Condor Technology Solutions, Inc. Grace RFTS Application Extension Phase.

16
Condor Technology Solutions, Condor Technology Solutions, Inc. Inc. Grace RFTS Application Extension Phase

Transcript of Condor Technology Solutions, Inc. Grace RFTS Application Extension Phase.

Page 1: Condor Technology Solutions, Inc. Grace RFTS Application Extension Phase.

Condor Technology Solutions, Inc.Condor Technology Solutions, Inc.

Grace RFTS Application

Extension Phase

Page 2: Condor Technology Solutions, Inc. Grace RFTS Application Extension Phase.

Presentation Overview

• Review of RFTS Project completed

• Successes and Work to still be done

• Proposal & Requirements review for RFTS Extension Phase

Meeting Agenda

Page 3: Condor Technology Solutions, Inc. Grace RFTS Application Extension Phase.

RFTS Original Goals

Business Objectives Assess and become acclimated to the current RFTS System -SUCCESS Complete Development on the new RFTS System - SUCCESS Compile Technical Documentation - SUCCESS Production Implementation - POSTPONEDCritical Success Factors Preservation of historical data going back to 1985 - SUCCESS Maintain connections to “Packages” database - SUCCESS Maintain references and connections to Word documents - SUCCESS

Project Review

Page 4: Condor Technology Solutions, Inc. Grace RFTS Application Extension Phase.

RFTS Project Breakdown

Prototype Modules

System Arch Definition

System App Design

Business Component Process Definition

Data Quality

Create Loading Plan

Code/Test SQL

Code & Test Modules

Create UAT Plans

Standards & Procedures

Create DB

System TestUser

Acceptance Test

Part 1: Evaluation of Code and Business Rules

Part 2: Analysis and Data Transfer Prep.

Part 3: Testing

Create Test Data

System Implementa

tion

Post-Implementa

tion

Part 4: Implementation

Transfer Data

Project Review

Page 5: Condor Technology Solutions, Inc. Grace RFTS Application Extension Phase.

Deliverables

• Part I - Evaluation of Code and Documentation of Business Rules – System Application Design Document– Business Component Flow Diagram– Business Component Process Definition

Document

• Based on these deliverables, Grace decided that there were additional system requirements

Project Review

Page 6: Condor Technology Solutions, Inc. Grace RFTS Application Extension Phase.

Deliverables

• Part II - · Technical Documentation and Historical Data Transfer Analysis– Document representing the physical data model– Data Quality Document– Loading Plan for Historical Data

Project Review

Page 7: Condor Technology Solutions, Inc. Grace RFTS Application Extension Phase.

Deliverables

• Part III - Testing– Representative Test Data– Complete and Fully Tested System

• Unit testing - OK

• System testing - OK

• User Acceptance - New Requirements!

Project Review

Page 8: Condor Technology Solutions, Inc. Grace RFTS Application Extension Phase.

RFTS Project Successes

• Documented Business Requirements

• Documented System Technical Design

• Analyzed and Prepared for Transfer of Historical Data

• Tested Application

Project Evaluation

Page 9: Condor Technology Solutions, Inc. Grace RFTS Application Extension Phase.

Closer Look at

• Some ordinary testing ‘bugs’ occurred during User Acceptance Testing– example: the cut & paste tool bar

missing some places

• End Users were quite dissatisfied with some of the application function.

• Decision was made to not complete the testing phase as system redesign was needed

User Acceptance Testing

Project Evaluation

Page 10: Condor Technology Solutions, Inc. Grace RFTS Application Extension Phase.

Work Still to be done

• Requirements - Do we have all the requirements defined ???

• Best way to determine all requirements for extension phase– Formal Facilitated Requirements Session – Repeat User Acceptance Testing

Project Evaluation

Page 11: Condor Technology Solutions, Inc. Grace RFTS Application Extension Phase.

Requirements Analysis and Development

• Data Modeling & Create Database – Data model ERA analysis with Grace team. Change or create data model solution.

• Test SQL, Code & Test Module – Code and test changes to forms, queries, modules and event procedures. Documents the problems and solutions and then apply selected solution.

• Data Quality – Identify and document changed tables and relationships. Map new table dependencies.

• Update Loading Plan – Prepare a solution by verifying key values. Develop and test queries for data transfer. Update documentation.

• Documentation – Update documentation on System Application Design, Business Component Process Definition, Physical Data Model, Data Quality Document and Loading Plan.

Proposal

Page 12: Condor Technology Solutions, Inc. Grace RFTS Application Extension Phase.

Testing

• System Testing – Condor will run user scenarios on the development system. Tests will be based on the new requirements. Condor will document problems and recommend solutions.

• Regression Testing - Condor will run user scenarios on the development system to test the existing functionality and confirm that errors were not introduced during modification. Tests will be based on a system test plan. Condor will document problems and recommend solutions.

Proposal

Page 13: Condor Technology Solutions, Inc. Grace RFTS Application Extension Phase.

Testing

• User Acceptance Testing – Your organization will perform repeat User Acceptance Testing. Tests are built from the requirements specified in the Business Component Process Definition Document. This is a period of time for the user to test the system and verify that all requirements were met. The Engagement Manager will document and prioritize issues. The engagement team will be available to resolve mission critical issues.

Proposal

Page 14: Condor Technology Solutions, Inc. Grace RFTS Application Extension Phase.

Data Transfer and Implementation

• Data Transfer – Condor will complete loading and verification of historical data according to the loading plan.

• System Implementation – The RFTS System will be implemented on the target platform. Condor will provide support before going into production. Condor will turn over and obtain sign-off for approval of the system.

Proposal

Page 15: Condor Technology Solutions, Inc. Grace RFTS Application Extension Phase.

Data Transfer and Implementation

• Post Implementation Support – GCP’s internal IT Department will address all hardware and infrastructure issues. Condor fully expects all mission critical software issues will be resolved during testing and implementation. Should a mission critical software issue be discovered post implementation Condor will assign highest priority to resolving this issue in a timely manner on a time and materials basis. Non critical software issues can be addressed in subsequent phases of the project.

Proposal

Page 16: Condor Technology Solutions, Inc. Grace RFTS Application Extension Phase.

Partnering for Success