13th October 2011
AGENDACollege of Fine Arts RedevelopmentConstruction Liaison Committee – Meeting No 22
Time: 6 - 7 pmDate: Thursday 13th October 2011Location: Level 1, F105
Items Speaker1. Welcome CLC Chairperson
2. Procedural matters CLC Chairperson
3. Apologies Adrian Boss
CLC Chairperson
4. Minutes from previous meeting CLC Chairperson
5. Actions from previous meetingSite lines to southern facade of Building F from Albion Avenue
CLC Chairperson
6. Project Status Update Hindmarsh
7. Future Exceptions Hindmarsh
8. Specialist Report Update
Nil to report
Hindmarsh
9. Current Complaints Register Hindmarsh
10. COFA Issues COFA
11. Any other business CLC Chairperson
12. Next meetingThursday 10th November 2011, Level 1, F105
Note
Site Preparation and External Works• Site Fences and Hoardings. (Continuous minor relocations will be required for the
entire project duration).• Sewer Diversions inside the site boundary.• Site Survey Work to boundaries and within the site (ongoing).
Building D• Piling Works (ongoing).• Bulk Excavation Works.• Remediation Works (ongoing).
Building F• Preparation Works for Structural Works to levels 3 and 4.• Temporary waterproofing to existing Level 3 Slab.
Construction Works undertakenSeptember 2011
Scheduled Construction Works1st October 2011 to 31st December 2011
External• B-Class hoardings to Greens Road and Napier Street return.• Sewer Diversion and Relocation Works to Albion Avenue and Napier Street.
Building D• Complete Shoring and Underpinning Works.• Complete Service Diversions required for Building D Works.• Bulk Excavation Works, including Remediation Works.• Commence concrete Sub and Superstructures.
Building F• Demolition Works.• Commence Lift Shaft Works.• Complete Level 4 and Roof Structures.• In-ground Services.• Detailed Excavation and Foundation Work.• Structural Works Northern Basement (Galleries and Café)
Selwyn Street
• Emergency and Service Vehicles
Expected “Exceptions”September 2011
Albion Avenue
• Sydney Water sewer diversion works.
(refer attached “Sewer Works” Plan)
Napier Street
• Sydney Water sewer diversion works.
(refer attached “Sewer Works” Plan)
Current Complaints Register
Complaints RegisterProject: COFA Campus Redevelopment
No: Date Complaint Description Complaint Summary ActionBy
Response Summary Status Refer toCOFA
30 9-May-11 Unauthorised loading oftruck
4:36pm, 10/5/2011 correspondence toCoFA website
ShaneEdwards
SE investigated and can confirm the followingprocedure has been implemented where by theperimeter blue wrought iron gates will now beclosed 95% of the time. One gate will be left openfor student and pedestrian traffic.
Closed.
Block F – Albion AvenueVisual Privacy Study