CONOCO PHILLIPS Spec

download CONOCO PHILLIPS Spec

of 21

Transcript of CONOCO PHILLIPS Spec

  • 7/25/2019 CONOCO PHILLIPS Spec

    1/21

  • 7/25/2019 CONOCO PHILLIPS Spec

    2/21

    CONOCO INDONESIA INC. LTD.PROJECTS DEPARTMENT

    SPECIFICATION

    TITLE DOCUMENT NUMBER REV DATE PAGE

    DESIGN CHANGE CONTROL PROCEDURE 84501-9200-9P-001 2 1 Mar 03 2 of 21

    Check with Document Control for latest available Revision

    REVISION CONTROL SHEET

    LATEST REV DATE ISSUED PREPARED REVIEWED APPROVED COMMENTS

    O 14 August 2002 C.Binks J.Sexton A.McIntosh Issued For Use

    1 1 October 2002 C.Binks R.Ford A.McIntosh Flowchart Updates

    2 1 March 2003 C.Binks R.Ford A.McIntoshDepartment Name

    Change

  • 7/25/2019 CONOCO PHILLIPS Spec

    3/21

    CONOCO INDONESIA INC. LTD.PROJECTS DEPARTMENT

    SPECIFICATION

    TITLE DOCUMENT NUMBER REV DATE PAGE

    DESIGN CHANGE CONTROL PROCEDURE 84501-9200-9P-001 2 1 Mar 03 3 of 21

    Check with Document Control for latest available Revision

    TABLE OF CONTENTS

    1. INTRODUCTION ..................................................................................................4

    2. APPLICABILITY...................................................................................................4

    3. DEFINITIONS ....................................................................................................... 5

    4. RESPONSIBILITIES.............................................................................................7

    5. REFERENCES .....................................................................................................7

    6. PREFERENCES...................................................................................................7

    7. DESIGN CHANGE REVIEW BOARD ................................................................13

    8. COMPLETION OF DESIGN CHANGE NOTICE FORMS ..................................14

    9. DISTRIBUTION ..................................................................................................15

    APPENDIX 1 DESIGN CHANGE FLOWCHARTS....................................16-18

    DESIGN CHANGE NOTICE FORM...............................................................19-20

    EXAMPLE OF A TYPICAL COST ESTIMATE SHEET......................................21

  • 7/25/2019 CONOCO PHILLIPS Spec

    4/21

    CONOCO INDONESIA INC. LTD.PROJECTS DEPARTMENT

    SPECIFICATION

    TITLE DOCUMENT NUMBER REV DATE PAGE

    DESIGN CHANGE CONTROL PROCEDURE 84501-9200-9P-001 2 1 Mar 03 4 of 21

    Check with Document Control for latest available Revision

    1. INTRODUCTION

    1.1. Purpose

    The purpose of this procedure is to ensure that all proposed changes to thedesign during the execution of the Project are fully documented, evaluated forimpact upon the Project and approved by all affected groups prior toimplementation of a change.

    The approval levels required prior to any change being made are also detailedherein and the procedure describes the process that controls project-wide designchanges.

    The procedure describes the overall Design Change Control System for theProject Team and defines the responsibilities for its implementation and thissystem provides the following:

    Compilation of all relevant information such as technical, cost, schedule,weight, life cycle cost, etc., which is essential for the evaluation of theproposed changes.

    A systematic process for obtaining management approval to implement achange on the Project.

    The opportunity for all affected groups and organizations to evaluate theeffect of each proposed change, including safety, reliability, weight,operability, and maintainability of the installations.

    Advance notification to all affected groups of pending changes to ensurecoherent change implementation planning.

    It is incumbent upon the Contractor to prepare and implement his ownprocedures and methods of controlling changes to the design of the Project.

    It is expected that the contractor have similar procedures within his organizationthat provide the facility of rigorous controls to any changes of the design.

    2. APPLICABILITY

    This procedure shall apply specifically to the Project Team in the instance wherethe Contractor is unable to control any proposed Design Change within his ownorganization or responsibility under the Contract. Typical examples would be, butnot limited to the following:

    a) A change in the Basis of Design document included as an integral part of theContract.

  • 7/25/2019 CONOCO PHILLIPS Spec

    5/21

    CONOCO INDONESIA INC. LTD.PROJECTS DEPARTMENT

    SPECIFICATION

    TITLE DOCUMENT NUMBER REV DATE PAGE

    DESIGN CHANGE CONTROL PROCEDURE 84501-9200-9P-001 2 1 Mar 03 5 of 21

    Check with Document Control for latest available Revision

    b) Anything having an external interface outwith the contractual boundary of the

    Contractors own organization (CIIL, MIGAS, other regulatory bodies, othercontractors etc.).

    c) Anything that affects equipment etc. purchased on a provisional sum basis.

    When these occasions arise this Procedure will apply to the Project Team.

    3. DEFINITIONS

    3.1 Design Change

    A Design Change is an alteration or addition to, or deletion from the Contract

    Basis of Design, anything having an external interface outwith the contractualboundary of the Contractors own organization, anything that affects equipmentetc. purchased on a provisional sum basis.

    The initial point of reference shall be the Contract Basis of Design and anysubsequent changes to engineering documentation generated throughout theProject Execution Phase.

    Design Changes shall be classified in accordance with the following criteria:

    3.1.1 Discretionary, those entirely within the Project Team orNon Discretionary, those required to comply with regulations or industry

    standards, or negotiations and agreements with third parties.

    3.1.2 Major Design Change

    A Major Design Change is one that meets one or more of the following criteria: -

    The total cost impact, increase or decrease, is greater than the affectedProject Managers Facility Authority limit.

    The cost impact exceeds the Project area budget.

    More than one facility within the Project is affected.

    The contractual acceptance criteria are changed.

    A change is required to the Project Master Schedule.

    The CIIL Operations Group consider there will be large impact on the lifecycle costs.

    The designation Major change will be confirmed by preliminary discussionbetween the appropriate Lead Engineers and Project Managers.

    No affected engineering documentation shall be issued for implementation priorto the approval of a Major Design Change.

  • 7/25/2019 CONOCO PHILLIPS Spec

    6/21

    CONOCO INDONESIA INC. LTD.PROJECTS DEPARTMENT

    SPECIFICATION

    TITLE DOCUMENT NUMBER REV DATE PAGE

    DESIGN CHANGE CONTROL PROCEDURE 84501-9200-9P-001 2 1 Mar 03 6 of 21

    Check with Document Control for latest available Revision

    3.1.3 Minor Design Change

    A limited design change that meets the following criteria: -

    There is no effect on the budget/schedule of more than one facility of theProject.

    The budget of the entire Project is not impacted

    The total cost impact is less than or equal to the Authority Limit of theFacility Project Manager.

    The change implementation will not have any negative impact on theProject Master Schedule.

    The change does not result in weight limits being exceeded or the centerof gravity being moved beyond the established spatial envelope.

    It is the action subsequent to a Site Query being raised by a supplier,fabricator or installation contractor.

    The CIIL Operations Group consider that there will not be any seriouseffect on the life cycle costs or development Net Present Value (NPV).

    No negative impact on reliability

    3.2 Manufacturing Change/Concession

    A manufacturing change/concession is a make operable/make fit or use as is

    change to approved engineering documentation. The request is made at amanufacturing, fabrication, erection or test site and is submitted to permitfabrication, assembly and/or test operations to proceed without schedule delay.The change/concession shall be documented in accordance with an approvedDesign Change Request system.

    3.3 Engineering Documentation

    Engineering documentation includes drawings, specifications, data sheets,material take-off lists, parts lists, technical instructions etc., produced inaccordance with the terms of the Contract for the Project.

    3.4 Design Change Request (DCR)

    This is a formal document by which any individual may request a change thatmerits a Design Change proposal be investigated.

    Any engineering or construction person working on the Project can initiate aDesign Change Request (DCR). This includes the Project Team and Contractorteams.

    A Design Change Request is initiated by completing the Design Change Notice(DCN) Form.

  • 7/25/2019 CONOCO PHILLIPS Spec

    7/21

    CONOCO INDONESIA INC. LTD.PROJECTS DEPARTMENT

    SPECIFICATION

    TITLE DOCUMENT NUMBER REV DATE PAGE

    DESIGN CHANGE CONTROL PROCEDURE 84501-9200-9P-001 2 1 Mar 03 7 of 21

    Check with Document Control for latest available Revision

    Such forms are considered to be in the Request state until all required

    approvals are obtained.

    3.5 Design Change Notice (DCN)

    A DCN is the formal instrument, document, or group of documents issued by theContractor which initiates, authorizes, and communicates the essence of theDesign Change throughout the Project, once a Design Change has beenapproved in accordance with Contractor procedures and, where applicable, thisProcedure.

    All DCN's will be consecutively numbered in accordance with the DocumentNumbering Specification 84501-9200-9L-001.

    3.6 Design Change Review Board (DCRB)

    The DCRB is the body empowered to review major design changes whenrequested to do so by the CIIL Projects Manager and shall consist of projectpersonnel as requested by the CIIL Projects Manager. The CIIL InfrastructureManager or his designated representative, shall chair the DCRB. This shall bereviewed dependant upon the geographical location.

    3.7 Non Discretionary Change

    A Non Discretionary change is an engineering design change that is required topermit design, engineering, fabrication or installation of an item to meet statutoryor safety requirements e.g. Government Agencies, Certifying Authority (MIGAS),Marine Surveyor, Operator Standards etc.

    4. RESPONSIBILITIES

    It is the responsibility of all Project personnel to implement this procedure.

    5. REFERENCES

    Project Specification 84501-9200-9L-001 Document Numbering.

    Project Specification 84501-9200-9P-002 Interdiscipline Check Procedure (IDC)

    6. PROCEDURE

    6.1 Initiation of a DCR/DCN

    It is expected that the Contractor will have his own procedure for the processingany potential design change up to the point of being passed to the Project Teamfor further action.

  • 7/25/2019 CONOCO PHILLIPS Spec

    8/21

    CONOCO INDONESIA INC. LTD.PROJECTS DEPARTMENT

    SPECIFICATION

    TITLE DOCUMENT NUMBER REV DATE PAGE

    DESIGN CHANGE CONTROL PROCEDURE 84501-9200-9P-001 2 1 Mar 03 8 of 21

    Check with Document Control for latest available Revision

    Prior to raising a DiscretionaryDCN, informal discussions as to the impact of the

    proposed change on the Project should be held between appropriate involvedparties to determine if there are any reasons why the proposed Design Changecannot be implemented and to prevent wasting time evaluating the DCN. If theindividual originating the request decides to proceed, he/she completes the DCNform contained herein.

    Completed DCN's should be forwarded to the corresponding Lead ProjectEngineer. DCN's originating outside of the Project should be directed to theProject Lead whose area will likely be impacted the most.

    If there is some uncertainty as to who to send the DCN to, Project Management should be consulted.

    A minor DCN will be approved by the Engineering Manager and shall beadministered by that group and will not require action outside of that facilitygroup.

    A major Design Change will require central administration, detailed costestimates, schedule impact etc. and require approval by the relevant managers.

    The Project Lead engineer within the group initiating the DCN, in conjunction withthe Cost and Planning groups, shall complete a DCN form and co-ordinate thecompilation of the requisite supporting information.

    Proposals for design changes outwith the Project group, e.g. Operations, Drilling,etc. shall be coordinated by the Project Facility Group most affected by theproposed change.

    6.2 Acceptance of DCN's by Lead Project Engineers

    The Lead Project Engineer receiving a Discretionary DCN should perform aninitial assessment to determine if the suggested Design Change is reasonableand consistent with the overall design philosophy. In order to proceed with a fullevaluation, the Project Lead should also determine whether or not sufficientinformation exists or can be sufficiently developed to assess the impact of thechange, and decide whether or not the change adds significant enough value to

    the project, given the inherent risk of any change.In this context, the Lead Project Engineer has veto power over any DiscretionaryDCN that he/she deems to be unreasonable, incapable of being assessed,inconsistent, or too risky. In such instances where this veto right is exercised, theLead Project Engineer is obligated to get back with the person who submitted theDCN and explain the rationale which led to its rejection.

    If the Lead Project Engineer agrees the DCN is Non Discretionary, then he/she isobligated to proceed with evaluation and has no veto rights. If there is any

  • 7/25/2019 CONOCO PHILLIPS Spec

    9/21

    CONOCO INDONESIA INC. LTD.PROJECTS DEPARTMENT

    SPECIFICATION

    TITLE DOCUMENT NUMBER REV DATE PAGE

    DESIGN CHANGE CONTROL PROCEDURE 84501-9200-9P-001 2 1 Mar 03 9 of 21

    Check with Document Control for latest available Revision

    question as to whether the DCN is Discretionary or Non Discretionary, Project

    Management should be consulted.

    The DCN serial number shall be assigned after acceptance by the Lead ProjectEngineer(s)

    6.3 Development of Supporting Information

    All DCN's accepted by the Lead Project Engineers are to be fully evaluated as totheir cost and schedule impact. The evaluation is to include a reasonableassessment of the foreseeable risks associated with implementing the change.

    The risk assessment should consider the probability of certain negative outcomes

    or impacts on other activities (including process safety) and include proposedmethods of risk mitigation.

    If the DCN has the potential to impact other project areas, the Lead ProjectEngineer must coordinate the evaluation with the Lead Project Engineer(s) sothat the final assessment properly reflects the totality of the impact that theDesign Change is expected to have.

    All DCN's are to be subjected to the Inter-Disciplinary Check (IDC) process(84501-9200-9P-002).

    No affected engineering documentation shall be issued for implementationprior to the approval of a Design Change Notice.

    The relevant Project Engineer shall:

    Collect supporting information to complete the DCN forms.

    Obtain the requisite inter-group approvals and comments.

    Obtain the estimated cost of change and establish the cost boundaries(Min and Max).

    Determine the current purchasing/manufacturing status and/or fabricationstatus of all items associated with the change and the effects.

    Obtain from planning any impact on the schedule.

    Categorize the DCN as Discretionary or Non-Discretionary, the financialand schedule impact will classify the DCN as Major or Minor accordingly.

    If the design change is classified as Major it should first be approved within theinitiating group, it can then be issued for input to the other groups affected.

    6.4 Co-ordination

    6.4.1 Design Changes

  • 7/25/2019 CONOCO PHILLIPS Spec

    10/21

    CONOCO INDONESIA INC. LTD.PROJECTS DEPARTMENT

    SPECIFICATION

    TITLE DOCUMENT NUMBER REV DATE PAGE

    DESIGN CHANGE CONTROL PROCEDURE 84501-9200-9P-001 2 1 Mar 03 10 of 21

    Check with Document Control for latest available Revision

    Engineers shall be responsible for the co-ordination and development of all

    design changes emanating from within their respective groups. This activityincludes maintaining all records, assigning DCN numbers according to theDocument Numbering Procedure, controlling document distribution and flow,arranging meetings and co-ordinating the development of the supportingdocumentation.

    They shall be responsible for assigning the minor or major classification.

    The Facility Project Manager of the initiating group shall be responsible forensuring that major changes are notified to all affected groups and are quicklyprogressed and approved/rejected by the Senior Project Manager.

    A register of all major DCNs will be maintained by Document Control who will beresponsible for allocation of sequential numbers.

    Affected groups outwith the Project will progress major changes in accordancewith their own Change Control Procedures.

    It is vital that a DCN is progressed as rapidly as possible and it is expected that amaximum of 2 weeks should be allowed from initiation to completion.

    6.4.2 Design Change Cost Estimates

    Each cost group shall be responsible for estimating the cost associated with theDCN

    The cost impact shall be broken down into its engineering, procurement,construction, and Project team components. Where increased costs are involved,the value of the perceived benefit must also be assessed in appropriate cost,NPV or NPC or operational terms.

    The Operations Manager will be responsible to ensure that any effect on life cyclecost is highlighted and taken into consideration.

    6.4.3 Design Change Schedule Impact Assessment

    The planning group shall be responsible for the evaluation of any schedule

    impact caused by a DCN. The planning group shall co-ordinate with the relevantProject engineers to obtain the information.

    The schedule impact is assessed by considering the time it takes to perform andverify additional engineering, change drawings, update plans, revise materialtake-off and procurement lists, and address any potential interaction betweenparallel activities or contracts.

    Major changes shall be coordinated by the Project Planner who shall beresponsible for raising changes as per Project Procedures.

  • 7/25/2019 CONOCO PHILLIPS Spec

    11/21

    CONOCO INDONESIA INC. LTD.PROJECTS DEPARTMENT

    SPECIFICATION

    TITLE DOCUMENT NUMBER REV DATE PAGE

    DESIGN CHANGE CONTROL PROCEDURE 84501-9200-9P-001 2 1 Mar 03 11 of 21

    Check with Document Control for latest available Revision

    6.5 Review of a Major DCN

    The initiating manager of a major DCN shall be responsible for ensuring that allaffected groups are involved in the DCN review.

    The project engineers from the groups affected shall review the DCN and shallrecord on the DCN form the cost/schedule impact and desirability of the proposedchange and recommend if it is accepted or rejected. If the recommendation is toreject the DCN then the reasons shall be clearly stated on the DCN form andreturned to the originator.

    The review shall include a reasonable assessment of the foreseeable risksassociated with implementing the change.

    The risk assessment should consider the probability of certain negative outcomesor impacts on other activities, including process safety, and include proposedmethods of risk mitigation.

    The initiating manager will be responsible for organizing the collation of all theinformation and its presentation for the approval process. If the recommendationfor acceptance is not unanimous then it is recommended that a DCRB beconvened for final resolution.

    6.6 Approvals

    Once the impact of the proposed Design Change has been fully assessed, theLead Project Engineer who coordinated the assessment will approve the DCNand forward it for distribution or further approval in accordance with the followingAuthority Limits:

    6.6.1 Major Design Changes

    Project Managers

    Discretionary and non-discretionary DCN's which have a negative scheduleimpact greater than one Week, increase project execution risks, or result in a costimpact of $250,000 or more require the approval of the respective ProjectManager.

    All DCN's which have or are deemed to have a reasonable chance of creating anegative schedule impact must be submitted to Project Managers.

    6.6.2 Minor Design Changes

    Once the impact of the proposed Design Change has been fully assessed, theLead Project Engineer who coordinated the assessment will approve the DCNand forward it for distribution or further approval in accordance with the followingAuthority Limits:

  • 7/25/2019 CONOCO PHILLIPS Spec

    12/21

    CONOCO INDONESIA INC. LTD.PROJECTS DEPARTMENT

    SPECIFICATION

    TITLE DOCUMENT NUMBER REV DATE PAGE

    DESIGN CHANGE CONTROL PROCEDURE 84501-9200-9P-001 2 1 Mar 03 12 of 21

    Check with Document Control for latest available Revision

    Lead Project Engineers

    Discretionary and non-discretionary DCN's which have no negative scheduleimpact, which do not increase the risk to project execution, and result in a costimpact of $100,000 or less require the approvals of the Engineering Manager.

    6.7 Hold Activity

    Whilst reviewing a major DCN, if it is considered necessary to initiate a HOLDon any engineering documentation, then the responsible Project engineer shall:

    Obtain approval to initiate a HOLD from his Manager.

    Advise the manufacturer (via procurement) or the fabrication site

    management team, of the proposed HOLD. Withdraw the engineering document concerned and initiate a HOLD on

    the affected area or activity.

    Advise all concerned parties including the Project manager of the HOLDaction taken.

    6.8 Prior Approvals

    In the case of Mandatory or urgent major changes that may have an immediateimpact on the project schedule, the Project manager may give approval toimplement the change prior to a full evaluation and documentation of the change.

    This shall be authorized in writing by formal communication.

    This should only be considered when serious schedule impact or cost penaltieswould be caused by the normal DCN processing operation.

    6.9 Implementation

    The Lead Project engineers for the affected groups shall be responsible for theimplementation of all DCNs by means of issuing formal communications andsupporting information to all affected groups.

    Project managers are responsible to ensure that all approved major DCNs areimplemented.

    When a DCN results in a CAPEX increase or decrease, the cost groups shall,where appropriate, initiate a Trend Notice in accordance with their relevantprocedure. The project cost group is responsible for co-ordination of any resultingreallocation of funds and shall inform the Contracts group immediately of anyimpending change.

    When a DCN results in a change to the Project Master Schedule the projectplanning group shall initiate a Change Notice in accordance with the approvedprocedures.

  • 7/25/2019 CONOCO PHILLIPS Spec

    13/21

    CONOCO INDONESIA INC. LTD.PROJECTS DEPARTMENT

    SPECIFICATION

    TITLE DOCUMENT NUMBER REV DATE PAGE

    DESIGN CHANGE CONTROL PROCEDURE 84501-9200-9P-001 2 1 Mar 03 13 of 21

    Check with Document Control for latest available Revision

    6.10 Issue of a Design Change Notice

    Subsequent to approval by the Project Manager(s) the DCN shall be issued tothe Operations Manager for record purposes.

    Upon completion of the final approval signatures Document Control shallcomplete the distribution to all affected parties.

    7. DESIGN CHANGE REVIEW BOARD

    When the requirement arises for a major DCN to be reviewed by the DCRB, theCIIL Infrastructure Project Manager shall notify the appropriate personnel of thetiming and any additional information necessary.

    The Project Lead Engineer responsible for raising the DCN will co-ordinatecollection of the information, organize the meeting, and supply a copy of the DCNdata package at least 24 hrs prior to the scheduled meeting.

    7.1 DCRB Attendees

    The CIIL Infrastructure Project Manager shall chair the DCRB, or delegate andshall include the following members:

    Originating Project Manager

    Affected Managers

    Originating Project Engineer

    Originating Lead Engineer

    Cost group representative

    Planning group representative

    Contracts group representative

    Operations, drilling, reservoir representatives as appropriate.

    Additional attendees may attend if so requested.

  • 7/25/2019 CONOCO PHILLIPS Spec

    14/21

    CONOCO INDONESIA INC. LTD.PROJECTS DEPARTMENT

    SPECIFICATION

    TITLE DOCUMENT NUMBER REV DATE PAGE

    DESIGN CHANGE CONTROL PROCEDURE 84501-9200-9P-001 2 1 Mar 03 14 of 21

    Check with Document Control for latest available Revision

    7.2 Proceedings

    The originating Project Manager shall present a summary of the DCN underreview providing the following as a minimum:

    Description of the change

    Reason for the change

    Effect on other groups or organizations

    Impact upon the Project

    Impact upon non-project activities, e.g. drilling.

    Minutes of the meeting shall be taken by a member of the originating group,noting requirements for additional data and recording decisions taken.

    The CII Infrastructure Coordinator may approve or reject the change at themeeting or may return the DCN later with the decision.

    8. COMPLETION OF DESIGN CHANGE NOTICE FORMS

    Appendix 1 contains the sample DCN form, 2 pages, to be completed for eachDCN submitted for approval. The entries are, for the most part, self-explanatory;however, the following comments may assist clarification.

    Page 1 Originating group

    Title indicative of the nature of the change

    Reason for Change reason for the requested change

    Change Description description of proposed change

    Other Groups Affected tick boxes of all groups affected

    Approvals signatures of persons approving the change

    Approved Box/Rejected Box Tick box accordingly prior to final approval

    by Project Manager

    Page 2

    Items Impacted tick boxes of drawings/document types affected

    Impact On impact should be detailed for each discipline

    References details of any Project documentation, correspondencerelating to the DCN

    Attachments details of any Project documentation, correspondencerelating to the DCN

  • 7/25/2019 CONOCO PHILLIPS Spec

    15/21

    CONOCO INDONESIA INC. LTD.PROJECTS DEPARTMENT

    SPECIFICATION

    TITLE DOCUMENT NUMBER REV DATE PAGE

    DESIGN CHANGE CONTROL PROCEDURE 84501-9200-9P-001 2 1 Mar 03 15 of 21

    Check with Document Control for latest available Revision

    Implementation Plan description of the implementation process for the

    DCN

    Appendix 2

    This is a typical example of a detailed cost estimate form.

    9. DISTRIBUTION

    The distribution shall be affected by Document Control, who shall retain and filethe original DCN, and copies shall be distributed to:

    CIIL Infrastructure Coordinator

    CIIL Operations Manager

    Project Manager

    Deputy Project Manager

    Area Project Managers

    Discipline Lead Engineers

    CIIL Projects Group Records Management Coordinator

    CIIL Document Controller

  • 7/25/2019 CONOCO PHILLIPS Spec

    16/21

    Check with Document Control for latest available Revision

    APPENDIX 1 SHEET 1 OF 3DESIGN CHANGE CONTROL PROCEDURE - EXECUTION PHASE

    INITIATION AND REVIEW OF A DESIGN CHANGE NOTICE

    DCR/DCNREQUEST

    RAISED

    INFORMALDISCUSSION

    HELD TO

    PROCEED

    YES/NO

    RETURN FORREWORK OR

    PROCEED WITHDCN

    NO

    YESCO& FLEA

    E

    COMPLETE DCN

    & FORWARD TOLEAD PROJECTENGINEER

    ORIGINATORINSISTS ON

    RAISING DCN

    NO

    OBTAINPLANNING

    IMPACT

    COLLECTSUPPORTING

    INFORMATION&

    COMPLETE DCN

    OBTAINREQUISITE

    INTER-GROUPAPPROVALS

    OBTAIN COSTIMPACT ANDBOUNDARIES

    MAX & MIN

    OBTAINPURCHASE,

    FABRICATIONSTATUS

    END

    YES/NO

    HOLD ONDOCUMENTSREQUIRED

    YES

    NO

    OBTAINMANAGERAPPROVALFOR HOLD

    ADVISE ALLPARTIES OFPROPOSED

    HOLD

    WITHDRAWDOCUMENT

    CONCERNED

    DESIGN CHANGE FLOWCHART DCN-1

    YES

  • 7/25/2019 CONOCO PHILLIPS Spec

    17/21

    APPENDIX 1 SHEET 2 OF 3DESIGN CHANGE CONTROL PROCEDURE - EXECUTION PHASE

    CATEGORIZATION AND APPROVAL OF A DESIGN CHANGE NOTICE

    COST IMPACT

  • 7/25/2019 CONOCO PHILLIPS Spec

    18/21

    APPENDIX 1 SHEET 3 OF 3DESIGN CHANGE CONTROL PROCEDURE - EXECUTION PHASE

    IMPLEMENTATION, ISSUE OF DESIGN CHANGE NOTICE

    DCN FULLYAPPROVED &SUPPORTING

    DOCUMENTATION

    INCREASE

    IN CAPEXES/NO

    CHANGE TOPROJECTMASTER

    SCHEDULE

    COST GROUPISSUE

    TREND NOTICE

    DOCUMENTCONTROL

    COMPLETE

    DISTRIBUTION

    FLOWCHART DCN-3

    DRAWINGS /DOCUMENTSREVISED AND

    APPROVED

    DRAWINGS /DOCUMENTSISSUED TORELEVANT

    PARTIES

    CONTINUED FROM

    FLOWCHART DCN-2

    NO

    YES

  • 7/25/2019 CONOCO PHILLIPS Spec

    19/21

    Check with Document Control for latest available Revision

    XXX PROJECTDESIGN CHANGE NOTICE

    Page 1 of 2

    TYPE ORIGINATING GROUP:

    DISCRETIONARY

    NON DISCRETIONARY

    DCN No.

    DATE :

    REV :

    TITLE

    REASON FOR CHANGE

    CHANGE DESCRIPTION ( ATTACH SKETCH/DRG)

    APPROVALS (AS APPROPRIATE)

    SUBSEA DATE:

    DRILLING DATE:

    OPERATIONS DATE:

    PIPELINE DATE:

    STRUCTURE DATE:

    TOPSIDES DATE:

    MARINE DATE:

    CALM BUOY DATE:

    SHEA DATE:

    RESERVOIR DATE:

    CII INFRASTRUCTURE MANAGER: DATE:

    APPROVED REJECTED

    T/S PROCESS

    T/S LAYOUT

    T/S STRUCTURAL

    T/S MECHANICAL

    T/S ELECTRICAL

    T/S INSTRUMENTS

    T/S SAFETY/ENV

    T/S HVAC

    T/S WEIGHT CONTROL

    T/S FABRICATION

    T/S NSTALLATION

    T/S E&I DESIGN

    T/S DRILLING

    W/H DESIGN

    W/H FOUNDATIONS

    W/H NAVAL ARCHITECT

    W/H MECH/INST/SYST

    W/H FABRICATION

    W/H INSTALLATION

    TEMPLATE/TIE BACK

    FLOWLINES

    RISERS

    CALM BUOY

    DRILLING

    RESERVOIR

    OPERATIONS

    EXPORT PIPELINE MIGAS

    PERMITS/GOVNT

    OTHER GROUPS AFFECTED

    AUTHOR:

    MATERIALS/SPECS

    Distribution Copies : Original Document Control

  • 7/25/2019 CONOCO PHILLIPS Spec

    20/21

    Check with Document Control for latest available Revision

    Page 2 of 2

    DCN No. DATE : REV :

    FLOW DIAGRAMS

    P&IDs

    PFDs

    ELECTRICAL OLDs

    GENERAL ARRANGEMENT

    STRUCTURAL

    ISOMETRICS

    INSTRUMENT DRGS

    ELECTRICAL DRAWING

    SPECIFICATIONS

    PLANS

    PROCEDURES

    MATERIAL TAKE OFF

    MATERIAL REQUISITION

    PURCHASE ORDERS

    VENDOR DOCUMENTS

    NOTES:

    IMPACT ON:Tick appropriate box and provide brief summary. Detailed impact to be provided as an attachment

    WEIGHT

    INTERFACES

    REGULATORY COMPLIANCE

    RELIABILITY/SAFETY

    COST (Life Cycle Analysis)

    FABRICATION

    INSTALLATION

    PROCUREMENT

    OPERATIONS

    SCHEDULE

    CHANGE IN CRITICALITY RATINGS

    REFERENCES(Use separate sheet if required)

    ATTACHMENTS(Use separate sheet if required)

    IMPLEMENTATION PLAN

    ITEMS IMPACTED :

  • 7/25/2019 CONOCO PHILLIPS Spec

    21/21

    XXX PROJECTDCN COST ESTIMATE FORM

    DCN No. DATE : REV :

    GROUP: SECTION:

    DESCRIPTION:

    PAGE OFREV:DATE:

    BASIS OF ESTIMATE:

    TOTAL

    ITEM DESCRIPTION UNIT QUANTITY RATE COST

    $