Construction Dewatering Rain for Rent 2018 Presented By: Justin Wolfe, P.E.

Transcript of Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control...

Page 1: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Click to edit master subtitle style

Construction

Dewatering

Rain for Rent

2018

Presented By:

Justin Wolfe, P.E.

Page 2: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Agenda

• Introduction

• Overview of Dewatering

• Gathering Key Information

• Dewatering Methods and Design Process

• Case Studies

• Questions

Page 3: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Dewatering

There are two main groups of groundwater control techniques:

• Methods that use low permeability cut-off walls and other barriers to exclude water from the excavation

• Methods that control groundwater by pumping from sumps or wells (known as construction dewatering)

Page 4: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Information required

• Potential sources of recharge

• i.e. rivers, creeks, canals, lakes, etc.

• Potential geotechnical impacts

• Soil settlement in the immediate vicinity of

nearby structure

• Groundwater contamination (nearby

landfill)

Page 5: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Information required

• Site elevation and size

• Excavation Depth

• Desired Dry-Depth (typically 2-3 feet below

the excavation)

• Soil description

• Groundwater elevation

• Time allotment for pre-drainage

• Typically dewatering systems require a

minimum 1 to 3 weeks before substantial

draw-down is achieved

Page 6: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Information required

• Boring Logs

• Geotechnical Report

• Soils Report

• Water quality/testing results for discharge

permit.

Page 7: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Dewatering – Wellpoint & Deep Well

Page 8: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Treatment

Page 9: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Treatment

Page 10: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Wellpoints

• Soil Types: Fine to coarse

• Effective for stratified soils

• Hydrology: High and low

conductivity | adjacent and remote

recharge

• Header Pipe: 6 inches or larger

• Approximately 60 to 80 points per

pump

• Header pipeline should not

exceed 500 to 700 feet in length

Page 11: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Wellpoints

• Excavation Depths: < 20 feet @ sea-level

• Typical Spacing: 6 to 12 feet

• Flow per point: <0.1 to 20 gpm

• System flow rate: low to a few thousand gpm

• At times well-point must be sand packed

Page 12: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Wellpoint Installation and Operation

• Requires excavator, jetting pump, and PVC wellpoint

• May require backhoe

• Drilling may be required in dense soils

• Individual wellpoints need to be carefully adjusted

(“trimming” or “fine-tuning”)

Page 13: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Jetting

Page 14: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Jetting

Page 15: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Jetting Video

Page 16: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Wellpoint design

Page 17: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Wellpoint design

Page 18: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Wellpoint

Page 19: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Wellpoint

Page 20: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Deep Well Dewatering

• Soil Types: performs best in clean sands and

gravel | typically poor in fine and clayey soils

• Can be effective in stratified soils

• Best when recharge is remote

• Individual deep wells need to be carefully

adjusted (“trimming” or “fine-tuning”)

• Timetable: Slow drawdown

Page 21: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Deep Well Dewatering

• Excavation Depths: Shallow to several hundred

feet

• Typical Spacing: Approx. 50 feet

• Full Range: 30 to 200 feet

• Flow per well: <0.1 to thousands of gpm

• System flow rate: low to tens of thousands of

gpm

• Typically 8 to 12inch diameter casings

• An electric submersible pump is installed in

each well.

Page 22: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Drilling

Page 23: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Deep Well

Page 24: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Power Distribution

Generator or Power Source

Master 3 Master 2

Master 1

Control

Panels Control

Panels

Control

Panels

Page 25: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Which Method is Best for Your Site?

Fine grained (silts and clayey sands)

Stratified soils

Wellgraded sands and gravel

Impermeable soils/rock at subgrade

Close

Distant

High (i.e. clean sands/gravels)

Low (i.e. silts, clayey sands, etc.)

Confined (cramped)

Excavation depths of 17 feet or less

Excavations exceeding 17 feet

Timetable (drawdown)

Quick

Slow

Characteristics

Typical Spacing

Flow Ranges per point/pump

System Flow Rate

Poor to Fair

Good

Poor to Fair

Good

Good

Good

Wellpoints Deep Wells

Good

Good

Good

Fair to Good

PoorGood

Poor to Fair

>1 to 20 gpm

Poor

Ok

Benching / Tiered System

>1 to thousand of gpm

Wellpoints vs. Deep Wells

a few to tens of

thousands of gpm

a few to thousands of

gpm

Poor

Ok

Good

Poor

Soil Types

Recharge

Conductivity

Site

50 to 100 ft

Ok

Ok

Ok

Ok

Ok

3 to 12 ft

Good

Page 26: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Case Study 1 (Wellpoint Dewatering)

• Dewatering Perimeter: 375 feet by 200 feet

• Desired Dry-Depth: 8 feet below grade

• Groundwater Depth: 2.5 feet

• Soil Type: Sand with silt

• Drawdown Time:

• 2 to 4 weeks

• Project Length: 3 Months

Page 27: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Wellpoint Detail

Page 28: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Case Study 1

Page 29: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Case Study 1

Page 30: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Case Study 1 (Project Summary) • Pumps: two (2) primary Vacuum Pumps

• Wellpoints: 94 jetted to 18 feet below grade

• Header Pipe: 6”

• System Flow Rate: 500 – 600 gpm

• Excavation Depth: 4 feet

• Desired dry-depth of 8 feet below grade

• Max Draw Down: 10 feet below grade

Page 31: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Case Study 2 (Deepwell)

Page 32: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Detailed Layout

Page 33: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Pump Test

Page 34: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Calculations

0

10

20

30

40

50

60

70

80

1 2 3 4

Flo

w R

ate

(gp

m)

Time (week)

K = 45 gpd/ft2

0

10

20

30

40

50

60

70

80

90

1 2 3 4

Flo

w R

ate

(gp

m)

Time (week)

K =55 gpd/ft2

Page 35: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Calculations Vs. Field Data Comparison

0.0

10.0

20.0

30.0

40.0

50.0

60.0

70.0

80.0

90.0

100.0

0 5 10 15 20 25 30 35 40

Flo

w-R

ate

(G

PM

)

Pumping Time (days)

Flow Rate Vs. Time

Field Data

K = 55 gpd/ft^2

K = 45 gpd/ft^2

Page 36: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Project Summary • Pumps: Twelve (12) 1/2HP Submersible Pumps

• Deep Wells: 24 inch bore with 8 inch casing

• Depth: Approximately 45-50 feet below grade

• Header Pipe: 3”

• System Flow Rate: 85 to 45 gpm

• Excavation Depth: 20 feet +/-

• Desired dry-depth of 23 feet below grade

• Customer successfully installed foundations in the dry

Page 37: Construction Dewatering€¦ · Dewatering There are two main groups of groundwater control techniques: • Methods that use low permeability cut-off walls and other barriers to exclude

Questions