  • NAVFAC HAWAII

    WORK ORDER NO. 1167518

    PROJECT

    for

    Construct Sun Control Wall At Building 67

    SHIPEA, Pearl Harbor Hawaii

    REQUEST FOR PROPOSAL APPROVED BY:

    Specification: _______________________________________________________ Cey H. Murakami, P.E. For Commander, NAVFAC: _______________________________________________ Mike J. Williams, P.E. Date: ______________________

  • Construct Sun Control Wall at Building 67 SHIPEA, Pearl Harbor, HI WO 1167518

    Table of Contents

    1. PART 1 PROPOSAL FORMS & DOCUMENTS

    By others.

    2. PART 2 GENERAL REQUIREMENTS

    Clarifications to basic contract requirements.

    3. PART 3 PROJECT PROGRAM

    Cover Page

    CHAPTER 1 PROJECT DESCRIPTION CHAPTER 2 PROJECT OBJECTIVES CHAPTER 3 SITE ANALYSIS CHAPTER 4 BUILDING REQUIREMENTS (Not used) CHAPTER 5 ROOM REQUIREMENTS (Not used) CHAPTER 6 ENGINEERING SYSTEMS REQUIREMENTS

    4. PART 4 PERFORMANCE TECHNICAL SPECIFICATIONS

    Cover Page

    A10FOUNDATIONSB10SUPERSTRUCTUREC10INTERIORCONSTRUCTIOND50ELECTRICALF20SELECTIVEBUILDINGDEMOLITIONZ10 GENERAL PERFORMANCE TECHNICAL SECIFICATION

    5. PART 5 PRESCRIPTIVE SPECIFICATIONS

    Not used.

    6. PART 6 ATTACHMENTS

    1. LOCATIONMAP2. VICINITYMAP3. Photos4. TitleSheet5. SitePlan6. SUNCONTROLWALL(Typ.)7. SUNCONTROLWALLOVEREXIST.ROLLUPDOOR8. ASBUILTDRAWINGS.9. SOILREPORT10. CATEX

  • Construct Sun Control Wall at Building 67 SHIPEA, Pearl Harbor, HI WO 1167518

    11. HAZMATTESTINGREPORT12. EXCAVATIONANDDEWATERINGINTHEPEARLHARBORNAVALCOMPLEX13. PHNSY&IMFsContractorEnvironmentalSpecificationGuildlines14. OSHEContractorBriefingSchedule15. PHNSY&IMFsSafetyandHealthWorkPracticesforContractors16. PHNSY&IMFsSecurityRequirements.

  • Construct Sun Control Wall at Building 67 WO 1167518 SHIPEA, Pearl Harbor, HI

    STANDARD TEMPLATE - PART ONE - PROPOSAL FORMS & DOCUMENTS - Page 1

    PART ONE - PROPOSAL FORMS & DOCUMENTS By others.

  • Construct Sun Control Wall at Building 67 WO 1167518 SHIPEA, Pearl Harbor, HI

    STANDARD TEMPLATE - PART TWO - GENERAL REQUIREMENTS - Page 1

    PART TWO - GENERAL REQUIREMENTS Refer to the basic contract requirements for Part 2 General Requirements. The following modifications and/or clarifications apply to this Task Order: 1. General Replace all references to the Resident Officer in Charge of Construction (ROICC) with

    Facilities Engineering and Acquisition Division (FEAD). 2. Section 01 31 19.50 20 - Level C partnering should be accomplished for this task order as described

    in Section 01 30 00.05 20 and may be accomplished as a part of the Pre-Construction Meeting to ensure that we achieve a quality project done right the first time, within budget, on schedule and without any safety mishaps.

    3. Section 01 32 17.05 20 - Network Analysis Schedules (NAS) for Design-Build: Requirements for this

    Task Order shall be as specified below.

    a. Para. 1.6.2.4 Anticipated Weather Delays: The number of anticipated non-workdays for each month due to adverse weather shall be as specified below.

    MONTHLY ANTICIPATED ADVERSE WEATHER DELAYS (Joint Base Pearl Harbor Hickam)

    JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC 3 2 2 0 0 0 0 0 0 1 2 3

    4. Section 01 33 10.0520 Design Submittal Procedures for Design-Build: Requirements for this Task Order shall be as specified below:

    a. Para 1.9.3 Sustainable Design: A minimum sustainable design goal to meet LEED certified level

    (26 points) is not applicable to this task order. Follow Para 1.9.3 to provide a design that incorporates sustainable techniques and materials.

    b. Para. 2.2.2 Required Design Submittals: Required submittals and durations for this Task Order shall be as specified below.

    i. 100% Design shall be submitted 80 day after award with 21 calendar days Government Review

    ii. Final Design - 14 calendar days Government Review

    Each submittal shall include Basis of Design, Calculations, Manufacturers Catalog Data and all review comment sheets with annotation of actions to be taken by the DB team.

    c. Para. 2.2.4 Review Copies of Design Submittal Packages: Required submittals for this Task Order shall be as specified below:

    100% Submittal:

    i. Nine (9) hard copies Half-Sized Plans / Three (3) CDs (electronic/pdf files) to the NAVFAC HAWAII Project Engineer.

    ii. Three (3) hard copies Half-Sized Plans / Three (3) CDs (electronic/pdf files) to the Facilities Engineering and Acquisition Division (FEAD).

  • Construct Sun Control Wall at Building 67 WO 1167518 SHIPEA, Pearl Harbor, HI

    STANDARD TEMPLATE - PART TWO - GENERAL REQUIREMENTS - Page 2

    Signature Submittal: Coordinate with NAVFAC HAWAII Project Engineer during this phase of submittal.

    i. One (1) hard copy / One (1) CD Half-Sized Plan / One (1) CD (pdf files) to the NAVFAC HAWAII Project Engineer.

    ii. One (1) hard copy / One (1) CD Half-Sized Plan / One (1) CD (pdf files) to the FEAD.

    Final Submittal:

    i. Nine (9) hard copies Half-Sized Plans / Three (3) CDs (electronic/pdf files) to the NAVFAC HAWAII Project Engineer.

    ii. Three (3) hard copies Half-Sized Plans / Three (3) CD (electronic/pdf files) to the FEAD.

    5. Section 01 58 00.05 20 Project Identification for Design-Build: Delete requirements for project identification.

  • Construct Sun Control Wall at Building 67 WO 1167518 SHIPEA, Pearl Harbor, HI

    PART THREE - PROJECT PROGRAM - Page 1

    PART THREE - PROJECT PROGRAM

    Project Program

    Construct Sun Control Wall At Building 67 FY13 Category Code 21349

    SHIPEA Pearl Harbor, Hawaii

    November 29, 2012

  • Construct Sun Control Wall at Building 67 WO 1167518 SHIPEA, Pearl Harbor, HI

    PART 3 - CHAPTER 1 - Page 1

    1.0 PROJECT DESCRIPTION This project is to construct interiorinfillSunControlWall(AluminumScreenLouverWall,7Total)betweensteelcolumnsbehindsouthfacingexteriorwindowsatBuilding 67. Each Sun Control wall (Aluminum Louver Screen Wall) is approximately 18 wide, 22-6 tall, and 3-6 above existing concrete floor except the Sun Control Wall located in above existing roll up door (7-6 x 9-8 WXH) will be approximately 18 wide, 15 tall. Each Sun Control Wall will be supported by free stand steel frame. Existingwindowisapproximately15'wideand24'tall. The sun control wall is employed to prevent the sunlight from entering into building. As result, heat from the sunlight will not negatively impact the precise operation and production of the Shaft Lathe.Building67,ahistoricalbuildingwithcategoryII,is a steel frame building. Electrical work includes relocating electrical items and rerouting electrical circuits as required to allow installation of new sun control wall. The project is located in Controlled Industrial Area (CIA) at Joint Base Pearl Harbor Hickam, Hawaii. --End of Section--

  • Construct Sun Control Wall at Building 67 WO 1167518 SHIPEA, Pearl Harbor, HI

    PART 3 - CHAPTER 2 - Page 1

    2.0 PROJECT OBJECTIVES 2.1 Mission Statement Pearl Harbor Naval Shipyard's primary mission is to provide regional maintenance at both the depot and intermediate levels to keep the surface ships and submarines of our nation's Navy 'Fit to Fight'. Plainly put, the Shipyard's mission is to perform any and all maintenance work other than routine repairs by sailors. Maintenance capabilities include overhauling, repairing, converting, alteration, refurbishing, defueling, refueling, and decommissioning of Navy vessels. Sun Control wall is required to mitigatesunlightpenetrationintobuilding67.

    2.2 Facility Function The existing Building 67 currently serves as Machine Shop. This project is critical to ensure the sunlight will not negatively impact the precise operation of the Shaft Lathe. 2.3 Project Specific Priorities 2.3.1 Sustainable Design

    Not Used.

    2.3.2 Storm Water Management (Low Impact Development) Not Used.

    2.3.3 Energy Conservation

    Not Used.

    2.3.4 Building Commissioning

    Not Used.

    2.3.5 Accessibility Requirements Not Used.

    2.3.6 Antiterrorism Criteria

    Not applicable. 2.4 Appropriate Design

    The contractor and its Architect/Engineer shall be responsible for understanding and conforming to all applicable design criteria associated with the facilities to be provided under this contract. In addition to the documents listed or identified elsewhere in this RFP, the following list of criteria and

  • Construct Sun Control Wall at Building 67 WO 1167518 SHIPEA, Pearl Harbor, HI

    PART 3 - CHAPTER 2 - Page 2

    documents are applicable under this contract.

    NAVFAC Design Guidance and Policy

    PACNAVFACENGCOM-74-A-E Guide, latest Ed.

    The Government is interested in a best value proposal that supports the functional needs of the user and activity. The levels of quality and durability shall be responsive to the function, mission effectiveness, and cost effectiveness of a strategically important and high use military facility expected to provide many years of services.

    2.5 Workflow Process

    2.5.1 Hours of Operation Normal operations in Building 67 area typically take places around clock, 1st shift 0630-1500, 2nd shift 1430-2300, and 3rd shift 2330-0700. Contractor is restricted to work daylight hours from 6:30 am to 3:00pm.

    2.5.2 Staffing/Occupancy

    Building 67 is occupied by 225 People.

    The number