Construction Phase

7
Community Development Departmen t Construction Phase

description

Construction Phase. PROJECT LIMITS. Cypress Point Parkway to Florida Park Drive ~ 1.23 miles. PROJECT BENEFITS. Reduce congestion (increase level of service and reduced travel times). Improve safety for vehicles and pedestrians as well as potential for accidents. - PowerPoint PPT Presentation

Transcript of Construction Phase

Page 1: Construction Phase

Community DevelopmentDepartme

nt

Construction Phase

Page 2: Construction Phase

Community DevelopmentDepartme

nt

PROJECT LIMITSCypress Point Parkway to Florida Park Drive ~ 1.23 miles

Page 3: Construction Phase

Community DevelopmentDepartme

nt

• Reduce congestion (increase level of service and reduced travel times).

• Improve safety for vehicles and pedestrians as well as potential for accidents.

• Improve mobility for emergency vehicles.• Improve westward hurricane evacuation operations.• Provide an 8-foot sidewalk along the roadway and bridge in both

directions to accommodate pedestrians and bicyclists.• Provide dedicated turn lanes.• Provide concurrent left turns at Cypress Point Intersection and

Old Kings Road.• Extension of street lighting.• Enhanced Landscaping and conversion of irrigation to re-use.

PROJECT BENEFITS

Page 4: Construction Phase

Community DevelopmentDepartme

nt

TREE RELOCATION

Indian Trails Sports Complex Waterfront Park

Page 5: Construction Phase

Community DevelopmentDepartme

nt

• Construction Phase: 2014 - 2015 FDOT has allocated funding for the construction phase in

the current fiscal year budget. Agreements for this Phase have been executed.

Interlocal between City & County. FDOT LAP Agreement between County & FDOT Supplemental FDOT LAP Agreement pending

approval & execution. (scheduled for County Commission Meeting on 12/16/2013.

Construction to begin early 2014 and to be completed by the end of 2015.

PROJECT DEVELOPMENT PROCESS

Streets Improvement FundProject Name December 2013 March 2014 June 2014 September 2014

Palm Coast Parkway Six-Lane Construction

1st Quarter 2nd Quarter 3rd Quarter 4th Quarter

City of Palm Coast2014 Capital Projects Timeline

10/8/2013

Page 6: Construction Phase

Community DevelopmentDepartme

nt

CITY COUNCIL ACTION6) Construction Contract

P&S Paving, Inc. $10,556,445.42 Contingency $ 1,055,644.54

7) Construction Inspection (CEI) Contract Hill International, Inc. $ 1,180,197.00 Contingency $ 118,019.00

8) Post-Design Services Change Order DRMP Engineers $ 160,691.00

9) FPL Street Light Agreements Relocation Agreement $ 114,139.00 Street Light Agreement $ 385,864.00

Page 7: Construction Phase

Community DevelopmentDepartme

nt

FDOTBudget:$10,328,232Actual: $10,328,232

CITY - UTILITY FUNDBudget: $1,000,000Actual: $1,000,000

CITY - STREET IMP. FUNDBudget: $2,459,738Actual: $2,242,679

TOTAL: Budget:

$13,788,058Actual

$13,570,997

CONSTRUCTION PHASE FUNDING