Pre-Construction Kickoff Meeting
August 6, 2015
![Page 2: Construction Kickoff Community Meeting Presentation August 6, 2015](https://reader034.fdocuments.net/reader034/viewer/2022042906/589b00d31a28abb85d8b494d/html5/thumbnails/2.jpg)
2
• Richard DeCarlo – Executive VP and Chief of Hospital Operations, UCSF Benioff Children’s Hospital Oakland
• Doug Nelson – Executive Director of Development & Construction, UCSF Benioff Children’s Hospital Oakland
• Tony Solano – Senior Project Manager, JLL
• Ed Walsh – Project Executive, Turner Construction Company
Welcome
![Page 3: Construction Kickoff Community Meeting Presentation August 6, 2015](https://reader034.fdocuments.net/reader034/viewer/2022042906/589b00d31a28abb85d8b494d/html5/thumbnails/3.jpg)
Oakland Children’s Hospital
■ Construction Management Plan■Project Communication■Site Logistics■Construction Activities – First 5 months■Construction Parking
■ Local Business Outreach
Agenda
![Page 4: Construction Kickoff Community Meeting Presentation August 6, 2015](https://reader034.fdocuments.net/reader034/viewer/2022042906/589b00d31a28abb85d8b494d/html5/thumbnails/4.jpg)
• Project Communication– Darrel Graef (Turner Supt) 510-764-3059– Project Signage (now posted on site)– Flyers and Project Website
• notifications of change to site conditions as it pertains to the neighborhood
• http://chonext100.org• Concerns/Issue Reporting
– Contact information are posted on Site Signage and Project Website
Construction Management Plan
![Page 5: Construction Kickoff Community Meeting Presentation August 6, 2015](https://reader034.fdocuments.net/reader034/viewer/2022042906/589b00d31a28abb85d8b494d/html5/thumbnails/5.jpg)
• Site Logistics– Hours of Operation per Conditions of Approval:
• M-F 7 AM to 7 PM• Saturdays as specifically approved by the Building Services
Division– Site Staging
• Confined to fenced construction area– Truck Route as approved by the City of Oakland
• Restricted to MLK, 52nd Street, 55th Street and Telegraph– Traffic Control plan as approved by the City of Oakland
Construction Management Plan
![Page 6: Construction Kickoff Community Meeting Presentation August 6, 2015](https://reader034.fdocuments.net/reader034/viewer/2022042906/589b00d31a28abb85d8b494d/html5/thumbnails/6.jpg)
53RD STREET
![Page 7: Construction Kickoff Community Meeting Presentation August 6, 2015](https://reader034.fdocuments.net/reader034/viewer/2022042906/589b00d31a28abb85d8b494d/html5/thumbnails/7.jpg)
![Page 8: Construction Kickoff Community Meeting Presentation August 6, 2015](https://reader034.fdocuments.net/reader034/viewer/2022042906/589b00d31a28abb85d8b494d/html5/thumbnails/8.jpg)
Truck Route
![Page 9: Construction Kickoff Community Meeting Presentation August 6, 2015](https://reader034.fdocuments.net/reader034/viewer/2022042906/589b00d31a28abb85d8b494d/html5/thumbnails/9.jpg)
Oakland Children’s HospitalConstruction Sequencing
Phase 1: Make Ready | Duration: 5 Months | Average Trade Count: 25
Bus Stop to be Relocated
![Page 10: Construction Kickoff Community Meeting Presentation August 6, 2015](https://reader034.fdocuments.net/reader034/viewer/2022042906/589b00d31a28abb85d8b494d/html5/thumbnails/10.jpg)
Oakland Children’s HospitalConstruction Sequencing
Phase 1 Make Ready
Construction Status• Parking Structure Renovation /
New Entrance Construction• Service Yard Construction• MLK Offsite Work• Demo / Relocation of MLK
Building after 90-day Advertisement
Logistics ItemsA. Potential Temporary Bus Stop
LocationB. Temporary FenceC. Temporary Vehicular Access
C
B
MLK JR Way(Sidewalk Closed)
A
![Page 11: Construction Kickoff Community Meeting Presentation August 6, 2015](https://reader034.fdocuments.net/reader034/viewer/2022042906/589b00d31a28abb85d8b494d/html5/thumbnails/11.jpg)
• Construction Parking– NO Parking in the residential neighborhood
• Subcontracts to include compliance with neighborhood and site parking restrictions
• Turner Superintendent to verify and track daily with trade foremen transportation/parking arrangements by their workers
• Violators will be immediately notified and given a warning. Next violation – will be removed from project
• Enforcement of CHO’s Residential Parking Permit program per the Traffic Demand Management Plan
Construction Management Plan
![Page 12: Construction Kickoff Community Meeting Presentation August 6, 2015](https://reader034.fdocuments.net/reader034/viewer/2022042906/589b00d31a28abb85d8b494d/html5/thumbnails/12.jpg)
• Parking Mitigations– Public Transit– Hospital Shuttle to and
from BART Station– CHO American Lot
• 20 spaces– Caltrans Lots
• 34 spaces
Construction Management Plan
Assumptions:Trades using Bart/Public Transit – 10 to 15%Trades carpooling – 40 to 50%Established Parking – 50 to 55 spaces
![Page 13: Construction Kickoff Community Meeting Presentation August 6, 2015](https://reader034.fdocuments.net/reader034/viewer/2022042906/589b00d31a28abb85d8b494d/html5/thumbnails/13.jpg)
Construction Management Plan
American Lot
Caltrans Lot
Caltrans Lot
Jobsite
![Page 14: Construction Kickoff Community Meeting Presentation August 6, 2015](https://reader034.fdocuments.net/reader034/viewer/2022042906/589b00d31a28abb85d8b494d/html5/thumbnails/14.jpg)
14Proposed RPP Boundary
RPP Boundary Map
![Page 15: Construction Kickoff Community Meeting Presentation August 6, 2015](https://reader034.fdocuments.net/reader034/viewer/2022042906/589b00d31a28abb85d8b494d/html5/thumbnails/15.jpg)
• Air Pollution/Noise Mitigation– Turner subcontracts include compliance with the
requirements of the Standard Conditions of Approval and Authorities Having Jurisdiction (AHJ)
– Regular discussion/reminder during Turner’s safety orientation and weekly subcontractor meetings
– Monitoring by an independent consultant
Construction Management Plan
![Page 16: Construction Kickoff Community Meeting Presentation August 6, 2015](https://reader034.fdocuments.net/reader034/viewer/2022042906/589b00d31a28abb85d8b494d/html5/thumbnails/16.jpg)
• Defined as businesses located within the East Bay Green Corridor:– Alameda– Albany– Berkeley– El Cerrito– Emeryville– Hayward– Oakland– Richmond– San Leandro
Project’s Local Business Participation
• Goal = 35%
• Current Projection= 45%
![Page 17: Construction Kickoff Community Meeting Presentation August 6, 2015](https://reader034.fdocuments.net/reader034/viewer/2022042906/589b00d31a28abb85d8b494d/html5/thumbnails/17.jpg)
Questions/Discussion?