1 BROOKHAVEN SCIENCE ASSOCIATES
Construction Management Readiness
Stephen Sawch, Assistant Director for Construction ManagementConventional Facilities Advisory Committee Review
March 10 –11, 2009
2 BROOKHAVEN SCIENCE ASSOCIATES
Construction Preparations Outline
• Safety – Critical Requirement• Construction Management Plan• Policies and Procedures• Construction Management Team• CF Field Office• External CM Oversight• Construction Readiness• CFAC Topics for Discussion• Path Forward
3 BROOKHAVEN SCIENCE ASSOCIATES
Construction Safety
• Objective – “Best in Class” Safety Program• Torcon - Proven Safety Record
• Safety performance highest weighted selection criteria• OSHA Voluntary Protection Program (VPP Contractor)• Goal of DOE VPP & Star Worksite for LT
• CF ESH Plan in Place• Regular meetings to continue improvements• Applied Lessons Learned in ESH Plan Development
• CF Staff Taken OSHA 10 Hour Course• Our success measured by our Safety Performance
4 BROOKHAVEN SCIENCE ASSOCIATES
Construction Management Plan
• Construction Management Scope• Methods & Procedures to Meet Project Objectives• Quality Assurance Plan and CM Plan Work in Concert
• CM Organization• Defines Responsibilities
• ESH for Conventional Facilities• ESH Plan and CM Plan Work in Concert
• Communication and Document Management• Define and Standardize Communication
5 BROOKHAVEN SCIENCE ASSOCIATES
Construction Management Plan
• Communication and Document Management cont’d• Establish Meeting & Reporting Requirements• Shop Drawing and RFI Routing
• Project Control Software • Purchased Primavera Contract Mgr. (formerly Expedition)• CF Team trained on Contract Manager• Create, Share and Access Project Documents
– Transmittals – Submittals – Correspondence– Web Based and is Used by Most Contractors
• Manage Submittals – Submittals Logs & Dunning Letters
6 BROOKHAVEN SCIENCE ASSOCIATES
Construction Management Plan
• Project Control Software– Issue and Track Noncompliance– Build and Link Issue Files with Documents
• Field Inspection & Oversight• Develop Project Checklist• Oversee Day to Day Activity• Document Nonconformance
• Testing & Commissioning• Test Record Index• Commissioning Contractor
7 BROOKHAVEN SCIENCE ASSOCIATES
Construction Management Plan
• Acceptance and Transition to Operations• Testing & Training Complete• O&M Documents Available• Punch List Preparation• BORE – Beneficial Occupancy Readiness Evaluation
• Change Control & Configuration Management• Technical Changes
– Reviewed & Approved– Documented (ECN –Engineering Change Notice)– Maintain As-Built Drawings – Monthly Updates Part of Pay Req.
8 BROOKHAVEN SCIENCE ASSOCIATES
CF Procedures Manual
• Used BNL’s Plant Engineering Policies & Procedures as basis for CF Procedures Manual
• Worked with Quality Assurance identified applicable Policies
• Successfully used for CFN• Transmittals, submittals, RFIs, reports, inspections
and closeout• Integrated Contract Manager Software into CF
Procedures Manual (Primavera)
9 BROOKHAVEN SCIENCE ASSOCIATES
CF Procedures Manual
10 BROOKHAVEN SCIENCE ASSOCIATES
CF Procedures Manual
11 BROOKHAVEN SCIENCE ASSOCIATES
Procedures – Inspection Forms
12 BROOKHAVEN SCIENCE ASSOCIATES
LT- CF Construction Team
• Staffing Requirements Determined• Roles and Responsibilities Identified• Project Team Established
• 3 Lead Engineers Hired• Administrative Assistant Hired• Construction Engineer/Civil & Electrical Inspectors Hired• Last Hire - Mechanical Inspector – Currently Interviewing
• Anticipate Staff Augmentation Requirements• Augment with CM Firm (Liro/Gilbane) Staffing• Inspectors/Clerk of Works/Administrative Assistant/Others
13 BROOKHAVEN SCIENCE ASSOCIATES
Construction Staffing Requirements
CONVENTIONAL FACILITIES 2008 2009 2010 2011 2012 2013 2014
DESIGN
BID & AWARD
SITE PREP
RING BUILDING
RING BUILDING CLOSE-OUT
LOBs
LOB CLOSE-OUT
CF PERSONNEL 2008 2009 2010 2011 2012 2013 2014 Division Status RESPONSIBILITIES
1 DIRECTOR CF Filled CF Oversight
2 ASSISTANT DIRECTOR DESIGN CF Filled A/E Design
3 ASSISTANT DIRECTOR CM CF Filled Construction Management
4 SCHEDULE ENGINEER PS Filled Scheduling/Cost tracking
5 CIVIL ENGINEER CF Filled A/E Design & Construction RFI's
6 MECHANICAL ENGINEER CF Filled A/E Design & Construction RFI's
7 ELECTRICAL ENGINEER CF Filled A/E Design & Construction RFI's
8 CONSTRUCTION ENGINEER CF Filled Construction Management
9 ADMINITIVE ASSISTANT CF* Filled Office Administration
10 CLERK OF THE WORKS CF* Plan 2Q09 Files/Logs/Record Keeping
11 CIVIL/ARCH. INSPECTOR CF Filled Field Inspection
12 MECHANICAL INSPECTOR CF* Plan 1Q09 Field Inspection
13 ELECTRICAL INSPECTOR CF Filled Field Inspection
14 SAFETY ENGINEER (1.5 FTE) ESH Filled Project Safety
15 PROCUREMENT (3 FTE) PS Filled Contracting
16 PE Engineers/Trades (1.5 FTE) PE Filled Utility/Fire Protection Support
17 ARCH./ENGINEERS (3.5 FTE) HDR Filled Design
Total of 22.5 FTE CF-Conventional Facilities/PS-Project Support/PE-Plant Engineering
* Either BNL hire or augmented staff
14 BROOKHAVEN SCIENCE ASSOCIATES
Construction Management Organization
15 BROOKHAVEN SCIENCE ASSOCIATES
Establish LT Field Office
• Field Staff of Approximately 10• Trailer Purchased – Delivery March 23• FFE Ordered• Utilities – Power and Communications Available• Services Required – Sanitary, Cleaning, Trash• Signage Plan Complete – Ordered Shortly• Occupy April 6
16 BROOKHAVEN SCIENCE ASSOCIATES
LT Field Office Site Plan
17 BROOKHAVEN SCIENCE ASSOCIATES
LT Field Office Layout
18 BROOKHAVEN SCIENCE ASSOCIATES
LT Field Office Furniture
19 BROOKHAVEN SCIENCE ASSOCIATES
External CM Construction Services
• Liro/Gilbane Provided Design Phase CM Services• Estimating• Value Engineering• Scheduling • Market Analysis
• Liro/Gilbane Hired for Construction Phase Services• Construction Delivery Changed – CM Limited Role• Monthly Construction Management Assessment• Staff Augmentation (As Required)
20 BROOKHAVEN SCIENCE ASSOCIATES
External CM Construction Services
Part A: Project Management Review• CM Assessment Scope
• Kick-off Meeting To Initiate Development of Construction Management Procedural Review (CMPR)
• Evaluation of CF Procedures• Evaluation of GC Schedule of Values• Assist In Development of Deliverables List• Monthly Site Visits With Conventional Facilities
Management Team (CFMT)• Attend Progress Meetings
21 BROOKHAVEN SCIENCE ASSOCIATES
External CM Construction Services
Part A: Project Management Review - Continued• Produce Construction Management Procedural Review
(CMPR) - A Monthly Report Outlining:– Administration (Staffing, Document Control, etc.)– Engineering (Submittals, RFIs) – Quality (Testing and Inspection)– Change Management Process (Review, Approve & Document)– Closeout (Warranties, As Built drawings, O&M Manuals, etc.)
• Evaluate and Provide Recommendations Regarding Management of Construction
22 BROOKHAVEN SCIENCE ASSOCIATES
External CM Construction Services
Part B: Staff Augmentation
• Anticipated Staff Augmentation Positions • Clerk of the Works (Office Engineer from CM)• Civil/Arch/Mech/Elect Inspectors (from CM)• Structural Engineer (from CM)
• Administrative Assistant (from BNL)
23 BROOKHAVEN SCIENCE ASSOCIATES
Construction Readiness
• BNL Warehouse Relocation- Complete• Site Prep - Civil - Complete• Site Prep - Electrical - Complete• Site Logistics - Complete• Site Access Planning - Complete• Visitor Badging/Training Facility Upgrade – Summer
09
24 BROOKHAVEN SCIENCE ASSOCIATES
Torcon Site Logistics Plan
25 BROOKHAVEN SCIENCE ASSOCIATES
CFAC Topics for Discussion
• Successful Ring Building Construction Start• How can we ensure a safe and smooth start for Torcon
– Establish Communication Channels– Collaborative Approach to Site Logistics Planning– Timely Response to RFIs & Submittals– Streamline Site Access for Contractors/Vendors– Streamline Equipment Inspection Process
26 BROOKHAVEN SCIENCE ASSOCIATES
CFAC Topics for Discussion
• Potential Acceleration of Ring Building Schedule
• Confirm Feasibility by Torcon • Confirm Funding Availability• Benefit from Current Market Conditions
27 BROOKHAVEN SCIENCE ASSOCIATES
CFAC Topics for Discussion
• Coordination w/ the Accelerated LOB Schedule
• Ensure LOB Design Meets Schedule• Prepare Revised Construction Program to Accommodate
LOB Design• Consider Contracting Options to Minimize Impacts
28 BROOKHAVEN SCIENCE ASSOCIATES
Path Forward
• Hire Mechanical Inspector – Complete Training• Implement ‘Best in Class’ Project Safety Program• Work with Torcon to Facilitate Mobilization• Work with Torcon to Implement Project Procedures• Establish effective communication, planning and execution• Interface CM Software Programs
• NSLS-II Contract Manager• Torcon Prolog
• Continuous improvement of CF Procedures Manual