Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION...
Transcript of Construction Management and Economicskanoglu/crs-cme-ss-cm4-pppin... · 2001-09-29 · CONSTRUCTION...
Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
I.T.U.FACULTY OF ARCHITECTURE
CONSTRUCTION MANAGEMENT & ECONOMICS
Basic Steps, Rules, Methods and Techniques inPlanning and Programming of Construction Projects
by
Dr. Alaattin Kanoğlu(Assoc.Prof., I.T.U.)
SPRING 2001-02
2Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
• The meaning and importance of project planning andprogramming function in construction management
• Decision levels in project planning and programming • Project Planning and Programming Process in Operational
Level• The Techniques being used for Project Planning and
Programming– Barcharts
– Line of balance diagrams
– Network Diagrams
CONTENT
3Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
Definition of Project Planning and Project Definition of Project Planning and Project Programming ConceptsProgramming Concepts
• Project Planning; means breaking down the project intothe activities that must be fulfilled to realize theproject; defining the type of relationships (predecessorsand successor activities) between these activities;visualizing the activities and logical relations.
• Project Programming; means calculating early and latestart-finish dates for the activities and for the project byassigning the duration of activities.
4Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
Decision Levels in Project Planning and Programming
Stratejik
Taktik Düzey
Operasyonel Düzey
Düzeystrategic level
tactical level
operational level
5Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
Aims of Project Planning and Programming
• to be able to foresee the problems that may occur at thebeginning or consecutive stages of project and study onprobable solutions in advance.
• to warn the management staff about the potantialproblems and related activities instead of the others.
• to provide the information related to cash flow that isvital for the finance of project.
• to provide the information related to effective use ofthe resources by minimizing the idle time of equipmentand labors.
6Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
• to provide the information related to resources requiredby activities .
• to provide the information for revising the schedule byconsidering the progress, delay and revised targets; tohelp the schedule that tends to derive from target to berevised.
Aims of Project Planning and Programming
7Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
Project Planning and Programming Techniques
• Bar Charts-Gantt Charts
• Line of Balance Diagrams
• Network Diagrams
• Arrow Diagrams
• Precedence Diagrams
8Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
KAZITEMELTAŞIYICI S.DUVARLAR
KALORİFER
DOĞRAMAELEKTRİK
SU TESİSATİNCE YAPIBİTİRMELER
OCAK ŞUBAT MART NİSAN MAYIS HAZİR TEMM AĞUST EYLÜL
BARCHARTS
JAN FEB MAR APR MAY JUN JUL AUG SEP
ACTIVITY A
ACTIVITY B
ACTIVITY C
ACTIVITY D
ACTIVITY E
ACTIVITY F
ACTIVITY G
ACTIVITY H
ACTIVITY I
ACTIVITY J
9Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
2
3
1 2 3 4 5 6 7
1
4
ekip 1
ekip 1
ekip 2
ekip 2
ekip 1
ekip 1
ekip 1
ekip 1
8 9 10 11 12 13 14 15 16 17 18 19 20
Birim
Süre
LINE OF BALANCE DIAGRAMS
unit
duration
team-2
team-1
team-2
team-1
team-1
team-1
team-1
team-1
10Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
LINE OF BALANCE DIAGRAMS
2
3
1 2 3 4 5 6 7
1
4
8 9 10 11 12 13 14 15 16 17 18 19 20
Birim
Süre
Kazı TemelKaba YapıDoğramalar Elektrik T.Su Tesisatıİnce Y.Bitirme
Proje Bitiş Süresi20 Ay
duration
unit
project completion time 15months
plumbing finishings
infrastruct.
carpentryfound.excavation electrical
plaster
11Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
LINE OF BALANCE DIAGRAMS
2
3
1 2 3 4 5 6 7
1
4
8 9 10 11 12 13 14 15 16 17 18 19 20
Birim
Süre
Kazı
Temel
Kaba Yapı
Doğramalar
Elektrik T.
Su Tesisatı
İnce Y.
Bitirme
Proje Bitiş Süresi
15 Ay
duration
unit
project completion time 15 months
plumbing finishingsinfrastruct.
carpentryfound.
excavation
electrical plaster
12Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
PRECEDENCE DIAGRAMS
18 25KAZI YAPILMASI
100015
NOTASYON
Eylemin en erken başlama zamanıEylemin en geç başlama zamanı
Eylemin kod no.'su Eylemin süresi (gün)
C 5
Ara zaman (Lag or Lead time)
İlişki tipi
Eylemin diğereylemle mantıksalilişkisi
EXCAVATION
ANNOTATION
early start date of activitylate start date of activity
lag timelogical relationship to successor activity
activity ID duration of activity
type of relationship
13Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
PRECEDENCE DIAGRAMS
TYPES OF ACTIVITY RELATIONSHIPS1. C (Conventional) Type: Finish-to-Start relationship (Lag time = 0)
0KAZI YAPILMASI
10C 0
10TEMEL KALIBI Y.15
1000 1010
KAZI YAPILM.
TEMEL KALIBI Y.
0 10 25TBAŞL. = K BAŞL.+ K SÜRE
+ ARA ZAMAN
TBAŞL. = 0+10+ 0 =10. gün
EXCAVATION 10 FOUND.FRMWK 15
FOUNDAT. FORMWORK
EXCAVATION
FSTART=ESTART + EDUR
+ LAGTIME
FSTART= 0 +10+0=10
14Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
PRECEDENCE DIAGRAMS
TYPES OF ACTIVITY RELATIONSHIPS1. C (Conventional) Type: Finish-to-Start relationship (Lag time> 0)
20BETON DÖKÜL.2
C 7 29KALIBIN SÖKÜL.2
2000 2010
BETON DÖK.
20 22KBAŞ
KBAŞ
29
C77 gün
KALIBIN SÖK.
31
POURING CONC 2 RELEASING FRMW 2
POUR. CONCRTFSTART=CSTART
+ CDURATION
+ LAG TIME
FSTART= 20+2+7= 29
RELS. FRMW
15Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
TYPES OF ACTIVITY RELATIONSHIPS2. S Type: Start-to-Start relationship
PRECEDENCE DIAGRAMS
30KABA İNŞAAT
15S 6 36
SIVA YAPILMASI30
3000 3010
KABA İNŞAAT
30 45S BAŞL. =
S BAŞL. =
36
SIVA YAPILMASI
66
S66 gün
BRICKWRK 15 PLASTER 30
BRICKWORK
PLASTER
PSTART=BSTART
+LAGTIME
PSTART=30+6=36
16Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
PRECEDENCE DIAGRAMS
36SIVA YAPILMASI
30
F 3 54DUVAR KAĞIDI Y.
153000 3010
SIVA YAPILMASI
36DBAŞLAMA = S BAŞL.
+ ARA ZAMAN
DBAŞLAMA. = 36 + 30 + 3 - 15 DUVAR KAĞIDI
54 66 69F3
3 gün
+ SSÜRE
- D SÜRE
= 54. gün
TYPES OF ACTIVITY RELATIONSHIPS3. F Type: Finish-to-Finish relationship
PLASTER 30 WALLPAPER 15
PLASTER
WALLPAPER
WSTART=PSTART
+ PDURATION
+ LAGTIME- WDURATION
WSTART=36+30+3-15=54
17Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
1
2
1 2 3 4 5 6 7
3
8 9 10 11 12
Birim
Süre
C1
TYPES OF ACTIVITY RELATIONSHIPS
Rule 1. If finish-to-start type relationship is an obligation between two activities, i.e. these two activities can not be overlapped, a Conventional (finish-to-start) type relationship must be assigned between them. The lag time is determined due to characteristics of each activities.
duration
unit
18Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
TYPES OF ACTIVITY RELATIONSHIPS
Rule 2. If finish-to-start type relationship is not obligatory between two activities, i.e., they both can be overlapped, and the duration of successor activity is longer than that of predecessor activity, then start-to-start type relationship can be assigned between these two activities. Lag time is determined as the duration of realizing the production of (1,2,3...n) units of predecessor activity or determined due to the characteristics of activities.
1
2
1 2 3 4 5 6 7
3
8 9 10 11 12
Birim
Süre
Duvar Örülmesi Sıva Yapılması
6 gün
9 gün
S2
plasterbrickwork
6 days9 days
duration
unit
19Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
TYPES OF ACTIVITY RELATIONSHIPS
Rule 3. If finish-to-start type relationship is not obligatory between two activities, i.e., they both can be overlapped, and the duration of predecessor activity is longer than that of successor activity, then start-to-start type relationship can be assigned between these two activities. Lag time is determined as the duration of realizing the production of (1,2,3...n) units of successor activity or determined due to the characteristics of activities.
1
2
3 4 5 6 7
3
8 9 10 11 12
Birim
Süre
Sıva Yapılması
9 gün
Duvar Kağıdı
6 gün
F2
2 13
wallpaper
plaster
duration
unit
9 days
6 days
20Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
TYPES OF ACTIVITY RELATIONSHIPS
Rule 4. Finish-to-finish type relationships cause the delay of start date of next activity (see electrical appliances) that has a start-to-start type relationship with the successor. Thus, the team that fulfills the successor activity naturally will be idle for some time. The solution is balancing the speed of this activity (see wallpaper) by reducing the number of laborers in the team.
1
2
3 4 5 6 7
3
8 9 10 11 12
Birim
Süre
Sıva Yapılması Duvar Kağıdı
2 13
Anahtar Montaj
x
y
Anahtar MontajBoş
Boş
idle
idle
plaster wallpaper appliances
appliancesduration
unit
21Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
PRECEDENCE DIAGRAMS
A B0 10
10 5
15C 20
35
15D
E
0+10=10 15+20=35 > 15+10=
10
100 110
120
130
140
THE ALGORITHM OF CRITICAL PATH METHOD - CPM
1. STEP: Forward pass: Calculation of Early Start Dates of activities.
22Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
PRECEDENCE DIAGRAMS
C (20 gün)
D (10 gün)
15 25
E (5 gün)
35 40
THE ALGORITHM OF CRITICAL PATH METHOD - CPM1. Rule: If an activity is the successor of more than one chain of activities then, early start date of the activity equals to the duration of the longest path. That’s why the greatest value that corresponds to the total duration of the longest path prior to that activity is chosen.
Explanation: Activity C and activity D must be completed to be able to start activity E. At the end of day 25 activity D is completed but C is not. Activity E can only start at the end of day 35.
C (20 days)
D (10 days) E (5 days)
23Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
PRECEDENCE DIAGRAMS
THE ALGORITHM OF CRITICAL PATH METHOD - CPM
2. STEP: Backward pass: Calculation of Late Start Dates of activities.
A B0 10
10 5
15C 20
35
15D
E
10
0 10
15
25
35
100 110
120
130
140
35-10=25
35-20=1525-5=20 > 15-5=10
10-10=0
24Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
PRECEDENCE DIAGRAMS
THE ALGORITHM OF CRITICAL PATH METHOD - CPM2. Rule: The total value of the late start date of an activity and durations of chains of successor activities can not be greater than the early start date of the last activity in network. That’s why minimum value is chosen in backward-pass.
Explanation: Assume that late start date of activity B is the greater value (20). Then, the earliest date that activity E can start is 45th day and the completion time of the project is 50th day. If the minimum value (10) is chosen, then the project will finish in 40 days.
C (20 gün)
D (10 gün)
15 25
E (5 gün)
35B (5 gün)10 40DOĞRU
YANLIŞ 20 25 35 45 50
TRUE
FALSE
B (5 days)
C (20 days)
D (10 days) E (5 days)
25Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
PRECEDENCE DIAGRAMS
BASIC CONCEPTS OF CRITICAL PATH METHOD - CPM
CRITICAL ACTIVITY: The activity, that cause a delay in schedule and increases the completion time of project; that has zero total float; that has an early start date which is equal to the late start date.
CRITICAL PATH: The longest path in network formed by the critical activities. The chain of activities that has zero total float. The chain that determines the completion time of project.
FLOAT: The limit of delay that is allowed for a certain activity. The maximum delay for an activity that does not affect the project completion time.
26Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
C (20 gün)
D (10 gün)
15 25
E (5 gün)
35B (5 gün)10 40
20 25 35 45 50������������������������������
Bolluk10 gün
PRECEDENCE DIAGRAMS
FLOAT10 days
B (5 days)
C (20 days)
D (10 days) E (5 days)
27Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
PRECEDENCE DIAGRAMS
A
B D
F
C E
S1
C1
F2
C0
C0
C0
S2
2
4
2
3
1
1
EXERCISE
28Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
PRECEDENCE DIAGRAMS
A
B D
F
C E
S1
C1
F2
C0
C0
C0
S2
2
4
2
3
1
10
1 5
3 5
8
EXERCISE STEP 1: Forward Pass for Early Start Dates
29Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
PRECEDENCE DIAGRAMS
A
B D
F
C E
S1
C1
F2
C0
C0
C0
S2
2
4
2
3
1
10
1 5
3 5
80
3
5
6
2
8
EXERCISE STEP 2: Backward Pass for Late Start Dates
30Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
PRECEDENCE DIAGRAMS
A
B D
F
C E
S1
C1
F2
C0
C0
C0
S2
2
4
2
3
1
10
1 5
3 5
80
3
5
6
2
8
EXERCISE STEP 3: Defining the critical path and floats
31Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
8 8 8
16 16 16 16
8 8 8
A Eylemi
B Eylemi
C Eylemi 8 8
Maximum Kaynak
Kapasitesi
32
24
16
08
Adam-saat (Düz işçi)10 2 3 4 5 6 7 8 Süre
0 1 2 3 4 5 6 7 8
8 8 8
16 16 16 16
88 8
A Eylemi
B Eylemi
C Eylemi 8 8
10 2 3 4 5 6 7 8������
Maximum Kaynak
Kapasitesi
32
24
16
08
Adam-saat (Düz işçi)
0 1 2 3 4 5 6 7 8
������
RESOURCE LEVELING
32Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Süre
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Süre
Kaynak Kullanım Profili
Kaynak KullanımProfili
Yığışımsız (Non-cumulative)
Yığışımlı (Cumulative)
Adam-saat
Adam-saat
S Eğrisi
08
16
243240
48
Düz işçi
100
200
300400500
600
Düz işçi
RESOURCE LEVELING
Resource requirement graph (cumulative)
Laborer mhr
Laborer mhr
S curveResource requirement profile (non-cumulative)
duration
duration
33Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
COST PLANNING
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Süre
Gerçekleşen Üretimin Parasal KarşılığıYığışımsız (Non-cumulative)
Maliyet
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Süre
A EylemiB EylemiC EylemiD EylemiE EylemiF Eylemi
Çubuk Diyagram
Earned Value Histogram (non-cumulative)
Barchart
Cost
Duration
Duration
ACTIVITIES
34Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Süre
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Süre
Gerçekleşen Üretimin Parasal Karşılığı
Gerçekleşen Üretimin Parasal Karşılığı
Yığışımsız (Non-cumulative)
Yığışımlı (Cumulative)
Maliyet
Maliyet
S Eğrisi
10
20
30
4050
60
100
200
300
400500
600
COST PLANNING
Earned Value Histogram (cumulative)
Earned Value Histogram (non-cumulative)Cost
Duration
Duration
Cost
S curve
35Dr. ALAATTIN KANOĞLUI.T.Ü. FACULTY OF ARCH.
11 12 13 14 15 16 17 18 19 20 22 23 24 25 26 27 28 29 30 Süre
100
200
300400500
600
Toplam Maliyet
Dolaysız Maliyetler
Dolaylı Maliyetler
Minimum MaliyetliProje Süresi
Maliyet
NormalProje Süresi
MinimumProje Süresi
COST-TIME TRADEOFF
indirect costs
direct costs
total costcost
duration
normal timeoptimum timecrash time