CONSTRUCTION PROGRESS UPDATE Vol. 12 November 2016 TO VALUED BUYERS OF BODAIJU RESIDENCES

Transcript of CONSTRUCTION PROGRESS UPDATE - Bodaiju...

CONSTRUCTION PROGRESS

UPDATE

Vol. 12November 2016

TO VALUED BUYERS OF

BODAIJU RESIDENCES

©Torreya Asset Holdings Co., Ltd.

Bodaiju Site Progress Report - Building A and B -

1

Dear valued buyers of Bodaiju Residences,

It is with great pleasure that I’m writing to you to share with you on the construction

progress for Bodaiju Residences.

Since the sales of Bodaiju Residences on 22nd August 2015, we had received over-

whelming support and much better than expected sales of Bodaiju Residences. With the

strong support, my construction team has been working endlessly to meet the construction

progress. After completing the UXO clearance and test piling works, we are currently

carrying out piling works in full force.

As part of our continuous engagement with you, I’m pleased to provide you with the

details of the construction in this report and endeavor to provide you with an update on

the construction every quarter.

Thank you for all the great support extended thus far.

Sincerely,

Toshihiko Muneyoshi

Founder/ Manager Director

Creed Group

©Torreya Asset Holdings Co., Ltd.

Construction Schedule Payment Schedule

Mar

Apr

May

Jun

Sep

Oct

Nov

Dec

2017

Jan

Feb

Jul

Aug

Mar

Nov.

2015

Oct.

Dec

2016

Jan

Feb

Vol. 12 November 2016

Bodaiju Site Progress Report - Building A and B -

2

GENERAL SCHEDULE (October 2015 – June 2017) CONSTRUCTION PROGRESS

We are completed the 8th Floor Structure Work in this

October. Structure Work of RF Floor plan to complete by

end of Feb 2017.

Piling works

Architectural

works

Interior works

MEP

works

Completion of

RF floor structure

preliminary

works - Mine investigation

- Ultimate load test, etc.

RC

Superstructure

※Construction’s Schedule might vary to take weather conditions and other factors into account.

Building ABuilding B

※The diagram above only serves to illustrate the construction progress. Actual construction may not be

carried out as per the illustration.

P1

P2

1F

2F

3F

5F

6F

7F

8F

9F

10F

11F

12F

13F

RF

P1

P2

1F

2F

3F

5F

6F

7F

8F

9F

10F

11F

12F

13F

RF

FOUNDATION WORK

COMPLETED. MARCH-2016

Completion of

foundation

Parking 1

Parking 2

Garden Deck

1st FLOOR STRUCTURE

COMPLETED. JUNE-2016

Completion of

1st floor structure

7th FLOOR STRUCTURE

COMPLETED. SEP-2016

Completion of

7th floor structure

NOW 8th FLOOR STRUCTURE

©Torreya Asset Holdings Co., Ltd. Vol. 12 November 2016

Bodaiju Site Progress Report - Building A and B -

3

FOUNDATION COMPLETION – March 2016 PHOTOS OF PROGRESS COMPLETION

©Torreya Asset Holdings Co., Ltd. Vol. 12 November 2016

Bodaiju Site Progress Report - Building A and B -

4

1FL. SUPER-STRUCTURE COMPLETION-June 2016 PHOTOS OF PROGRESS COMPLETION

©Torreya Asset Holdings Co., Ltd. Vol. 12 November 2016

Bodaiju Site Progress Report - Building A and B -

5

7FL. SUPER-STRUCTURE COMPLETION-Sep. 2016 PHOTOS OF PROGRESS COMPLETION

©Torreya Asset Holdings Co., Ltd.

B1 View – Building A

Bodaiju Site Progress Report - Building A and B -

6

SEPTEMBER 2016 SITE VIEW (BUILDING A & B)

In October 2016 we already complete the 8th Floor Structure Work and reinforcement work of 9th Floor for Building A & B.

Vol. 12 November 2016

A1

A2

B1

B2

A1 View – Building A

A2 View – Building AB2 View – Building A

©Torreya Asset Holdings Co., Ltd.

Bodaiju Site Progress Report - Building A and B -

7

9FL-BEAM & SLAB FORM WORK (BUILDING A & B) 9FL-BEAM & SLAB REINFORCEMENT (BUILDING A & B)

Reinforcement Work site activities of Building A & B on 9th Floorwhich completed in this October.

Slab and Beam Form Work installation activities in our constructionsite in October 2016.

Vol. 12 November 2016

©Torreya Asset Holdings Co., Ltd.

Bodaiju Site Progress Report - Building A and B -

8

8FL-RE-BAR CHECK & CLEANING (BUILDING A & B) 8FL-CONCRETE TEST AT SITEMixed-Concrete was tested at site before casting building A& B Structure, 8FL Slab and Beam.

Re-Bar Checking activates of Building A & B at construction site byour engineer.

Vol. 12 November 2016

©Torreya Asset Holdings Co., Ltd.

Bodaiju Site Progress Report - Building A and B -

9

8FL-MEP WORK (BUILDING A & B) 8FL-CONCRETE WORK (BUILDING A & B)

This is Water Piping Work of Building A & B was completed inSeptember 2016.

Pipe for electricity in 7th Floor Slab was laid to be ready forconcreting.

Vol. 12 November 2016

©Torreya Asset Holdings Co., Ltd.

BUILY-IN WAREDROPE INSTALLATION

HANGING KITCHEN CABINET & DUCT INSTALLATION

Bodaiju Site Progress Report - Building A and B -

10

MASONRY WORK (BUILDING A & B) BUILT-IN FURNITURE SETUP (MOCK UP UNIT)

This is Built-in Wardrobe and Hanging Kitchen’s cabinetinstallation activities of Mock Up units in Building A.

MASONRY WORK is the brick work after finish structure work ineach floor. This is our site activities in October 2016.

Vol. 12 November 2016