Concrete Testing 1
-
Upload
jhe-inibam -
Category
Documents
-
view
231 -
download
1
Transcript of Concrete Testing 1
-
7/25/2019 Concrete Testing 1
1/12
A practical guide for site personnel
Site sampling andtesting of concrete
Cubes have a vital role totest that the concretestrength meets thespecification requirement.
However, the cube resultswill be meaningless unlessthe sampling and testingprocedures given in this
booklet are followedcarefully.
PARTOF THE MINERAL PRODUCTS ASSOCIATION
Sampling amended booklet amended:Layout 1 4/8/09 14:14 Page 1
-
7/25/2019 Concrete Testing 1
2/12
This practical guide for site personnel covers:
Sampling,
The slump test
The flow test
Making cubes
Storing cubesit also gives guidance toSafety
This practical guide for site personnel isintended to be used in conjunction withthe poster Site sampling and testingconcrete
Sampling amended booklet amended:Layout 1 4/8/09 14:14 Page 2
-
7/25/2019 Concrete Testing 1
3/12
SamplingThe standard compositesample
BSEN12350-1
To ensure it is representative of thewhole load a standard sampleconsists of scoopfuls taken from
four different parts of the load andcollected in buckets.
Scoopfuls must be taken throughthe moving stream, as the load isdischarged, sampling the wholewidth and depth not just the toppart. The size of sample taken shouldbe 11/2times the estimated volume
required for testing.
Slump test - 6 litresFlow test - 41/2 litresCube test - 1 litre for each cube
Let very first concrete go
Take a scoopful from part 1Take a scoopful from part 2
Take a scoopful from part 3Take a scoopful from part 4Let the last concrete go
Complete a sampling certificate andrecord which sampling method wasused.
The alternative spotsample
BS EN 206-1:2000,clause 5.4.1
Do not use this method to makecubes
For an early check on the
consistence of concrete delivered ina truck mixer, this alternative methodof spot sampling from the initialdischarge may be used. Additionaltolerances will be applicable forconcrete sampled by this method.
Scoopfuls must be taken through themoving stream sampling the whole
width and depth.
Let very first concrete go
Take six scoopfuls from the next0.3m3
Take six scoopfuls after the first0.3m3 has been discharged.
1
Sampling amended booklet amended:Layout 1 4/8/09 14:14 Page 3
-
7/25/2019 Concrete Testing 1
4/12
The slump test BS EN12350-2Step 1
Empty the sampling buckets ontothe mixing tray
Scrape each bucket clean
Step 2 Thoroughly remix the sample,shovelling into a heap Turn the heap over to formanother
Do this three timesStep 3 Flatten the finalheap by repeated-ly digging-in the
shovel vertically Lift the shovelclear each time
Step 4 Ensure the slump cone and baseplate are clean and damp
Place the metal plate on solidlevel base away from vibration or
other disturbance
Place the cone on the plate andstand on the foot-pieces
Step 5 Fill the cone in three equal depthlayers
Use the standardslump rod
Rod each layer25 times
Spread the blowsevenly Heap theconcrete above thetop of the cone before rodding thethird layer over the area
Make sure the rod just penetratesthe layer below
Step 6 Top up if necessary Use the rodwith a sawingand rollingmotion to strikethe concretelevel with the
top of the coneStep 7
Carefullyclean off spillagefrom sides and base plate whilstmaintaining foot pressure
2
Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 4
-
7/25/2019 Concrete Testing 1
5/12
Step 8 Carefullyliftthe cone straightup and clear, to acount of between2 and 5 seconds
Step 9
Lay the rodacross theupturned slumpcone
Measurethe distancebetween theunderside of
the rod and the highest point of theconcrete the true slump
Record the distance to thenearest 10mm
Check and record the kind ofslump
If the slump isnt true, take anew sample and repeat the test
If the second slump isnt true,
get advice
Complete the sampling andtesting certificates
There are threekinds of slump
TrueShear
Collapse
You will need this equipment(always clean and dry the equipment
after use)
Small scoop
Slump rod
Square-mouthed shovel
Mixing tray
Buckets or wheelbarrow
Sampling and testing certificates
Steel rule
Damp cloth
Sampling scoop Slump cone and rigid metal plate
3
Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 5
-
7/25/2019 Concrete Testing 1
6/12
The flow test BS EN12350-5First find a suitable location for aflow table. It must be placed on afirm, flat and level surface. It may benecessary to prepare an area for thetable.
Step 1
Empty the sampling buckets onto
the mixing tray
Scrape each bucket cleanStep 2
Thoroughly remix the sample asdescribed for the slump test
Step 3
Ensure themould and tableare clean anddamp
Place themould on thecentre of thetable and stand on the foot-pieces
Fill the mould in two layers,tamping each layer ten times withthe tamping bar
If necessary add more concrete tofill the top layer
Use the tamping bar to strike thetop layer level with the top of themould
Step 4
Carefully clean off spillage fromaround the mould and table top
Step 5
Wait 30 seconds from striking off
Carefully lift the
mould straight upand clear to acount of between3 and 6 seconds
Step 6
Stabilise the flow table bystanding on the toe board at the
front of the table
Step 7
Slowly lift the table top by thehandle until it reaches the upperstop
Allow the table to fall freely Repeat this cycle to give a total of15 drops
Each cycle should take about4 seconds
4
Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 6
-
7/25/2019 Concrete Testing 1
7/12
Step 8
Measure the largest dimension ofconcrete spread in two directions,parallel to the table edges
Record the flow value as d1 + d2divided by 2
Report any segregation which mayhave occurred around the sampleedge
Complete the sampling andtesting certificates
You will need this equipment(always clean and dry the equipment
after use)
Sampling scoop
Small scoop
Damp cloth
Buckets or wheelbarrow
Hardwood tamping bar
Square mouth shovel
Mixing tray
Flow table
700mm rule
Sampling and testing
certificates
5
Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 7
-
7/25/2019 Concrete Testing 1
8/12
Making cubes BS EN12390-2Collect a composite sample to thestandard method described above.Concrete sampled using thealternative spot method must not beused to make cubes.
Step 1
Check that
the mouldsare clean andlightly oiledwith all boltstightened sothat therewill be no leakage
Ensure that the correct halves ofthe moulds are used and that thecorner lifting pins are correctlylocated
Thoroughly remix the sample asdescribed for theslump test
Step 2
Fill the mouldwith concretein 50mm layersusing the tampingbar, compact theconcrete with nofewer than 25 tamps for each of thetwo layers in a 100mm mould and
no fewer than 35 tamps for for eachof the three layers in a 150mmmould
For very high workability concreteyou may not need the minimumnumber of tamps
Step 3
After tampingof each layer, tapthe sides of themould with thehide hammer untillarge bubbles ofair cease toappear on the surface and the holesleft by the tamping bar are closed
Step 4
Remove surplus concrete andsmooth over with a float
Wipe clean themould edges
Number themoulds foridentification andrecord details andimmediately placewhere they are tobe storedovernight
6
Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 8
-
7/25/2019 Concrete Testing 1
9/12
Step 5
Cover each mould with a dampcloth and plastic sheet
Store inside at room temperature(15-250C) e.g. on top of the curingtank
Protect the cube moulds at alltimes from high and low
temperature (especially sub-zerotemperatures) and drying winds
Complete the sampling and cubemaking certificates
You will need this equipment(always clean and dry the equipment
after use)
Sampling scoop
Small scoop
Damp cloth and plastic sheeting
Buckets or wheelbarrow
Tamping bar
Brush and mould oil
Curing tank
Hide hammer
Maximum/minimum thermometer
Square-mouthed shovel
Felt tip pen or crayon
Cube moulds Spanner
Mixing tray
Damp cloth
Sampling. cube making and storagecertificates
7
Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 9
-
7/25/2019 Concrete Testing 1
10/12
Storing cubes BS EN12390-2Having stored the moulds atbetween 15_250C the cubes shouldbe removed from the moulds noearlier than 16 hours and no laterthan 72 hours after casting.
Step 1
Record the maximum/minimum
overnight storage temperatures onthe certificate
Step 2
Slacken all nuts Part the sides of the mould,tapping gentlywith the hide
hammer Lift offcarefully
Remembernew cubes areeasily damagedunless handled carefully
Step 3 Mark each cube with itsidentification number on two of itscast sides
Step 4 Place thecubes in thecuring tankwith the watertemperaturecontrolled at200C20C andthe cubes covered by water
Step 5
Clean and reassemble the moulds Make sure the power supply is notswitched off day or night
Check the temperature range dailyusing the maximum/minimum
thermometer Keep a record of the readings
Please note
If you have no curing tank,transport the cubes to the testinglaboratory within the 72 hour period
For despatch to the testlaboratory, wrap the wet cubes in
damp cloths, and then plastic bagsand pack in trays
Attach the certificates forsampling, testing, cube making andstorage to the package along withthe order for testing
8
Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 10
-
7/25/2019 Concrete Testing 1
11/12
The first rule of working withconcrete is to be protected.
Ensure that the personnel arewearing adequate safety
equipment.
If fresh, wet concrete touches
the skin, it can cause cementburns - some of which dontcause pain or dermatitis.
The longer the skin is in contactwith the concrete, the worse theinjury will be. So it makes senseto protect yourself by wearingsafety goggles, waterproof
gloves, a sturdy jacket,waterproof trousers and long
boots.
If wet concrete does contactyour skin, wash immediately andthoroughly with clean water.And if your eyes are affected, seek
medical help immediately.
Remove and wash anyprotective clothes or boots thatbecome impregnated with freshconcrete, but making sure youwash yourself first.
The water in the curing tank ishighly alkaline so ensure thatgloves are used when handlingcubes in the tank.
Fresh concrete is heavy, with abarrow load weighing over 100kg.
So carrying just a small volumemay cause physical injury.
Therefore organise enough help sothat you can place, compact andfinish the work before it setswithout straining yourself.
Safety
9
Safety spectaclesor goggles
Wellington boots
Always wearlong trousers
Protect your handsat all times withwaterproof gloves
If you cant avoid kneelingin concrete, mortar orscreed, wear knee pads oruse an impervious mat
Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 11
-
7/25/2019 Concrete Testing 1
12/12
The other practical guide for site personnel inthis series is:Placing, compacting and curing concrete.
TCC/03/42
There are also A2 size posters of each of these
publications.Placing, compacting and curing concrete.
TCC/03/41
Site sampling and testing of concrete.
TCC/03/39
All advice or information from Mineral Products Association is intended for use inthe UK only by those who will evaluate the significance and limitations of its con-tents and take responsibility for its use and application. No liability(including that for negligence) for any loss resulting from such advice orinformation is accepted by Mineral Products Association or its subcontractors,suppliers or advisors. Readers should note that the publications from MineralProducts Association are subject to revision from time to time and shouldtherefore ensure that they are in possession of the latest version.
Ref:TCC/03/40ISBN 978-1-904818-74-8Published May 2009
Mineral Products Association
Produced and printed byThe Book on the Wall Company.
Published by
Mineral Products Association
Gillingham House,
38-44 Gillingham Street,
London SW1V 1HU
Tel: +44(0) 20 7963 8000
www.mineralproducts.org
Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 12