CONPRO Final Project
-
Upload
davidson-ferreira -
Category
Documents
-
view
1.741 -
download
0
Transcript of CONPRO Final Project
MSC PROJECT MANAGEMENT PROGRAMME
MODULE 6 – CONTRACTS AND PROCUREMENT
PROJECT- CASE STUDY:
NORTH BRISTOL NHS – SOUTHMEAD INTEGRATED COMMUNITY
HOSPITAL REDEVELOPMENT PROJECT – PROCUREMENT PLAN
FINAL PROJECT
Student name: Davidson Ferreira
Student ID: 15799388
Date: 29-October-2011
Module 6: Contracts and Procurement
Individual project: Final Project Report
Case Study: Southmead Hospital Redevelopment Procurement Plan
Rev. A
University of Liverpool – Laureate Online Education 29-October-2011
Page 2 of 14
Table of Contents
1. PROJECT BACKGROUND AND OBJECTIVES ............................................................... 3
1.1. PROJECT OBJECTIVES .................................................................................... 4
2. PROCUREMENT PLAN FOR THE HOSPITAL DEVELOPMENT .................................... 5
2.1. PLAN SCHEDULE GANTT CHART ..................................................................... 5
2.2. SUPPLIER SELECTION PLAN ........................................................................... 7
2.3. CONTRACT AWARDING PLAN .......................................................................... 8
2.4. CONTRACT TYPES AND APPLICATION SPECIFICATIONS ................................ 8
3. FOUR PROCUREMENT ISSUES FACED BY PROCUREMENT MANAGERS IN NHS ... 9
3.1. POST TENDER NEGOTIATIONS ....................................................................... 9
3.2. SUSTAINABILITY AND COMMUNITY IMPACT .................................................... 9
3.3. ENVIRONMENTAL IMPACT ............................................................................... 9
3.4. USE OF INFORMATION TECHNOLOGY ............................................................. 9
4. STRATEGY TO HANDLE PROCUREMENT FOR UK HOSPITAL ................................. 10
4.1. STRATEGY FOR POST TENDER NEGOTIATIONS ........................................... 10
4.2. SUSTAINABILITY AND COMMUNITY IMPACT .................................................. 10
4.3. USE OF INFORMATION TECHNOLOGY ........................................................... 11
4.4. SUSTAINABILITY, COMMUNITY AND ENVIRONMENTAL IMPACT .................... 11
5. CONCLUSION ............................................................................................................... 12
6. REFERENCE LIST ........................................................................................................ 13
Module 6: Contracts and Procurement
Individual project: Final Project Report
Case Study: Southmead Hospital Redevelopment Procurement Plan
Rev. A
University of Liverpool – Laureate Online Education 29-October-2011
Page 3 of 14
1. PROJECT BACKGROUND AND OBJECTIVES
As part of North Bristol Trust program, the Southmead Integrated Community Hospital
redevelopment project has been approved for the construction of new facilities
capacity to support a service activity forecasted for up to 30,000 patients.
The full capacity expected is shown in the activity table below:
Table 1: New Southmead Community Hospital Activity (North Bristol NHS Trust, 2009:
4)
Activity Category Patients Per Year
Outpatients and Triage 26,242
Minor Injuries 24,000
Diagnostic Tests (Plain film and ultrasound) 33,661
Therapy Appointments 30,000
Inpatient spells to avoid admission to acute hospital 657
Inpatient spells for community rehabilitation 500
Public procurement strategies in the health sector is related to these strategic aims of
NHS procurement plans for the Southmead Hospital redevelopment project as it is
expected to take the majority of the project funding under the current approval amount.
(Munday, M. & Roberts, A. 2010: 8)
The procurement team of will recognize the value of public procurement strategies
have on developing a knowledge-based economy, promoting low-carbon strategies,
delivering social and territorial cohesion, and meeting environmental targets.
Therefore, the procurement team need to commit through national and local
procurement policies to strategies that take such objectives into account, i.e. flexibility
to accommodate limitations to local or regional contractors.(NHS EU Office, nd.: 9)
Module 6: Contracts and Procurement
Individual project: Final Project Report
Case Study: Southmead Hospital Redevelopment Procurement Plan
Rev. A
University of Liverpool – Laureate Online Education 29-October-2011
Page 4 of 14
1.1. PROJECT OBJECTIVES
The purpose of the procurement plan is to establish the North Bristol NHS trust
methodology to acquire its products and services objectives through fair and
transparent procurement practices while having a positive impact on the local
community and environment.
The main project goals are:
- Prepare a procurement plan for the hospital construction and development
- Identify four procurement issues faced by procurement managers in NHS
in UK.
- Develop a strategy to handle procurement for UK hospital, by addressing
the issues faced by NHS manager in UK.
In order to meet the activity requirements set in table 1, the project team is
tasked with design and construction management of the new community
hospital facilities as well as the refurbishment of medical service equipment.
To support the project team, a procurement plan needs to be developed to
guide the procurement professionals, bidding vendors and the technical team
to understand and successfully execute the procurement plan to procure
services and goods required to complete the project within budget, scope and
schedule.
A procurement flow path is shown below to illustrate the procurement process
and the various stakeholders’ integration on the process. The Gantt chart on
the section to follow will describe the process including the time lime factor.
Figure 1.1 Procurement process stakeholder’s interaction
Module 6: Contracts and Procurement
Individual project: Final Project Report
Case Study: Southmead Hospital Redevelopment Procurement Plan
Rev. A
University of Liverpool – Laureate Online Education 29-October-2011
Page 5 of 14
2. PROCUREMENT PLAN FOR THE HOSPITAL DEVELOPMENT
2.1. PLAN SCHEDULE GANTT CHART
The early develop of a procurement plan in from of Gantt chart will enable both
the procurement team but most important the sponsor stakeholder a relative
quick overview of main activities, their relation and the overall timeline of the
procurement process. The Gantt chart, is a live document, thus, it is expected
to change as the procurement process starts and therefore, several updates
will be done prior to completion of the project. Therefore, it is important that in
particular to large size project, a dedicated planner position is made available
to collect and publish project schedule updates on the overall project
execution, but also for the procurement activities as this will support and alert
the procurement team on any forecasted delays and their impact on the project
completion as these may enter the project critical path.
The typical procurement process will entail the following major activities:
- Selection of services to be procured: which will entail several discussions
on make-or-buy decision, customization vs. off the shelf services and
goods. (Sollish, F., Semanik, J., Morris, P.W.G. ed. & Pinto, J.K. ed. 2011: 157)
- Selection of which goods to be procured; will be a follow-up from the
technical teams, but it will take the project sponsor to approve the selection
of items (services and goods) to which will be pursue through outsourcing
and which will use the in-house resources. Vendors may be contacted
directly or available data (web, catalogs, etc.). The end result will be a list
of services and goods (special hospital equipment, systems, bulk
equipment’s and materials, etc.) pre-approved for procurement. Scope
specifications as well as preliminary data sheets for equipment are
expected by the procurement team to be developed in order to support the
next phase of the procurement plan (the development of the contracting
plan).
- Development of contracting plan: one of the most important phases, as the
team needs to consider a variety to factor, like local vs. national vs.
international supplier affecting quality, schedule and standardization of
products and services. The contracting plan shall be in accordance with
rules and regulations and most important the terms and conditions
guidelines of NHS contracting strategy.
- Preparation and issuing of Invitation To Tender (ITT) to potential suppliers:
at this stage, the procurement team will have a set of requirements (scope
specifications, windows of deliverables, supplier characteristics) so that all
pre-selected vendors will be issued with a set of relevant Invitation to
Module 6: Contracts and Procurement
Individual project: Final Project Report
Case Study: Southmead Hospital Redevelopment Procurement Plan
Rev. A
University of Liverpool – Laureate Online Education 29-October-2011
Page 6 of 14
Tender (ITT) for bidding on the service or product line the NHS believes
they can supply according to their requirements. It is also in this phase,
where a majority of clarifications is conducted and only a handful of
vendors remain interested on continuing the bidding process. The NHS
function teams, also take a chance to update the technical specifications in
order to ensure there are procuring a existing product or service.
- Preparation and issue of request for proposal on service acquisitions;
likewise for goods, not all pre-specified services SOW, can be executed as
preliminary intended, thus important to allow the vendor (service
contractors) to have an input on the outcome of the product, as this may
not only benefit to the contractors, but also the buying party as this formers
may be more up-to-date on new technologies or techniques that could
improve performance, reduce cost or simply less expensive.
- Preparation and issue of request for quotations on both services and goods
potential suppliers. This final set of activities will provide the procurement
team with the documentation and data required to complete the most
important step on the evaluation process, thus is critical that all vendors
bidding for the same service or product provide quotations that are
structured as per NHS guidelines for a fair and standardize evaluation.
- Perform bid evaluations and complete supplier selection process, is a
complex process, and in particular to public enterprise more so. Guidelines
on bidding evaluation and bidding criteria are touched on the next section
and details on similar procurement strategy plans (see Torbay NHS Care
Trust, 2010: 7-11)
- Award winning contractors with Contract Agreements for review and
acceptance, discuss non-price related final points and update contract
based on the agreed (finalized) terms and condition including deliverable(s)
date(s), quality specifications, etc. This is further discussed in following
sections.
- Contract management, involving (according to contract agreement)
contract performance review activities, reporting, audits and scope
changes within agreed terms and conditions.
- Contract closure activities, including review and acceptance of punch list
items for services and material/equipment quality certificates by respective
function/department review teams and finally make final payments and
issuance of contract completion certificate along with all closeout
documentation.
Module 6: Contracts and Procurement
Individual project: Final Project Report
Case Study: Southmead Hospital Redevelopment Procurement Plan
Rev. A
University of Liverpool – Laureate Online Education 29-October-2011
Page 7 of 14
Figure 2.1 bellow illustrates a typical procurement process plan, with a
standard cascade of activities required for an effective procurement program
for non-complex projects in a summarized form (full expanded Gantt chart is
available under appendix B of this report for further details).
Figure 2.1: Collapsed Gantt Chart: Typical Procurement process
2.2. SUPPLIER SELECTION PLAN
In order ensure a significant level of cross-discipline buy-in for the selection
criteria de supplier selection team shall involve representatives from all areas
with invested interest on the serviced and/or goods to be procured (Cavinato,
J.L., Flynn, A.E. & Kaufmann, R.G. 2006: 728).
Additionally, supplier selection criteria (above meeting policies and regulations)
will be based on service/material costs and by the supplier administrative costs
under the awarded contract. (Cavinato, J.L., et. al. 2006: 744)
Typical selection process will be governed by the relationship between supplier
price/service/quality/technology and may include the following (Sollish, et al.
2011: 57-73)
- Evaluating offers
- Suppler responsiveness
- Capabilities assessment
- Competitive value
Module 6: Contracts and Procurement
Individual project: Final Project Report
Case Study: Southmead Hospital Redevelopment Procurement Plan
Rev. A
University of Liverpool – Laureate Online Education 29-October-2011
Page 8 of 14
2.3. CONTRACT AWARDING PLAN
The use of traditional processes for procurement management, in particular for
public enterprises/entities has shown to be a to be relatively inefficient, as the
timeline from issuing ITT/RFP/RFQ to a contract award stage can be long and
use considerable amount of time and resources from the procurement team
and more critical from other invested interest departments. (Cavinato, J.L., et.
al. 2006: 429)
Although widely recommended approach for supplier selection is indeed the
lowers price citus paribus, the NHS procurement team is not obligated to select
“the lowest price” tender. Instead, there is the possibility of awarding a contract
to “the most economically advantageous tender”, in which case they can use
criteria linked to the subject-matter of the contract in question (such as quality,
price, technical merit, supplier location (local or national), after-sales service,
delivery date and completion date), all of which have to be weighted in
descending order of importance. Munday, M. & Roberts, A. (2010: 9)
2.4. CONTRACT TYPES
Procurement plan will incorporate the outsourcing of services and the
purchasing of goods. As the diversity of acquiring items vary in complexity and
size, the contracts type developed to ensure the primary objectives as
discussed before will include among others the following contract types: (as
defined in PMBOK (2008: 322), cited in Heldman, K. (2009: 290)
- Fixed price or lump sum: which will be typically used for all low risk projects
where complexity and/or bidders understanding of the scope of work
specifications is sufficient to low the risk of implementation. Also for
projects where the project team does not anticipate major changes.
- Cost reimbursable: for procurement of equipments where specification
were not fully developed and final specification can be modified after
contract award.
- Time and materials (T&M): typical for service contracts only, due to the
uncertainty level and the complexity, in particular due to the fact that the
project team expects major scope changes
The three categories selected above are described in relation to the
procurement objectives of the Southmead Hospital redevelopment project, and
not in general, as this may entail additional parameters.
Module 6: Contracts and Procurement
Individual project: Final Project Report
Case Study: Southmead Hospital Redevelopment Procurement Plan
Rev. A
University of Liverpool – Laureate Online Education 29-October-2011
Page 9 of 14
3. FOUR PROCUREMENT ISSUES FACED BY PROCUREMENT MANAGERS IN NHS
3.1. POST TENDER NEGOTIATIONS
In NHS procurement, post tender negotiation, or price negotiation after tender
submittal, is not permitted. (NHS Barnet, 2009:37)
In theory, if bidding suppliers are aware that PTN is not allowed, then it is
expected the best price for the service scoped. In practice it doesn’t work as
not all aspects of the scope of work will be clarified to a minimum risk, and in
particular to specialty services and equipment specifications, thus it is
expected further clarifications/discussion and this may happen only after
contract award and supplier will not spend resources on clarifications without
some assurance of winning the bid or even after a PO is secured.( Peter W. G.
Morris and Jeffrey K. Pinto (2007: 308)
3.2. SUSTAINABILITY AND COMMUNITY IMPACT
Better public funds management, means capital procurement team in the NHS,
has to achieve this through delivering better-quality healthcare buildings and
improved value for money. The issues in safeguarding such objectives involve
the following challenges: ( Peter W. G. Morris and Jeffrey K. Pinto 2007: 274-
276)
• Creating a partnership program that will develop long-term agreements
with the local private sector to deliver better value for money and a better
service for patients while monitoring contract performance through
performance management
• Qualifying the NHS to be a best client while endorsing the use of high-
quality designs.
3.3. ENVIRONMENTAL IMPACT
A study sponsored by Torbay NHS Care Trust, (2010: 10) has revealed that
More than half of the NHS England total carbon footprint is associated with the
products and services it procures, as this account for 60% of the total NHS
carbon footprint. In order to balance cost vs. quality and environmental impact,
procurement manager will need to perform complex bid evaluation such that
none of the parameters is outside the regulation and guidelines established.
3.4. USE OF INFORMATION TECHNOLOGY
The implementation of eCommerce within government departments is
recognised as a major initiative, and is fully reinforced in this procurement plan.
This may prove a challenge to local supplier and smaller business ability to
engage the e-tendering process and therefore hinder the local community.
Module 6: Contracts and Procurement
Individual project: Final Project Report
Case Study: Southmead Hospital Redevelopment Procurement Plan
Rev. A
University of Liverpool – Laureate Online Education 29-October-2011
Page 10 of 14
4. STRATEGY TO HANDLE PROCUREMENT FOR UK HOSPITAL
The purpose of the procurement strategy is to set out the approach to accomplishing
its service and goods delivery objectives through the application of good procurement
practice.
As hospital patients and users in general are depended on the secure availability of
quality services and accountability for spending public funds, it requires proper
economic decisions. All public sector procurement processes are required to be
transparent, open to competition and secure best value (Pamela Nicholson, 2010: 3)
Although not comprehensive, below are four issues faced by NHS procurement
manager in UK as identified early in section 3 of this report, the proposed solution
overview.
4.1. STRATEGY FOR POST TENDER NEGOTIATIONS
Although, tendering and post tender negotiation are core important of
purchasing and supply management and, thus, all procurement professionals
should be competent in their application and use, CIPS, (nd.: 1) it is not
applicable for the current procurement plan for Southmead Hospital
redevelopment project, as stated before by NHS regulation.
Therefore, In order to still produced value for money on the procured goods
and services, the procurement team and project team in general will invest
careful attention to the early tendering process through the use of ITT, RFI,
RFP and finally RFQ clarification section to ensure that suppliers have a clear
understanding of the scope of work specification as well as the terms and
conditions for the specific contract they will be bidding to.
4.2. SUSTAINABILITY AND COMMUNITY IMPACT
The key procurement principles that will address the challenges with
sustainability and community impact on the procurement plan such that both
the local community as we the environment benefit from the project at the
implementation phase are: Barnet NHS (2009: 7-9)
• Procurement strategy is consistent with Department of Health regulation
and legislative guidelines.
• Procurement strategy needs to ensure procurement processes are
effective, are transparent and are equitable. NHS Barnet NHS (2009: 7)
• Procurement policy will be fair, transparent, equitable and non–
discriminatory.
• Value for Money is a pre-requisite of services and goods procured.
Module 6: Contracts and Procurement
Individual project: Final Project Report
Case Study: Southmead Hospital Redevelopment Procurement Plan
Rev. A
University of Liverpool – Laureate Online Education 29-October-2011
Page 11 of 14
4.3. USE OF INFORMATION TECHNOLOGY
Public bodies must consider the application of the public procurement rules in
procuring the e-tendering solution or service itself.
E-tendering delivers suppliers with electronic access to ITT and associated
documents and permits suppliers to securely lodge their completed tenders
electronically. These tenders are then released to authorised staff in the
procuring organisation after the closing date for the submission of tenders. For
the purposes of this project, an e-tendering service will be assumed to include
secure hosting of electronic tender-boxes and possibly other related services,
as well as the software solution.(OGC, 2010: 5)
E-tendering solutions may include tools such as:
o requirement development
o supplier selection and pre-qualification
o contract performance and vendor management
4.4. ENVIRONMENTAL IMPACT
Part of the procurement strategy, under the bidder selection criteria, the project
team will consider the footprint of the products being procured across all
bidding contractors and consider the “greenest” service and/good as a
advantage point on the selection process. The objective is to ensure among
other the following are met: NHS Care Trust, (2010: 10)
• Meeting current Waste Electrical and Electronic Equipment Regulations
for areas such as equipment disposal.
• Reduction in surplus packaging at supplier locations prior shipping. And
effective use of re-useable containers.
• Minimize travelling of people, goods and services including raw
material, as this will affect cost reduction as well.
• Ensuring that all contract terms and conditions are accommodating for
sustainable procurement activities.
• The development of a local sustainability policy reflecting the
environmental considerations and social responsibilities of good
procurement practice.
• Reducing both our own and our contractors’ carbon footprint
Module 6: Contracts and Procurement
Individual project: Final Project Report
Case Study: Southmead Hospital Redevelopment Procurement Plan
Rev. A
University of Liverpool – Laureate Online Education 29-October-2011
Page 12 of 14
5. CONCLUSION
The strategic procurement plan will take into account the following priorities: (Pamela
Nicholson, 2010: 15)
• Ethical Procurement: working towards the recommendations of the NHS in Saving
Carbon Improving Health and developing the Trust’s Ethical Procurement Policy
in accordance with national guidelines.
• Supply chain management: creating viable and efficient supplier markets,
developing effective supplier relations.
• Strategic procurement: finding and developing more innovative and proactive
ways of achieving year on year cost and quality improvements through market
segmentation, demand consolidation.
• eCommerce: Endorsing the use of e-business technology for early vendor
information acquisition, demand analysis, business to business trading and
specifically electronic tendering, catalogue management and product control as
well as the all-suite of activities supporting contract performance monitoring and
even payments via electronic transfer of funds.
• Change management: developing proactive methods of delivering real and
sustainable changes in the project that are benefits to health and social care
services, given the cost of project changes.
• Collaboration: constantly reviewing the configuration of demand and options for
effective networking and inter-trust supply collaboration within the local health
economy and the wider public sector network.
Module 6: Contracts and Procurement
Individual project: Final Project Report
Case Study: Southmead Hospital Redevelopment Procurement Plan
Rev. A
University of Liverpool – Laureate Online Education 29-October-2011
Page 13 of 14
6. REFERENCE LIST
Laureate Education Inc. (2011), “North Bristol- Integrated Community Hospital
development specifications: Final module project: Contracts and procurement
module”. Week 4 Assignment question. Laureate Online Education B.V.
Peter W. G. Morris and Jeffrey K. Pinto (2007) “The Wiley Guide to project technology, supply chain & procurement management” John Wiley & Sons, Inc., Hoboken, New Jersey.
Max Munday & Annette Roberts (2010) “The Economic Impact of NHS Procurement:
A Study of the Aneurin Bevan Health Board”, Welsh Economy Research Unit.
NHS Barnet (2009), “Procurement Strategy 2009-2014”, available online at:
www.barnet.nhs.uk/files/trustuploads/procurement%20strategy.pdf, last accessed on
23-Sep-2011.
CIPS, (ND.), “Tendering and Post Tender Negotiation”, CIPS Knowledge Works.
Available online at: www.cips.org. Last accessed on 20-Oct-2011.
Pamela Nicholson, (2010), “Corporate Procurement Strategy”, available online at:
www.torbaycaretrust.nhs.uk/publications/.../ProcurementStrategy.pdf, last accessed
on 26-September 2011.
www.bipsolutions.com, “Selling to the NHS – A Guide for Suppliers”, available on-line
at: http://www.bipsolutions.com/briefings/Briefings2004/Brief04_08.php, last accessed
on 18-Sep-2011.
Sollish, F., Semanik, J., Morris, P.W.G. ed. & Pinto, J.K. ed. 2011. Planning and
administering project contracts and procurement. Laureate Education, Inc., custom ed.
Hoboken: John Wiley & Sons.
Cavinato, J.L., Flynn, A.E. & Kaufmann, R.G.7th Ed. (2006) Supply management handbook. 7th Ed. New York: McGraw-Hill [Online]. Available from: http://site.ebrary.com.ezproxy.liv.ac.uk/lib/liverpool/docDetail.action?docID=10 155019 (Accessed: 19 Oct 2011).
Project Management Institute (2008) A guide to the project management body of
knowledge. 4th Ed. Newton Square, PA:
Project Management Institute.Heldman, K. (2009) “PMP project management
professional exam study guide”. 5th Ed. Indianapolis: Wiley Publishing Inc.
Office of Government Commerce (OGC) 1 HM Treasury (2010) “Implementing e-tendering. London: OCG [Online]. Available from: http://www.ogc.gov.uk/documents/etendering_ Guidance.pdf (Accessed: 15 September 2011).
Module 6: Contracts and Procurement
Individual project: Final Project Report
Case Study: Southmead Hospital Redevelopment Procurement Plan
Rev. A
University of Liverpool – Laureate Online Education 29-October-2011
Page 14 of 14
APPENDIX A: PROCUREMENT PLAN MAJOR ACTIVITIES GANTT CHART
ID Task Name Duration
1 PROCUREMENT PROCESS 840 days
2 PURCHASE SERVICE SELECTION 15 days
3 SERVICE MAKE OR BUY DECISION PROCESS 2 wks
4 CROSS FUNCTION APPROVALS 1 wk
5 PURCHASE GOODS SELECTION 90 days
6 PRELIMINARY GOODS/MATERIAL SPECIFICATIONS 6 wks
7 VENDORS INPUT ON SPECIFICATIONS 8 wks
8 GOODS/MATERIALS/EQUIPMENT DETAIL SPECIFICATION AND DATA SHEETS 4 wks
9 CONTRACTING PLAN 50 days
10 Prepare set of policies and regulations for selected procurement goods/services 8 wks
11 Prepare preliminary bidders list 2 wks
12 REQUEST FOR INFORMATION 20 days
13 Issue invitation to tender for pre-selected bidders list 3 wks
14 Hold preliminary scope clarifications meetings 1 wk
15 REQUEST FOR PROPOSALS 40 days
16 Issue RFPs 2 wks
17 Issue typical contract terms and conditions for supplier review and comments 1 wk
18 Hold scope and compliance clarifications meeting with suppliers 1 wk
19 Perform supplier qualification process 4 wks
20 REQUEST FOR QUOTATIONS 25 days
21 Issue Request For Quotations 1 wk
22 Hold price/scope specifications negotiations 4 wks
23 SUPPLIER SELECTION 45 days
24 Prepare bid tab for evaluations 4 wks
25 Conduct supplier bid evaluations 4 wks
26 Prepare list of winning contractors and have management approval 1 wk
27 CONTRACT AWARDING 25 days
28 Select contract type 2 wks
29 Issue contract agreement to winning contractors 1 wk
30 Receive and accpetance of contract agreement 1 wk
31 Issue contract management plan 1 wk
32 Issue bidding results to all bidding suppliers 1 wk
33 CONTRACT MANAGEMENT 480 days
34 Perform regular contract review/audits 24 mons
35 Prepare and issue score cards 24 mons
36 Issue correction letters to out of scope suppliers 24 mons
37 Make payments according to terms and conditions 24 mons
38 CONTRACT CLOSURE 50 days
39 Review and Accept punch list items 4 wks
40 Hold contract closeout meeting with supplier and target departments 2 wks
41 Issue contractor score card 2 wks
42 Make final payments 1 wk
43 Issue certificate of contract completion 1 wk
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A
4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Qu
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
MODULE 5: CONTRACTS AND PROCUREMENT
FINAL PROJECT
DAVIDSON FERREIRA
SOUTHMEAD REDEVELOPMENT PROJECT
TYPICAL PROCUREMENT PROCESS
SERVICES AND SPECIAL EQUIPMENT PURCHASE
TYPICAL PROCUREMENT PROCESS GANTT CHART
FOR SERVICES AND SPECIAL EQUIPMENT ACQUISITION
Project: Gantt Chart.mpp
Date: Tue 11-10-11