Confidential – © 2013. All rights reserved Mysore - Intelligent Transport System
Submitted By – CMCDated 20th November 2014
ITS Project for Mysore City Transport Project Status Report
KARNATAKA STATE ROAD TRANSPORT CORPORATION
Confidential – © 2013. All rights reserved Mysore - Intelligent Transport System 2
Agenda
Solution Overview
Project Scope and Components
Current Status of Project
Operations Status
Action Plan Ahead
Operations Team Structure
Operations Review Mechanism
Support required from KSRTC
Confidential – © 2013. All rights reserved Mysore - Intelligent Transport System 3
Solution Overview
Confidential – © 2013. All rights reserved Mysore - Intelligent Transport System 4
Project Scope and Components
Video Wall
Application / Database Servers
Network Firewall / Routers / Switches
ITS
ETA
MIS Reports
GIS
EMS
Commuter Portal
SMS
IVRS
Shelters - 2” 2 Line – 59
Shelters – 2” 4 Line - 63
Platforms – 4” 4 Line – 45
Terminals – 10 Line – 20
Terminals – 16 Line – 6
VMUs - 500
In-Bus Displays – 500
Voice Announcement System
DG Set – 82.5 KVA
UPS – 20 KVA x 2
ITS
CCS / Data Centre PIS Display Boards
Commuter Related
Applications
PowerIn-Bus Equipments
Crew Training
Officials Training
Training
Confidential – © 2013. All rights reserved Mysore - Intelligent Transport System 5
Activities / Components Current Status Date
On-Going Equipment service requirements
In Bus Equipment Currently 419 buses are Reporting in DSR 10.12.2014
In Bus display All in-bus display issues resolved 15.11.2014
In Bus Audio New set of audio files, for the new routes, being loaded to VMU 10.12.2014
PIS – LED (2/4 line) Nearing completion; We are restring boards whenever utility power is provided 30.11.2014
Data Center/CCS/Depot Equipment working normally, as expected
Operations & Maintenance support On-going since inauguration On-going
Current Status of Project
• Conditional Operational Acceptance Provided• ‘Cure’ Period Action Target Date : 15.11.2014• Current Status
Confidential – © 2013. All rights reserved Mysore - Intelligent Transport System 6
Current Status of Project
• Dynamic Status – 19.11.2014
Confidential – © 2013. All rights reserved Mysore - Intelligent Transport System 7
Activities / Components Current Status Date
Spares mobilization of Operations
Fast moving spares Timers, Speakers, Antenna, Hard disks, FAN assembly, NW switch etc – procured 11.11.2014
Spare Units VMU, IBD, 2/4 line display, Network box 10.12.2014
40”/ 55” Display Panel – Samsung has discontinued supplies, service support only
Additional spares Controller cards, display modules being procured 30.11.2014
Current Status of Project
• ‘Cure’ Period Actions - Current Status (continued)
Confidential – © 2013. All rights reserved Mysore - Intelligent Transport System 8
Disaster Recovery and Training
Disaster Recovery
• Disaster Recovery Site Facility in CMC Bangalore Servers, Application components - Tested and Ready for use Will be fully functional within one month of Operational Acceptance
Refresher Training
• Refresher training provided for Crew and operations officials (jointly with KSRTC)
Confidential – © 2013. All rights reserved Mysore - Intelligent Transport System 9
Key Observations from IBI and ICT reports
Action Plan Ahead
Sl No Type of issue Current Status and Action Plan Target Date
1Delivery of 102
Hands--free to depot • Handed over from stores to depot stores Completed
2ETA/ ETD display to be improved during
Operations
• ETA/ ETD demonstrated. • CMC to work closely with KSRTC Operations
Team to improve ETA/ETD during operations 31.03.2015
3 MIS Reports• Few changes suggested by KSRTC and ICT. • Under review with KSRTC MCTD and CO. • To be developed subject to technical feasibility.
31.12.2014
4
ETA Display in LED board and LCD boards are not
matching
• Display boards refreshed every 40 seconds• CMC will work with KSRTC to address the issue
if the mismatch is longer than 40 seconds. 31.12.2014
Confidential – © 2013. All rights reserved Mysore - Intelligent Transport System 10
Team Structure Deployed
CMC Project Delivery Manager
CMC Onsite Operations ManagerData
center Team
(4 persons)Netw
ork Engineer
Server Engineer
Desktop
and PIS
Engineer
Application suppo
rt Engineer
In Bus Equipment Team
(12 persons)
Bannimanta
p Depot team
Kuvempunagar
Depot Team
Satgalli
Depot Team
Vijaya nagar Depot Team
Dispatcher and
Helpdesk team
(6 persons)Dispat
chers
Helpdesk/ EMS
Analysts
KSRTC DC, MCTD
KSRTC ITS Operations team
Confidential – © 2013. All rights reserved Mysore - Intelligent Transport System 11
Operations Team
Depot Support TeamNAME OF THE EMPLOYEE QUALIFICATION
1. AVINASH T N DIPLOMA IN EE
2. SANDEEP C V ITI IN FITTER
3. MALLIKARJUN ITI IN FITTER
4. MADHUSUDAN T MDIPLOMA IN TOOLS AND TECH
5. MAHADEVASWAMY ITI IN FITTER
6. RAVI KIRAN ITI IN FITTER
7. HARISH G N DIPLOMA IN CS
8. VINOD DIPLOMA IN EC
9. SIDDANAIK ITI IN FITTER
10. NANJENDRA ITI IN AUTOMOBILE
11. VARUN ITI IN TURNER
12 Sandeep HD DIPLOMA IN EC
Operations Team details
CCS Team & Application SupportNAME OF THE EMPLOYEE QUALIFICATION DESIGNATION1. CHETHAN DIPLOMA IN EC NETWORK ENGINEER 2. SENTHIL RAJESH ENGINEERING IN EC SERVER ENGINEER3. SHYLESH MSC-IT PIS Display4. CHARAN PATIL B.COM DISPATCHER 5. AKASH ENGINEERING IN EC DISPATCHER6. MAHADEVASWAMY B.B.M DISPATCHER7. PAKSHAK BE APPLICATION SUPPORT8. Amit Anand BE APPLICATION SUPPORT9. Sowmya B BE APPLICATION SUPPORT
Project Management teamLOKESH M ENGINEERING IN EE On-site Operations Manager GVVR Srinivas BE and M-Tech-IT Project Delivery Manager
Off-site : L3 Support / core team
Confidential – © 2013. All rights reserved Mysore - Intelligent Transport System 12
Escalation Matrix
Project Delivery Manager
National Delivery Head
Regional SBU Head
On-site Operations Manager
Confidential – © 2013. All rights reserved Mysore - Intelligent Transport System 13
Operations - Review Mechanism
Review and Reporting • Review and reports
• Review of Issue Logs for various sub-systems • Day-to-day Operational Parameters, Challenges• Schedule changes (Form-4)• Route/ Bus stop additions, deletions and modifications
• Dash Board Review
Monthly Server & Network Availability Rep
Availability_&_Resolution_report_-_Last_3
Confidential – © 2013. All rights reserved Mysore - Intelligent Transport System 14
Support needed from KSRTC
Support needed
Request help in enabling payments
Review and waiver of proposed LD
Reimbursement towards Additional SoW submitted by CMC
• Validation and Deployment of Additional Routes• Design and Rollout of Timer Functionality• De-Installation and reinstallation of In Bus Equipment• Enhancements to Commuter Portal• Enhanced SMS Functionality• Development of Additional MIS Reports• Schedule Creation and updating Database• De-installation and reinstallation of PIS LED boards• Repair of 10 line Display in Karanji lake (Water seepage)• Replacement of damaged VMU screens• Enhancements to GPS/GIS application• Operations and Maintenance support (Dec 2012 to till date)• Marketing and Promotional activities for KSRTC
Power supply to be made available for display boards
Confidential – © 2013. All rights reserved Mysore - Intelligent Transport System 15