Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION...

35
Dr. ALAATTIN KANOĞLU I.T.Ü. FACULTY OF ARCH. I.T.U. FACULTY OF ARCHITECTURE CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, Methods and Techniques in Planning and Programming of Construction Projects by Dr. Alaattin Kanoğlu (Assoc.Prof., I.T.U.) SPRING 2001-02

Transcript of Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION...

Page 1: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

I.T.U.FACULTY OF ARCHITECTURE

CONSTRUCTION MANAGEMENT & ECONOMICS

Basic Steps, Rules, Methods and Techniques inPlanning and Programming of Construction Projects

by

Dr. Alaattin Kanoğlu(Assoc.Prof., I.T.U.)

SPRING 2001-02

Page 2: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

2Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

• The meaning and importance of project planning andprogramming function in construction management

• Decision levels in project planning and programming • Project Planning and Programming Process in Operational

Level• The Techniques being used for Project Planning and

Programming– Barcharts

– Line of balance diagrams

– Network Diagrams

CONTENT

Page 3: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

3Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

Definition of Project Planning and Project Definition of Project Planning and Project Programming ConceptsProgramming Concepts

• Project Planning; means breaking down the project intothe activities that must be fulfilled to realize theproject; defining the type of relationships (predecessorsand successor activities) between these activities;visualizing the activities and logical relations.

• Project Programming; means calculating early and latestart-finish dates for the activities and for the project byassigning the duration of activities.

Page 4: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

4Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

Decision Levels in Project Planning and Programming

Stratejik

Taktik Düzey

Operasyonel Düzey

Düzeystrategic level

tactical level

operational level

Page 5: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

5Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

Aims of Project Planning and Programming

• to be able to foresee the problems that may occur at thebeginning or consecutive stages of project and study onprobable solutions in advance.

• to warn the management staff about the potantialproblems and related activities instead of the others.

• to provide the information related to cash flow that isvital for the finance of project.

• to provide the information related to effective use ofthe resources by minimizing the idle time of equipmentand labors.

Page 6: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

6Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

• to provide the information related to resources requiredby activities .

• to provide the information for revising the schedule byconsidering the progress, delay and revised targets; tohelp the schedule that tends to derive from target to berevised.

Aims of Project Planning and Programming

Page 7: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

7Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

Project Planning and Programming Techniques

• Bar Charts-Gantt Charts

• Line of Balance Diagrams

• Network Diagrams

• Arrow Diagrams

• Precedence Diagrams

Page 8: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

8Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

KAZITEMELTAŞIYICI S.DUVARLAR

KALORİFER

DOĞRAMAELEKTRİK

SU TESİSATİNCE YAPIBİTİRMELER

OCAK ŞUBAT MART NİSAN MAYIS HAZİR TEMM AĞUST EYLÜL

BARCHARTS

JAN FEB MAR APR MAY JUN JUL AUG SEP

ACTIVITY A

ACTIVITY B

ACTIVITY C

ACTIVITY D

ACTIVITY E

ACTIVITY F

ACTIVITY G

ACTIVITY H

ACTIVITY I

ACTIVITY J

Page 9: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

9Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

2

3

1 2 3 4 5 6 7

1

4

ekip 1

ekip 1

ekip 2

ekip 2

ekip 1

ekip 1

ekip 1

ekip 1

8 9 10 11 12 13 14 15 16 17 18 19 20

Birim

Süre

LINE OF BALANCE DIAGRAMS

unit

duration

team-2

team-1

team-2

team-1

team-1

team-1

team-1

team-1

Page 10: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

10Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

LINE OF BALANCE DIAGRAMS

2

3

1 2 3 4 5 6 7

1

4

8 9 10 11 12 13 14 15 16 17 18 19 20

Birim

Süre

Kazı TemelKaba YapıDoğramalar Elektrik T.Su Tesisatıİnce Y.Bitirme

Proje Bitiş Süresi20 Ay

duration

unit

project completion time 15months

plumbing finishings

infrastruct.

carpentryfound.excavation electrical

plaster

Page 11: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

11Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

LINE OF BALANCE DIAGRAMS

2

3

1 2 3 4 5 6 7

1

4

8 9 10 11 12 13 14 15 16 17 18 19 20

Birim

Süre

Kazı

Temel

Kaba Yapı

Doğramalar

Elektrik T.

Su Tesisatı

İnce Y.

Bitirme

Proje Bitiş Süresi

15 Ay

duration

unit

project completion time 15 months

plumbing finishingsinfrastruct.

carpentryfound.

excavation

electrical plaster

Page 12: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

12Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

PRECEDENCE DIAGRAMS

18 25KAZI YAPILMASI

100015

NOTASYON

Eylemin en erken başlama zamanıEylemin en geç başlama zamanı

Eylemin kod no.'su Eylemin süresi (gün)

C 5

Ara zaman (Lag or Lead time)

İlişki tipi

Eylemin diğereylemle mantıksalilişkisi

EXCAVATION

ANNOTATION

early start date of activitylate start date of activity

lag timelogical relationship to successor activity

activity ID duration of activity

type of relationship

Page 13: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

13Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

PRECEDENCE DIAGRAMS

TYPES OF ACTIVITY RELATIONSHIPS1. C (Conventional) Type: Finish-to-Start relationship (Lag time = 0)

0KAZI YAPILMASI

10C 0

10TEMEL KALIBI Y.15

1000 1010

KAZI YAPILM.

TEMEL KALIBI Y.

0 10 25TBAŞL. = K BAŞL.+ K SÜRE

+ ARA ZAMAN

TBAŞL. = 0+10+ 0 =10. gün

EXCAVATION 10 FOUND.FRMWK 15

FOUNDAT. FORMWORK

EXCAVATION

FSTART=ESTART + EDUR

+ LAGTIME

FSTART= 0 +10+0=10

Page 14: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

14Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

PRECEDENCE DIAGRAMS

TYPES OF ACTIVITY RELATIONSHIPS1. C (Conventional) Type: Finish-to-Start relationship (Lag time> 0)

20BETON DÖKÜL.2

C 7 29KALIBIN SÖKÜL.2

2000 2010

BETON DÖK.

20 22KBAŞ

KBAŞ

29

C77 gün

KALIBIN SÖK.

31

POURING CONC 2 RELEASING FRMW 2

POUR. CONCRTFSTART=CSTART

+ CDURATION

+ LAG TIME

FSTART= 20+2+7= 29

RELS. FRMW

Page 15: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

15Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

TYPES OF ACTIVITY RELATIONSHIPS2. S Type: Start-to-Start relationship

PRECEDENCE DIAGRAMS

30KABA İNŞAAT

15S 6 36

SIVA YAPILMASI30

3000 3010

KABA İNŞAAT

30 45S BAŞL. =

S BAŞL. =

36

SIVA YAPILMASI

66

S66 gün

BRICKWRK 15 PLASTER 30

BRICKWORK

PLASTER

PSTART=BSTART

+LAGTIME

PSTART=30+6=36

Page 16: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

16Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

PRECEDENCE DIAGRAMS

36SIVA YAPILMASI

30

F 3 54DUVAR KAĞIDI Y.

153000 3010

SIVA YAPILMASI

36DBAŞLAMA = S BAŞL.

+ ARA ZAMAN

DBAŞLAMA. = 36 + 30 + 3 - 15 DUVAR KAĞIDI

54 66 69F3

3 gün

+ SSÜRE

- D SÜRE

= 54. gün

TYPES OF ACTIVITY RELATIONSHIPS3. F Type: Finish-to-Finish relationship

PLASTER 30 WALLPAPER 15

PLASTER

WALLPAPER

WSTART=PSTART

+ PDURATION

+ LAGTIME- WDURATION

WSTART=36+30+3-15=54

Page 17: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

17Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

1

2

1 2 3 4 5 6 7

3

8 9 10 11 12

Birim

Süre

C1

TYPES OF ACTIVITY RELATIONSHIPS

Rule 1. If finish-to-start type relationship is an obligation between two activities, i.e. these two activities can not be overlapped, a Conventional (finish-to-start) type relationship must be assigned between them. The lag time is determined due to characteristics of each activities.

duration

unit

Page 18: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

18Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

TYPES OF ACTIVITY RELATIONSHIPS

Rule 2. If finish-to-start type relationship is not obligatory between two activities, i.e., they both can be overlapped, and the duration of successor activity is longer than that of predecessor activity, then start-to-start type relationship can be assigned between these two activities. Lag time is determined as the duration of realizing the production of (1,2,3...n) units of predecessor activity or determined due to the characteristics of activities.

1

2

1 2 3 4 5 6 7

3

8 9 10 11 12

Birim

Süre

Duvar Örülmesi Sıva Yapılması

6 gün

9 gün

S2

plasterbrickwork

6 days9 days

duration

unit

Page 19: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

19Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

TYPES OF ACTIVITY RELATIONSHIPS

Rule 3. If finish-to-start type relationship is not obligatory between two activities, i.e., they both can be overlapped, and the duration of predecessor activity is longer than that of successor activity, then start-to-start type relationship can be assigned between these two activities. Lag time is determined as the duration of realizing the production of (1,2,3...n) units of successor activity or determined due to the characteristics of activities.

1

2

3 4 5 6 7

3

8 9 10 11 12

Birim

Süre

Sıva Yapılması

9 gün

Duvar Kağıdı

6 gün

F2

2 13

wallpaper

plaster

duration

unit

9 days

6 days

Page 20: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

20Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

TYPES OF ACTIVITY RELATIONSHIPS

Rule 4. Finish-to-finish type relationships cause the delay of start date of next activity (see electrical appliances) that has a start-to-start type relationship with the successor. Thus, the team that fulfills the successor activity naturally will be idle for some time. The solution is balancing the speed of this activity (see wallpaper) by reducing the number of laborers in the team.

1

2

3 4 5 6 7

3

8 9 10 11 12

Birim

Süre

Sıva Yapılması Duvar Kağıdı

2 13

Anahtar Montaj

x

y

Anahtar MontajBoş

Boş

idle

idle

plaster wallpaper appliances

appliancesduration

unit

Page 21: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

21Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

PRECEDENCE DIAGRAMS

A B0 10

10 5

15C 20

35

15D

E

0+10=10 15+20=35 > 15+10=

10

100 110

120

130

140

THE ALGORITHM OF CRITICAL PATH METHOD - CPM

1. STEP: Forward pass: Calculation of Early Start Dates of activities.

Page 22: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

22Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

PRECEDENCE DIAGRAMS

C (20 gün)

D (10 gün)

15 25

E (5 gün)

35 40

THE ALGORITHM OF CRITICAL PATH METHOD - CPM1. Rule: If an activity is the successor of more than one chain of activities then, early start date of the activity equals to the duration of the longest path. That’s why the greatest value that corresponds to the total duration of the longest path prior to that activity is chosen.

Explanation: Activity C and activity D must be completed to be able to start activity E. At the end of day 25 activity D is completed but C is not. Activity E can only start at the end of day 35.

C (20 days)

D (10 days) E (5 days)

Page 23: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

23Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

PRECEDENCE DIAGRAMS

THE ALGORITHM OF CRITICAL PATH METHOD - CPM

2. STEP: Backward pass: Calculation of Late Start Dates of activities.

A B0 10

10 5

15C 20

35

15D

E

10

0 10

15

25

35

100 110

120

130

140

35-10=25

35-20=1525-5=20 > 15-5=10

10-10=0

Page 24: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

24Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

PRECEDENCE DIAGRAMS

THE ALGORITHM OF CRITICAL PATH METHOD - CPM2. Rule: The total value of the late start date of an activity and durations of chains of successor activities can not be greater than the early start date of the last activity in network. That’s why minimum value is chosen in backward-pass.

Explanation: Assume that late start date of activity B is the greater value (20). Then, the earliest date that activity E can start is 45th day and the completion time of the project is 50th day. If the minimum value (10) is chosen, then the project will finish in 40 days.

C (20 gün)

D (10 gün)

15 25

E (5 gün)

35B (5 gün)10 40DOĞRU

YANLIŞ 20 25 35 45 50

TRUE

FALSE

B (5 days)

C (20 days)

D (10 days) E (5 days)

Page 25: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

25Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

PRECEDENCE DIAGRAMS

BASIC CONCEPTS OF CRITICAL PATH METHOD - CPM

CRITICAL ACTIVITY: The activity, that cause a delay in schedule and increases the completion time of project; that has zero total float; that has an early start date which is equal to the late start date.

CRITICAL PATH: The longest path in network formed by the critical activities. The chain of activities that has zero total float. The chain that determines the completion time of project.

FLOAT: The limit of delay that is allowed for a certain activity. The maximum delay for an activity that does not affect the project completion time.

Page 26: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

26Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

C (20 gün)

D (10 gün)

15 25

E (5 gün)

35B (5 gün)10 40

20 25 35 45 50������������������������������

Bolluk10 gün

PRECEDENCE DIAGRAMS

FLOAT10 days

B (5 days)

C (20 days)

D (10 days) E (5 days)

Page 27: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

27Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

PRECEDENCE DIAGRAMS

A

B D

F

C E

S1

C1

F2

C0

C0

C0

S2

2

4

2

3

1

1

EXERCISE

Page 28: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

28Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

PRECEDENCE DIAGRAMS

A

B D

F

C E

S1

C1

F2

C0

C0

C0

S2

2

4

2

3

1

10

1 5

3 5

8

EXERCISE STEP 1: Forward Pass for Early Start Dates

Page 29: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

29Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

PRECEDENCE DIAGRAMS

A

B D

F

C E

S1

C1

F2

C0

C0

C0

S2

2

4

2

3

1

10

1 5

3 5

80

3

5

6

2

8

EXERCISE STEP 2: Backward Pass for Late Start Dates

Page 30: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

30Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

PRECEDENCE DIAGRAMS

A

B D

F

C E

S1

C1

F2

C0

C0

C0

S2

2

4

2

3

1

10

1 5

3 5

80

3

5

6

2

8

EXERCISE STEP 3: Defining the critical path and floats

Page 31: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

31Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

8 8 8

16 16 16 16

8 8 8

A Eylemi

B Eylemi

C Eylemi 8 8

Maximum Kaynak

Kapasitesi

32

24

16

08

Adam-saat (Düz işçi)10 2 3 4 5 6 7 8 Süre

0 1 2 3 4 5 6 7 8

8 8 8

16 16 16 16

88 8

A Eylemi

B Eylemi

C Eylemi 8 8

10 2 3 4 5 6 7 8������

Maximum Kaynak

Kapasitesi

32

24

16

08

Adam-saat (Düz işçi)

0 1 2 3 4 5 6 7 8

������

RESOURCE LEVELING

Page 32: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

32Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Süre

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Süre

Kaynak Kullanım Profili

Kaynak KullanımProfili

Yığışımsız (Non-cumulative)

Yığışımlı (Cumulative)

Adam-saat

Adam-saat

S Eğrisi

08

16

243240

48

Düz işçi

100

200

300400500

600

Düz işçi

RESOURCE LEVELING

Resource requirement graph (cumulative)

Laborer mhr

Laborer mhr

S curveResource requirement profile (non-cumulative)

duration

duration

Page 33: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

33Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

COST PLANNING

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Süre

Gerçekleşen Üretimin Parasal KarşılığıYığışımsız (Non-cumulative)

Maliyet

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Süre

A EylemiB EylemiC EylemiD EylemiE EylemiF Eylemi

Çubuk Diyagram

Earned Value Histogram (non-cumulative)

Barchart

Cost

Duration

Duration

ACTIVITIES

Page 34: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

34Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Süre

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Süre

Gerçekleşen Üretimin Parasal Karşılığı

Gerçekleşen Üretimin Parasal Karşılığı

Yığışımsız (Non-cumulative)

Yığışımlı (Cumulative)

Maliyet

Maliyet

S Eğrisi

10

20

30

4050

60

100

200

300

400500

600

COST PLANNING

Earned Value Histogram (cumulative)

Earned Value Histogram (non-cumulative)Cost

Duration

Duration

Cost

S curve

Page 35: Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION MANAGEMENT & ECONOMICS Basic Steps, Rules, ... NOTASYON Eylemin en erken başlama

35Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.

11 12 13 14 15 16 17 18 19 20 22 23 24 25 26 27 28 29 30 Süre

100

200

300400500

600

Toplam Maliyet

Dolaysız Maliyetler

Dolaylı Maliyetler

Minimum MaliyetliProje Süresi

Maliyet

NormalProje Süresi

MinimumProje Süresi

COST-TIME TRADEOFF

indirect costs

direct costs

total costcost

duration

normal timeoptimum timecrash time