotels, museums, civic services, as well as cultural and entertainment
venues. Interestingly, cars and traditional services will be strategically placed underground in several
basement levels, ensuring a pedestrian - friendly atmosphere.
2010 - 2016
Sidra residential
project/Sidra Village
137 1,165 units
(75,995 sq m)Adjacent to the new Sidra Hospital, Sidra Village will provide 1,165 flats for its nursing staff. The village will
consist of 658 one-bedroom apartments of app. 50 sq m each, and 507 two-bedroom apartments of app.
85 sq m each.
Under Construction
- 28 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Qatar: Major Construction Projects (cont’d)
Major Ongoing Projects
BMI, Lusail, Festival City Doha, Msheireb, Doha News, Construction Week Online, Qatar Construction News, Mazaya Holding, The Peninsula Qatar, Qatar Tenders, Barwa, MEED
Project Name Value, USD mn Capacity/Length Overview Timeframe
Residential Construction (cont'd)Barwa Al-Baraha
Workers' City
1,000 1,800,000 sq m Located in close proximity to the Industrial Area, Barwa Al Baraha development is designed to serve as an
integrated workers' city that will accommodate 53,000 low-income expats and employees, making it the
GCC's largest workers' accommodation. In January 2014 the first phase of the project was completed, thus
establishing Qatar's largest truck and vehicle parking space. As of February 2015, the second phase of the
development was still underway. It comprises the construction of 64 buildings with 132 rooms each, as well
as amenities like dining and laundry services, shops, a mosque, sports fields, used car showrooms and
office space.
Launched in 2008.
Under construction
as of February 2015
Transport InfrastructureDoha Metro 36,000 230 km and 107
stations
Running underground as well as at elevated and at-grade levels, it will consist of four lines – Red (Coast)
Line, Green (Education) Line, Gold (Historic) Line, and Blue (City) Line. During the first phase 37 stations
will be constructed and over 86.5 km of track will be laid by 2019. In the second phase (2020 – 2026), 70
stations and some 146 km of track will be added to the network.
National Railway
Network
28,800 350 km It will be built in four phases between 2015 and 2030. Phase 1 foresees the construction of approximately
143 km of operational railway track with 34 turnouts (main tracks), one station, three freight yards, one
intermodal yard, 59 bridges and 36 culverts (a tunnel for a road or drain going under a road or railroad). In
February 2015, Qatar Rail launched a new prequalification process for the civil works on the first phase.
Upon completion, the network will consist of five lines - freight line from Mesaieed Port to Ras Laffan, mixed
line (passenger and freight) from Doha to Dukhan, mixed line from Doha to Al Shamal, mixed line from
Doha to Saudi Arabia, and high speed passenger line from Doha to Bahrain.
2015
Sharq Road Project 12,000 The project consists of 12 km. series of tunnels and bridges connecting Hamad Intl Airport, Katara Cultural
Village and the Dafna/West Bay business district of Doha.
Postponed
New Doha Port 7,400 26,000,000 sq m The finished port site will have per annum capacity of 1.7 mn tonnes of general cargo, 1 mn tonnes of
grains, 500 000 vehicles, and 37 500 tonnes of livestock. The port basin will be approximately 3.8 km long,
700 m wide and 17 m deep. In addition, a new base for the Qatar Emiri Naval Forces (QENF) will be built
offshore of the new port to provide technical and logistic support. The Qatar Economic Zone 3 (QEZ3) will
also be located adjacent to the port. As of May 2015, the port site is 67% completed, while the QENF base
is 17% ready and the QEZ3 is 62% finished. A major contract award by Q2 2015 will be for the construction
of 225 buildings in the naval base. The contract for the construction of security facilities to serve the naval
base is also expected.
- 29 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Qatar: Major Construction Projects (cont’d)
Major Ongoing Projects Road Infrastructure Projects
BMI, Lusail, Festival City Doha, Msheireb, Doha News, Construction Week Online, Qatar Construction News, Mazaya Holding, The Peninsula Qatar, Qatar Tenders, Barwa, MEED, Ashghal
Project
Name
Value,
USD
mn
Capacity/
Length
Overview
Transport Infrastructure (cont'd)
Light Rail
Network/
Lusail City -
Doha
2,500 45 km The rail network will have 4 lines and 38
stations at at-grade and underground levels.
The first line should be operational by 2018,
while the remaining three lines are to be
completed by 2020
Hamad
International
Airport
Extension
n/a 300,000
sq mThe extension will increase the size of the
passenger terminal to approximately 900,000 sq
m and will add 24 plane gates. Upon completion
of the extension project, HIA will have annual
capacity of 50 million passengers, 2 million
tonnes of cargo and 320,000 aircraft landings
and take-offs.
Project Name Value,
USD mnExpected
Completion
Date
New Orbital Highway and Truck route, 145 km
road section 3,760 2017
New Orbital Highway and Truck route , 44 km
road section
Contract to be awarded as of
May 2015
East West Corridor
1,070 2017
Dukhan Highway East, 9.7 km. of dual four-lane
road 1,020 2017
Lusail Expressway, 5.3 km. four-lane highway
962 2017
Rawdat Al Khail Street project, 10 km of new dual
carriageway 632
2016
Al Wakra Bypass, 11 km. of dual five-lane
carriageway 601 2017
North Road enhancements, 95.2 km. of route
594 2016
Dukhan Highway Central, 15 km. of double four-
lane road 385
2016
Al Rayaan Road, Phase 1, 2.9 km. of dual
carriageway 280 2016
Al Rayaan Road, Phase 2, 5.5 km four-lane dual
carriageway, 6 km of side roads and 11 km
associated service roads
944
2017
Local road projects 6,140
(approx. total
cost)
Q2 2016
- 30 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Qatar: Major Construction Projects (cont’d)
Major Ongoing Projects - Utilities FIFA World Cup 2022 stadiums Construction, USD 4bn
BMI, Lusail, Festival City Doha, Msheireb, Doha News, Construction Week Online, Qatar Construction News, Mazaya Holding, The Peninsula Qatar, Qatar Tenders, Barwa, MEED
Project Value,
USD mn
Capacity Expected
Completion
Status
Ras Laffan D IWPP, Ras Laffan
Industrial City
3,000 2,520 MW 2018 In tender/Tender
launched
Mega Reservoir Corridor Main 1
(Packages A&B), Doha
2,000 120 km 2016 Contract Awarded
North Doha Sewage Treatment Works
Project, Umm Slal Ali, Doha (Phase 1)
1,500 Contract Awarded
Ras Abu Fontas (RAF) A2 Seawater
Desalination Plant, Abu Fontas, Doha
502 58.4 mn m3
per year
2015 Under
construction
Al-Dhakhira city Sewerage system
project
374 Contract Awarded
Qatargas LNG Plant Wastewater plant,
Ras Laffan Industrial City
125 2016 Contract Awarded
Qatar Power Transmission System
Expansion Plan - Phase 11 (Stage 1)
948.6 km Contract Awarded
Qatar Power Transmission System
Expansion Plan - Phase 11 (Stage 2)
173 km 2016 Contract Awarded
Water and electricity plant, Umm Al-
Haul
2400 MW 2017 In tender/Tender
launched
Mesaimeer Surface and Ground Water
Tunnelling project
9.7 km 2017 Under
construction
Doha West Wastewater treatment
recycling plant Expansion
63.87 mn m3
per year
Contract Awarded
Stadium Planned Capacity Completion Date
Khalifa Intl Stadium (existing) Expansion by 15,000
seats to achiebve total
capacity of 60,000 seats
2017
Al Rayaan Stadium (existing) Demolition and
reconstruction leading to
40,000 seat capacity
2019
Qatar Foundation Stadium
(new - confirmed)
40,000 seats 2019
Al Wakrah Stadium
(new - confirmed)
45,000 seats 2018
Al Bayt Al Khor Stadium
(new - confirmed)
60,000 seats 2019
Lusail Iconic Stadium
(new - to be confirmed)
86,000 seats To be specified
Al Shamal Stadium
(new - to be confirmed)
45,000 seats To be specified
Doha Port Stadium
(new - to be confirmed)
45,000 seats To be specified
Qatar University Stadium
(new - to be confirmed)
43,000 seats To be specified
Al Gharafa Stadium
(new - to be confirmed)
45,000 seats To be specified
Sports City Stadium
(new - to be confirmed)
45,000 seats To be specified
Umm Salal Stadium
(new - to be confirmed)
45,000 seats To be specified
- 31 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Qatar: Investment Climate
FDI
Regime
FDI regime is primarily regulated by Investment Law No. 13/2000. It generally limits foreign investments to 49% of the capital for most business
activities, with a Qatari partner(s) holding at least 51%. Gulf Cooperation Council nationals are treated as Qatari citizens in the ownership of
companies listed on the Qatar Exchange. However, the law allows, upon obtaining special government approval, up to 100% ownership by foreign
investors in certain sectors, including: agriculture, industry, health, education, tourism, development and exploitation of natural resources, energy,
mining, banking, insurance, business consultancy & technical services, information & communication services, cultural services, sports services,
entertainment services, and distribution services. Meanwhile, certain sectors are not open for domestic or foreign competition, including public
transportation, electricity and water, steel, cement, and fuel distribution and marketing. In these sectors, a single semi-public company has complete
or predominant market control.
A majority foreign stake in a project could be obtained only if the project fits into the country's development plans. In addition, preference is given to
projects that use raw materials available on the local market, manufacture products for export, produce a new product or use advanced technology,
facilitate the transfer of technology and know-how to the Qataris, and promote the development of national human resources.
In bids for government procurement the country treats preferentially suppliers that use local materials. As a rule, participation in tenders with a value
of QAR 1mn or less is confined to local contractors registered by the Qatar Chamber of Commerce, and tenders with a value of more than this
amount do not require any local commercial registration for participation, but in practice certain exceptions exist.
Right to
Private
Ownership
and
Establishment
The establishment of all private business entities in Qatar is regulated by the Commercial Companies Law, Law No. 5/2002.
Law No.15/1990 prohibits that foreign investors engage in a joint stock company with Qatari partners. As a consequence, joint ventures involving
foreign partners are usually established as limited liability partnerships. Foreign partners in ventures organised as limited liability partnerships must
pay the full amount of their contribution to capital in cash, or in kind, prior to the start of operations. Usually, such firms are required to set aside 10%
of profits each year in a statutory reserve until it equals 50% of the venture's authorised capital. This requirement is the only legal restriction to a
foreign company desiring to repatriate all of its annual profit after tax deduction.
Since August 2014, foreign investors can hold up to a combined total of 49% of the shares of Qatari companies listed on the Qatari Exchange.
Upon government approval, non-Qataris may have the right to land use over real estate for a renewable term of 99 years.
Depending on the case, foreign investors might be offered incentives that include natural gas priced at 0.6-0.75 USD per MBTU (Million British
Thermal Units); electricity offered at less than 0.02 USD per KWH; industrial land offered at 0.27 USD per sq m per year for a period of 50 years,
including options for renewing the lease; exemption from customs duties on imports of machinery, equipment and spare parts; exemption from
export duties; exemption from corporate taxes for up to 10 years and from income taxes; low cost financing through Qatar Development Bank
(QDB); and flexible immigration and employment rules to enable the import of foreign labour.
US Department of State, May 2015
- 32 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Qatar: Investment Climate (cont’d)
Tax Rates
and
Access to
Credit
.
Dispute
Settlement
Being a signatory to the 1958 New York Convention and a member of the International Center for the Settlement of Investment Disputes (ICSID),
Qatar accepts binding international arbitration in case of investment disputes.
The local legal establishments that facilitate dispute settlement include the Alternative Dispute Resolution (ADR) Centre as well as the International
Court and Dispute Resolution Centre.
There is no set duration for dispute resolution and the time to obtain a resolution depends on the case. The Qatar International Court and Dispute
Resolution Centre publishes past judgments on its website, which may be used as a reference: http://www.qfccourt.com/Judgement.html.
Labour
Conditions
Qatar's labour force consists primarily of expatriate workers. As of February 2015, non-Qatari residents are estimated to be around 89% of the population in the
country, making up for one of the world’s highest ratios of migrant workers to population. The largest group of foreign workers comes from the Indian sub-continent.
All expatriate labour must have a Qatari sponsor. Therefore, foreign investors should start discussing labour visa issues with their sponsors/local agents/partners in
the early stages of contract negotiation. In order to bring an expatriate employee into the country, sponsors must submit a request to the labour ministry. It controls
the number of workers that may come to Qatar through a quota system. The country has labour agreements with some countries that stipulate a minimum wage for
certain types of work, but in general minimum wage is not regulated by the government. Since 2004, Qatari citizens have the right to form workers' committees in
private enterprises with more than 100 Qatari citizen workers. Non-citizens are not eligible to form worker committees. Workers in the government sector, regardless
of their nationality, are not allowed to join unions. Under the labour law, workers are granted the right to bargain collectively and to sign joint agreements. However,
collective bargaining is not freely practiced, and the US Department of State reports that there are no workers employed under collective bargaining contracts.
US Department of State, May 2015
Since 2010, all non-Qatari companies and foreign partners in Qatari companies are subject to a 10% (corporate) flat rate. The only exception is in the
energy sector where there is a 35% tax rate on all oil and gas operations, unless exempted by Emiri Decree. Qatari nationals do not pay any kind of
corporate or income tax, except the “zakat” that amounts to around 2.5% of profits.
Under Law No. 13/2000, the finance ministry may grant a tax holiday of up to 10 years for new foreign investments in key sectors. Other exemptions
may be granted under Law No. 21/2009 on a case-by-case basis for a period of up to 6 years.
There is no restriction on the flow of capital and the US Department of State reports that foreign companies are essentially treated the same as local
ones. Almost all import transactions are controlled by standard letters of credit processed by local banks and their correspondent banks in the
exporting countries. Credit facilities are provided to local and foreign investors within the framework of standard international banking practices.
Foreign investors are usually required to have a guarantee from their local sponsor/local equity partner.
- 33 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
IV. Saudi Arabia
- 34 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Saudi Arabia: Sector Highlights
Currently, construction in Saudi Arabia benefits from extensive government investments in the sector. Thanks to its strong oil reserves, the state provides robustsupport to the infrastructure segment (transport, energy & utilities, social) as it is building a strong industrial base to sustain its economy in the future when oilreserves will eventually shrink. Besides the diversification policy, some other key growth drivers are the rapidly growing demographics (implying increasedresidential and commercial building), the religious tourism to the Muslim world’s two holiest shrines of Makkah and Madinah (implying expansion of the Grandmosques and the cities around them), as well as beneficial government policies (expected relaxation of foreign investment laws that would permit 100% foreignownership).
Growth Drivers
Non-residential Construction
The residential segment is growing healthily as, among other projects, the government has launched a USD 68bn housing program, aiming to
address the housing shortage among lower income Saudis. The construction of 500,000 housing units with adjacent facilities started in 2011 and
will be completed in 2016. In addition, more than 17,000 residential villas will be constructed over the same period in order to house the Saudi
National Guard personnel and their families.
Some of the most impressive non-residential projects that are currently being undertaken in Saudi Arabia comprise the construction of four
economic cities at total cost of USD 163bn. Each of them, being designed around at least one globally competitive industry, would become a
vigorous driver of growth by attracting foreign and local investments, opening up the economy and ultimately making it less dependent on oil and
gas. Other mega projects in the segment include the USD 40bn business and industrial Sudair City, and the USD 7.5bn Waad Al Shamaal
Phosphate City.
The Saudi government has allocated enormous investments for transport infrastructure. The major project in the subsector is the construction of a 9,900 km longnational railway network – it is underway and should be finished by 2040 at a total cost of USD 97bn. Public transportation developments are also gainingmomentum with multibillion metro networks being built in Riyadh, Jeddah, and Makkah. The USD 28bn expansion of King Abdulaziz Intl Airport stands out amongthe multitude of airport infrastructure projects in the country.
The Saudi government is also heavily investing in social infrastructure. Currently, there are ongoing works on the rehabilitation of 500 schools, construction of 3universities, 27 new hospitals and health facilities, and 8 medical cities.
Infrastructure
Residential Construction
- 35 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Comments
Saudi Arabia: Economic Indicators
The Saudi economy grew at a robust CAGR of 5.2% over the 2009-2014 period. BMI Research experts project favorable 3.7% y/y growth in 2015, despitethe drop of oil prices. BMI Research claims that economic advancement will be driven by strong fiscal stimulus and high oil production but expects theireffect to lessen from 2016 onwards. Moderate inflation is anticipated in 2015 at 3.2% y/y change of the consumer price index. However, in the mid-terminflation may rise following the extended period of robust growth, coupled with loose fiscal and monetary policy.It is worth noting that between 2011 and 2014 construction grew intensively by a CAGR of 12.6% - at a much faster pace than the economy, whichincreased by 3.8% a year during the same period.
Selected Economic Indicators
CEIC, World Bank, Ministry of Economy and Planning – Saudi Arabia, Oxford Economics, BMI
2009 2010 2011 2012 2013 2014
GDP, constant prices 2005 (USD bn) 406 425 467 493 506 523
GDP, constant prices 2010 (SAR bn) n/a 1,976 2,172 2,289 2,350 2,432
GDP, current prices (USD bn) 429 527 670 734 744 746
GDP, current prices (SAR bn) 1,609 1,976 2,511 2,752 2,791 2,798
Real GDP Growth Rate (%) 1.8 4.8 10.0 5.4 2.7 3.5
GDP: Producer Values: Building and Construction, (SAR bn) 80 91 107 119 135 153
GDP: Producer Values: Building and Construction, Growth Rate
(%) 0.9 12.9 17.9 10.7 13.6 13.7
Foreign Direct Investment, net inflows (USD bn, current) 36.5 29.2 16.3 12.2 9.3 n/a
Consumer Price Index (%) 5.1 5.3 5.8 2.9 3.5 2.7
- 36 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Comments
Saudi Arabia: Construction Industry Forecast
Experts from Oxford Economics project an almost twofold increase of the Saudi construction output value-added index in 2030 compared to
2015. The development of the sector in Saudi Arabia would thus closely follow the estimates for Africa and would be a bit below those for the
Middle East. Sector growth by 2020 will be driven mainly by the huge investments in the four economic cities, in rail and public transportation
infrastructure, and in energy and utilities infrastructure. However, BMI experts allow for possible cancellations of major infrastructure projects
due to redirection of funds and attention to the possible Saudi military intervention in Iraq or Yemen.
Construction, Output (value-added index, 2015=100)
Oxford Economics, BMI Research, EMIS Insight
100108
122
148
180
100
113
138
168
202
100107
120
148
182
2015 2017 2020 2025 2030
Saudi Arabia Middle East Africa
- 37 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Saudi Arabia: Construction Data
Building Permits Issued
Building Permits Issued by Region, 2014
Licensed Building Area
Licensed Building Area by Region, 2014
CEIC, Ministry of Municipal and Rural Affairs – Saudi Arabia
Riyadh 25.7%
Makkah 23.6%
Eastern Province16.0%
Qaseem 8.1%
Madinah 7.1%
Asir 5.6%
Hail 3.3%
Tabouk…
Jawf 2.1%Najran 1.8%
Other 4.0%
Riyadh 25.3%
Eastern Province19.7%
Makkah 17.7%Asir 9.2%
Qaseem 7.9%
Madinah 6.8%
Hail 2.8%
Tabouk…
Jazan 2.1%Northern Border 2.1%
Other 4.0%
89,7
87 112,
362
100,
756 11
7,07
8
113,
519
5.6%
25.1%
-10.3%
16.2%
-3.0%
2010 2011 2012 2013 2014
Building permits issued, units YoY change, %
40,4
02
46,7
72 53,5
88
49,4
27
47,5
49
-2.4%
15.8% 14.6%
-7.8% -3.8%
2010 2011 2012 2013 2014
Licenced building area, thou sq.m. YoY change, %
- 38 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Saudi Arabia: Major Construction Projects
Alfanar, MEED, Construction Week Online, Oil & Gas Journal, Dar Al-Handasah, Gulf Business, Arab News, American Council of Engineering Companies, Arabtec, Yasref, Arabian Business, The National, Emaar, BBC, CNN, Ernst & Young, The GCC Power and Water Forum, Business Korea, Creamer Media’s Engineering News, Hajr Electricity Production Company, Arabian Bemco, Parsons, Bechtel, Oxford Business Group
Project Name Value, USD mn Capacity/Length Overview Timeframe
Commercial Construction
King Abdullah
Economic City
(KAEC)
100,000 181,000,000 sq m Located some 100 km north of Jeddah, KAEC is being built from scratch on previously unoccupied desert
land. Once completed, the impressive mixed-use development will consist of 4 key components – King
Abdullah Port, Industrial Valley, Downtown, and Coastal Communities. KAEC will benefit from
sophisticated multi-modal connectivity by sea, rail, and road. According to BBC News, as of March 2015
only 15% of the project has been developed. As of May 2015 KAEC’s population was about 3,000 people;
it is expected to roughly double by the end of 2015 and hit 50,000 by end-2020, rising to the ultimate target
of 2mn around 2035.
Q2 2006 - Q1 2020
Sudair City
Development
40,000 The development comprises the construction of a business and industrial city in Sudair, 120 km north of
Riyadh. The future city, spreading over approx. 265 sq km, will accommodate about 1mn residents and is
designed to alleviate the growing congestion in Riyadh and reduce migration to the capital city.
It will include commercial, residential, technological, sports and leisure areas, and will be intersected by
several key services, including the north-south railway and the country’s main east-west oil pipeline. Now
in execution stage, the budget for the project has subsequently been revised upwards from USD 16bn to
USD 40bn, as announced by MEED.
Expected completion
Q4 2029
Jazan Economic
City (JEC)
27,000 100,000,000 sq m JEC is being built 60 km northwest of Jazan city on the Red Sea coast. It is being developed with a focus
on energy and labour-intensive industries. Once completed, the development will feature a port, an
industrial zone, commercial and cultural centres, residential areas, and academic and vocational training
institutions.
Expected completion
Q4 2036
Knowledge
Economic City
(KEC)
8,000 4,800,000 sq m site
area,
9,000,000 sq m
built-up area
KEC, which is being built on the outskirts of Medina, is focused on knowledge-based industries, including
information technology and life sciences. The project is a mixed-use development offering commercial,
residential, educational, and hospitality amenities as well.
Q2 2009 - Q4 2020
Prince Abdulaziz
Bin Mousaed
Economic City
(PABMEC)
8,000 156,000,000 sq m PABMEC will be built in the city of Hail with a focus on logistics & transportation, agriculture, minerals and
construction materials. Among its key components will be a logistic & transportation centre, an agro-
industrial zone, a knowledge centre, a petrochemical industries district, a residential area, an
entertainment area, and a mining centre.
2009 - 2025 As of
2015 the project is on
hold, after the design
stage has been
executed.
- 39 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Saudi Arabia: Major Construction Projects (cont’d)
Project Name Value, USD mn Capacity/Length Overview Timeframe
Commercial Construction (cont'd)
Abraj Kudai Towers
in Makkah
3,500 60,000 sq m site area
1,400,000 sq m built-
up area
The project is a mixed-use residential and commercial complex that consists of a large podium topped by
12 towers. In addition, it accommodates facilities like a shopping mall, restaurants and food courts, a
convention centre and car parking lots.
Q4 2013 - Q1 2019
Jabal Omar
Development in
Makkah
2,700 2,500,000 sq m The mixed-use project foresees the construction of a residential and commercial centre in an area close to
the Grand mosque in Makkah. The development, which would be built in 5 stages, consists of 39
commercial and residential towers. The area of the development has been divided into two areas, the
northern area which includes fourteen 6-storey buildings and a 6-storey prayer building, and the southern
area with includes the other towers.
Q3 2008 - Q1 2020
Jeddah Gate
Development
1,600 553,000 sq m site
area
Jeddah Gate is a massive development located in the heart of Jeddah. It is positioned on two sites -the
first is spread over 413,000 sq m and the second is spread over 140,000 sq m. Upon completion, the
project will become the new centre of the city, comprising 6,000 residential units, 230,000 sq m of
commercial space and 75,000 sq m of gross rentable area for retailers.
Q1 2008 - Q1 2020
Kingdom Tower in
Jeddah
approx. 1,230 Height of more than
1,000 m
As of June 2015 final height was not yet confirmed. Expected completion
by the end-2018
Residential Construction
Saudi Housing
Project
68,000 500,000 residential
units
After the social discontent uprisings in the Arab world in 2011, the late King Abdullah announced a plan to
build 500,000 homes in Saudi Arabia over several years. Aiming to reduce home shortages and
depressed living standards, that are politically sensitive, the plan foresees the construction of homes
throughout the country - spreading out from Tabouk in the north to Khamis Mushayt in the south and from
Dammam in the east to Jeddah in the west. However, the project timeframe has been delayed due to
sluggish bureaucracies, difficulties in obtaining suitable land and the complexity of allocating aid. To
address these bottlenecks, the housing ministry has revised its strategy and in 2014 it adopted a new
program dubbed ESKAN - the Arabic word for housing. Under the new scheme, Saudi families seeking
assistance, in the form of state-subsidised home loans or subsidised sales of land or housing units, are
being given two months to register on a website. Once approved, applicants will pay for their subsidised
homes or land, or pay off their loans, in monthly instalments over 10 years through a 25% deduction of
their monthly income, as explained by Reuters.
Q3 2011 -Q3 2016
Completion date is
likely to be extended
due to bureaucratic
difficulties
Alfanar, MEED, Construction Week Online, Oil & Gas Journal, Dar Al-Handasah, Gulf Business, Arab News, American Council of Engineering Companies, Arabtec, Yasref, Arabian Business, The National, Emaar, BBC, CNN, Ernst & Young, The GCC Power and Water Forum, Business Korea, Creamer Media’s Engineering News, Hajr Electricity Production Company, Arabian Bemco, Parsons, Bechtel, Oxford Business Group
- 40 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Saudi Arabia: Major Construction Projects (cont’d)
Project Name Value, USD mn Capacity/Length Overview Timeframe
Residential Construction (cont'd)
National Guards'
Housing Project:
Phase 2
3,600 The project aims to provide the Saudi National Guard personnel with comfortable living facilities and
services. Its second phase involves the construction of 17,200 residential villas and 15 schools in the
National Guard residential cities located in Riyadh, Jeddah, Dammam, Hail, Al-Qassim, Madinah, Hofuf,
Taif, and Yanbu.
2011 -2016
Construction of
5,000 Villas in
Eastern Province
1,350 6,000,000 sq m site
area 1,600,000 sq m
built-up area
The residential development consists of 5,000 Villas of Type “A and B” and includes complete
infrastructure works. The housing site is divided into 5 developments. The project should have been
finished in Q4 2014, but according to the contractor, Arabtec Construction LLC, the works are ongoing as
of July 2015.
Q4 2010 - ongoing
(according to the
website of Arabtec
Construction LLC)
Energy, Utilities and Mining
Yanbu Refinery
Project (Yasref)
10,000 400,000 bpd (barrel
per day)
Yanbu Refinery, also known as the Red Sea Refining Company RSRC Refinery or YASREF, is an
integrated petroleum refinery. It processes 100% Arabian Heavy Crude and produces gasoline, high
quality diesel, and liquefied petroleum gases (LPG) as well as byproduct sulfur and petroleum coke for
export. The refinery includes processing units for the separation and conversion of the feed crude into
finished products, utility and offsite systems to support the refinery operation, and associated feed,
intermediate and product storage facilities. The refinery is scheduled to reach its full capacity in Q2 2015.
However, it has gradually started shipping since January 2015.
Q3 2010 - Q1 2015
Waad Al Shamaal
Phosphate City
Development
7,500 440,000,000 sq m Once completed, the city will have a mining complex with seven world-scale phosphate processing
facilities. In addition, the city will be able to accommodate about 100,000 people - industrial workers and
their families.
2013 - 2022
Rabigh Power Plant
Extension: Phase 6
3,400 The plant expansion would boost the region’s generation capacity by 2,800 megawatts. The project
comprises production, installation and test of equipment and facilities at the plant, which will generate
power using four 700 megawatt units.
2010 - 2015
Shuqaiq Steam
Power Plant
3,300 2,640 MW Shuqaiq Thermal Power Plant is scheduled to be built at around 135 km north of Jazan. It is designed as a
2,640 MW heavy oil-fired supercritical pressure power plant.
Q3 2013 - Q3 2018
Alfanar, MEED, Construction Week Online, Oil & Gas Journal, Dar Al-Handasah, Gulf Business, Arab News, American Council of Engineering Companies, Arabtec, Yasref, Arabian Business, The National, Emaar, BBC, CNN, Ernst & Young, The GCC Power and Water Forum, Business Korea, Creamer Media’s Engineering News, Hajr Electricity Production Company, Arabian Bemco, Parsons, Bechtel, Oxford Business Group
- 41 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Saudi Arabia: Major Construction Projects (cont’d)
Project Name Value, USD mn Capacity/Length Overview Timeframe
Energy, Utilities and Mining (cont'd)Jeddah South
Thermal Power
Plant
3,120 2,640 MW Once completed, the oil-fired thermal power plant will be able to produce enough electricity for about two
million people, or 5% of Saudi Arabia’s entire power generation capacity.
Expected completion
by the end of 2017
Wasit Gas Plant 1,900 3,000,000,000 cfd
(cu feet/day)
The construction of the Wasit gas plant, located north of Jubail, is commissioned by Saudi Aramco. Upon
completion, it will be one of the largest gas plants not linked to oil wells ever built by the company. The
plant will have capacity to process up to three billion cubic feet per day of non-associated gas from the
offshore fields Hasbah and Arabiyah. Saudi Aramco claims that Wasit and another project, Karan, that has
been in operation since 2012, will likely boost Saudi Arabian natural gas output by an estimated 40%.
Although construction of the main Wasit plant was almost finished in April, 2015, the complex will not be
fully operational before the end of 2015 or the first quarter of 2016, according to Gulf Business and Arab
News sources.
Q1 2011 - Q4
2015/Q1 2016
Jazan IGCC
(integrated
gasification
combined-cycle)
Power Plant
1,700 Upon completion, the Jazan IGCC complex’s gasification unit will have a capacity to convert vacuum
residue produced in the adjacent Jazan refinery into 2.11 million normal cu m/hr of syngas that will be
evenly used to produce purified hydrogen for the refinery and to fuel the IGCC plant. The total output of the
plant is expected to be app. 2,400 MW.
Q2 2014 - Q4 2017
Rabigh 2 IPP 1,600 2,060 MW The Rabigh II Independent Power Plant will use natural gas as its main fuel and Arabian super light as its
backup fuel, with the application of a combined-cycle power plant in a configuration of three groups, each
comprising two gas turbines of enhanced efficiency, two heat recovery steam generators and one triple-
pressure steam turbine, as explained by Engineering News.
Commercial operation
should begin in 2017
Riyadh PP10
Steam Turbines
Power Plant
1,434 1,300 MW The project scope is to convert the Simple Cycle Gas Turbine (SCGT) Plant in Riyadh to Combined Cycle
Gas Turbine Plant for blocks A1, A2, B1, B2 and C1 including supply of common balance of plant for all
blocks. The configuration of each combined cycle block will include 4 Gas Turbine Generators + 4 Heat
Recovery Steam Generating (HRSG) units + 1 Steam Turbine Generator + 1 Air Cooled Condenser with
a total of 10 Blocks with provision for installation of TIAC System in the future.
Q4 2011 - Q3 2015
Riyadh PP12
Combined Cycle
Power Plant
1,260 2,175 MW (1,740
MW after deducting
all plant auxiliary
consumption at
ambient condition)
The plant site is located 100 km west of Riyadh. It will use sales gas as primary fuel and Distillate and
Arabian Super Light as secondary. The configuration of each combined cycle block will include 4 Gas
Turbine Generators + 4 Heat Recovery Steam Generating (HRSG) units + 1 Steam Turbine Generators +
1 Air Cooled Condensers.
Q2 2012 - Q2 2015
Alfanar, MEED, Construction Week Online, Oil & Gas Journal, Dar Al-Handasah, Gulf Business, Arab News, American Council of Engineering Companies, Arabtec, Yasref, Arabian Business, The National, Emaar, BBC, CNN, Ernst & Young, The GCC Power and Water Forum, Business Korea, Creamer Media’s Engineering News, HajrElectricity Production Company, Arabian Bemco, Parsons, Bechtel, Oxford Business Group
- 42 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Saudi Arabia: Major Construction Projects (cont’d)
Project Name Value, USD mn Capacity/Length Overview Timeframe
Social InfrastructureExpansion of the
Grand Mosque in
Makkah
Over 26,000 1,470,000 sq m The Grand Mosque is currently undergoing a third expansion following the expansion works commenced
by late King Abdullah in 2011. By far, they are estimated to amount at around USD 26 bn, and the third
expansion plan is set to surpass that. It consists of five large projects, including the King Abdullah
Expansion Structure, courtyards, tunnels, buildings for service facilities and the first ring road. The plan
foresees the construction of 1.47mn sq m of development, capable of hosting 1.6mn worshipers, with 78
gates at the ground floor surrounding the expansion building.
Q1 2010 - Q1 2016
King Abdullah bin
Abdulaziz Medical
City
6,800 2,600,000 sq m built-
up area
King Abdullah bin Abdulaziz Medical City Project encompasses two medical complexes situated in Riyadh
and Jeddah. Each one of them costs USD 3.4bn and comprises the construction and fit-out of two medical
complexes with built-up area of 1.3mn sq m each and individual capacity of 1,000 beds for security forces
and their families.
2015 - 2020
Rehabilitation
Centres for
Prisoners
3,400 2011 - 2017
King Khalid Medical
City in Dammam
1,200 700,000 sq m King Khalid Medical City (KKMC) will be built some 20 km southwest of Dhahran. The campus will consist
of a 1,500-bed hospital, as well as residential buildings, a hotel, a commercial complex, educational
facilities, a research centre, and recreational facilities.
Expected completion
in 2018
King Abdullah
Medical City,
Makkah
1,067 Among other facilities, the medical city would include a 150-bed cardiac centre, a 100-bed centre
specialising in surgery and organ transplants, and a 200-bed cancer treatment and surgery unit, as
specified by Oxford Economics.
The project is in
prequalification phase
King Faisal Medical
City in Asir, Phases
1 & 2
507 157,862 sq m (Phase
2)
The medical city is being built in two phases. Phase 1 that comprises the construction of a 500-bed
hospital, is scheduled for completion by May 2015 The remainder of the contract should be finished until
April 2017. It will consist of an 850-bed hospital building with 5 centres for cardiac, oncology,
neuroscience, ophthalmology and rehabilitation activities
Expected completion
by April 2017.
King Fhad Medical
City (KFMC)
Expansion, Riyadh
426 The expansion of KFMC foresees the construction of a 510-bed medical city, a 50,000 sq m Neuroscience
Centre, a 55,000 sq m Cancer Centre, a 4-storey Cardiac Centre, a 4-storey Service Building, and
associated facilities.
Expected completion
by the end of 2016
Prince Mohammad
Bin Abdul Aziz
Medical City in Al
Jouf, Phases 1 & 2
312 2,000,000 sq m site
area
The project foresees the construction of two 500-bed hospital buildings in two phases. Expected completion
for Phase 1 by
October 2015/ Phase
2 by October 2017
Alfanar, MEED, Construction Week Online, Oil & Gas Journal, Dar Al-Handasah, Gulf Business, Arab News, American Council of Engineering Companies, Arabtec, Yasref, Arabian Business, The National, Emaar, BBC, CNN, Ernst & Young, The GCC Power and Water Forum, Business Korea, Creamer Media’s Engineering News, Hajr Electricity Production Company, Arabian Bemco, Parsons, Bechtel, Oxford Business Group
- 43 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Saudi Arabia: Major Construction Projects (cont’d)
Project Name Value, USD mn Capacity/Length Overview Timeframe
Transport InfrastructureNational Railway
Network
97,000 9,900 km During the first USD 16.8 bn stage, continuing from 2010 to 2025, 5,500 km are to be built. In the second
USD 55.7 bn phase 3,000 km are to be built between 2026 and 2033. In the last USD 24.8 bn stage, 1 400
km of railway will be constructed between 2034 and 2040. Among other improvements and construction
works, the first stage foresees the construction of the connection to the GCC railway network with lines
between Batha at the UAE border - Hofuf and Jubail - Ras Al Khair - Kuwait border, as well to Qatar and
Bahrain. In addition, some other major projects that are part of the first 2010-2025 phase are the railway
landbridge between Riyadh and Jeddah, the Haramain high speed railway connecting Makkah – Jeddah –
Madinah, and the north-south mineral line between the northern regions, Ras Al Khair/Jubail and the
capital Riyadh.
Expected completion
for Phase 1 by
2025/Phase 2 by
2033/Phase 3 by 2040
Jeddah Public
Transportation
Program (JPTP)
approx. 35,000 approx. 1,300 km The Masterplan of Jeddah Public Transportation foresees the construction of a 1,356 km multi modal
public transport system. It will consist of a metro network of 149 km, a 16 km tram and 74 km light rail
transit system, a 308 km rapid bus network and 210 km major bus routes, 350 km of local bus feeder, and
195 km of commuter rail.
The Project should be
completed by 2033
King Abdulaziz
International Airport
(KAIA) Expansion
approx. 28,000 KAIA is undergoing a massive expansion that is organised in three phases. Upon completion, the
expansion would lead to ultimate capacity of around 80mn passengers a year. While Phase 1, costing
about USD 7bn, is being finalised in 2014-2015, Phases 2 & 3 are in study stage.
Q4 2010 - Q4 2035
Riyadh Metro Rail
Project
23,000 178 km Once completed, the metro network will comprise six lines and 85 stations including underground,
elevated and at-grade sections. In addition, an 85 km three-line Bus Rapid Network (BRT) will be built and
integrated with the metro stations
Q3 2013 - Q4 2018
Makkah Metro Rail
Project
16,000 182 km The Makkah metro will consist of 4 lines and 88 stations, whose construction will be spread over 3 phases.
Phase 1 will take 3 years and cost USD 6.8bn. Phase 2 should be completed for 5 years at a cost of USD
5bn, and the final USD 4.5bn stage will take 2 years.
2015 - 2025 estimated
Asir - Jazan Road
Connection
1,600 135 km The road would stretch from Al-Far'a recreation park in the south of Abha to Beesh in the north of Jazan
area. Tender documentation concerning the construction of the road was accepted until April 5th, 2015.
Makkah - Jazan
Road Connection
1,100 The tender documentation concerning the construction of the road was accepted until April 20th, 2015.
Alfanar,MEED, Construction Week Online, Oil & Gas Journal, Dar Al-Handasah, Gulf Business, Arab News, American Council of Engineering Companies, Arabtec, Yasref, Arabian Business, The National, Emaar, BBC, CNN, Ernst & Young, The GCC Power and Water Forum, Business Korea, Creamer Media’s Engineering News, Hajr Electricity Production Company, Arabian Bemco, Parsons, Bechtel, Oxford Business Group
- 44 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Saudi Arabia: Major Construction Projects (cont’d)
Ongoing Airport Expansion Projects Road Infrastructure Projects, Saudi Arabia
Saudi Tenders, Alfanar, Arab News, NACO - Netherlands Airport Consultants, SUSRIS – Saudi-US relations information service, Zawya
Projects via KFHR
Project City Value, USD
mn
Expansion Scope
Abha Regional Airport Abha 1,000From 9,400 sq m to 78,000
sq m and annual capacity of
5mn passengersKing Abdullah bin Abdulaziz
Airport
Jizan 900 Construction of a new 55,000
sq m airport with annual
capacity of 3.6mn
passengers.King Khalid International
Airport
Riyadh 500Capacity expansion from 15
to 20-25mn passengers a
yearAl Qassim Domestic Airport Buraydah 270
From 5,500 sq m to 36,000
sq m and annual capacity of
1.5mn passengersAl Baha Domestic Airport Al Baha 160
Annual capacity expansion
from 200,000 to 500,000
passengersAl Jouf Domestic Airport Al Jouf 100
From 2,900 sq m to 13,000
sq m and annual capacity of
1mn passengersArar Domestic Airport Arar 84
From 1,810 sq m to 7,560 sq
m and annual capacity of
518,000 passengersNew International Airport Taif Tender is in
progress as of
June 2015
Upon completion, the 57 sq
km airport will have annual
capacity of 400,000
passengers.
Project Value,
USD mn
Expected
Completion Date
Rennovation of Qulaiba-Abu Ajram road 757.0 Q2 2015
Jubail - Al Qassim expressway 97.0 July 2016
Hail - Madina dual carriageway extension 48.0 July 2016
Riyadh Roads - Group 20 48.0 Q1 2017
Abu Hadriyah/ Hafr Al Batin/ Rafha road refurbishment 37.3 H2 2015
Madina to Tabouk expressway road 37.3 Project in progress as
of May 2015
Northern Borders roads rehabilitation 37.1 January 2016
Al Jamjom to Al Zema highway 37.0 2017
Jazan coastal highway extension 37.0 Project in progress as
of May 2015
Yanbu to Al Sharaf roads repair 35.0 December 2015
Al Kharj to Al Gwayiyyah dual carriageway 33.4 July 2016
King Fahed and Rawda road intersection 28.8 Q2 2015
Al Jawf Main Roads - Group 1 27.5 H1 2016
Jazan agricultural roads - Group 26 27.2 July 2016
Madina roads extension - Group 17 24.0 July 2016
Riyadh roads extension 27.2 July 2016
Jazan roads extension 22.5 July 2015
Makkah Road Group 21 22.5 September 2016
Al Kharj to Riyadh/Dammam highway dualisation
diversion 21.5 July 2016
Smaller projects 288.0
(total value)
Projects in progress as
of May 2015
- 45 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Saudi Arabia: Investment Climate
FDI
Regime
The US Department of State considers Saudi Arabia as an attractive and relatively stable market for investment. The Saudi foreign direct investment law permits
foreigners to invest in almost all sectors of the economy with priority being given to investments in industry, transportation, education, health, communications
technology, life sciences, and energy; as well as in the four "Economic Cities" that are at various stages of development. However, there is a “negative list” that
currently prohibits FDI in 2 industrial sectors and 13 service sectors, among them real estate investment in Mecca and Medina, some subsectors in printing and
publishing, audiovisual services, land transportation services excluding inter-city transport by trains, and upstream petroleum. All foreign investment projects in
Saudi Arabia must obtain a license from the Saudi Arabian General Investment Authority (SAGIA). Investments in specific sectors may require additional licences
from other government authorities, including, but not limited to, the Saudi Arabian Monetary Agency (SAMA), the Capital Market Authority (CMA), or the
Communications and Information Technology Commission (CITC). SAGIA licences should be granted or refused within 30 days of receiving an application and
supporting documentation from the prospective investor. In an attempt to ensure that investors do not just acquire and hold licenses without investing, SAGIA
performs periodic licence reviews. However, these reviews might be seen as disincentive to longer-term investment commitments as the possibility of cancellation
adds uncertainty for investors. While SAGIA has set up the infrastructure to support foreign investment, the US Department of State notes that many companies
consider the process cumbersome and time-consuming.
Importantly, SAGIA is responsible to maintain and review periodically the activities included in the “negative list” of sectors with prohibited FDI regime.
Right to
Private
Ownership
and
Establishment
Foreign investors are not required to take local partners in many sectors and may own real estate for company activities. However, offices practicing law, accounting and auditing, design, architecture, engineering, or civil planning or providing healthcare, dental, or veterinary services must have a Saudi partner with holding at least 25% stake of the total investment.
Foreign investors are allowed to transfer money from their Saudi-based enterprises outside of the country and can also sponsor foreign employees. The minimum capital requirements to establish business entities range from zero to SAR 30mn (USD 8mn) depending on the sector and the type of investment.
Foreign partners in service and contracting ventures organised as limited-liability partnerships must pay, in cash or in kind, 100% of their contribution to the authorised capital. Despite the bureaucracy and red tape that accompany the establishment of such an entity, foreign investment is generally welcome in Saudi Arabia as long as it promotes economic development, transfers foreign expertise to Saudi Arabia, creates jobs for Saudis, and/or expands Saudi exports. There are no legal requirements for foreign investors topurchase from local sources or export a certain percentage of output, and their access to foreign exchange is unlimited. While not required to procure from local sources, investors may avoid import duties on raw materials only if they can prove that these are not available locally. There is no requirement that the share of foreign equity be reduced over time. Investors are not required to disclose proprietary information as part of the regulatory approval process, except where issues of health and safety are concerned.
US Department of State, May 2015
- 46 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Saudi Arabia: Investment Climate (cont’d)
Tax Rates
and
Access to
Credit
In July 2003, the corporate tax rate on foreign investors was lowered to a flat 20%. It replaced a tiered system with tax rates as high as 45%. While
this has been a step towards a more balanced treatment of foreign and Saudi-owned capital, the government tax policy still favours Saudi
companies and joint ventures with Saudi participation. Hence, Saudi investors do not pay corporate income tax, but are subject to a 2.5% tax, or
“zakat,” on net current assets.
After the financial crisis of 2008, followed by the default on USD 20bn in debt by two Saudi business concerns and the debt restructuring in Dubai,
credit availability has been limited to all parties. Credit became somewhat more available in 2011 and 2012, but extraordinary public spending has
limited the demand for private lending. In addition to large-scale supplemental programmes, credit is available from several government institutions,
such as the Saudi Industrial Development Fund, which allocate credit based on government-set criteria rather than market conditions. In order to
qualify for credit, companies must have a legal presence in Saudi Arabia. The private sector has access to term loans, and there have been a
number of issuances of sharia-compliant bonds, known as "sukuk," but there is no fully developed corporate bond market.
Dispute
Settlement
The US Department of State notes that Saudi Arabia does not offer a transparent and comprehensive legal framework for resolving commercial
disputes although the government is making progress in this direction. The indicator that affects most negatively the country’s ranking in the World
Bank’s “Doing Business” report is resolving insolvency, on which it ranks 163rd out of 189 economies (data from June, 2014).
Disputes with the government and over commercial issues generally fall under the jurisdiction of the Saudi Board of Grievances. The Board also
reviews all foreign arbitral awards and foreign court decisions to ensure that they comply with Sharia law. This review process can take years, and
outcomes are unpredictable. Even after a decision is reached in a dispute, enforcement of a judgment can take years. Therefore it is highly
advisable to consult with local counsel prior to investing in order to review legal options and appropriate contractual provisions for dispute resolution.
Labour
Conditions
Recruitment of expatriate labour in Saudi Arabia is regulated by the labour ministry and the interior ministry. The large majority of the private sector workforce
consists of workers coming from Bangladesh, Egypt, India, Pakistan, the Philippines, and Yemen with Westerners making up less than 2% of the labour force.
However, the labour ministry aims to reduce the expatriate population from approximately 30% currently to 20% of the total population. Hence, the government
encourages the so-called “saudisation” - recruitment of Saudi employees - through a series of incentives and limits placed on the number of visas for foreign
workers available to companies. The “Nitaqat” plan, which was rolled out in 2011, has divided companies into sectors, each with a different set of quotas for Saudi
employment based on company size. In 2013, the labour and interior ministries launched a campaign to deport illegal and improperly documented workers, which
has resulted in higher labour costs for many businesses. In addition, all companies operating in Saudi Arabia, regardless of sector or size, are currently obliged to
pay USD 640 per year for each expatriate employee in excess of the number of the company’s Saudi employees. Saudi labour law forbids union activity, strikes,
and collective bargaining. However, the government allows companies that employ more than 100 Saudis to form "labour committees". The minimum age for
employment is 14.
US Department of State, May 2015
- 47 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
V. United Arab Emirates
- 48 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
United Arab Emirates: Sector Highlights
Construction
Activity
in the
Emirate of
Dubai
Within the UAE, the emirate of Dubai is the undisputed leader in terms of construction activity. The emirate is far ahead of the other emirates in
terms of buildings that are completed or are under construction. In 2014, some 7,400 buildings were finished there with 57% of them being
residential villas (built both for private and investment purposes) and 32% being commercial space. The number of completed buildings in 2014 grew
by 5.6% y/y and continued the trend of recovery after the 2009 crash of the real estate market in Dubai. Within the 2010–2014 period, the residential
and commercial segments were the most volatile ones. The number of completed buildings dropped sharply in 2011-2012 but also led the 2013-
2014 recovery, reflecting directly the market instability.
The value of completed buildings in 2014 was AED 27.1bn – a 25% increase compared to the previous year. Value was mainly contributed by multi
storey developments – tall mixed-use buildings accounted for 39% of the total value in the sector in 2014.
Over the 2010–2014 period, construction in Dubai hit rock bottom in 2012. The value of completed buildings, which was around AED 16bn that year,
was grossly half the value realised in 2010. However, the sector has recovered rapidly and is now on its way to reach its 2010 value levels thanks to
tighter regulations, coupled with strong fundamental demand.
In 2014, approximately 21,000 buildings were under construction in the emirate of Dubai. Their number decreased by 24.1% y/y mainly due to the
sharp decrease of stores under development, which dropped by almost 63% y/y. On the other hand, investment villas under construction have
partially offset the decline of commercial space. Notably, their number almost tripled in 2014 compared to 2013.
Construction
Activity
In
Other
Emirates
The construction activity in the emirates of Abu Dhabi, Ajman, and Fujairah was weaker than that in Dubai. For instance, in
2014 around 3,300 buildings were completed in the emirate of Abu Dhabi – less than half of the number for the same year
in Dubai. Marking a substantial 51% y/y decline, the drop in Abu Dhabi is mainly attributed to the residential segment.
Indeed, the completed residential buildings in 2014 were 53% less than in 2013.
BMI experts note that the biggest risk in the Emirati construction sector over the 2015-2020 period stems namely from
private investment in Abu Dhabi - it could be adversely affected by lower oil prices as the economy of the emirate is
strongly dependent on oil.
In 2014, some 2,600 building permits were issued in the emirate of Fujairah, almost half of them concerning residential
developments. Although over the 2010-2014 period the number of permits issued per annum remained relatively stable,
the emirate saw a major increase of the licensed area in 2014. More than 1.6mn sq m were licensed for construction,
almost double the previous year.
EMIS Insight
- 49 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Comments
United Arab Emirates: Economic Indicators
The Emirati economy grew steadily at a CAGR of 4% over the 2009-2014 period. BMI experts anticipate 4% y/y real GDP growth in 2015. Dubai will continue to account fora larger share of the growth compared to Abu Dhabi thanks to increased activity in trade, tourism and real estate. The private sector’s access to credit in 2015 will beconstrained as commercial banks increase provisioning to safeguard against potential loan losses due to the debt funding cliff.According to BMI, inflation is set to rise to 4% y/y.Over the 2011-2014 period, construction grew quite slowly by a mere 2.6% a year. Indeed, UAE was among the three MENA countries with slowest growth during the time,together with Tunisia and Yemen. The country is recovering slowly after the real estate crisis that hit it in 2009. During the 6-year period under analysis, the Emiraticonstruction sector registered a growth of over 5% only in the last year. Nevertheless, the high growth trend will continue as the UAE is hosting the World Expo 2020 event– a sure boost for the industry in the upcoming years.
Selected Economic Indicators
CEIC, World Bank, BMI, Euromonitor
2009 2010 2011 2012 2013 2014
GDP, constant prices 2005 (USD bn) 200 203 213 223 235 243
GDP, constant prices 2007 (AED bn) 1,155 1,104 1,059 990 941 926
GDP, current prices (USD bn) 254 286 347 372 402 402
GDP, current prices (AED bn) 931 1,051 1,280 1,371 1,422 1,467
Real GDP Growth Rate (%) (5.2) 1.6 4.9 4.7 5.2 3.6
GDP: Construction, (AED bn) 121 122 122 120 125 132
GDP: Construction, Growth Rate (%) (1.3) 1.4 (0.1) (1.4) 3.4 6.1
Foreign Direct Investment, net inflows (USD bn, current) 4.0 5.5 7.7 9.6 10.5 n/a
Consumer Price Index (%) 1.6 0.9 0.9 0.7 1.1 2.3
- 50 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Comments
United Arab Emirates: Construction Industry Forecast
Experts from Oxford Economics forecast an almost twofold increase of the Emirati construction output value-added index in 2030 compared to 2015. Like in Saudi
Arabia, the development of the construction sector in the United Arab Emirates follows closely the dynamics in Africa and lags slightly behind the Middle East.
Within the UAE, Dubai is forecast to be the outperforming market over the 2015-2020 period as the city will be the host of the World Expo 2020 – a major driver for
the construction industry. However, healthy growth is generally expected throughout the UAE, according to BMI experts. Indeed, in an attempt to offset the drop in
oil prices, the UAE would continue to see major investments in tourism related projects, infrastructure and non-residential building segments. For instance, some of
the major growth drivers between 2015 and 2020 would be projects related to airport expansions, rail and public transport infrastructure, energy and utilities
infrastructure, as well as mixed-use cities and man-made islands designed to become huge tourist attractions.
Construction, Output (value-added index, 2015=100)
Oxford Economics, BMI Research, EMIS Insight
100111
126
151177
100
113
138
168
202
100 107
120
148
182
2015 2017 2020 2025 2030
United Arab Emirates Middle East Africa
- 51 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
United Arab Emirates: Construction Regional Data
Number and Type of Completed Buildings, units – Emirate of Dubai Value of Completed Buildings, AED mn – Emirate of Dubai
Municipality of Dubai, CEIC
2,656
1,529 1,661
2,8422,557
836
1,017309
1,817
1,654
2,119
1,176
1,230
1,7432,362
183
167
129
183
358
243
163
116
219
165
309
195
171
146
220
48
62
35
57
816,394
4,309
3,651
7,0077,397
2010 2011 2012 2013 2014
Floor arearatios
Multi storey
Publicfacilities
Industrial
Stores
Investmentvillas
Private villas
Total
4,9703,436 3,239
4,353 3,857
699
1,522 5391,358
2,320
1,7701,639
800839
3,276
5,543
5,006
2,2151,974
2,434
13,291
8,244
6,797
8,941
10,643
4,548
7,660
2,394
4,267
4,616
30,821
27,507
15,984
21,732
27,146
2010 2011 2012 2013 2014
Floorarearatios
Multistorey
Publicfacilities
Industrial
Investment villas
Privatevillas
Total
- 52 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
United Arab Emirates: Construction Regional Data (cont’d)
Number and Type of Buildings Under Construction, units – Emirate of Dubai Number and Type of Completed Buildings, units - Emirate of Ajman
Municipality of Dubai, Licensing and Engineering Control Section - Building Department in Ajman, CEIC
6,483 6,671 7,0466,163 5,733
2,256 1,4482,412
2,298
6,307
13,80613,573
15,477 16,884
6,298
445 410
453 641
721
705 632
745 590
651
870 779
793867
937
296 258
274297
409
24,861
23,771
27,20027,740
21,056
2010 2011 2012 2013 2014
Floor arearatios
Multi storey
Publicfacilities
Industrial
Stores
Investmentvillas
Private villas
Total
608
416
624 618
742
64
50
29
26
4653
50
37
29
3421
29
28
23
438
18
33
47
43
454
180
230
808
181
1,208
743
981
1,551
1,089
2009 2010 2011 2012 2013
Others
Commercial
Publicfacilities
Industrial
Residential/commercial
Residential
Total
- 53 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
United Arab Emirates: Construction Regional Data (cont’d)
Number and Type of Completed Buildings, units – Emirate of Abu Dhabi Average Estimated Cost per sq m, AED - Emirate of Abu Dhabi
Statistics Center – Abu Dhabi
3,96
6
3,14
8
3,62
0
3,47
5
4,12
6
3,90
7
3,73
5
3,69
6
3,50
9
3,42
7
3,41
1
3,14
83,37
8
3,27
1 3,58
5
2,94
4
3,36
5
3,70
2
3,48
3
3,62
4
3,669
3,4913,567
3,377
2011 2012 2013 2014
Below 300 sq m 300-599
600-899 900-1200
More than 1200 sq m Average
4,601
7,505
6,067
2,839
889
754
43
46
256
214
197
191
132
170
212
105
240
161
274
117
6,118
8,804
6,793
3,298
2011 2012 2013 2014
Commercial
Publicfacilities
Industrial
Residential/commercial
Residential
Total
- 54 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
United Arab Emirates: Construction Regional Data (cont’d)
Number and Type of Building Permits Issued, units - Emirate of Fujairah Licensed Area for Construction - Emirate of Fujairah
Fujairah Municipality, Dibba Municipality
1,208 1,260 1,180 1,1371,262
125 77 8773
119
107192
132178
117
9198
185260
296
732 360272 249
289
319
483 731
606
494
2,582
2,4702,587
2,503 2,577
2010 2011 2012 2013 2014
Others
Commercial
Publicfacilities
Industrial
Residential/commercial
Residential
Total
2,18
6
1,75
1
1,07
6 1,07
5
1,65
6
96.6%
-19.9%
-38.6%
0.0%
54.0%
2010 2011 2012 2013 2014
Licenced Area, thou sq m YoY change, %
- 55 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
United Arab Emirates: Major Construction Projects
Major Ongoing Projects
Construction Week Online, MEED, The National, Reuters, Al Habtoor City Brochure, World Nuclear Association, Aldar, Arabian Business, Gulf Today, Arab News, Zawya Projects, Trade Arabia, Gulf Construction Online, Business Insider, Emirates 24/7 News, Dubai World Central
Project Name Value, USD mn Size/Length/Capacity Timeframe
Commercial ConstructionYas Island Development 37,000 25,000,000 sq m land area Expected completion in Q4 2018
Al Reem Island 37,000 6,300,000 sq m land area Expected completion in Q1 2023
Saadiyat Island Development 27,000 27,000,000 sq m land area Expected completion in Q4 2018
Masdar City 22,000 6,000,000 sq m site area Expected completion in Q4 2025
Downtown Burj Khalifa 20,000 2,000,000 sq m land area Expected completion in Q1 2020
Al Raha Beach Development 15,000 5,000,000 sq m Estimated completion date in Q4 2021
Ghantoot Green City 15,000 60,000,000 sq m site area Estimated completion date in Q1 2020
Dubai Marina 12,300 6,100,000 sq m land area Expected completion in Q4 2015
Meydan City 10,000 Expected completion in Q4 2019
Desert Rose City, Dubai 9,500 140,000,000 sq m Construction works are expected to start in 2016 and
could take around 10 years.
Mohammed bin Rashid City 8,168 5,016,764 sq m of land area Q1 2013 - Q1 2027 (estimated)
Al-Marjan Island Development 8,000 A cluster of five islands covering 2,700,000 sq m Expected completion in Q4 2017
Construction of 37 Towers in Abu Dhabi and Dubai 6,000 84,000 sq m total plot area
1,300,000 sq m total built-up area
Q1 2014 - Q1 2018
Dubai Pearl 6,000 1,858,060 sq m total built-up area After the project has been delayed, it is due for
completion by 2018
Arzanah Development 6,000 1,400,000 sq m land area Expected completion in Q4 2016
- 56 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
United Arab Emirates: Major Construction Projects (cont’d)
Major Ongoing Projects
Project Name Value, USD mn Size/Length/Capacity Timeframe
Commercial Construction (cont'd)Port of Arabia (Mina al-Arab) 5,500 1,500,000 sq m land area Expected completion in Q1 2017
International City, Dubai 5,000 22,000 residences 5,000 retail units Expected completion in Q1 2020
Nujoom Islands, Sharjah 5,000 5,574,182 sq m Expected completion in Q4 2015
Al Habtoor City, Dubai 3,000 Over 3,000 hotel and residential units Q3 2012 - Q3 2016
Al Mamzar Beachfront Development, Dubai 2,723 4,000 residential units, 300 hotel rooms, and
250,000 sq m of retail outlets
As of April 2015, design works were underway.
Expected completion in Q4 2018
Dubai Parks and Resorts Complex 2,722 Complex of five theme parks Q1 2014 -2016 (Phase 1)
Al Manhal Development, Abu Dhabi 2,000 600,000 sq m of land area Q1 2012 - Q1 2017 (estimated)
Bluewaters Island 1,600 Man-made island located off the Jumeirah Beach
Residence (JBR) coastline.
Q2 2013 - Q1 2018
Saraya District of Abu Dhabi 1,400 136,000 sq m land area Expected completion by the end of 2015
Jewel of the Creek Development 1,360 123,955 sq m site area Q1 2012 - Q1 2017
Address Residence Fountain Views 1,000 A three-60-storey-tower complex. Q1 2014 - Q1 2017 (estimated)
Damac Towers 1,000 Over 1,800 residential units and 800-room 5-star
hotel
Expected completion in 2016
Taj Arabia at Falcon City of Wonders in Dubai 1,000 743,000 sq m land area, 213,677 sq m built-up
area
Expected completion in Q4 2017
Expo 2020 Venue, Dubai Complete project cost
undisclosed
Site area of 4.38 sq km, including residential,
hospitality and logistics zones.
In January 2015, a consortium was appointed to manage
all construction-related activities
Deira Islands Complete project cost
undisclosed
Land area of 15.3 sq km, comprising four islands,
21-kilometre beachfront and accommodating over
357,000 people upon completion.
Tender bids were being accepted by January 2015.
Aladin City, Dubai Project cost undisclosed as
of February 2015
Six towers, linked by air-conditioned bridges. Construction works are expected to start in 2016
Construction Week Online, MEED, The National, Reuters, Al Habtoor City Brochure, World Nuclear Association, Aldar, Arabian Business, Gulf Today, Arab News, Zawya Projects, Trade Arabia, Gulf Construction Online, Business Insider, Emirates 24/7 News, Dubai World Central
- 57 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
United Arab Emirates: Major Construction Projects (cont’d)
Major Ongoing Projects
Project Name Value, USD mn Size/Length/Capacity Timeframe
Residential Construction 2,300 homes situated on Yas Island, in Al Falah, and in
Al Ain
1,552 Expected completion in 2016
Social InfrastructureAl Ain New Hospital 1,170 358,000 sq m, 719-bed capacity Q1 2014 - Q1 2018
Energy, Utilities and MiningFour Nuclear Reactors, Barakah 20,000 5,600 MW total capacity Q1 2012 - Q1 2020
Al Gharbia Chemicals Industrial City 20,000 12 plants Expected completion in Q2 2017
Upper Zakum Full Field Development 15,600 Expansion should lead to capacity increase of
250,000 bpd
Expected completion in Q4 2015
Fujairah Oil Refinery 3,500 Processing capacity of about 200,000 bpd of crude
oil.
According to Zawya Projects, the EPC contract should
be awarded by June 2015 and the project should be
completed by end-2018.
Nasr Full Field Development Project, Packages 1,2,3 2,936 EPC contracts were awarded in November 2014. The
start-up of the project is scheduled to be achieved by
end-2018 and final commissioning by Q2 2019.
North East Bab Field Development, Phase 3: Al
Dabbiya Field
2,250 2014 - 2018
Abu Dhabi Alumina Refinery, Shaheen 2,000 Capacity of 2 mn tonnes of alumina annually in an
initial phase and additional 2 mn tonnes in a
second phase.
2014-2020
Hassyan Power Plant, Dubai Estimated cost of over
2,000
1,200 MW Q1 2014 - Q1 2021 (estimated)
Construction Week Online, MEED, The National, Reuters, Al Habtoor City Brochure, World Nuclear Association, Aldar, Arabian Business, Gulf Today, Arab News, Zawya Projects, Trade Arabia, Gulf Construction Online, Business Insider, Emirates 24/7 News, Dubai World Central
- 58 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
United Arab Emirates: Major Construction Projects (cont’d)
Major Ongoing Projects
Project Name Value, USD mn Size/Length/Capacity Timeframe
Transport InfrastructureAl Maktoum Intl Airport, Dubai 32,000 Annual capacity of 220 mn passengers and 16 mn
tonnes of cargo once the expansion is completed.
The expansion will be carried out in two phases over a
six to eight year period.
Dubai Metro 14,352 Includes the construction of the Red, Green, Blue,
Purple, Gold, and the Pink lines.
Expected completion by 2030.
National Rail Network, Phases 2 & 3 9,620 907 km long Tendering for final design and build contracts for Phase
2 is in progress.
Dubai Intl Airport, Dubai 7,800 Annual capacity increase of 30 mn passengers
upon completion.
Expected completion in 2018.
Abu Dhabi Metro 7,000 130 km two-way track metro network Expected completion in Q4 2018
Midfield Terminal, Abu Dhabi Intl Airport 2,960 Construction of 700,000 sq m main terminal
building with initial annual capacity of 27-30 million
passengers.
Expected completion in Q3 2017.
Dubai Water Canal 2,000 3 km long, 80 - 120 m wide, 80,000 sq m public
space
Expected completion in Q4 2016
Mafraq-Ghweifat Main Road 1,400 327 km long Expected completion in 2017.
Al Ain International Airport Expansion Undisclosed Q1 2014 - Q1 2017
Construction Week Online, MEED, The National, Reuters, Al Habtoor City Brochure, World Nuclear Association, Aldar, Arabian Business, Gulf Today, Arab News, Zawya Projects, Trade Arabia, Gulf Construction Online, Business Insider, Emirates 24/7 News, Dubai World Central, Airport Technology, Airport Data
- 59 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
United Arab Emirates: Investment Climate
FDI
Regime
At present, the Emirati regulatory and legal framework favours local over foreign investors. The UAE maintains non-tariff barriers to investment in the form of
restrictive agency, sponsorship, and distributorship requirements. In order to do business in the UAE outside one of the free zones, a foreign business in most cases
must have a UAE national sponsor, agent or distributor, with at least 51% ownership of the business.
The US Department of State reports that government tendering in UAE is not conducted according to generally accepted international standards, and re-tendering is
the norm. Federal tenders must be accompanied by a bid bond in the form of an unconditional bank guarantee for 5% of the value of the bid. However, UAE federal
government entities can tender internationally since foreign companies sometimes are the only suppliers of specialised goods or services that are not widely
available. Incentives are given to foreign investors in the free zones. Outside the free zones, no incentives are given, although the ability to purchase property as
freehold in certain favoured projects in Dubai would appear to be an incentive aimed at attracting foreign investment, as noted by the US Department of State.
Four major laws affect foreign investment in the UAE: the Federal Companies Law, the Commercial Agencies Law, the Federal Industry Law, and the Government
Tenders Law. These laws, especially the Federal Companies Law, are seen as the largest obstacles to foreign direct investment in the UAE. In addition to the
mandatory Emirati majority stake in businesses involving foreign partners, these laws stipulate that branch offices of foreign companies must have a national agent,
that distribution of foreign companies’ products in the UAE is only possible through exclusive commercial agents that are either UAE nationals or companies wholly
owned by UAE nationals, that industrial projects must either be managed by a UAE national or have a board of directors with a majority of UAE nationals, among
others.
Right to
Private
Ownership
and
Free Zones
The UAE restricts foreign ownership of land, with rules varying from emirate to emirate. Individual emirate policies allow non-GCC nationals to have
freehold or leasehold rights in designated areas, but as codifying and procedures for title documentation remain to be established, it remains unclear
whether the "freehold" title means the same as it does in Europe or the United States. In December 2010, Abu Dhabi Executive Council (ADEC)
issued Resolution No. 64 of 2010 on Regulations of Property Ownership stipulating that non-UAE individuals or legal entitites have the right to own,
buy, sell, rent, mortgage and invest in investment areas. Non-UAE nationals may hold “mustaha” rights for up to 50 years (subject to renewal for a
similar duration) and sign “usufruct” contracts for up to 99 years in properties located inside the investment areas.
The major attraction of the free trade zones (FTZ) is the waiver of the requirement for majority local ownership. Hence, in the free zones, foreigners
may own up to 100% of the equity in an enterprise. In addition, all free zones provide 100% import and export tax exemption, 100% exemption from
commercial levies, 100% repatriation of capital and profits, multi-year leases, assistance in labour recruitment, and advanced infrastructure and
logistic environment including easy access to sea and airports, buildings for lease, and energy connections (often at subsidised prices). Moreover,
the free zone authorities provide significant support services, such as sponsorship, worker housing, dining facilities, and security. According to the
UAE Embassy in the UK, there are 21 FTZ around the UAE, the biggest ones among them being Jebel Ali Free Zone, Sharjah Airport Intl Free Zone,
Dubai Airport Free Zone, Dubai Media City, Dubai Internet City, and RAK Free Trade Zone.
US Department of State, June 2014
- 60 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
United Arab Emirates: Investment Climate (cont’d)
Tax Rates
and
Access to
Credit
There is no personal income tax in the UAE. Foreign banks, outside of the free zones, pay 20% tax on their profits. Foreign oil companies
with equity in concessions pay taxes and royalties on their proceeds. There are no consumption taxes, and the GCC states formally
implemented a single import tariff of 5% on most goods. Companies located in the numerous "free zones" across the UAE are exempt from
the tariff on imports and re-exports that do not leave the zones. However, some exceptions do exist.
Dubai imposes a rental housing tax on expatriates equaling 5% of the rental charges.
UAE’s financial system is highly integrated and concentrated, thus remaining exposed to global vulnerabilities. However, in 2013 the IMF
noted that “the banking system maintains significant capital and liquidity buffers, and non-performing loans may finally have peaked at 8.7% in
December 2012,” suggesting a significant turnaround in the UAE banking sector’s post-2008-2009 crisis health.
Dispute
Settlement
In 2006, UAE entered effectively the UN Convention on the Recognition and Enforcement of Foreign Arbitral Awards. As a result, arbitration awards
issued in the UAE are enforceable in all 138 states that have acceded to the Convention, and any award issued in another member state is directly
enforceable in the UAE. In general, disputes are resolved by direct negotiation and settlement between the parties themselves, by recourse in the
legal system, or arbitration. In order to enforce arbitration judgments rendered in the UAE, a court certification that may take a long time is required.
Commonly, commercial disputes involving foreign parties are heard in the civil courts in the federal system in front of a three-judge panel. However,
commercial disputes might also come before the criminal courts, if one of the parties alleges criminal fraud or theft arising from a contractual dispute.
All cases involving banks and financial institutions are required to be heard by civil courts. Interestingly, the Court of Dubai International Financial
Center (DIFC) is also instrumental in commercial disputes resolution. The DIFC Court system operates independently of the UAE legal system on
commercial disputes as part of the DIFC free zone. In October 2011, the Vice President and Prime Minister of the UAE and Ruler of Dubai signed a
law allowing any Dubai-based business to use the English language DIFC Courts to resolve commercial disputes.
Labour
Conditions
The US Department of State reports that around 85% of UAE residents are non-Emiratis and approx. 98% of private sector labour are foreign
workforce. To alter this ratio, the government has set a goal to increase UAE nationals’ participation in the workforce, dubbed “Emiratisation”. As of
December 2010, all private corporations were required to reserve at least 15% of positions for UAE nationals. At banks, Emiratis must comprise at
least 40% of the workforce. The UAE National Human Resource Development and Employment Authority (Tanmia), is the federal body responsible
for fostering Emiratisation. In May 2009, the cabinet approved the establishment of the UAE Emiratisation Council (UEC), which is responsible for
formulating policies and standards to promote Emiratisation and for supporting the development of skills and competitiveness among nationals.
Given Emiratis’ strong preference for public sector employment, in 2013, the UAE labour ministry proposed changes to its labour law to attract more
citizens into the private sector. The changes include proposals to bring private and public sector salaries in line; adjust working hours and days, and
increase the number of private sector holidays.
Visas, residence permits, and work permits are required of all foreigners in the UAE except nationals of the GCC countries.
US Department of State, June 2014
- 61 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
VI. Main Players
- 62 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Top M&A Deals
Top 15 M&A Deals in the Construction Sector in MENA, 2013 and 2014
DealWatch
Date Target Company Deal Type Buyer Country of BuyerDeal Value Stake
USD (mn) (%)
18-Jan-13 Orascom Construction Industries SAE Acquisition OCI NV Netherlands 7300.00 97.44
(Official data)
29-Sep-14 Emaar Malls Group PJSC IPO Undisclosed buyer(s) n/a 1579.61 15.37
(Official data)
11-Nov-14 Arabtec Holding PJSC Minority stake Aabar Investments PJS UAE 962.67 15.99
purchase (Market estimate)
8-Jan-13 Sorouh Real Estate PJSC Acquisition Aldar Properties PJSC UAE 920.00 100.00
(Official data)
8-Jul-13 Arabtec Holding PJSC SPO Undisclosed buyer(s) n/a 641.10 50.00
(Official data)
11-Jul-13 Archirodon Group NV Minority stake Undisclosed buyer(s)
n/a 190.00 40.00
purchase (Official data)
18-Feb-13 Aldar Properties PJSC Minority stake Mubadala Development Co PJSC
UAE 188.92 8.84
purchase (Official data)
13-Jul-14 Rooya Group Acquisition Pioneers Holding Co Egypt 171.95 60.00
(Official data)
17-Jun-14 Al Hammadi Company for Development and
InvestmentIPO Undisclosed buyer(s)
n/a 168.00 30.00
(Official data)
12-Jun-14 Arabtec Holding PJSC Minority stake Undisclosed buyer(s) n/a 160.60 2.75
purchase (DW estimate)
3-Dec-14 Residences Dar Saada SA IPO Undisclosed buyer(s) n/a 127.45 20.00
(Official data)
26-Nov-13 Target Engineering Construction Co. LLC Minority stake Arabtec Holding PJSC
UAE 73.50 38.00
purchase (Official data)
18-Jul-13 Petrofac Emirates LLC Acquisition Nama Development Enterprises;
Petrofac Ltd
UAE; United
Kingdom70.00 51.00
(DW estimate)
13-Nov-14 Eshraq Properties Co
Buy-back of sharesEshraq Properties Co
UAE 58.72 10.00
(DW estimate)
14-Aug-14 Arabtec Holding PJSC Open market Undisclosed buyer(s)
n/a 48.00 0.95
purchase (Market estimate)
- 63 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
M&A Activity, 2013-2014
Number and Value of Top Deals in MENA’s Construction Sector
Distribution of Top Deals by Deal Type (%)
Distribution of Top Deals by Deal Value, USD (%)
Distribution of Top Deals by Region of Investors (%)
DealWatch
8,40
9
0901
74 0 329
1,8001,149
3
0
3
1
0
2
3 3
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2013 2014
Total value of deals (USD mn) Number of Deals
Minority stake purchase
33.3%
Acquisition26.7%
IPO 20.0%
SPO 6.7%
Buy-back of shares 6.7%
Open market purchase 6.7%
Undisclosed43.8%
UAE 37.5%
Netherlands6.3%
Egypt 6.3%
United Kingdom 6.3%
50.1-100mn; 33.3%
500.1-1000; 33.3%
> 1000mn; 22.2%
0-50mn; 11.1%
- 64 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Arabtec Holding PJSC
Income Statement (Consolidated, USD mn)
Arabtec Holding PJSC is a United Arab Emirates-based
company that was established in 1975 and acts as a holding
company to its subsidiaries, primarily investing in the
construction sector through the acquisition of contracting and
related companies. Listed on the Dubai Financial Market
since 2004, the company is one of the largest heavy
construction players in MENA.
Its projects vary greatly and include offshore and onshore oil
and gas installations, airport development, aircraft
maintenance hangars, passenger terminals, departure
lounges, fuel tank farms, drainage & electrical high and low
voltage, contracting services to residential projects, luxury
villas, hotel interiors, cinema complexes, hypermarket fit
outs, food courts.
The company has organised its operations in the following
business lines:
o High Rise Development
o Residential Development
o Hotels and Hotel Interiors
o Airport Development
o Commercial Development
o Luxury villas
o Stadiums
o Mixed Use Development
o Industry Projects
o Oil & Gas
Balance Sheet (Consolidated, USD mn)
Highlights
Company Data, EMIS Insight
1,54
2
2,00
9 2,66
7
134
193
162
38 103
58
8.7%9.6%
6.1%
2012 2013 2014
Net Revenues EBITDA Net Profit EBITDA margin
2,44
1
3,49
0
3,91
1
912 1,57
1
1,62
5
152
(417
.82)
45
1.14
-2.17
0.28
2012 2013 2014
Total Assets Shareholders' Equity Net Debt Net Debt/EBITDA
- 65 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Arabtec Holding PJSC (cont’d)
Share Price Statement, 2014
Arabtec is a key contractor in some of the largest airport
infrastructure projects in UAE. They include the
construction of:
o Midfield Terminal Building at Abu Dhabi Intl Airport – a
USD 2.9bn contract awarded to a JV between
Arabtec,TAV and CCC,
o Air Traffic Control Tower at Dubai World Central Intl
Airport (DWC) in 2007-2008 – a USD 40mn contract,
o Cargo Terminal Building at DWC – a USD 76mn contract,
o Passenger Terminal at DWC – a USD 26.7mn contract
awarded to Arabtec/Max Boëgl JV,
o Central Utility Plant at - a USD 7.1mn contract,
o TD-119 VIP Pavilion & Crew Access Building at Dubai Intl
Airport – a USD 1.9mn contract,
o Expansion of Terminal 2 at Dubai Intl Airport – a USD
163mn contract,
o Renovation and expansion of Dubai Intl Airport Terminal 1
– a USD 50.1mn contract.
Currently Arabtec employs over 40,000 people.
Allocation of Shareholders’ Equity by Geography, 2014
Highlights
Company Data, EMIS Insight
5.26
8.71
4.96
4.32
3.91
4.73
3.513.18
5.03
6.09
4.56
3.61
Q1 Q2 Q3 Q4Highest price, quarter averageLowest price, quarter averageClosing price, quarter average
Local 68%
Arab 17%
GCC 6%
Others 9%
- 66 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Drake & Scull International PJSC
Income Statement (Consolidated, USD mn)
Drake & Scull International PJSC, or DSI, became a publicly
listed company in 2008 when it rolled out its IPO on the
Dubai Financial Market.
The company specialises in mechanical, electrical and
plumbing services along with infrastructure, water and power
and civil construction services.
DSI has streamlined its operations in the following units:
o Drake and Scull Construction offers general construction
services for commercial, industrial, power and water as well
as heavy general contracting projects.
o Drake and Scull Engineering offers engineering (MEP and
Water and Power) services for large scale projects in
aviation, education, mixed use, residential, tourism, district
cooling, hotels, commercial offices and data centres.
o Drake and Scull Rail offers complete EPC solutions for all
systems and services for stations, depots and tunnels.
o Drake and Scull Oil and Gas offers construction and
construction management contracting services to the
petrochemical industry.
o Drake and Scull Development focuses on public-private
partnerships for large scale infrastructure projects in the
MENA region, South Asia and Europe.
o Passavant Energy and Environment develops technologies
and processes in municipal wastewater, sludge, water and
industrial wastewater treatment.
Balance Sheet (Consolidated, USD mn)
Highlights
Company Data, EMIS Insight
905
1,33
0
1,29
8
60 98 81
26 45 27
6.7%
7.4%
6.2%
2012 2013 2014
Net Revenues EBITDA Net Profit EBITDA margin
1,75
3
1,95
3 2,33
3
755
811
839
188
181 41
8
3.12
1.84
5.18
2012 2013 2014
Total Assets Shareholders' Equity Net Debt Net Debt/EBITDA
- 67 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Drake & Scull International PJSC (cont’d)
Backlog by Business Stream, 2014
DSI has executed mechanical, electrical and plumbing
engineering works on airport infrastructure projects
including:
o International Airport Terminal phase II, Abu Dhabi – UAE,
o Extension for Military Airbase, Dubai – UAE,
o Kai Tak Airport - Hong Kong,
o Phase I Air Cargo Terminals - Hong Kong,
o New Doha International Airport CP15 – Qatar,
o Dar Es Salaam International Airport,Dar Es Salaam –
Tanzania.
• The company has also incorporated HVAC (heating,
ventilation, and air conditioning), smoke ventilation,
general air extraction, fire protection & alarm systems, exit
systems, and electrical distribution systems in railway
infrastructure projects that include:
o Channel Tunnel Rail Link Line Infrastructure - London UK,
o St. Pancras Station Redevelopment -London UK,
o Jubilee Line Extension Project - London, UK.
DSI has established offices in UAE, Saudi Arabia, Kuwait,
Oman, Qatar, Egypt, Jordan, Algeria, Iraq, Thailand,
Vietnam, India, China, Germany, Romania, and Turkey.
Backlog by Geography, 2014
Highlights
Company Data, EMIS Insight
General contracting
42%
Engineering38%
Oil & gas 15%
Water treatment 5%
Saudi Arabia35%
Egypt 18%
Dubai 10%
Jordan 7%
Abu Dhabi 8%
Algeria 6%
Qatar 5%
Kuwait 2%Iraq 1%
Others 8%
- 68 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Combined Group Contracting Co.
Income Statement (Consolidated, USD mn)
Combined Group Contracting Company, or CGC, was
established in 1965 in Kuwait as a limited liability
company. The company became a publicly traded
shareholding company in 2006, when it was listed on the
Kuwait Stock Exchange with a capital of approx. USD
40mn.
The company operates in the construction industry and its
activities include carrying out civil, mechanical and
contracting work, trading of loose and packaged cement,
manufacturing and selling building materials and related
products.
Through its branches and subsidiaries, CGC is present in
Kuwait, Saudi Arabia, UAE, Qatar, Syria, Iraq, Lebanon
and Oman.
Among the assets owned by the company are a concrete
mixing plant with a production capacity of 160 cubic
meters / hour, asphalt plants with production rate of 440
tonnes/hour, and an extensive fleet of earth moving, road
paving and construction vehicles, as well as pumping
equipment together with numerous other transportation
vehicles
Currently CGC employs around 10,000 people.
Balance Sheet (Consolidated, USD mn)
Highlights
Company Data, EMIS Insight
847
694
44416
2
114
9392
56 24
19.1%
16.5%
21.0%
2012 2013 2014
Net Revenues EBITDA Net Profit EBITDA margin
1,32
9
1,39
0
1,32
6 838
911
915
69
169
108
0.43
1.48
1.15
2012 2013 2014
Total Assets Shareholders' Equity Net Debt Net Debt/EBITDA
- 69 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Combined Group Contracting Co. (cont’d)
Revenues by Division in 2014, KWD thou
In the Roads & Infrastructure sector, the company has
executed projects in countries like Kuwait, UAE, Qatar,
Indonesia, and Mongolia.
Some of the major road infrastructure projects that CGC
has worked on include:
o Design, construction and completion works on a sea
bridge connecting Kuwait City and Subiyah (project still in
progress). CGC’s share of total works on the bridge
amounts to approx. USD 570mn.
o Infrastructure development of small and medium scale
industrial area in Doha, Qatar. The USD 189.6mn project
was completed in March 2012.
o Infrastructure development for north residential and west
waterfront areas at Lusail City, Doha, Qatar, The USD
183.2mn project was completed in January 2013.
o Construction, completion and maintenance of the
interchanges of the main highways (Sixth Ring Road)
connecting to new housing area at South Jahra, Kuwait.
The USD 140.2mn project was completed in November,
2013.
Revenues by Geography in 2014
Highlights
Company Data, EMIS Insight
52,357
38,486
19,026 17,489
5,532 5,015
1
Construction Highways Water & Electricity
Oil Maintenance & Services Others
Kuwait 66%
Qatar 21%
UAE 13%
- 70 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Galfar Engineering And Contracting SAOG PLC
Income Statement (Consolidated, USD mn)
Founded in 1972, Galfar Engineering & Contracting
SAOG, also known as Galfar, is the largest construction
company in Oman with capabilities in the Oil & Gas,
Roads & Bridges, and Civil & Utilities sectors. It operates
in Oman, and in other GCC countries as well as in India.
The company is listed on the Muscat Securities Market.
It offers to its clients various services in the fields of
engineering, procurement, construction, operations &
maintenance, and project management.
Galfar’s Roads & Bridges Unit was established in 1989.
Since then, it has completed the construction/
rehabilitation of over 1,500 km of roads in Oman. The unit
has a central full-fledged materials testing laboratory for
soil, asphalt and concrete testing in addition to various
site laboratories. It is also self-sufficient in the production
of major road building materials such as aggregates and
asphalt.
Galfar owns 1,134 heavy machines, 794 light machines,
811 miscellaneous machines, 977 electrical machines, 69
stationary plants, 1,614 heavy vehicles and 2,178 light
vehicles.
It employs more than 23,000 people and is the largest
employer of Omani nationals in the private sector.
Balance Sheet (Consolidated, USD mn)
Highlights
Company Data, EMIS Insight
855 1,
104
969
104
116
88
24 20.1
6
0.44
12.2%
10.5%
9.1%
2012 2013 2014
Net Revenues EBITDA Net Profit EBITDA margin
1,18
7
1,28
4
1,30
6
237
276
267
421 51
3
522
4.034.42
5.95
2012 2013 2014
Total Assets Shareholders' Equity Net Debt Net Debt/EBITDA
- 71 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
Galfar Engineering And Contracting SAOG PLC (cont’d)
Segment Results, OMR thou
Some of the major roads & bridges projects that are
already completed include the dualisation of Wadi Adai Al
Amerat Road, Rushtaq-Miskin Road, the rehabilitation of
Batinah Highway, and the USD 340mn value Muscat
Expressway.
Transport infrastructure projects that are currently being
executed by Galfar include:
o Construction of Batina Expressway (Package 1), value of
contract USD 422mn,
o Development of Salalah International Airport Project,
value of contract USD 236mn,
o Rasl Al Hadd Airport Development Project (Package 2,
Airfield Development), value of contract USD 104mn,
o Construction of Hasik - Ash Shuwaymiyah Asphalt Road,
value of contract USD 288mn,
o Dualisation of Nizwa - Thumrait Road (Izz - Adam
Section), value of contract USD 132mn,
o Dualisation of Taqah - Mirbat Road, value of contract USD
105mn,
o Construction of Grade Separated Junctions along Batinah
Highway - Stage 3 (Part 1), value of contract USD 59mn,
o Procurement and construction of asphalt road in the
Khazzan area, value of contract USD 24.2mn.
Segment Assets, OMR thou
Highlights
Company Data, EMIS Insight
9,009
1,550 1,083 1,054 107 61 5
(126)(2,620) (2,343)
December, 2013 December, 2014
Construction Manufacturing Hiring of equipment
Training Inter segments
496,539 514,568
4,641 6,387 3,138 2,893 178 133
(8,738) (21,696)December, 2013 December, 2014
Construction Manufacturing Hiring of equipment
Training Inter segments
- 72 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
National Marine Dredging Company PSC
Income Statement (Consolidated, USD mn)
Income Statement (Consolidated, USD mn)
The National Marine Dredging Company was established
in 1976 as a unit of Abu Dhabi National Petroleum
Company. It became an independent shareholding
company in 1979. The company is listed on the Abu
Dhabi Securities Exchange.
It is primarily engaged in the execution of dredging
contracts and associated land reclamation works in the
territorial waters of the United Arab Emirates and Qatar.
The dredging and reclamation works, the company’s main
business, comprise capital and maintenance dredging
(inclusive deepening of water passages); artificial island
construction; land reclamation using dredged material;
and creating water channels, intakes and outfalls.
Since 2009, the company has diversified its operations
into marine construction as well. It includes activities like
construction of breakwaters, revetments, groins and
related rock works; concrete armour protection;
construction of gravity quay walls, retaining and
diaphragm walls; boat ramps and slipways; beach
construction and nourishment; and marinas and pontoons.
Balance Sheet (Consolidated, USD mn)
Highlights
Company Data, EMIS Insight
847
694
444
162
114
9392
56 24
19.1%
16.5%
21.0%
2012 2013 2014
Net Revenues EBITDA Net Profit EBITDA margin
1,32
9
1,39
0
1,32
6 838
911
915
69
169
108
0.43
1.48
1.15
2012 2013 2014
Total Assets Shareholders' Equity Net Debt Net Debt/EBITDA
- 73 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Source:
National Marine Dredging Company PSC (cont’d)
Growth in 2013 vs. 2010
Among the projects undertaken by the National Marine Dredging
Company are dredging works to construct a “Destination
Village” to host the Volvo Ocean Race in Abu Dhabi in 2011;
dredging works to nourish the beach of Yas Island; rehabilitation
and 2.7 km. extension of the Corniche public beach in Abu
Dhabi; land reclamation on Sir Baniyas Island; dredging and
sand reclamation to create the Nareel Island in 2007; site
preparation works on Al Maryah Island (Abu Dhabi); and
dredging and sand reclamation works to create Al Gurm Island
Resort.
Marine construction projects include dredging the channel and
basin of the Sulphur terminal at Ruwais Port and creation of 20
mn m³ artificial island; dredging a navigation channel at
Ghantoot Harbour; capital and maintenance dredging at berths
14 & 15 at Jebel Ali Port in Dubai; dredging and reclamation for
the new central areas of Fujairah Port, deepening of the then
existing port to a depth of -15 m. and dredging of a complete
new basin to a depth of -18 m.; dredging, reclamation and
marine works for the New Fishing Port at Abu Dhabi (2009-
2011); construction of the Mussafah Channel, Abu Dhabi, (63.5
km. long, 200 m. wide; 9 m. deep); and design and
construction of a private marina (Al Bateen Marina) for the
berthing of yachts with a design depth of – 8.5 m., New Abu
Dhabi Datum.
The company’s fleet consists of cutter suction dredgers (CSD)
with capacity from the small Beaver dredger Jananah (1,795
KW) to the most powerful automated dredger the Al Sadr
(20,725 KW). The dredgers are supported by tugs and multicat
crafts, and A-Frame barges wherever necessary.
Market Capitalisation vs. Equity to Market Value
Highlights
Company Data, EMIS Insight
19%18%
11%
0.29%
1
Revenue growth Fixed assets growth
Equity growth Share price growth
2,27
6
2,08
7
2,27
8
1,95
9
1.05
1.36 1.35
1.70
2006 2007 2008 2009
Market capitalisation, AED mn Equity to market value
- 74 -Any redistribution of this information is strictly prohibited.
Copyright © 2015 EMIS, all rights reserved.
Contact:
Corporate Headquarters
6-8 Bouverie Street
London EC4Y 8DD
UK
Voice: +44 20 7779 8100
Fax: +44 20 7779 8224
Americas Headquarters
225 Park Avenue South
New York, New York 10003
US
Voice: +1 212 610 2900
Fax: +1 212 610 2950
Asia Headquarters
Eucharistic Congress Bldg. No.
III
4th Floor, 5 Convent Street
Mumbai 400 001
India
Voice: +91 22 22881123
Fax: +91 22 22881137
Disclaimer:
The material is based on sources which we believe are reliable, but no warranty, either expressed or implied, is provided in relation to the accuracy or completeness
of the information. The views expressed are our best judgment as of the date of issue and are subject to change without notice. EMIS and Euromoney Institutional
Investor PLC take no responsibility for decisions made on the basis of these opinions.
Any redistribution of this information is strictly prohibited. Copyright © 2015 EMIS, all rights reserved. A Euromoney Institutional Investor company.
About EMIS Insight
EMIS Insight is a unit of EMIS that produces proprietary strategic research and analysis. The service features market overviews, industry trend analysis, legislation
and profiles of the leading sector companies provided by locally-based analysts.
About EMIS
Founded in 1994, EMIS (formerly known as ISI Emerging Markets) was acquired by Euromoney Institutional Investor PLC in 1999. EMIS works from over 15 offices
around the world to deliver electronic information products, by subscription, to institutional customers globally. EMIS provides hard-to-get information covering more
than 100 emerging markets. Its flagship products are EMIS Intelligence and EMIS Professional.
EMIS clients include top investment banks, corporations, law firms, consultants, investment and insurance companies, universities and libraries, multilateral
organisations, and others.