Proppant Management CONEXPLO 2014 Presented by: Juan Carlos Bonapace

Transcript of Conexplo proppant management 2014 mendoza

Page 1: Conexplo proppant management 2014 mendoza

Proppant Management

CONEXPLO 2014

Presented by: Juan Carlos Bonapace

Page 2: Conexplo proppant management 2014 mendoza

© 2014 HALLIBURTON. ALL RIGHTS RESERVED. 2

2010-11

• 1st Los Molles Shale Completion

• 1st Los Molles Shale Hztal Well Completion

• 1st Cacheuta Shale Completion (Cuyo Basin)

2012

• 1st Vaca Muerta Shale Completion & Dual Micro-Seismic

• 1st Vaca Muerta Shale Hztal Well Completion & Micro-Seismic

2013

• 1st Vaca Muerta Shale Integrated Project

• 1st Vaca Muerta Continous Multistate Completion (AccesFrac)

• 1st Vaca Muerta Hztal Gas Well Completion

• 1st Vaca Muerta PinPoint Completion (CobraMax)

2014

• 1st D-129 Shale Completion (GSJ Basin)

• 1st Vaca Muerta MultiPAD Completion

• 1st Agrio Shale Completion

• 1st Vaca Muerta Hztal Completion 100% Bulk proppant transportation

• 1st Vaca Muerta Hztal Completion 100% Proppant Managment

SHELL

TOTAL

CAPEX

YPF

G&P

HALLIBURTON Experiences

Page 3: Conexplo proppant management 2014 mendoza

© 2014 HALLIBURTON. ALL RIGHTS RESERVED. 3

Unconventional Resources

• Type of Treatment in Unconventional

– Hybrid Frac – (Slickwater, Linear Gel and Crosslinked Fluid)

– 50 to 75% Low Visc (Slickwater, Linear Gel)

– Multiple mesh proppant

• Tight Gas Wells

– Vertical / Horizontal

• Stages-Thickness: 7 (500m) / 7 (700m)

• Water: 3,200m3 / 2,500m3

• Proppant: 15,000 sks / 8,500 sks

• Shale Oil & Gas Wells

– Vertical / Horizontal

• Stages-Thickness: 4 to 6 (170 to 250m) / 6 to 14 (1000m)

• Water: 5,000 to 10,000m3 / 10,000 to 15,000m3

• Proppant: 13,000 to 23,000 sks / 25,000 to 55,000 sks

Page 4: Conexplo proppant management 2014 mendoza

© 2014 HALLIBURTON. ALL RIGHTS RESERVED. 4

ARGENTINA Shale Plays

** Halliburton Data Base

Page 5: Conexplo proppant management 2014 mendoza

© 2014 HALLIBURTON. ALL RIGHTS RESERVED. 5

Vaca Muerta Shale Plays

** Halliburton Data Base

Page 6: Conexplo proppant management 2014 mendoza

© 2014 HALLIBURTON. ALL RIGHTS RESERVED. 6

Proppant Importation• Vessel transport• BsAs port

• Ocean Containers

Proppant Transport• Road (truck)• BsAs to Nqn

Proppant Storage• Large storage sites• Excessive manipulation

• Big Bag

Manual loading• Handling on location• Additional personnel

• Unsafety

Transport from Storage toWellsite

• High traffic of materials• Overcrowding

Storage at Wellsite• Space at wellsite• Additional resources

• Forklifts, cranes

Current Proppant Logistic – Manual Loading

Page 7: Conexplo proppant management 2014 mendoza

© 2014 HALLIBURTON. ALL RIGHTS RESERVED. 7

Proppant Importation• Break Bulk Vessel• Bahia Blanca port

• Up to 10,000 Ton

Proppant Transport• Multiple Options• Rail / Road (truck)

• B.Blanca to VMuerta

Big Bag to Bulk• Improve load velocity• Option to load

Truck (bulk) or Plant

Plant – Big Storage• High Sotrage capacity• 1,800 to 3,600 Ton

• Multiple mesh

Bulk Transport to Wellsite• Truck (30 Ton each)• Improve velocity (time)

Bulk Loading• Efficient discharge• Reduce spaces and additional

resources• Safety

Future Proppant Logistic - Bulk Loading

Page 8: Conexplo proppant management 2014 mendoza

© 2014 HALLIBURTON. ALL RIGHTS RESERVED. 8

• New Proppant Storage Plant - (1st Plant outside USA)

– Increase Proppant Storage

– Improve Proppant delivery

– Total Surface: 3,500m2

• Warehouse 650m2

• Capacity: 1,200 Ton (2,650,000 lb)

– 1st phase: 3 silos

• Capacity: 1,800 Ton (3,900,000 lb)

– 2nd phase – Expansion / Q1-2016

• Capacity: 3,600 Ton (7,800,000 lb)

Proppant Management - Storage

Page 9: Conexplo proppant management 2014 mendoza

© 2014 HALLIBURTON. ALL RIGHTS RESERVED. 9

Proppant Management - Transloading

• Transloading Option

– Satellital Storage Center

• Relocable

• Near to well site

• Mesh (lower percentages)

• Improve logistic time and cost

Page 10: Conexplo proppant management 2014 mendoza

© 2014 HALLIBURTON. ALL RIGHTS RESERVED. 10

• Bulk Transport & Loading

– Improve Proppant Transport and Loading

• Reduction time and cost

• safety and efficiency

– 1st phase: 8 Truck

• Capacity: 240Ton (530,000 lb)

– 2nd phase: 6 Truck / Q2-2015

• Capacity: 180Ton (400,000 lb)

Proppant Management - Bulk Transport, Loading and Wellsite

• Wellsite Storage

– Increase storage capacity (wellsite)

• Efficiency

– 4 Storage Unit (M.Mover) / Q2-2015

• Capacity: 1,000,000 lb

Page 11: Conexplo proppant management 2014 mendoza

© 2014 HALLIBURTON. ALL RIGHTS RESERVED. 11

Case Histories - Proppant Management

• 2 Hztal well: 13 Frac Stages

• Total Proppant. 56,500 sks• 3 Proppant Mesh

• 14 bulk transport (> 90 trips)• Plant and Satellital Storage Center

• Hztal well: 10 Frac Stages

• Total Proppant. 55,000 sks• 3 Proppant Mesh

• 14 bulk transport (> 85 trips)• Central and Satellital Storage Center

Page 12: Conexplo proppant management 2014 mendoza

© 2014 HALLIBURTON. ALL RIGHTS RESERVED. 12

2011/2013 Logistic

Proppant Management

2014 Logistic

Page 13: Conexplo proppant management 2014 mendoza

© 2014 HALLIBURTON. ALL RIGHTS RESERVED. 13

www.halliburton.com/

[email protected]

Juan Carlos BonapaceTechnology Manager Neuquén District

(Unconventional Tech Team)

Phone: +(54-299) (449 1100) Ext 1127

Fax: +(54-299) (449 1145)Cell: +(54-9-299) (4515952)

For more information