CONSTRUCTION PROJECT STATUS REPORT Student Health ...
Transcript of CONSTRUCTION PROJECT STATUS REPORT Student Health ...
![Page 1: CONSTRUCTION PROJECT STATUS REPORT Student Health ...](https://reader030.fdocuments.net/reader030/viewer/2022013005/61cd831a07141a5ea42f0cdb/html5/thumbnails/1.jpg)
FACILITIES MANAGEMENT Capital Construction & Renovation
Date: July 22, 2021 Report No. 17
CONSTRUCTION PROJECT STATUS REPORT
Student Health & Wellness Center
Construction Manager: Architects: Barton Malow Company, Charlottesville, VA VMDO & Duda Paine
Current Status: Construction Start: March 5, 2019 Construction Completion: August 23, 2021 Substantial Completion Completion Status: 96% Complete Bid Package
Current ActivitiesInterior Painting & Finishes Millwork Furniture and Equipment Mechanical, Electrical, Plumbing Life Safety Systems Testing Landscape Final Grading and Prep
Future Activities: Interior Painting & Finishes Mechanical, Electrical, Plumbing Life Safety Systems Testing Mechanical Systems Test and Balance Landscaping
Report prepared by: Amy Eichenberger, UVA Senior Project Manager [email protected] (434) 924-8627
Richard Sergi is the UVA Senior Construction Administration Manager [email protected] (434) 996-4570
![Page 2: CONSTRUCTION PROJECT STATUS REPORT Student Health ...](https://reader030.fdocuments.net/reader030/viewer/2022013005/61cd831a07141a5ea42f0cdb/html5/thumbnails/2.jpg)
2
Recent Construction Photos:
![Page 3: CONSTRUCTION PROJECT STATUS REPORT Student Health ...](https://reader030.fdocuments.net/reader030/viewer/2022013005/61cd831a07141a5ea42f0cdb/html5/thumbnails/3.jpg)
3
![Page 4: CONSTRUCTION PROJECT STATUS REPORT Student Health ...](https://reader030.fdocuments.net/reader030/viewer/2022013005/61cd831a07141a5ea42f0cdb/html5/thumbnails/4.jpg)
4