Transcript of Construction Cost$81,145,453 Notice of Completion04/01/2009 07/15/2014 FSC Meeting.
El Cerrito High SchoolNew Construction
Construction Cost $81,145,453Notice of Completion 04/01/2009
07/15/2014 FSC Meeting
El Cerrito High SchoolMulti-Use Sports Field
Construction Cost $4,324,683Notice of Completion 10/10/2012
07/15/2014 FSC Meeting
Preliminary Budget $6,000,000 Budget Increased to $11,000,000
(on 03/13/2012 per Facilities Subcommittee)
Budget – based on Bid Opening (11/05/2013) $21,000,000(per Board Approval 11/20/2013)
Bid Award $13,438,000 (Notice to Proceed 01/27/2014)
El Cerrito High SchoolStadium
07/15/2014 FSC Meeting
El Cerrito High SchoolStadiumBid Tally
07/15/2014 FSC Meeting
Classroom and Administration Building $81,145,453
Multi-Use Sports Fields $ 4,324,683
Stadium $13,438,000
Miscellaneous
◦ Temporary Campus $ 9,744,423
◦ Campus Demolition $ 1,946,013
◦ Underground Utility Package $ 2,218,345
◦ Furniture and Fixtures $ 1,904,031
◦ Technology $ 842,682
◦ Small Projects and Soft Costs $33,592,722
Projected Final Cost$149,156,352
Spent to Date
$135,424,136
El Cerrito High SchoolTotal Cost Overview
07/15/2014 FSC Meeting