Construction of LLP HMA Pavements

Pre-bid MeetingSolano 80; 04-4A0104

District 4Oakland , CA

September 14, 2012

Bob Humer

Page 2: Construction of LLP HMA Pavements

Caltrans Contract Solano Project 04-4A0104

Page 3: Construction of LLP HMA Pavements

Pavement Cross Section

Page 4: Construction of LLP HMA Pavements

Pavement Cross Section

Page 5: Construction of LLP HMA Pavements

Structural Sections

Page 6: Construction of LLP HMA Pavements

Overview

Special RequirementsProject LLP Mix Designs

ConstructionSuccesses

Page 7: Construction of LLP HMA Pavements

Special RequirementsThis project includes special testing requirements for the mix design of HMASee section 10-1.41, "Hot Mix Asphalt (Long Life)" of the Special Provisions for the special testing requirements.This testing will take significantly longer than the testing specified in Section 39-1.03, "Hot Mix Asphalt Mix Design Requirements," of the Standard Specifications.

Page 8: Construction of LLP HMA Pavements

Special Requirements 10-1.41, "Hot Mix Asphalt (Long Life)“– Prepaving conference shall be held no more

that 30 days following approval of the contract.

– Review special provisions for those required to attend.

– If a party cannot attend this mandatory meeting at the time scheduled, the meeting will be delayed until such time as all parties can be present, or the meeting will be repeated with all parties present.

Page 9: Construction of LLP HMA Pavements

Solano Project 04-4A0104

Specification Section 10-1.41 “Hot Mix Asphalt (Long Life)” Required Mix Designs– HMA (15% Max RAP, Long Life) PG 64-28PM– HMA (25% RAP, Long Life) PG 64-10• You may request in writing to the Engineer to use

a “softer” PG binder to meet the Performance requirements

• *HMA mixes must meet permanent deformation, fatigue, stiffness, and Hamburg wheel tracking test requirements.

*HMA aggregates must be treated with Lime (Marination)

Page 10: Construction of LLP HMA Pavements

LLP Structural SectionSolano Project (Main line)

0.2’ HMA (15% Max. RAP Long Life) (PG 64-28PM)

0.25’ HMA (25% RAP Long Life) (PG 64-10)

HMA (leveling course) (PG 64-10)

2 LLP Mix Designs!!!

NTS

Existing Cracked & Seated PCC or HMA

GPI*

* GeoSynthetic Pavement Interlayer / Fabric

0.1’ HMA –O

Page 11: Construction of LLP HMA Pavements

Long Life Pavement Projects Quantity of Materials Per Mix Design

Caltrans ProjectTypical Long Life

Preliminary Mix Design(includes CT 371)

5 gal binder~500 lb aggregate

5 gal binder~500 lb aggregate

Performance Testing(includes specimen

fabrication)10 gal binder~ 1,200 lb aggregateShear

FatigueHamburg

Page 12: Construction of LLP HMA Pavements

Long Life Pavement ProjectsEstimated Time Per Mix Design

Caltrans ProjectTypical Long Life

Preliminary Mix Design(includes CT 371)

3 weeks 3 weeksPerformance Testing(includes specimen

fabrication)Shear ~ 3 weeksFatigue ~ 6 weeksHamburg ~ 1 week

Page 13: Construction of LLP HMA Pavements

LLP Mix Design ProcessMake every effort to insure that consistent and uniform virgin aggregates are available for use on entire project.Collect sufficient aggregates, virgin and RAP, during mix design process for mix design testing.Allow a minimum of 3 weeks for each HMA preliminary mix design.Allow a minimum of 10 to 12 weeks per mix design for performance testing.

Page 14: Construction of LLP HMA Pavements

HMA Performance Testing

Performance tests required for this project are very different from the usual HMA tests. Few labs in the nation can perform these tests.

Page 15: Construction of LLP HMA Pavements

HMA Performance Testing

Three labs listed in the Special Provisions can perform HMA performance tests for this project:

– University of California Pavement Research Center (UC-PRC), Richmond, CA

– Advanced Asphalt Technologies (AAT), Sterling, VA

– The Asphalt Institute, Lexington, KY

Page 16: Construction of LLP HMA Pavements

Construction of LLP HMA

Binder content range during production Job Mix Formula Target Value ±0.3%. Compaction of LLP HMA during production to 94% - 97% of Maximum Theoretical Density (Gmm).Consistency, Consistency, Consistency

Page 17: Construction of LLP HMA Pavements

Successes on Previous LLPSufficient Number of Quality Control Staff– Timely test data are essential.– Qualified personnel that understand field

operations and can quickly interpret laboratory test data.

Page 18: Construction of LLP HMA Pavements

Successes on Previous LLPStaging and Contingency PlansEstablishing a good working platform on which to pave.

Page 19: Construction of LLP HMA Pavements

Successes on Previous LLPEffective CommunicationThese projects are a true Partnership between the Contractor and Caltrans.