Concrete Testing 1

download Concrete Testing 1

of 12

Transcript of Concrete Testing 1

  • 7/25/2019 Concrete Testing 1

    1/12

    A practical guide for site personnel

    Site sampling andtesting of concrete

    Cubes have a vital role totest that the concretestrength meets thespecification requirement.

    However, the cube resultswill be meaningless unlessthe sampling and testingprocedures given in this

    booklet are followedcarefully.

    PARTOF THE MINERAL PRODUCTS ASSOCIATION

    Sampling amended booklet amended:Layout 1 4/8/09 14:14 Page 1

  • 7/25/2019 Concrete Testing 1

    2/12

    This practical guide for site personnel covers:

    Sampling,

    The slump test

    The flow test

    Making cubes

    Storing cubesit also gives guidance toSafety

    This practical guide for site personnel isintended to be used in conjunction withthe poster Site sampling and testingconcrete

    Sampling amended booklet amended:Layout 1 4/8/09 14:14 Page 2

  • 7/25/2019 Concrete Testing 1

    3/12

    SamplingThe standard compositesample

    BSEN12350-1

    To ensure it is representative of thewhole load a standard sampleconsists of scoopfuls taken from

    four different parts of the load andcollected in buckets.

    Scoopfuls must be taken throughthe moving stream, as the load isdischarged, sampling the wholewidth and depth not just the toppart. The size of sample taken shouldbe 11/2times the estimated volume

    required for testing.

    Slump test - 6 litresFlow test - 41/2 litresCube test - 1 litre for each cube

    Let very first concrete go

    Take a scoopful from part 1Take a scoopful from part 2

    Take a scoopful from part 3Take a scoopful from part 4Let the last concrete go

    Complete a sampling certificate andrecord which sampling method wasused.

    The alternative spotsample

    BS EN 206-1:2000,clause 5.4.1

    Do not use this method to makecubes

    For an early check on the

    consistence of concrete delivered ina truck mixer, this alternative methodof spot sampling from the initialdischarge may be used. Additionaltolerances will be applicable forconcrete sampled by this method.

    Scoopfuls must be taken through themoving stream sampling the whole

    width and depth.

    Let very first concrete go

    Take six scoopfuls from the next0.3m3

    Take six scoopfuls after the first0.3m3 has been discharged.

    1

    Sampling amended booklet amended:Layout 1 4/8/09 14:14 Page 3

  • 7/25/2019 Concrete Testing 1

    4/12

    The slump test BS EN12350-2Step 1

    Empty the sampling buckets ontothe mixing tray

    Scrape each bucket clean

    Step 2 Thoroughly remix the sample,shovelling into a heap Turn the heap over to formanother

    Do this three timesStep 3 Flatten the finalheap by repeated-ly digging-in the

    shovel vertically Lift the shovelclear each time

    Step 4 Ensure the slump cone and baseplate are clean and damp

    Place the metal plate on solidlevel base away from vibration or

    other disturbance

    Place the cone on the plate andstand on the foot-pieces

    Step 5 Fill the cone in three equal depthlayers

    Use the standardslump rod

    Rod each layer25 times

    Spread the blowsevenly Heap theconcrete above thetop of the cone before rodding thethird layer over the area

    Make sure the rod just penetratesthe layer below

    Step 6 Top up if necessary Use the rodwith a sawingand rollingmotion to strikethe concretelevel with the

    top of the coneStep 7

    Carefullyclean off spillagefrom sides and base plate whilstmaintaining foot pressure

    2

    Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 4

  • 7/25/2019 Concrete Testing 1

    5/12

    Step 8 Carefullyliftthe cone straightup and clear, to acount of between2 and 5 seconds

    Step 9

    Lay the rodacross theupturned slumpcone

    Measurethe distancebetween theunderside of

    the rod and the highest point of theconcrete the true slump

    Record the distance to thenearest 10mm

    Check and record the kind ofslump

    If the slump isnt true, take anew sample and repeat the test

    If the second slump isnt true,

    get advice

    Complete the sampling andtesting certificates

    There are threekinds of slump

    TrueShear

    Collapse

    You will need this equipment(always clean and dry the equipment

    after use)

    Small scoop

    Slump rod

    Square-mouthed shovel

    Mixing tray

    Buckets or wheelbarrow

    Sampling and testing certificates

    Steel rule

    Damp cloth

    Sampling scoop Slump cone and rigid metal plate

    3

    Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 5

  • 7/25/2019 Concrete Testing 1

    6/12

    The flow test BS EN12350-5First find a suitable location for aflow table. It must be placed on afirm, flat and level surface. It may benecessary to prepare an area for thetable.

    Step 1

    Empty the sampling buckets onto

    the mixing tray

    Scrape each bucket cleanStep 2

    Thoroughly remix the sample asdescribed for the slump test

    Step 3

    Ensure themould and tableare clean anddamp

    Place themould on thecentre of thetable and stand on the foot-pieces

    Fill the mould in two layers,tamping each layer ten times withthe tamping bar

    If necessary add more concrete tofill the top layer

    Use the tamping bar to strike thetop layer level with the top of themould

    Step 4

    Carefully clean off spillage fromaround the mould and table top

    Step 5

    Wait 30 seconds from striking off

    Carefully lift the

    mould straight upand clear to acount of between3 and 6 seconds

    Step 6

    Stabilise the flow table bystanding on the toe board at the

    front of the table

    Step 7

    Slowly lift the table top by thehandle until it reaches the upperstop

    Allow the table to fall freely Repeat this cycle to give a total of15 drops

    Each cycle should take about4 seconds

    4

    Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 6

  • 7/25/2019 Concrete Testing 1

    7/12

    Step 8

    Measure the largest dimension ofconcrete spread in two directions,parallel to the table edges

    Record the flow value as d1 + d2divided by 2

    Report any segregation which mayhave occurred around the sampleedge

    Complete the sampling andtesting certificates

    You will need this equipment(always clean and dry the equipment

    after use)

    Sampling scoop

    Small scoop

    Damp cloth

    Buckets or wheelbarrow

    Hardwood tamping bar

    Square mouth shovel

    Mixing tray

    Flow table

    700mm rule

    Sampling and testing

    certificates

    5

    Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 7

  • 7/25/2019 Concrete Testing 1

    8/12

    Making cubes BS EN12390-2Collect a composite sample to thestandard method described above.Concrete sampled using thealternative spot method must not beused to make cubes.

    Step 1

    Check that

    the mouldsare clean andlightly oiledwith all boltstightened sothat therewill be no leakage

    Ensure that the correct halves ofthe moulds are used and that thecorner lifting pins are correctlylocated

    Thoroughly remix the sample asdescribed for theslump test

    Step 2

    Fill the mouldwith concretein 50mm layersusing the tampingbar, compact theconcrete with nofewer than 25 tamps for each of thetwo layers in a 100mm mould and

    no fewer than 35 tamps for for eachof the three layers in a 150mmmould

    For very high workability concreteyou may not need the minimumnumber of tamps

    Step 3

    After tampingof each layer, tapthe sides of themould with thehide hammer untillarge bubbles ofair cease toappear on the surface and the holesleft by the tamping bar are closed

    Step 4

    Remove surplus concrete andsmooth over with a float

    Wipe clean themould edges

    Number themoulds foridentification andrecord details andimmediately placewhere they are tobe storedovernight

    6

    Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 8

  • 7/25/2019 Concrete Testing 1

    9/12

    Step 5

    Cover each mould with a dampcloth and plastic sheet

    Store inside at room temperature(15-250C) e.g. on top of the curingtank

    Protect the cube moulds at alltimes from high and low

    temperature (especially sub-zerotemperatures) and drying winds

    Complete the sampling and cubemaking certificates

    You will need this equipment(always clean and dry the equipment

    after use)

    Sampling scoop

    Small scoop

    Damp cloth and plastic sheeting

    Buckets or wheelbarrow

    Tamping bar

    Brush and mould oil

    Curing tank

    Hide hammer

    Maximum/minimum thermometer

    Square-mouthed shovel

    Felt tip pen or crayon

    Cube moulds Spanner

    Mixing tray

    Damp cloth

    Sampling. cube making and storagecertificates

    7

    Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 9

  • 7/25/2019 Concrete Testing 1

    10/12

    Storing cubes BS EN12390-2Having stored the moulds atbetween 15_250C the cubes shouldbe removed from the moulds noearlier than 16 hours and no laterthan 72 hours after casting.

    Step 1

    Record the maximum/minimum

    overnight storage temperatures onthe certificate

    Step 2

    Slacken all nuts Part the sides of the mould,tapping gentlywith the hide

    hammer Lift offcarefully

    Remembernew cubes areeasily damagedunless handled carefully

    Step 3 Mark each cube with itsidentification number on two of itscast sides

    Step 4 Place thecubes in thecuring tankwith the watertemperaturecontrolled at200C20C andthe cubes covered by water

    Step 5

    Clean and reassemble the moulds Make sure the power supply is notswitched off day or night

    Check the temperature range dailyusing the maximum/minimum

    thermometer Keep a record of the readings

    Please note

    If you have no curing tank,transport the cubes to the testinglaboratory within the 72 hour period

    For despatch to the testlaboratory, wrap the wet cubes in

    damp cloths, and then plastic bagsand pack in trays

    Attach the certificates forsampling, testing, cube making andstorage to the package along withthe order for testing

    8

    Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 10

  • 7/25/2019 Concrete Testing 1

    11/12

    The first rule of working withconcrete is to be protected.

    Ensure that the personnel arewearing adequate safety

    equipment.

    If fresh, wet concrete touches

    the skin, it can cause cementburns - some of which dontcause pain or dermatitis.

    The longer the skin is in contactwith the concrete, the worse theinjury will be. So it makes senseto protect yourself by wearingsafety goggles, waterproof

    gloves, a sturdy jacket,waterproof trousers and long

    boots.

    If wet concrete does contactyour skin, wash immediately andthoroughly with clean water.And if your eyes are affected, seek

    medical help immediately.

    Remove and wash anyprotective clothes or boots thatbecome impregnated with freshconcrete, but making sure youwash yourself first.

    The water in the curing tank ishighly alkaline so ensure thatgloves are used when handlingcubes in the tank.

    Fresh concrete is heavy, with abarrow load weighing over 100kg.

    So carrying just a small volumemay cause physical injury.

    Therefore organise enough help sothat you can place, compact andfinish the work before it setswithout straining yourself.

    Safety

    9

    Safety spectaclesor goggles

    Wellington boots

    Always wearlong trousers

    Protect your handsat all times withwaterproof gloves

    If you cant avoid kneelingin concrete, mortar orscreed, wear knee pads oruse an impervious mat

    Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 11

  • 7/25/2019 Concrete Testing 1

    12/12

    The other practical guide for site personnel inthis series is:Placing, compacting and curing concrete.

    TCC/03/42

    There are also A2 size posters of each of these

    publications.Placing, compacting and curing concrete.

    TCC/03/41

    Site sampling and testing of concrete.

    TCC/03/39

    All advice or information from Mineral Products Association is intended for use inthe UK only by those who will evaluate the significance and limitations of its con-tents and take responsibility for its use and application. No liability(including that for negligence) for any loss resulting from such advice orinformation is accepted by Mineral Products Association or its subcontractors,suppliers or advisors. Readers should note that the publications from MineralProducts Association are subject to revision from time to time and shouldtherefore ensure that they are in possession of the latest version.

    Ref:TCC/03/40ISBN 978-1-904818-74-8Published May 2009

    Mineral Products Association

    Produced and printed byThe Book on the Wall Company.

    Published by

    Mineral Products Association

    Gillingham House,

    38-44 Gillingham Street,

    London SW1V 1HU

    Tel: +44(0) 20 7963 8000

    www.mineralproducts.org

    Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 12