CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group...
Transcript of CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group...
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN
INTRODUCTION:
BACKGROUND & PURPOSE OF THE PROJECT:
The proposed group housing project “Affordable Group Housing (Expansion)” is coming up at
Khasra nos: 799, 800, 805, 808, 811, 812, 64, 65, 72, 73, 81, 82, 83, 84, 85, 86, Village Thikaria &
Bagru Khurd, Tehsil Sanganer, District Jaipur, Rajasthan.
Environmental Clearance for the existing project was granted vide letter no. F1 (4)/SEIAA/ SEAC-
Raj/ Sectt./ Project/ Cat. 8 (a)B/ (379)/ 08-09 dated 09.09.2011.
Details of proposed expansion are given as:
Total Plot Area
Plot Area Existing (Sq.m.) Proposed (Sq.m.) Total (Sq.m.)
52% 12896.00 1,000.00 13,896.00
48% 11904.00 500.00 12,404.00
Total 24,800 1,500 26,300.00
Total Built up Area
52% 16,729.52 - 16,729.52
48% 27,955.00 19,768.6 47,723.60
Total 44,684.52 19,768.6 64,453.12
Ground Coverage
52% 4,075.63 Nil 4,075.63 (15.50%)
48% 2,181.13 1,366.25 3,547.38 (13.49%)
Total 6,256.76 1,366.25 7,623.01 (28.99%)
Max. Height
52% 12.10 m. --
48% 42.5 m. 47.5 m.
BUILT UP AREA BREAKUP (48%):
Sr. No. Floors Gross Built up Area (sq. m.) FAR Area (sq. m.)
1. Upper Basement 6,518.30 Nil
2. Stilt Floor 3,748.57 14.40
3. Ground Floor 3,547.38 2,855.11
4. First Floor 3,547.38 2,855.11
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
5. Second Floor 3,547.38 2,855.11
6. Third Floor 3,547.38 2,855.11
7. Fourth Floor 3,547.38 2,855.11
8. Fifth Floor 3,547.38 2,855.11
9. Sixth Floor 3,547.38 2,855.11
10. Seventh Floor 3,547.38 2,855.11
11. Eight Floor 3,547.38 2,855.11
12. Ninth Floor 1,637.61 1,310.03
13. Tenth Floor 1,637.61 1,310.03
14. Eleventh Floor 1,637.61 1,310.03
15. Mumty, Lift Lobby 308.74 Nil
16. Water tank, Machine Room 308.74 Nil
Total 47,723.60 29,640.48
PROJECT FACILITIES:
Details of Flats
Particulars 1 BHK 2 BHK 3 BHK Total
52% 352 48 - 400
48% 27 183 186 396
PARKING DETAILS (TOTAL):
Parking required : 665 ECU
(existing: 466 ECU; expansion: 199 ECU)
Parking provided : 704 ECU
(existing: 469 ECU; expansion: 235 ECU)
Parking Calculations:
FAR area : 29,640.48 sq. m.
ECU required : 1 ECU per 75 sq. m. of FAR area + 25 % Visitors Parking
: 413 + 103
Total ECU required : 516 ECU
Total ECU Provided : 551 ECU
Details of parking provided:
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
S.
No.
Details Cars Two Wheelers Total
ECU
Basis of
ECS
Total area
required
Total area
provided
1. Open 162 - 162 23 sq. m. 3,726 sq. m. 3,726 sq. m.
2. Stilt 90 66 (22 ECU) 112 28 sq. m. 3,136 sq. m. 3,136 sq. m.
3. Basement 209 204 (68 ECU) 277 32 sq. m. 8,864 sq. m. 8,864 sq. m.
Total 461 270 (90 ECU) 551 15,726 sq. m. 15,726 sq. m.
POWER REQUIREMENT (48%):
S. No. Description Existing Proposed Total Remarks
1. Source of supply 33 KV supply will be from nearest GSS.
2. Electrical Load
Connected load 2651 KW 1509.80 KW 4160.80 KW Increase by 57%
Max Demand 1325.50 KW 754.90 KW 2080.4 KW
3. DG Sets
No. of DG sets 1 Nil 1 No change
Capacity 250 kVA Nil 250 kVA
Fuel consumption 40.8 l/hr Nil 40.8 l/hr
Fuel HSD (Sulphur content:
0.05%)
HSD (Sulphur
content: 0.05%)
Load Breakup:
Area
Description
Electrical
Load
Total Electrical
Connected Load
(CL)
Maximum
Demand
Load
Transformer
Rating @130%
of MDL
Power
Factor @
0.9
Proposed
Transformer
Watt/Sqft. KW KW KW KVA KVA
Block-1 8 924 462.00 600.60 667.33 750
Block-2 8 977 488.40 634.92 705.47 750
Block-3 8 1040 520.00 676.00 751.11 750
Block-4 8 960 480.00 624.00 693.33 750
Common Load
250
Total 3901 1950 2536 2817 3250
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
WATER DEMAND:
The daily water requirement for the project will be 399 KLD (227 fresh + 172 recycled)
Existing : 350 KLD (179 fresh+ 170 recycled)
Proposed : 49 KLD (48 fresh+ 2 recycled)
BASIS OF WATER DEMEND (48%):
S.
No.
Particulars Population Fresh water
demand
Recycled water
demand
Total water
demand
1. Group Housing 2001 @65 LPCD: 130 KLD @21 LPCD: 42 KLD 172 KLD
2. Visitors 300 @ 6 LPCD: 2 KLD @ 3 LPCD:1 KLD 3 KLD
3. Staff & Admin 25 @21 LPCD: 1 KLD @9 LPCD: 1 KLD 2 KLD
4. Landscaping 1,860.60 sq. m. -- 18 KLD 18 KLD
5. General Washing 21,973.46 sq. m. -- 11 KLD 11 KLD
Total 133 KLD 73 KLD 206 KLD
Fresh water
133 KLD
Recycled/
Reused
water
73 KLD
Group Housing
(130 KLD)
Staff & Admin/Visitor
(3 KLD)
Flushing (44 KLD)
151 KLD
Waste Water
S
T
P
Capacity
200 KLD
105 KLDSludge &
Evaporation
losses
8 KLD
Total STP treated water
WATER BALANCE (48%)
Daily Water Demand = 133 + 73 = 206 KLD
2 KLD
44 KLD Supplied to
farmers
70 KLD
Landscaping & General
washing (29 KLD)
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
IDENTIFICATION, PREDICTION AND EVALUATION OF IMPACTS:
Environmental impact can be defined as any alteration of environmental conditions, adverse or
beneficial, caused or induced by the action or set of actions under consideration.
Various operations involved in the proposed project have been studied in details to identify, predict
and evaluate impacts on various environmental components. The identified impacts were
quantified using mathematical models to a possible extent so as to estimate the future
environmental scenario.
AIR ENVIRONMENT:
AMBIENT AIR MONITORING REPORT
Agency hired: Vison Labs
(Vendor code: EES/ ADM / LSUP/ 031/ 032):
Instrument used: Respirable Dust Sampler & Fine Particle Sampler, CO Analyzer
Sampling date: 26-27.05.2014, Duration: 24 hrs.
Parameter Observation Permissible
(maximum)
PM10 (µg/m3) 69.9 < 100
PM2.5 (µg/m3) 32.5 < 60
SO2 (µg/m3) 6.3 < 80
NO2 (µg/m3) 23.5 < 80
Co(µg/m3) 601 <2000
CONSTRUCTION PHASE:
SOURCES MANAGEMENT
Dust & emissions from vehicular
exhaust.
• Regular sprinkling of water on the haul - road.
• Speed restriction of all vehicles.
• Vehicles will be checked for PUC certification.
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
The fugitive dust emission
sources are:
• Haul road movements
• Construction
• Material Handling
• Finishing
• Water spraying to prevent dust pollution from different sources
of construction.
• All transportation vehicles will be suitably covered with tarpaulin
& overloading of the vehicles will be avoided.
• Covering of the construction site on all four sides to a
considerable height to prevent dust emissions and other
pollutants to the surrounding environment.
• Ensuring vehicles stick to the access track to prevent mud and
dirt being deposited on roads.
POST CONSTRUCTION PHASE:
DG sets: Stack height calculation
There will be no additional DG set required for the project. Power back up to the common areas
and essential services will be arranged through existing DG set of capacity 250 kVA – 1 no. The
details are tabulated as under:
S.
No.
Capacity of D.G. Set, kVA Fuel consumption Density of oil Sulphur
content
Stack
Height
1. 250 kVA- 2 nos. 40.8 l/hr/per DG 800-850 kg/cm3 0.05% 49.0 m
Calculation of stack height:
The stack height of proposed DG set is calculated as under:
H = 0.2 (√capacity of the DG set in kVA)
= 0.2 x (√250)
= 0.2 x 15.81
= 3.16 m
Say = 4.0 m
However, a safe stack height of 49.0 m above the roof of DG house will be provided .
Impact on Air Quality
The impact on air quality is assessed based on emissions of the proposed DG set and vehicular
emissions. NOx and CO will be the important pollutants emitting from these sources.
Prediction of impacts on air environment has been carried out employing mathematical model based
on a steady state Gaussian plume dispersion model designed for multiple point sources for short
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
term. In the present case, AERMOD Version 7.1.0 dispersion model for different stability state
Gaussian plume dispersion, designed for multiple point and line sources for short term and developed
by United States Environmental Protection Agency [USEPA] has been used for simulations from point
and line sources.
Model Input Data
For the modeling purpose, all pollutants as described above are considered. The details of stack
emissions and line emissions envisaged from the project are given in Table-1 (a) & (b).
TABLE-1 (a) STACK EMISSION DETAILS
S. No. Parameters Units DG Set (250 kVA) Stack- I
1 Stack Height m 49
2 Top diameter of flue m 0.15
3 Flue gas velocity m/sec 14
4 Exit Flue gas temperature oK 453
5 Flue gas flow rate m3/sec 0.247
6 Emission rate at stack exit
A NOx g/KWh < 9.2
B CO g/KWh < 3.5
TABLE-1 (b) LINE EMISSION DETAILS
Parameter Emission rate per ECU (g/sec/m)
NOx 1.17 x 10-6
CO 1.46 x10-5
Presentation of Results
In the present case, model simulations have been carried out for the study period. The Ground level
concentrations are computed for 24-hr average. Maximum Ground level concentrations of NOx and
CO for study period were 0.83 µg/m3 and 0.67 µg/m3 respectively. The obtained GLC’s are well
within the stipulated CPCB standards. The incremental ground level concentrations for NOx and CO
are given in Table-2 (a).
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
TABLE-2 (a)
Predicted 24-Hourly Short Term Maximum Incremental Concentrations
Pollutant Maximum Incremental
Concentration (µµµµg/m3)
(X,Y) coordinates
(m)
Towards Direction
NOx 0.83 (- 200 , 0) W
CO 0.67 (- 100 , 400) NNW
Resultant Concentrations after Implementation of the Project
The maximum incremental GLCs due to the proposed project for NOx and CO are superimposed on
the maximum baseline concentrations recorded during the study period. The cumulative
concentrations (baseline+incremental) after implementation of the project are tabulated below in
Table-2 (b). The predicted ground level concentration isopleths for various parameters during
study period is given in Figure- 1 & 2 respectively.
TABLE-2 (b)
Details of maximum incremental concentration of pollutants on the surroundings
Parameters Baseline Incremental GLC’s,
µg/m3
Resultant GLC’s,
µg/m3
Standard, µg/m3
NOx 24.3 0.83 25.1 80
CO 725 0.67 726 2000
It is seen from the above table, the resultant GLC’s obtained at Project Site are well within the
CPCB standards (dated 18th November, 2009).
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
FIG.1
Isopleths Showing Maximum Incremental Ground Level Concentrations of NOx
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
FIG.2
Isopleths Showing Maximum Incremental Ground Level Concentrations of CO
MANAGEMENT PLAN
SOURCES MANAGEMENT
• Exhaust from D.G. set of
capacity 250 kVA- 1 nos.
• EPA/CPCB certified DG set conforming to the standards will be
deployed.
• D.G. set will be provided with effective stack height (49.0 m) as per
the norms of CPCB above the roof of the D.G. house.
• Low sulphur content fuel (HSD - Sulphur content 0.05%) will be used.
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
• Emission due to vehicular
exhausts especially
congestions during peak
traffic hours.
• Sufficient width of driveways to ensure smooth traffic movements.
• Provisions of fully internalized parking including the parking facilities
for the visitors.
• Guided traffic - ways within the project site.
• Speed humps will be installed for speed restrictions inside the project
area.
WATER ENVIRONMENT:
BASE LINE WATER QUALITY:
Location: Project Site
Date of sampling: 26-27.05.2014
Parameter Results Complete Test as Per IS :10500-1991
Desirable Limit Permissible Limit
Physical Parameter
Colour, Hazen Units <01 < 5 < 25
Odour Unobjectionable Unobjectionable -
Taste Agreeable Agreeable -
Turbidity, NTU 1.3 <5 .0 <10.0
pH value 7.68 6.5 - 8.5 -
Chemical Parameter
Total Hardness as CaCO3,mg/l 664 < 300 mg/l < 600 mg/l
Iron (as Fe),mg/l 0.11 < 0.3 mg/l < 1.0 mg/l
Chloride (as Cl),mg/l 340.8 < 250 mg/l < 1000 mg/l
Residual Free Chlorine, mg/l <0.02 < 0.2 --
Fluoride (as F), mg/l 1.18 < 1.0 < 1.5
Total Dissolved solids, mg/l 1564 < 500 mg/l < 2000 mg/l
Calcium( as Ca), mg/l 147.2 < 75 mg/l < 200 mg/l
Magnesium (as Mg), mg/l 71.0 < 30 mg/l < 100 mg/l
Copper (as Cu), mg/l 0.068 < 0.05 mg/l < 1.5 mg/l
Manganese as Mn 0.009 < 0.1 mg/l < 0.3 mg/l
Sulphate (as SO4), mg/l 244.8 < 200 mg/l < 400 mg/l
Nitrate (as N03), mg/l 10.7 < 45.0 mg/l No relaxation
Phenolic compounds, mg/l <0.001 < 0.001 mg/l < 0.002
Mercury(as Hg), mg/l <0.0001 < 0.001 mg/l No relaxation
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
Arsenic (as As), mg/l <0.001 < 0.01 No relaxation
Cyanide(as Cn),mg/l <0.001 < 0.05 No relaxation
Lead( as Pb),mg/l <0.001 < 0.05 No relaxation
Zinc (as Zn),mg/l 0.38 < 5 < 15 mg/l
Chromium (as Cr),mg/l <0.001 < 0.05 No relaxation
Selenium(as Se),mg/l <0.001 < 0.01 No relaxation
Cadmium(as Cd), mg/l 0.005 < 0.01 No relaxation
Aluminum (as Al),mg/l <0.001 < 0.03 mg/l < 0.2 mg/l
Alkalinity(as CaCO3 ),mg/l 460 < 200.0 mg/l < 600 mg/l
Boron (as B) mg/l 0.038 < 1.0 mg/l < 5 mg/l
Anionic detergents(as MBAS),mg/l <0.001 < 0.2 < 1 mg/l
Conductivity uS/cm 2,426 - -
Mineral oil <0.001 <0.01 <0.03
Bacteriological Parameter
Coliform/100 ml, MPN/100 ml Nil - 10.0 (Max)
Escherichia coli/100 ml Absent - Absent
Monitoring report is enclosed as Annexure IV.
CONSTRUCTION PHASE:
SOURCES MANAGEMENT
• Generation of sewerage • Temporary septic tank followed by soaks - pit will be provided.
• Significant water demand
for construction.
• Curing water will be sprayed and after liberal curing all concrete
structures will be covered with gunny bags that will conserve water.
• There will be provision of using polymer dispersion and air entraining
agents to reduce the water demand for construction.
• Un-captured run off from
the site may contaminate
ground water aquifers.
• The rain water entering into the pit will be screened for the removal of
heavy silt and other materials.
• Provisions will be made to ensure the construction vehicles stick to the
access track to prevent mud & dirt being deposited on roads.
• Fence will be constructed around the site to trap sediments whilst
allowing the water to flow through.
• Up - slope water will be diverted with turf and due care will be taken not
to mix mortar in locations that will drain into storm water system.
• Unsanitary conditions • The civil contractor will be employed and will be responsible for site
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
during rainy season. sanitation and will be bound by the management to adhere to healthy
level of sanitation.
• There will be no stagnant water at site, as the runoff from the relevant
areas will be systematically drained into the storm water line. There will
be provision of cleaning the storm - water line periodically.
POST CONSTRUCTION PHASE:
Waste water generation and treatment:
The waste water generated from various domestic activities will be to the tune of 262 KLD which
will be treated in the sewage treatment plant of appropriate capacity.
SEWAGE TREATMENT PLAN
STP based on Extended Aeration technology with capacity of 300 KLD will be installed for waste
water treatment. Physico - chemical characteristics of influent and effluent are given as:
Parameters Influent Treated effluent
pH 7.5 - 8.5 7 - 8
Suspended solids 250- 275 mg/l <10 mg/l
BOD 300 - 350 mg/l <5 mg/l
COD 450 - 550 mg/l <60 mg/l
Oil & Grease 8 -10 mg/l <5 mg/l
Coliforms (MPN/ 100 ml) 5-8 x 105 - 107 50 – 500/ less
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
SCHEMETIC LAYOUT OF STP:
RAINWATER HARVESTING SCHEME:
Rain Fall Data (last 10 years):
Source: Water Resource Department, Rajasthan
907
646750
377
572 553407 392
805
563
0
200
400
600
800
1000
2012 2011 2010 2009 2008 2007 2006 2005 2004 2003
Ra
infa
ll i
n m
Year
Rainfall Data
annual rainfall standard deviation average
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
CALCULATION OF PEAK DISCHARGE:
S.
No
Type of
Structure/ Surface
Area [A]
(sq. m.)
Run off
Coefficient
[C]
Intensity
of rainfall
(m/hour)
Total discharge
[Q]
(m3/hr)
1. Roof top area 8,781.29 0.90 0.06 474.19
2. Plantation/Landscape Area 5,364.07 0.30 0.06 96.55
3. Parking & paved areas 12,154.64 0.75 0.06 546.96
Grand Total (1-3) 26,300.00 1,117.70 say 1,118
VOLUME OF RAIN WATER DRAINAGE
Total Rain Water Flow : 1,118 m3/hr
Considering 15 minutes of peak rainfall,
Runoff volume : 279.5 m3/hr
Volume of each pit : 27 m3 (3 m x 3 m x 3 m)
Total no. of rain water harvesting pits required : Total run-off volume/ volume of each pit
: 279.5/27
: 10.35 say 11 nos.
11 Nos. Rain Water Harvesting pit of size 3 m length x 3 m width x 3 m depth with PVC slotted
pipe upto minimum depth of 35 m.
TOTAL RAIN WATER RECHARGE THROUGH RAINWATER HARVESTING:
S.
No
Type of
Structure/ Surface
Area [A]
(sq. m.)
Run off
Coefficient
[C]
Intensity
of rainfall
(m/annum)
Total discharge [Q]
(m3/annum)
1. Building foot print area 8,781.29 0.90 0.597 4,718.19
2. Landscape Area 5,364.07 0.30 0.597 960.70
3. Parking & paved areas 12,154.64 0.75 0.597 5,442.24
Grand Total (1-3) 26,300.00 11,121.13 m3/annum,
say 11,200 m3/annum
Total Annual Recharge to Ground Water Regime of the area through rainwater harvesting
structure would be 11,200.00 m3/annum.
Project : Affordable Group Housing
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services EIA coordinator Sunita Mantri
RAIN WATER HARVESTING SCHEME
MITIGATION MEASURES
S. No. Anticipated impacts
1. Daily water demand: 399 KLD
Existing: 350 KLD
Proposed:49 KLD
2. • Daily waste water generation:
KLD
• Surface / ground water
contamination due to untreated
wastewater
4. • Un-captured storm water run
Affordable Group Housing (Expansion)
Projects Pvt .Ltd.
Private Limited, Jaipur
Authorized Signatory
RAIN WATER HARVESTING SCHEME
Anticipated impacts Mitigation measures / Management
KLD • Daily fresh water demand reduced to
KLD existing + 48 KLD proposed)
of Environment Management Plan which will be met
from ground water (Existing Bore well:
• The maximum annual recharge will be to the tune of
11,200.00 cu. m. (Existing: 10,500.00 cu. m.)
harvesting the storm water.
Daily waste water generation: 262
contamination due to untreated
• Domestic waste water will be treated in sewage treatment
plant based on Extended Aeration
capacity of 300 KLD.
• Treated water from STP will be used for flushing (
landscaping & general washing (96
Farmer (70 KLD).
captured storm water run-off. • The runoff from the building terraces, paved areas and
CP&EMP
Authorized Signatory
Mitigation measures / Management
fresh water demand reduced to 227 KLD (179
after implementation
of Environment Management Plan which will be met
Existing Bore well: - 6 no.).
The maximum annual recharge will be to the tune of
(Existing: 10,500.00 cu. m.) by
water will be treated in sewage treatment
Extended Aeration technology with
Treated water from STP will be used for flushing (76 KLD),
96 KLD), Supplied to
The runoff from the building terraces, paved areas and
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
• Flooding or logging of storm water
drains
landscape areas will be channelized to the rain water
harvesting structures designed on the peak intensity of
rainfall (60 mm/hr) to accommodate peak surface runoff,
which will avoid the problems of flooding. Details of
existing as well proposed rain – water channels and pit is
given in Utility/ Mosaic Plan (Annexure VI)
• The storm - water drains will be cleaned in the pre-
monsoon phase so that the water logging can be avoided.
LAND ENVIRONMENT:
SOIL MONITORING REPORT
Date of Monitoring: 26-27.05.2014
S. No. Parameter Result
1. pH (10 % slurry) 7.65
2. Conductivity 133 µmhos/cm
3. Moisture Content <1.00 %
4. Total Organic Matter 1.02 %
5. Phosphorous (as P) 42 mg/100gm
6. Nitrogen (as N) 196 mg/100gm
7. Potassium (as K) 68 mg/100gm
8. Sodium (as Na) 1.26 mg/100gm
9. Texture (Clay) 44%
10. Texture (Sand) 30%
11. Texture (Silt) 26%
12. Iron (as Fe) 0.06 mg/kg
13. Chloride (as Cl-) 1.04 mg/100gm
14. Water Holding Capacity 21.6 %
15. Zinc (as Zn) 3.12 mg/kg
16. Copper (as Cu) 0.18 mg/kg
17. Cadmium (as Cd) 0.02 mg/kg
18. Bulk Density 1.30 gm/cc
19. Porosity 42% v/v
20. Pearmability 4.8 Cm/s
21. Alkali Metals 0.28 mg/kg
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
22. Lithium < 0.01 mg/kg
23. Boron (as B) 0.06 mg/kg
24. Appearance Light Brown Colour
Soil monitoring report is enclosed as Annexure VI.
CONSTRUCTION PHASE:
SOURCES MANAGEMENT
• Construction waste:
1,498 MT.
• The construction waste will be stacked properly.
• The recyclable waste (metal, wood, etc.) will be sold to the
vendors.
• The inert waste (brick, masonry, concrete, etc. will be used for
road making, filling and for strengthening the approach roads.)
POST CONSTRUCTION PHASE:
The total waste generation in the project will be 1,848 kg/day. The details are tabularized as:
S. No. Bins Particulars Quantity Treatment Disposal
1. Green
(households)
Compostable waste
Kitchen waste
Garden waste
Total: 1230 kg/day
Existing: 624 kg/day
Proposed: 606
kg/day
No in-situ
treatment.
Collected and
stored at
designated
places.
Will be sent to
Jaipur Municipal
Corporation
disposal sites.
2. Dark grey
bins
(households)
Non – biodegradable
waste + recyclable
waste:
Plastics
Metal
Glass
Misc.
Total: 618 kg/day
Existing: 416 kg/day
Proposed: 202
kg/day
No in-situ
treatment.
Collected and
stored at
designated
places.
Will be sent to
Jaipur Municipal
Corporation
disposal sites.
3. Blue
(households)
Paper waste
Paper
Newspaper
Cardboards
Packing material
Not Quantified Efforts to recycle
to the best
possible extent.
Will be collected
on daily basis.
Sold to the
vendors for
recycling.
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
NOISE ENVIRONMENT:
NOISE MONITORING REPORT
Date of Monitoring: 26-27.05.2014
S. No. Monitoring time Unit in dB(A)
1. 06.00 53.6
2. 07.00 54.8
3. 08.00 56.9
4. 09.00 57.3
5. 10.00 55.9
6. 11.00 54.3
7. 12.00 53.9
8. 13.00 54.8
9. 14.00 51.9
10. 15.00 53.1
11. 16.00 55.8
12. 17.00 56.4
13. 18.00 54.8
14. 19.00 53.0
15. 20.00 50.7
16. 21.00 47.9
17. 22.00 45.2
18. 23.00 43.6
19. 24.00 42.8
20. 01.00 40.6
21. 02.00 38.6
22. 03.00 41.6
23. 04.00 48.9
24. 05.00 51.4
Leq day dB(A) 54.8
Leq Night dB(A) 46.3
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
CONSTRUCTION PHASE:
During construction phase following will be the tentative sources of noise:
Name of Source Noise level at 16 m from
source {dB (A)}
Noise level at 1 m from source
{dB (A)}
Back hoe/Loader 81 105
Dump truck 83 107
Generator Not considered 75 (as prescribed by CPCB)
To understand the combined effect of these noise levels on the nearby community, Custic 3.2
(Lakes Environmental – USEPA approved) scientific model has been used to estimate the noise
levels at different distances from the proposed project. All the major noise generating machineries
like D.G. Sets, Pumps, Trucks, vibrators, drilling machine, etc., are considered in this model. The
noise level at project boundary due to different sources is calculated based on the following
formula:
Lp2 = Lp1 – 20 log (r2 / r1) – Ae1, 2
where, Lp1 and Lp2 are sound levels at points located at distance r1 / r2 from the source and Ae1,2 is
the excess attenuation due to environmental conditions. The resultant noise level is obtained by
adding existing maximum levels to that of predicted level.
The predicted noise levels based on the above analysis at the project boundary considering that
there is no attenuation on account of barriers, will be as follows:
LOCATION MAX.EXISTING MAX. PREDICTED RESULTANT MAX
Project Site 54.2 56 58.2
All values are in dB(A)
From the above, it is clearly seen that there will be no significant impact on the surrounding
community due to noise from the proposed activity.
Further due to natural attenuation effects, by proper green belt development, design / maintenance
of machines, providing PPE’s to workers, etc., the impact on noise levels will be minimal.
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
CONSTRUCTION PHASE:
SOURCES MANAGEMENT
Major sources of
noise pollution:
• Vehicular traffic
• Heavy moving
machinery
• Operation of D.G.
sets, etc.
• The construction area will be shielded with help of tarpaulin sheets.
• Complete construction work especially heavy earth work will be done during day
time.
• Traffic planning and management will be made adequate to ensure uninterrupted
traffic movement in the area so as to minimize the noise due to congestion.
• The vehicles will be regularly maintained and optimum use of the same will be
made.
• Moving parts of the machines will be maintained properly so as to avoid metal-
to-metal impact noise.
• The D.G. sets used will be eco - friendly with minimum noise.
• Ear - plugs will be provided to the workers.
POST CONSTRUCTION PHASE:
SOURCES MANAGEMENT
• The source of
noise in the post
construction
phase may be
due to the road
traffic, operation
of D.G. sets.
• EPA/CPCB certified DG sets conforming to the standards for noise will be used.
• D.G. sets will be housed in an inbuilt acoustic enclosure, which will help to contain
the noise within the permissible standards.
• The driveways will have sufficient width so that there is no congestion of vehicles
during peak hours which will lead to increase in the noise levels.
• Adequate parking including provisions of visitors parking.
• Entry & exits will be manned with trained & efficient security to ensure smooth flow
of vehicles.
• There will be less starting and stopping and the vehicles will be speed restricted to
ensure the noise remains within the permissible limits.
• The area will cover 20.40% (5,364.07 sq.m.) area under landscape, which will help
to absorb noise.
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
ENERGY:
• The DG sets will be used only in case of power cuts or failure for back up. Low - sulphur -
content fuel (Sulphur content 0.05%) will be used.
• Energy - efficient compact Fluorescent Lamps to be used as these CFL give same illumination
with less wattage compared to GLS Lamps.
• Sodium vapour lights will be used for external lighting.
• Power factor will be maintained around 0.90 and above. All capacitors will be provided with
Harmonic Filters to avoid distortion in Voltage
• to minimize the losses.
• Insulation of exposed walls and roof will be done to minimize heat gains inside the building.
This will help to reduce the air conditioning demand of the buildings.
• About 7.5 KL of hot water requirement of top two floors and villas will be met through solar hot
water generators 30 nos of capacity 250 L each.
Expenditure on Environmental Measures:
S.
No.
Particulars Capital Cost Annual recurring cost
Existing Proposed Existing Proposed
1 Acoustic enclosures & stack attached
to DG sets
2.0 lacs 2.0 lacs
0.50 lacs 0.20 lacs
2 STP 30.0 lacs 20.0 lacs 2.0 lacs 1.0 lacs
3 Rain water harvesting 20.0 lacs 2.0 lacs 2.0 lacs 0.20 lacs
4 Solid waste management 5.0 lacs 2.0 lacs 1.0 lacs 0.20 lacs
5 Pollution monitoring 2.0 lacs 1.0 lacs 0.50 lacs 0.20 lacs
6 Fire fighting & emergency handling 25.0 lacs 5.0 lacs 0.50 lacs 0.20 lacs
7 Green Belt 3.0 lacs 1.0 lacs 0.30 lacs 0.10 lacs
8 Training in the area of environment &
occupational health.
- - - -
Total 87.0 lacs 33.0 lacs 6.8 lacs 2.10 lacs
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
BIODIVERSITY
Biodiversity is often taken to refer mainly to the diversity of species, especially where conservation
is under discussion. Biotic component comprises of both plant animal communities which interact
not only within and between them self but also with abiotic i.e. physical and chemical components
of the environment. Generally a biological community is being dependent on the environmental
conditions and resources of its location may change if there are many major changes in the
environment. The number of variables like temperature, humidity, atmospheric conditions, soil,
topography, etc. is responsible for maintaining the homeostasis of the environment and a change
in any one or more of these variables may tend to destabilize the ecosystem. In such cases the
change may be mostly irreversible. Therefore, the need to assess the changes of the animal and
plant resources is primary requisite as these living things determine the environmental healthiness
of any given ecosystem or environment.
Biological impact assessment generally includes listing of plants and animals present at the project
site. The identified species are then checked for their status according to IUCN list of threat
categories viz., endemic, endangered, vulnerable, rare, indeterminate and insufficiently known. In
certain cases it is also considered desirable to conduct vegetation analysis using standard phyto-
sociological methods.
Field studies were undertaken in the month of April 2014. The proposed site and habitats adjacent
to the site were surveyed for flora and fauna species, consequently, little habitat for native species
exists and fauna species composition on-site is very low.
1. SCOPE OF WORK
The biological study of the area has been conducted in order to understand the ecological
status of the existing flora and fauna to generate baseline information and evaluate the
probable impacts on the biological environment.
The present scope of work was undertaken with the following objectives:
• To collect the baseline terrestrial biodiversity status regarding flora and fauna in the
project area.
• To assess the frequency, density, abundance, Importance Value Index (IVI) and
Shannon-Wiener Diversity Index (flora).
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
• To evaluate the dominant species of plant and animal. Secondary data also be collected
from the local residents and authenticated list of flora and fauna by the Department of
Forest, Govt. of Rajasthan, Rajasthan.
• To identify the endangered / threatened / scheduled species in the study area (both flora
and fauna). The conservation plan will be given if any wildlife species of schedule I is
present there.
• To mark the wetlands and other ecologically sensitive areas such as national parks/
sanctuaries.
• To provide the conservation plan and suggestion / recommendation for social forestry
green belt / plantation.
• To assess the effect of construction and operation of the project on existing ecology.
On the basis of onsite observations a checklist of flora and fauna was prepared.
2. DESCRIPTION OF THE STUDY AREA
The site is located between latitude 26°50'14.83"N and longitudes 75°37'2.68"E at Bhankrota,
District-Jaipur, Rajasthan. The site is about 21 km from Jaipur towards Ajmer on Jaipur-Ajmer
highway.
3. METHODOLOGY
To achieve the above objectives, study of the area was undertaken at project site. The field
sampling was conducted during the period of April 2014.
FLORAL STUDY
The vegetation sampling was carried out by using the least count quadrate method across
different habitats. The quadrants are useful for quantification of density and abundance of the
vegetation in the study area. The size and number of quadrates needed were determined using
the species area curve (Mishra, 1968) and the running mean method (Kershaw, 1973).
Summarization of previously used methods and recommendations led to the use of more than
often (10x10m) quadrates laid out for sampling the tree stratum and 1x1m quadrates for herbs and
grasses. DBH of trees was also determined. All individuals > 10 cm GBH (Girth at Breast Height)
were included in tree category. However, for examining the shrub species 3x3m sample plots were
laid out.
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
The data collected for biodiversity information were quantitatively analyzed for density, frequency,
abundance and Shannon-Wiener Diversity Index. The relative values of frequency, density and
dominance of all the species were summed up to represent Importance Value Index (IVI). The
followings are the formulae to derive frequency, density, abundance, Importance Value Index (IVI)
etc.
Total number of quadrate in which species occurred Frequency = ————————————————————————------ x 100 Total number of quadrate studied Total number of individuals of a species Density = —————————————————---------------------------- Total number of quadrate studied Total number of individuals of species in all quadrate Abundance = ————————————————————————— Total number of quadrate in which species occurred
Total Basal Area Dominance = ————————————————— Total area sampled Frequency of the species Relative Frequency = —————————————— x 100 Total frequency of all species Density of the species Relative Density = ——————————————x 100 Total density of all species Abundance of the species Relative Abundance = —––———————————— x 100 Total abundance of all species
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
Dominance of the species Relative Dominance = —––———————————— x 100 Total Dominance of all species Importance Value Index (IVI) = Relative frequency + Relative density +Relative dominance
Shanon – Weaver Index (1948):
The number of species and number of individuals in a community is measure of species
diversity which depends on stability of the habitat. Vegetation of the study area was assess by
determining Shannon – Weaver diversity index (1948)
D = -Σ (ni / n) log2 (ni / n)
ni = Number of individuals of each species in the sample
n = Total number of individuals
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
3.1. FLORA :
FLORAL STUDY:
Tree (10 x 10m)
S.
N
o
Specie
s name
Binomial
name
Total
No of
quadrat
e
studied
Total no of
quadrate
in which
species
occurred
Total no of
individual
of species
in all
quadrate
Densi
ty
Relative
Density
Frequenc
y
Relative
Frequenc
y
Basal
area
(m2)
Relative
Dominan
ce
Importanc
e
Value
Index
(IVI)
SWD
Index
H= - ∑ Pi
( lnPi)
1 Neem Azadirachta
indica 25 3 4 0.16 19.048 12 23.077 0.139 34.090 76.2144 -0.31585
2 Babool Acacia
nilotica 25 10 17 0.68 80.952 40 76.923 0.268 65.910 223.7856 -0.17106
0.48691
Shrub (3 x3m)
S.
N
o
Species
name
Binomial
name
Total No
of
quadrate
studied
Total no of
quadrate in
which
species
occurred
Total no of
individual
of species
in all
quadrate
Dens
ity
Relative
Density
Freque
ncy
Relativ
e
Freque
ncy
Abunda
nce
Relativ
e
Abund
ance
Importan
ce
Value
Index
(IVI)
SWD
Index
H= - ∑
Pi
( lnPi)
1
Vilayati
Babool
Prosopis
juliflora 25 7 11 0.44 9.02 28 11.67 1.57 9.52 30.20 -0.231
2
Phog
shrub
Calligonum
polygonoide 25 8 13 0.52 10.66 32 13.33 1.63 9.84 33.83 -0.246
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
s
3 Kair
Capparis
decidua 25 9 16 0.64 13.11 36 15.00 1.78 10.77 38.88 -0.265
4
Bui Aerva
tomentosa 25 5 12 0.48 9.84 20 8.33 2.40 14.53 32.70 -0.242
5
Aak Calotropis
procera 25 8 17 0.68 13.93 32 13.33 2.13 12.87 40.14 -0.269
6
Khimp Leptadenia
pyrotechnica 25 6 18 0.72 14.75 24 10.00 3.00 18.17 42.92 -0.278
7
Munja
grass
Saccharum
munja 25 6 11 0.44 9.02 24 10.00 1.83 11.10 30.12 -0.231
8 Ber
Zizyphus
nummularia 25 11 24 0.96 19.67 44 18.33 2.18 13.21 51.22 -0.302
2.063
Herb (1 x 1m)
S.
N
o
Species
name
Binomial
name
Total
No of
quadr
ate
studi
ed
Total no of
quadrate
in which
species
occurred
Total no
of
individual
of
species
in all
quadrate
Densi
ty
Relative
Density
Freque
ncy
Relative
Frequenc
y
Abunda
nce
Relative
Abunda
nce
Importan
ce
Value
Index
(IVI)
SWD
Index
H= - ∑ Pi
( lnPi)
1 Peeli
Doodhak
Launaea
nudicaulis 25 12 28 1.12 8.86 48 11.54 2.33 6.30 26.70 -0.247
2 Satyanasi Argemone
mexicana 25 14 41 1.64 12.97 56 13.46 2.93 7.90 34.34 -0.226
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
3 Sarphonk
a
Tephrosia
purpurea 25 9 35 1.4 11.08 36 8.65 3.89 10.50 30.22 -0.227
4 crabgrass
Digitaria
sanguinali
s 25 5 16 0.64 5.06 20 4.81 3.20 8.64 18.51 -0.253
5 Gokharu
herb
Tribulus
terrestris 25 14 43 1.72 13.61 56 13.46 3.07 8.29 35.36 -0.217
6 Bermuda
Grass
Cynodon
dactylon 25 11 46 1.84 14.56 44 10.58 4.18 11.29 36.42 -0.261
7 Motha Cyperus
rotundus 25 12 31 1.24 9.81 48 11.54 2.58 6.97 28.32 -0.191
8 Tawa-
tawa
Euphorbia
hirta 25 5 11 0.44 3.48 20 4.81 2.20 5.94 14.23 -0.155
9 Bitter
cucumber
Citrullus
colocynthi
s 25 4 14 0.56 4.43 16 3.85 3.50 9.45 17.72 -0.142
10 Crowfoot
grass
Eleusine
indica 25 6 19 0.76 6.01 24 5.77 3.17 8.55 20.33 -0.155
11 Cobbler's
Pegs
Bidens
pilosa 25 9 21 0.84 6.65 36 8.65 2.33 6.30 21.60 -0.172
12
Jungli
Tulsi
Ocimum
tenuifloru
m 25 3 11 0.44 3.48 12 2.88 3.67 9.90 16.26 -0.189
2.434
Project : Affordable Group Housing (Expansion) CP&EMP
Promoted by : Siddha Infra Projects Pvt .Ltd.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory
3.2 FAUNA:
FAUNAL STUDY
Primary faunal studies were conducted during study in and around the project site.
The different methods adopted were as follows:
• Physical observation by the survey method conducted in the study area for the faunal
diversity study.
• Secondary data were gathered from the local habitant with the discussion.
• Data collected from the other sources for the complete biological environmental studies.
• Rapid surveys were carried out at the Siddha Aaagan site at Bhankrota, district Jaipur (Raj).
Intensive surveys were conducted at study site, which would be subjected to higher degree
of disturbance by project related activities. Data on the presence/absence of the different
faunal species in the project area was recorded largely based on direct and indirect
evidence such as tracks, spoors, dung and calls. Secondary information sources such as
published information, unpublished reports, personal communication and informal interviews
with villagers were also taken into account for supplementing primary data collected during
field studies. Standard field guides were used for identification of faunal species during the
surveys (Peater, 1980).
• Avifaunal studies (Bird surveys) were conducted at the sampling points marked for intensive
study. While traversing the area, birds were identified either by direct sighting or by calls.
Casual observations were also recorded as and when the team moved through the study
area. Field guide by Ali & Ripley, (1983) was used to identify bird species. Existing
checklists of avian species (Anon., 1998) of the project area was also consulted and
validated.
ENDANGERED/ THREATENED/ENDEMIC ANIMALS
Faunal studies were also conducted during April 2014. During the survey of the study site, no
threatened/ endemic species in and around the study area were observed.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator
Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan
Promoted by: Eldeco Infrastructure & Properties Ltd.
Major Features in the Study Area
Feature Name / Status
National Park / Sanctuary Nil
Biosphere Reserve /Tiger Reserve/ Elephant Reserve /any other Reserve
Nil
Habitat for migratory birds Nil
Corridor for animals of Schedule I & II of the Wildlife (Protection) Act, 1972
Nil
REPTILIAN
Particulars
S.
No.
Common name
Binomial name
Family
Schedule
IW(P)A / IUCN
Reptilian 1 Russell's viper Daboia russelii Viperidae IV
2 Garden Lizard/Girgit Calotes versicolor Agamidae LC
3 Common House Gecko Hemidactylus frenatus Gekkonidae LC
4 Yellow-Green House
Gecko
Hemidactylus flaviviridis Agamidae LC
A) AVIS OR AVIFUANA
Site specific avifaunal species observed during the site visit:
S. No. Common Name Binomial Name Family Schedule
IUCN/IW(P)A
1. House sparrow Passer domesticus Passeridae IV
2. Rock Pigeon Columba livia Columbidae IV
3. Common Bulbul Pycnonotus barbatus Pycnonotidae IV
Avifaunal species observed surrounding area of sight during visit:
S. No. Common Name Binomial Name Family Schedule
IUCN/IW(P)A
1. Common Kingfisher Alcedo atthis Alcedinidae IV
2.
Common Myna Acridotheres tristis Sturnidae IV
3.
Indian Robin Saxicoloides fulicatus Muscicapidae IV
4. Crow Pheasant Centropus sinensis Cuculidae IV
5 Rose-Ringed Parakeet Psittacula krameri Psittacidae IV
Enkay Enviro Services Private Limited, Jaipur EIA coordinator
Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan
Promoted by: Eldeco Infrastructure & Properties Ltd.
4. Indian Ring Dove Streptopelia decaocto Columbidae IV
5. House crow Corvus splendens Corvidae V
6. Brown Rock Chat Cercomela fusca Muscicapidae IV
7. Oriental Magpie-Robin Copsychus saularis Muscicapidae IV
8. Indian Black Drongo Dicrurus macrocercus Dicruridae IV
E) MAMMALIA
Particulars S. No Common Name Binomial Name Family Schedule
Mammals 1 Mongoose / Neola Herpestes edwardsi Herpestidae IV
2 Five stripped palm squirrel Funambulus pennantii Sciuridae IV
3 Indian Hedgehog Paraechinus micropus Erinaceidae IV
4 Buffalo or Domestic Asian
water buffalo
Bubalus bubalis Bovidae IV
5 Common House rat Rattus rattus Muridae V
6 Indian porcupine Hystrix indica Hystricidae IV
7 Indian field mouse Mus booduga Muridae V
8 Grey Musk Shrew Suncus murinus Soricidae IV
c. Endangered species Not observed during the study period.
d. Endemic species Not observed during the study period .
e. Migratory species Avifaunal species may be migratory.
f. Aquatic fauna NIL
4.0 Green Belt Development
The greenbelt development plan aims at overall improvement in the environmental
conditions of the region. Green belt planning will be done with ecological perspectives
for project. Nature of pollutants, availability of space and dominant wind directions
should be considered. This will help in reducing the concentration of pollutants and will
also be effective in attenuating noise levels.
The plan with a five-fold objective addresses issues such as
� prevention of land degradation due to activities during construction phase;
� enhancing the forest cover for increasing the biodiversity of the region;
� providing aesthetic value to the project area and consequently inviting a
proportionate tourist flux;
� Enhancing the ecological equilibrium of the area;
Enkay Enviro Services Private Limited, Jaipur EIA coordinator
Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan
Promoted by: Eldeco Infrastructure & Properties Ltd.
� A large proportion in combating soil erosion.
4.1 Criteria for selection of plant species
Moreover, keeping in view the characteristics of soil, water quality and topography of
the area the following additional aspects should also be considered;
� Fast growing and perennial species;
� Large leaf area index;
� Locally available species which are tolerable to soil and climate of area;
� Low water requirement and heat tolerant;
� Pest resistant species;
� Tolerance to inorganic chemicals;
5.0 Guidelines and Techniques for Greenbelt Development
A detailed survey was conducted with respect to existing, vegetation, types, diversity
and density etc. in the project area for development of greenbelt around project
components. The greenbelt plan has been formulated considering the parameters
such as climate, soil types etc. Greenbelt within and outside the premises will
attenuate dust emission and noise during construction. The greenbelt is also
developed for the efficient use of land and to improve the aesthetic quality of the
environment.
A careful plan of the plantation is necessary for the most efficient and economic
management. The following points should be borne in mind while developing the
greenbelt are:
� Trees growing up to 10 m or above in height with perennial foliage will be
planted around the proposed project.
� Planting of trees will be undertaken in appropriate encircling rows around the
project site.
� Generally fast growing species will be planted. Plant species should be
selected as per the environmental scenario and condition of the proposed
study site.
� Evergreen trees should be planted.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator
Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan
Promoted by: Eldeco Infrastructure & Properties Ltd.
� Short growing trees should be allotted at the front and tall at the back for easy
watching and to improve the appearance.
� A good fence is essential. Live fencing is economic and cheap to other kind of
fences. The plants suitable for live fencing should be drought resistant, easy to
propagate from seed, quick growing, have dense foliage, should stand severe
pruning and should be thorny.
The inter-connecting/approach roads to various project components, within the
colonies, working sites will be developed with avenue plantation, at a distance of 2 – 3
m wherever required tree guards shall be installed for protection of these plants.
The shrubs and climbers should be planted even in between the tree spaces.
Farmyard manure should also be applied to the pits of the plants for good survival.
A nursery should be created for supply of saplings, and its maintenance should be
followed. However, the saplings could also be obtained from nurseries being
developed for compensatory afforestation.
5.1 Selection of Plant Species
Keeping in view the climatic conditions, status of soils and vegetation types in and
around the project area the following species of plants have been found suitable for
plantation around the colonies, road sides and various components of the project.
Plants species for greenbelt development are as in Table 1.
In addition to above some flowering plants, shrubs, herbs, and climber plants species
will also be planted for beautification in the project area.
5.2 Spacing and Pit Size
The spacing and pit size would be vary according to the choice of species and
compatibility of various species to grow together in a niche. Small trees would be
planted at a distance of 3 m apart, while broadleaf species would be planted at a
spacing of 5 m. The pit size would be 30 cm x 30 cm x 30 cm for shrubs and herbs
whereas for the broadleaf species the size of 3 x 3 x 3 foot needs to be adopted.
5.3 Fencing and Closure
Enkay Enviro Services Private Limited, Jaipur EIA coordinator
Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan
Promoted by: Eldeco Infrastructure & Properties Ltd.
A minimum block plantation would be undertaken by providing barbed wire fencing
including watch and ward for assuring protection from biotic interference.
5.4 Plantation Guard and Protection from Fire
Protection of plantation is greatest challenge from villagers and their cattle damage
the plantations before they are established. Hence protection of plantation is of
paramount importance and guards should be arranged for two to three years. Most of
the plants shall be guarded against fire, mainly in the summer season.
5.5 Suggested plants
Table 1: Following listed species are suggested to develop greenbelt around the project site:
S.No Type of Plants (Common name) Botanical name
1. Ashok Polyalthia longifolia
2. Shisham Dalbergia sissoo
3 Ardu Ailanthus excelsa
4 Kachnar Bauhinia variegata
5 Gulmohar Delonix regia
6 Neem Azadirachta indica
7 Satani Alstonia scholaris
8 Kadam Anthosephalus cadamba
9 Bottle Brush Callistemon citrinus
10 Palas Butea monosperma
11 Date Palm Phoenix sylvestris
12 Fan palm/ Bismarckia Palm Bismarck Palm
13 Sago Palm Cycas revolute
14 Jacaranda Jacaranda cuspidifolia
15 Royal Palm Roystonea regia
16 Amaltas Cassia fistula
Shrub
S.No. Common Name Botanical Name
1 Thunja Thuja occidentalis
2 Croton Codiaeum variegatum
3 Chandni Gardenia florida
Enkay Enviro Services Private Limited, Jaipur EIA coordinator
Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan
Promoted by: Eldeco Infrastructure & Properties Ltd.
4 Rubber plant Ficus elastica
5 Arocraria Arocraria sp.
6 Snake plant Sansevieria trifasciata
7 Chandni Tabernaemontana divaricata
8 Bougainvillea Bougainvillea glabra
9 Fire bush Hamelia patens
Herbs
S.No. Common Name Botanical Name
1 Genda Tagetes patula
2 Rose Rosa macdub
3 Crown Daisy Garland chrysanthemum
4 Flox Phlox subulata
5 Moss rose Portulaca grandiflora
5.6 Post Plantation Care
� When the soil is dry below the surface of the mulch, it is time to water.
� Keep the soil moist but not soaked;
� Overwatering causes leaves to turn yellow or fall off.
� Water in trees at least once a week, barring rain, and more frequently during
hot weather.
� Continue until mid-fall, tapering off for lower temperatures that require less-
frequent watering.
� Other follow-up care may include minor pruning of branches damaged
during the planting process.
� Prune sparingly immediately after planting and wait to begin necessary
corrective pruning until after a full season of growth in the new location.
� Tree guard should be around the saplings until the plant reaching at mature
stage.
� Fertilizers and pesticides/insecticides should be given proper time.
6.0 IMPACT OF PROJECT ACTIVITIES ON BIODIVERSITY
DIRECT, INDIRECT AND CUMULATIVE IMPACT ON FLORA
Enkay Enviro Services Private Limited, Jaipur EIA coordinator
Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan
Promoted by: Eldeco Infrastructure & Properties Ltd.
� Direct Impact
� Clearing of project site for construction activities – The project site is a waste rocky
land with sparse growth of trees and spiny shrub which are commonly distributed
throughout and none of rare, endangered or threatened or endemic species was
observed during survey / reported. Therefore no impact on biodiversity is
envisaged.
� Indirect Impact
� Construction activity is likely to affect the movement of the animal
� Increase in noise may affect the feeding, breeding and movement of animals.
Felling of trees may affect the avifauna
� Likely settling of dust to be generated by movement of vehicles and running of
crusher for construction activities on leaves may results in to stunted growth of
vegetation and may also affect the capacity of production.
� Large numbers of labour population will influx the area during construction phase.
The major threat to surrounding flora is through collection of fuel wood by labour for
cooking purposes and thereby loss of trees.
� Dumping of huge quantity of excavated earth material may lead to loss of flora in
the project area
� The soil erosion due to natural and anthropogenic activities may cause major threat
to survival of vegetation.
� Cumulative Impact
� Indirect and cumulative impacts are associated with various construction activities
such as clearing of vegetation for establishment of various project units, movement
of vehicles, construction equipments & machineries etc, interferences due to influx
of labours etc.
� The loss of land for various project unit will also not adversity affect the fauna as
similar habitat is present throughout the project immediate influenced area.
Therefore, impact due to loss of habitat for birds, reptiles and mammals of the
project area is not expected.
� Impacts on surrounding fauna due to movement of vehicles, machinery,
equipments and work force may slightly interfere in animal movements. As most of
the domestic animals Cows, Buffaloes, Goats, Sheep’s and Donkeys are guided &
Enkay Enviro Services Private Limited, Jaipur EIA coordinator
Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan
Promoted by: Eldeco Infrastructure & Properties Ltd.
controlled by the owners/caretakers and hence any causality in terms of killing or
accident are not expected.
� Intermittent settlements any adverse impacts on wildlife are ruled out.
7.0 EFFECTIVE REMOVAL OF POLLUTANTS
(1) Plants grow under conditions of adequate nutritional supply (for healthy and
better growth),
(2) Absence of water stress (to maintain openness of stomatal apertures and form
of epidermal structures),
(3) Well-exposed to atmospheric conditions of light and breeze ( i.e. away from
engineering structures hindering free flow of air) to maintain free interaction
with gases.
� Characters of plants including shapes of crowns considered necessary for effecting
absorption of pollutant gases and removal of dust particles are as follows:
1) Tolerance towards pollutants in question, at concentrations, that are not
too high( to be instantaneously lethal)
2) Longer duration of foliage,
3) Freely exposed foliage , through
• Adequate height of crown,
• Openness of foliage in canopy,
• Big leaves( long and broad laminar surfaces),
• Large number of stomatal apertures,
• Stomata well- exposed ( in level with the general epidermal surface)
7.1 REMOVAL OF SUSPENDED PARTICULATE MATTER
1) Height and spread of crown,
2) Leaves supported on firm petioles,
3) Abundance of surfaces on bark and foliage, through
• Roughness of bark,
• Epidermal outgrowth on petioles,
Enkay Enviro Services Private Limited, Jaipur EIA coordinator
Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan
Promoted by: Eldeco Infrastructure & Properties Ltd.
• Abundance of auxiliary hairs,
• Hairs or scales on laminar surfaces,
• Stomata protected (by wax, arches/rings, hairs etc.)
The plant species should be capable of sorption of dust pollutants and barrier of noise
pollution. Combined deficiency of a variety of species will be contributed to reach the
goals of restrict the pollution.
8.0 MITIGATION OF IMPACT: The mitigation measures of biological impacts are aimed
at (in order of preference):
i) Avoid impact,
ii) Minimize impact,
iii) Rectify impact,
iv) Compensate for impact.
Setting aside or exclusion of critically important areas, compensatory afforestation,
creation of green belts, rehabilitation of species or individuals are basic actions taken
for mitigation of impact. While creating green belt and undertaking the afforestation
works, it is required to plant indigenous/local plants and as for as possible exotics
should not be introduced. The cost of eco-restoration of the site should be included in
the project cost. This is desirable on two counts:
i) It ensures allocation of fund for undertaking the rehabilitation of the area
during and also after the project period is over.
ii) It also acts as deterrent in selection of site for the project by bringing in the
cost of eco-restoration which can be enormous in cases where activities are
proposed on a critical ecosystems.
9.0 RECOMMENDATION
At present the project site is a barren waste land with sparse growth of herbs and
shrub and few trees
� Construction activities will be restricted to day hours only.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator
Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan
Promoted by: Eldeco Infrastructure & Properties Ltd.
� Poaching of animals by labourers will be strictly prohibited. It may be
ensured by the contractors that no hunting is practiced at the site by any
of the workers.
� Ward and watch for the animal movement in and around the project area
during construction phase will be provided.
� Environment and Wildlife Conservation awareness program will be
organized for both work force and surrounding villages.
� All the vehicles delivering materials to the site shall be covered to avoid
spillage of material.
� Approach road used by vehicles shall be kept clean and clear of dust.
� All earth work shall be protected to minimize dust generation.
� All crusher used in construction shall confirm to relative dust emission
devises.
� All vehicles equipment machinery used in construction shall be fitted by exhaust
silencers.
� Equipments should be maintained regularly and sound proof gadgets should be
used.
� Cutting of trees should be strictly prohibited in the area for other construction
work.
� Provision of proper fencing to the plantation area.
� Watchman should be provided to care of plantation for 3-5 years
10.0 CONCLUSION
The present study is with the objective to minimize adverse environmental impacts as
discussed. The study covers all possible environmental issues involved in the project
and the necessary mitigation measures. It was observed that diversity of trees were
low while the shrub and herbs were in quite better in diverse condition which can be
sustain by the cultivation of native and local species in post construction phase.
Faunal diversity of the site was also low but avifaunal diversity of the site is much
better than the other faunal diversity. Therefore, we can say that the biological
diversity of the study site not much more impacted by the present proposed
infrastructure development and the sustainable environment scenario can be retained
Enkay Enviro Services Private Limited, Jaipur EIA coordinator
Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan
Promoted by: Eldeco Infrastructure & Properties Ltd.
by the proper landscaping. Taking appropriate mitigation measures for the
sustainable environment at the site and the surrounding area is our sole
responsibility.
SOCIO ECONOMIC ENVIRONMENT
OBJECTIVES
The broad objectives of the socio-economic impact assessment are:-
1. To study the socio-economic status of the people living in the study area.
2. To assess the impact on socio-economic environment due to the project
concerned.
3. To evaluate the community development measures proposed to be taken up
by the Project Proponent, if any.
4. To suggest community development measures that needs to be taken for
the study area with stakeholder engagement.
The studies carried out are descriptive and exploratory in nature.
The information analyzed for the project has been collected from various secondary
sources, which has been supported by the extensive site visits and field
observations.
SAMPLING METHOD
The studies are conducted on a target sample; and references are drawn on the basis
of survey.
A target sample of 10 people is interviewed selected on the basis of non probability
sampling with access to the nearest habitation to the extent possible.
The proposed group housing project promoted by Siddha Infra Project Limited, in
village Thikariya & Bagru Khurd, Tehsil Sangner, District Jaipur. There are 5
habituations of respective 5 villages in the Study area of 2.0 km. periphery. There are
also few scattered houses and development Schemes within 2.0 km. periphery of
respective 5 villages.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator
Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan
Promoted by: Eldeco Infrastructure & Properties Ltd.
Habitation and Human settlement
The habitations of developing urbanization Thikariya, Bagru Khurd, Harchandpur at Deoliya,
Rampurawas Deoliya and Balmukundpura villages are in vicinity. There are several plotted
development scheme in the vicinity.
Population
The total population of the study area (2.0 km. periphery) is approx. 6,324. There are 895
households as per the Census of India, 2011 and approx. 7 members per household. The
proposed project falls in village Thikariya and Bagru Khurd. Details are given in the Table 0.1:-
Table 0.1: Population Composition of Study Area
*Sources: Census of India, 2011
Gender Distribution
Out of the total population, 50.90% are male and 49.10% are female in the study area. As
according to the above mentioned table, the gender ratio of the study area is approx 964 per
thousand male. The gender ratio of the study area is very pleasent as it compared to the
district Jaipur (910) and state Rajsthan (928). It is tabulated below:-
Table 0.2: Gender Ratio of the Study Area
Census of India, 2011
Sl. No. Name TRU Households Population Male Females
1. Bagru Khurd Rural 194 1438 725 713
2. Balmukundpura @
Nada Rural 96 684 348 336
3. Harchandpura @
Deoliya Rural 177 1490 760 730
4. Rampurawas Deoliya Rural 83 484 254 230
5. Thikariya Rural 345 2238 1137 1101
Total 895 6334 3224 3110
Sl. No. Location Gender Ratio
1. Gender Ratio of the Study Area 964
2. Gender Ratio in the Children (0-6 Age Group) of Study Area 905
3. Gender Ratio of District Jaipur 910
4. Gender Ratio of Rajsthan State 928
5. Gender Ratio of India 943
Enkay Enviro Services Private Limited, Jaipur EIA coordinator
Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan
Promoted by: Eldeco Infrastructure & Properties Ltd.
Literacy Profile
An average literacy rate of the study area as per census 2011 is 63.09%. The male
literacy with respect to the male population is 58.76% and the female literacy with
respect to the female population is 41.24%. The literacy gap between male & female is
approx. 17.52%. There are 36.91% people in our study area is illiterate. In the study
area of the project the literacy is as reflected from the following table:-
Table 0.3: Literacy Profile of the Study Area
*Sources: Census of India, 2011
Occupation
Occupational structure of the workforce indicates the economic activity of the region. The
occupational patterns include cultivators, agricultural labourers, and household industry
workers. The work participation rate of the study area is 28.97% in which males are 75.69%
63.09
36.91
58.76
37.4741.24
62.53
Literate Illiterate
Literacy Profile of the Stuey Area
Total Male Female
Sl. No. Name Literates
Total Male Female
1. Bagru Khurd 847 495 352
2. Balmukundpura @ Nada 343 209 134
3. Harchandpura @ Deoliya 934 576 358
4. Rampurawas Deoliya 334 200 134
5. Thikariya 1538 868 670
Total 3996 2348 1648
Enkay Enviro Services Private Limited EIA coordinator
Project: ELDECO Eden Park (Expansion)
Promoted by: Eldeco Infrastructure & Properties Ltd.
and females are 24.31%. The employment rate in the 2.0 Km
marginal workers and non workers are as follows:
� The Main workers constitute
whether as female worker’s participation is
� The Marginal workers constitute
workers of 58.70%.
� The Non Workers constitute
women 59.31% in the no
Table 0.4
S.
No
Name of the
Village
Main Workers
Total Males
1. Bagru Khurd 316 295
2. Balmukundpura
@ Nada 165 152
3. Harchandpura
@ Deoliya 425 327
4. Rampurawas
Deoliya 127 103
0
10
20
30
40
50
60
70
80
90
Total Worker Non
OCCUPATIONAL STRUCTURE OF THE PEOPLE IN THE STUDY AREA
Private Limited, Jaipur
Conceptual Plan and Environmental Management Plan
Eldeco Infrastructure & Properties Ltd.
The employment rate in the 2.0 Km. periphery for main workers,
marginal workers and non workers are as follows:
The Main workers constitute 79.95% in which male worker’s participation is
whether as female worker’s participation is 15.68%.
The Marginal workers constitute 20.05% with the male workers of 41.30
The Non Workers constitute 71.03%; and there is distribution of men
% in the non working population.
Table 0.4: Occupational Structure of the Study Area
Main Workers Marginal Workers
Males Female Total Males Female Total
21 58 24 34 1064
13 114 8 106 405
98 16 15 1 1049
24 46 10 36 311
Non-worker Main Worker Marginal Worker
OCCUPATIONAL STRUCTURE OF THE PEOPLE IN THE STUDY AREA
Conceptual Plan and Environmental Management Plan
periphery for main workers,
% in which male worker’s participation is 84.32%
41.30% and female
%; and there is distribution of men 40.79% and
: Occupational Structure of the Study Area
Non Workers
Males Female
406 658
188 217
418 631
141 170
Marginal Worker
OCCUPATIONAL STRUCTURE OF THE PEOPLE IN THE STUDY AREA
Total
Male
Female
Enkay Enviro Services Private Limited, Jaipur EIA coordinator
Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan
Promoted by: Eldeco Infrastructure & Properties Ltd.
5. Thikariya 434 360 74 134 95 39 1670 682 988
Total 1467 1237 230 368 152 216 4499 1835 2664
*Sources: Census of India, 2011
SOCIAL INFRASTRUCTURE AVAILABLE
Infrastructure Profile of the study area (1 k.m.)
*Table as provided by the building & construction manual
Note:
DWF: Drinking Water Facility C : Canal P : Phone
Tp : Tap L : Lake B : Bus
W : Well S :Spring RS : Railway Service
T : Tank O : Others NW : Navigable Waterways
TW : Tube Well PO : Post Office CB : Commercial Bank
HP : Hand Pump TO : Telegraph Office CoB : Co-operative
Bank
R : River PT : Post & Telegraph Offices
a) Educational Facilities
For the educational point of view our study area is rich. There are a lot number of educational
institutions are running around the project site. Siddha School in the Siddha Compound,
Government Upper Primary School, Bagru Khurd, 2.02 km. (SE), Government Primary
School, Thikariya, 1.4 km. (NNE), Rajsthan Dental College and Hospital, 0.53 km. (NW),
Manipal University, 1.20 km. (NNW), Parasrampuria Gem International School, 2.41 km.
(NNE), Government Senior Secondary School, Kalwara, 4.63 km. (SE) exist from the project
site.
Village DWF
Tp W T T
W
H
P
R C L S O P
O
T
O
PT P B RS NW CB CoB
1.0 km Y Y Y Y Y Y N N N N N N N N Y Y N N N N
Enkay Enviro Services Private Limited, Jaipur EIA coordinator
Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan
Promoted by: Eldeco Infrastructure & Properties Ltd.
b) Medical Facilities
There are also medical facilities exist on the project site. Rajsthan Dental College and
Hospital 0.80 km. (NW), Radha Govind Nursing Home, Kalwara, 4.79 km. (SSE) and
Rukmini Devi Memorial Hospital, Kalwara 4.98 km. (SSE) from the site.
c) Place of Worship
Following place of worship have been observed near the site:- Thakur ji Ka Temple,
1.61 km. (ENE), Shri 1008 Chandraprabhu Digambar Jain Mandir, 2.23 km. (NNE), Bad
ke Balaji Mandir, 2.79 km. (NE) and Shri Ram Chandra Mission Ashram, 3.37 km. (ENE).
d) Others
In the Siddha campus, Siddha School for the children of worker and Siddha Community
Center is available. There are first Aid Fox is available and experienced medical doctor is
visiting regularly.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator
Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan
Promoted by: Eldeco Infrastructure & Properties Ltd.
Socio Economic Observations
� The major occupations in the area involve private jobs and small retailing.
� The children were observed to be with malnutrition in the village Thikariya, Bagru
Khurd, Balmukundpura and Rampurawas @ Deoliya.
� There are working women in the study area equally as the male workers.
� Girl child education is predominantly promoted in the region and is good.
� Personal hygiene and awareness of cleanliness is good.
� Public toilets are missing in public places.
� Animal health care, mainly cattle, improves and keeps up the human health care.
� Government run healths programmes are organized in the villages falling in the study
are.
� Electricity supply is available.
� Television and FM radio is the medium of mass communication.
SOCIO ECONOMIC IMPACT
CHANGES IN COMMUNITY DEMOGRAPHICS:-
S.
no.
Existing variables/
situations of Socio-
economic Issues :
Predict (adverse/ favorable) impacts
(reasons for variations & bias of
representative data).
Mitigation measures. In
numbers.
1 Habitation in the Buffer
Zone: The existing
habitation in the
The proposed project will fulfill the
housing requirements of approximately
2019 people. The housing requirements
Regular Eco club activities
will be organized for various
environment protection and
Enkay Enviro Services Private Limited, Jaipur EIA coordinator
Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan
Promoted by: Eldeco Infrastructure & Properties Ltd.
villages Thikariya 1.78
km. (NE), Bagru Khurd
1.24 km. (SE),
Harchandpur @
Deoliya 1.57 km.
(WSW), Rampurawas
@ Deoliya 1.24 km.
(NW) and
Balmukundpura 1.71
km. (NNW) are rural
with pucca and semi-
pacca houses.
of urbanizing city of Jaipur will be
fulfilled with sustainable and inclusive
growth. The proposed project will
contribute to reduce the housing
shortage in the State, especially in
EWS/LIG categories. It will also lead to
temporary influx of approx. 200 workers
during the construction phase (peak)
and approx 25 people post operation.
This may lead to the locality
development and further. The project
will create supporting businesses, post
construction commercial activity &
indirect employment.
awareness activities
amongst the existing
residents from Thikariya,
Bagru Khurd, Harchandpur
@ Deoliya, Rampurawas
@ Deoliya and
Balmukundpura and
students of nearby
government schools, and
the incoming society of
residents in the proposed
project.
EMPLOYMENT IMPACT
S.no
.
Existing variables/
situations of Socio-
economic Issues :
Predict (adverse/ favorable) impacts
(reasons for variations & bias of
representative data).
Mitigation measures. In
numbers.
2 The existing
inhabitants in the
study area are
primarily either
engaged in the
Industrial Jobs or
private petty jobs.
Direct, (Local), Employment
Generation.
A minimum of approx. Rs. 1.19# crore
of direct money incomes could be
generated by the local people in the
region through the construction
activities.
Post construction phase: Towards
administration and staff approx. 25
Jobs.
Further, employing local
residents helps to maintain
the demographic profile of
the neighboring villages.
A proper direction given to
the villagers would help route
the savings for growth.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator
Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan
Promoted by: Eldeco Infrastructure & Properties Ltd.
3 Indirect
Employment
The secondary
employment activities
in the study area
include local labour
(daily basis), head
loading, and dairy
etc.
The security and administration will
generate post construction
opportunities. Indirect employment
Approx. 50 will also be generated
through the potential residents posing
demand of helpers, (for household
activities).
Construction materials will be
procured locally. Thus there
is a possibility of generation
of local trading opportunities,
though temporary in the
operation phase of the
project.
#: Proposed manpower [200] * [199] (Calculated at the minimum wage rate per day
of semi-skilled, Raj.) = 39,800 * 300 (approx. working days) = Rs. 1,19,40,000/-
GROWTH OF POSITIVE EXTERNALITIES
S.no. Existing variables /
situations of Socio-
economic Issues :
Predict (adverse/ favorable)
impacts (reasons for variations
& bias of representative data).
Mitigation measures. In
numbers.
4 The local markets are in
Thikariya 1.78 km. (NE),
Bagru Khurd 1.24 km. (SE)
& Mahapura 5.5 km. (ENE)
and small unorganized
markets around the main
roads.
In Thikariya, Bagru Khurd and
Mahapura, for example demand
for communication facilities, (for
each apartment), super markets
for convenience (staples, impulse
& emergency) goods is estimated
to increase.
Considering the proposed
region as rural and semi
urban, hence the mixed
income group of all the
apartments would create
the demand for all
construction related and
petty shops in the
surrounding for electrical,
mechanical, carpentry,
black smithy, and plumbing
thereby developing
positive externalities.
GROUP HOUSING V/S INDEPENDENT HOUSES
S.no. Existing Predict (adverse/ favorable) impacts Mitigation measures.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator
Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan
Promoted by: Eldeco Infrastructure & Properties Ltd.
variables/situations of
Socio-economic Issues :
(reasons for variations & bias of
representative data).
In numbers.
5 India subsists 15% of the
world population in 2.5%
of the worlds land area.
Hence with rising
population affects a
growing need of
accommodation. Group
housing provide vertical
structures and fulfills
housing requirement on a
single piece of land
whereas independent
housing expands
horizontally thereby
occupying more land,
(which further meets the
crisis of shortage of land
and rising land prices).
Growing vertical than horizontal will not
put the burden of rising prices of land on
the society :-
Considering the same piece of land
area:
Number of apartments provided by the
proposed project = 411 flats
Number of houses provided by the
independent houses = 50 approx.
(Calculated on the similar built up area
as of flats)
Further, it is analyzed that, owning an
independent house is more expensive
option than owning an apartment with
common amenities, thus resulting in
lesser number of persons entering the
independent housing market.
Proposed group
housing structures
aims at not putting the
burden of water and
sanitation on society
through its Rain water
harvesting structures
and Sewage treatment
plants.
HEALTH & RELATED IMPACTS:
S.
no.
Existing
variables/situations of
Socio-economic Issues :
Predict (adverse/ favorable)
impacts (reasons for
variations & bias of
representative data).
Mitigation measures. In
numbers.
6 Site Security
The site location is around open
vacant plots with low density
population.
Construction phase site specific
security shall be managed
Adequate security
arrangement will be made to
ensure that the local
inhabitants and the stray cattle
are not exposed to the
Enkay Enviro Services Private Limited, Jaipur EIA coordinator
Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan
Promoted by: Eldeco Infrastructure & Properties Ltd.
accordingly. potentials injury during
construction activities.
7 Health impacts – on
mental, physical, and
social well being.
The proposed project will not
adversely impact the mental,
physical and social well being.
Expectations in Fair pay,
employee care, social
responsibility commitments
etc. will be timely met.
Greivance redressal
mechanism will be made to
handle complaints from the
study area.
8. Loss/ gain of health &
fitness in short term (>1)
or long term (<1):
The deterioration in health &
fitness of the habitation will be
negligble for a temporary phase
during construciton activities.
Regular health camps to trace
the develeopments and control
any ill-consequences during
construction activities.
9. Loss/gain of view by study
area inhabitants:
The project is located in midst of
scattered housing and vacant
lands.
Plantation & landscaping will
be done, Cleanliness will be
maintained in and around the
group housing premises during
construction and post
consrtruction phases.
10. Loss/gain of culture and
religion: It is clearly stated
in as per the Human
Rights, that the obligation
of States is to promote
universal respect for, and
observance of, culture &
religion.
The proposed project will follow
universal respect for, and
observance and protection of,
human rights and fundamental
freedoms for all.
The proposed project
expansion will promote neither
selective, nor relative, but
universal respect through
contribution in various
festivities, equal observance
and protection among
employees and societies at
large in all community activities
and social responsibility.
Enkay Enviro Services Private Limited, Jaipur EIA coordinator
Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan
Promoted by: Eldeco Infrastructure & Properties Ltd.
TERTIARY IMPACTS
S.
No
.
Existing variables/
situations of Socio-
economic Issues :
Predict (adverse/ favorable)
impacts (reasons for variations &
bias of representative data).
Mitigation measures. In
numbers.
11 Economic benefits to
immediate community
and public revenue.
If the proposed group housing
project operationalizes, it is
expected to appreciate the land
prices of the LIG/MIG housing and
petty shops in the vicinity (in 2.0
k.m. vicinity).
The project after its
commencement and
operation will generate
revenue for government,
as registry, stamp duty and
House tax, to Jaipur
Development Authority.
12 Quality of Life The proposed project will provide
housing to approximately 2019
people in the project. This is a huge
society development itself. This is
descent housing in which the
residents will enjoy all facilities and
amenities of a civilized society with
adequate STP, parking and 24
hours electricity and Lower
maintenance cost.
Every measure will be
done to avoid
inconvenience of the
people and maintained
their safety and security.
13. Gain of leisure, peace
and serenity
The inner city congestions reveal
that residents in inner core of the
city have concerns regarding
housings posing a challenge with
the rising population.
The proposed project will
provide comfortable
housing for those willing to
move out of inner city.
14 CSR Benefits The proposed project aims to
contribute to sustainable community
development in the concerned
areas of Health, Employment,
Sanitation & facilities, and Women
empowerment.
An action plan is with
monetary allocation is
given below :
Enkay Enviro Services Private Limited, Jaipur EIA coordinator
Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan
Promoted by: Eldeco Infrastructure & Properties Ltd.
Corporate Social Responsibility
The proposed project is commited towards CSR with respect to its applicability with, The
Companies Act 2013.
S.
No.
Activities Capital Cost (Rs. in Lacs)
First
Year
Second
Year
Third
Year
Fourth
Year
Fifth
Year
1. Health camps at the nearest Government
Hospital.
Health camps will be organized by a
Certified government/private doctor and
medical practitioner including treatment and
medicine distribution drive. Following major
health issues has been observed in the
study area:-
Malnutrition,
Sun-burn disease,
Dental decay & checkup
In addition following activities will be done
in the village Thikariya and Bagru Khurd.
Typhoid and Hepatitis B Vaccination Camp.
Women awareness programme on health.
Eye patient will be identified in the village
and cataract surgery will be done in the eye
camp organized by Siddha Infra Private
Limited.
5.0 4.0 3.0 2.0 2.0
2. Regular Eco club activities:-
Establishment of a Eco- Club and
organization of various environment
protection and awareness activities
amongst the existing residents of Thikariya
1.78 km. (NE), Bagru Khurd 1.24 km. (SE)
and the students of Government Upper
Primary School Bagru Khurd 2.0 km. (SE),
3.0 3.0 2.0 2.0 2.0
Enkay Enviro Services Private Limited, Jaipur EIA coordinator
Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan
Promoted by: Eldeco Infrastructure & Properties Ltd.
Government Primary School, Thikariya 1.4
km. (NNE), and the student of Siddha
School in Siddha Compound with the
incoming society of residents in the
proposed project.
3. Facilities development in education /sports/
Installation of fans /Desktop computer
every year in the Government Upper
Primary School Bagru Khurd and
Government Primary School Thikariya.
3.0 2.0 2.0 2.0 1.0
4. Women Empowerment through self –
earning & sustainable Self Help group in
the village Bagru Khurd and Thikariya.
Women of these villages will be trained in
embroidery, stitching, bag-making, crotia &
macramé.
3.0 2.0 2.0 2.0 1.0
5. Erection, fittings and maintenance of
Rainwater storage structures and modular
toilets for Girls and Boys in the following
locations in the study area :
Upper Primary School Bagru Khurd,
Government Primary School School,
Thikariya,
5.0 2.0 2.0 ---- ----
Total 19.0 13.0 11.0 8.0 6.0
Capital Cost : Rs. 57.00 Lacs.
***************