CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group...

54
Project : Affordable Group Housing (Expansion) CP&EMP Promoted by : Siddha Infra Projects Pvt .Ltd. Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN INTRODUCTION: BACKGROUND & PURPOSE OF THE PROJECT: The proposed group housing project “Affordable Group Housing (Expansion)” is coming up at Khasra nos: 799, 800, 805, 808, 811, 812, 64, 65, 72, 73, 81, 82, 83, 84, 85, 86, Village Thikaria & Bagru Khurd, Tehsil Sanganer, District Jaipur, Rajasthan. Environmental Clearance for the existing project was granted vide letter no. F1 (4)/SEIAA/ SEAC- Raj/ Sectt./ Project/ Cat. 8 (a)B/ (379)/ 08-09 dated 09.09.2011. Details of proposed expansion are given as: Total Plot Area Plot Area Existing (Sq.m.) Proposed (Sq.m.) Total (Sq.m.) 52% 12896.00 1,000.00 13,896.00 48% 11904.00 500.00 12,404.00 Total 24,800 1,500 26,300.00 Total Built up Area 52% 16,729.52 - 16,729.52 48% 27,955.00 19,768.6 47,723.60 Total 44,684.52 19,768.6 64,453.12 Ground Coverage 52% 4,075.63 Nil 4,075.63 (15.50%) 48% 2,181.13 1,366.25 3,547.38 (13.49%) Total 6,256.76 1,366.25 7,623.01 (28.99%) Max. Height 52% 12.10 m. -- 48% 42.5 m. 47.5 m. BUILT UP AREA BREAKUP (48%): Sr. No. Floors Gross Built up Area (sq. m.) FAR Area (sq. m.) 1. Upper Basement 6,518.30 Nil 2. Stilt Floor 3,748.57 14.40 3. Ground Floor 3,547.38 2,855.11 4. First Floor 3,547.38 2,855.11

Transcript of CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group...

Page 1: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN

INTRODUCTION:

BACKGROUND & PURPOSE OF THE PROJECT:

The proposed group housing project “Affordable Group Housing (Expansion)” is coming up at

Khasra nos: 799, 800, 805, 808, 811, 812, 64, 65, 72, 73, 81, 82, 83, 84, 85, 86, Village Thikaria &

Bagru Khurd, Tehsil Sanganer, District Jaipur, Rajasthan.

Environmental Clearance for the existing project was granted vide letter no. F1 (4)/SEIAA/ SEAC-

Raj/ Sectt./ Project/ Cat. 8 (a)B/ (379)/ 08-09 dated 09.09.2011.

Details of proposed expansion are given as:

Total Plot Area

Plot Area Existing (Sq.m.) Proposed (Sq.m.) Total (Sq.m.)

52% 12896.00 1,000.00 13,896.00

48% 11904.00 500.00 12,404.00

Total 24,800 1,500 26,300.00

Total Built up Area

52% 16,729.52 - 16,729.52

48% 27,955.00 19,768.6 47,723.60

Total 44,684.52 19,768.6 64,453.12

Ground Coverage

52% 4,075.63 Nil 4,075.63 (15.50%)

48% 2,181.13 1,366.25 3,547.38 (13.49%)

Total 6,256.76 1,366.25 7,623.01 (28.99%)

Max. Height

52% 12.10 m. --

48% 42.5 m. 47.5 m.

BUILT UP AREA BREAKUP (48%):

Sr. No. Floors Gross Built up Area (sq. m.) FAR Area (sq. m.)

1. Upper Basement 6,518.30 Nil

2. Stilt Floor 3,748.57 14.40

3. Ground Floor 3,547.38 2,855.11

4. First Floor 3,547.38 2,855.11

Page 2: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

5. Second Floor 3,547.38 2,855.11

6. Third Floor 3,547.38 2,855.11

7. Fourth Floor 3,547.38 2,855.11

8. Fifth Floor 3,547.38 2,855.11

9. Sixth Floor 3,547.38 2,855.11

10. Seventh Floor 3,547.38 2,855.11

11. Eight Floor 3,547.38 2,855.11

12. Ninth Floor 1,637.61 1,310.03

13. Tenth Floor 1,637.61 1,310.03

14. Eleventh Floor 1,637.61 1,310.03

15. Mumty, Lift Lobby 308.74 Nil

16. Water tank, Machine Room 308.74 Nil

Total 47,723.60 29,640.48

PROJECT FACILITIES:

Details of Flats

Particulars 1 BHK 2 BHK 3 BHK Total

52% 352 48 - 400

48% 27 183 186 396

PARKING DETAILS (TOTAL):

Parking required : 665 ECU

(existing: 466 ECU; expansion: 199 ECU)

Parking provided : 704 ECU

(existing: 469 ECU; expansion: 235 ECU)

Parking Calculations:

FAR area : 29,640.48 sq. m.

ECU required : 1 ECU per 75 sq. m. of FAR area + 25 % Visitors Parking

: 413 + 103

Total ECU required : 516 ECU

Total ECU Provided : 551 ECU

Details of parking provided:

Page 3: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

S.

No.

Details Cars Two Wheelers Total

ECU

Basis of

ECS

Total area

required

Total area

provided

1. Open 162 - 162 23 sq. m. 3,726 sq. m. 3,726 sq. m.

2. Stilt 90 66 (22 ECU) 112 28 sq. m. 3,136 sq. m. 3,136 sq. m.

3. Basement 209 204 (68 ECU) 277 32 sq. m. 8,864 sq. m. 8,864 sq. m.

Total 461 270 (90 ECU) 551 15,726 sq. m. 15,726 sq. m.

POWER REQUIREMENT (48%):

S. No. Description Existing Proposed Total Remarks

1. Source of supply 33 KV supply will be from nearest GSS.

2. Electrical Load

Connected load 2651 KW 1509.80 KW 4160.80 KW Increase by 57%

Max Demand 1325.50 KW 754.90 KW 2080.4 KW

3. DG Sets

No. of DG sets 1 Nil 1 No change

Capacity 250 kVA Nil 250 kVA

Fuel consumption 40.8 l/hr Nil 40.8 l/hr

Fuel HSD (Sulphur content:

0.05%)

HSD (Sulphur

content: 0.05%)

Load Breakup:

Area

Description

Electrical

Load

Total Electrical

Connected Load

(CL)

Maximum

Demand

Load

Transformer

Rating @130%

of MDL

Power

Factor @

0.9

Proposed

Transformer

Watt/Sqft. KW KW KW KVA KVA

Block-1 8 924 462.00 600.60 667.33 750

Block-2 8 977 488.40 634.92 705.47 750

Block-3 8 1040 520.00 676.00 751.11 750

Block-4 8 960 480.00 624.00 693.33 750

Common Load

250

Total 3901 1950 2536 2817 3250

Page 4: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

WATER DEMAND:

The daily water requirement for the project will be 399 KLD (227 fresh + 172 recycled)

Existing : 350 KLD (179 fresh+ 170 recycled)

Proposed : 49 KLD (48 fresh+ 2 recycled)

BASIS OF WATER DEMEND (48%):

S.

No.

Particulars Population Fresh water

demand

Recycled water

demand

Total water

demand

1. Group Housing 2001 @65 LPCD: 130 KLD @21 LPCD: 42 KLD 172 KLD

2. Visitors 300 @ 6 LPCD: 2 KLD @ 3 LPCD:1 KLD 3 KLD

3. Staff & Admin 25 @21 LPCD: 1 KLD @9 LPCD: 1 KLD 2 KLD

4. Landscaping 1,860.60 sq. m. -- 18 KLD 18 KLD

5. General Washing 21,973.46 sq. m. -- 11 KLD 11 KLD

Total 133 KLD 73 KLD 206 KLD

Fresh water

133 KLD

Recycled/

Reused

water

73 KLD

Group Housing

(130 KLD)

Staff & Admin/Visitor

(3 KLD)

Flushing (44 KLD)

151 KLD

Waste Water

S

T

P

Capacity

200 KLD

105 KLDSludge &

Evaporation

losses

8 KLD

Total STP treated water

WATER BALANCE (48%)

Daily Water Demand = 133 + 73 = 206 KLD

2 KLD

44 KLD Supplied to

farmers

70 KLD

Landscaping & General

washing (29 KLD)

Page 5: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

IDENTIFICATION, PREDICTION AND EVALUATION OF IMPACTS:

Environmental impact can be defined as any alteration of environmental conditions, adverse or

beneficial, caused or induced by the action or set of actions under consideration.

Various operations involved in the proposed project have been studied in details to identify, predict

and evaluate impacts on various environmental components. The identified impacts were

quantified using mathematical models to a possible extent so as to estimate the future

environmental scenario.

AIR ENVIRONMENT:

AMBIENT AIR MONITORING REPORT

Agency hired: Vison Labs

(Vendor code: EES/ ADM / LSUP/ 031/ 032):

Instrument used: Respirable Dust Sampler & Fine Particle Sampler, CO Analyzer

Sampling date: 26-27.05.2014, Duration: 24 hrs.

Parameter Observation Permissible

(maximum)

PM10 (µg/m3) 69.9 < 100

PM2.5 (µg/m3) 32.5 < 60

SO2 (µg/m3) 6.3 < 80

NO2 (µg/m3) 23.5 < 80

Co(µg/m3) 601 <2000

CONSTRUCTION PHASE:

SOURCES MANAGEMENT

Dust & emissions from vehicular

exhaust.

• Regular sprinkling of water on the haul - road.

• Speed restriction of all vehicles.

• Vehicles will be checked for PUC certification.

Page 6: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

The fugitive dust emission

sources are:

• Haul road movements

• Construction

• Material Handling

• Finishing

• Water spraying to prevent dust pollution from different sources

of construction.

• All transportation vehicles will be suitably covered with tarpaulin

& overloading of the vehicles will be avoided.

• Covering of the construction site on all four sides to a

considerable height to prevent dust emissions and other

pollutants to the surrounding environment.

• Ensuring vehicles stick to the access track to prevent mud and

dirt being deposited on roads.

POST CONSTRUCTION PHASE:

DG sets: Stack height calculation

There will be no additional DG set required for the project. Power back up to the common areas

and essential services will be arranged through existing DG set of capacity 250 kVA – 1 no. The

details are tabulated as under:

S.

No.

Capacity of D.G. Set, kVA Fuel consumption Density of oil Sulphur

content

Stack

Height

1. 250 kVA- 2 nos. 40.8 l/hr/per DG 800-850 kg/cm3 0.05% 49.0 m

Calculation of stack height:

The stack height of proposed DG set is calculated as under:

H = 0.2 (√capacity of the DG set in kVA)

= 0.2 x (√250)

= 0.2 x 15.81

= 3.16 m

Say = 4.0 m

However, a safe stack height of 49.0 m above the roof of DG house will be provided .

Impact on Air Quality

The impact on air quality is assessed based on emissions of the proposed DG set and vehicular

emissions. NOx and CO will be the important pollutants emitting from these sources.

Prediction of impacts on air environment has been carried out employing mathematical model based

on a steady state Gaussian plume dispersion model designed for multiple point sources for short

Page 7: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

term. In the present case, AERMOD Version 7.1.0 dispersion model for different stability state

Gaussian plume dispersion, designed for multiple point and line sources for short term and developed

by United States Environmental Protection Agency [USEPA] has been used for simulations from point

and line sources.

Model Input Data

For the modeling purpose, all pollutants as described above are considered. The details of stack

emissions and line emissions envisaged from the project are given in Table-1 (a) & (b).

TABLE-1 (a) STACK EMISSION DETAILS

S. No. Parameters Units DG Set (250 kVA) Stack- I

1 Stack Height m 49

2 Top diameter of flue m 0.15

3 Flue gas velocity m/sec 14

4 Exit Flue gas temperature oK 453

5 Flue gas flow rate m3/sec 0.247

6 Emission rate at stack exit

A NOx g/KWh < 9.2

B CO g/KWh < 3.5

TABLE-1 (b) LINE EMISSION DETAILS

Parameter Emission rate per ECU (g/sec/m)

NOx 1.17 x 10-6

CO 1.46 x10-5

Presentation of Results

In the present case, model simulations have been carried out for the study period. The Ground level

concentrations are computed for 24-hr average. Maximum Ground level concentrations of NOx and

CO for study period were 0.83 µg/m3 and 0.67 µg/m3 respectively. The obtained GLC’s are well

within the stipulated CPCB standards. The incremental ground level concentrations for NOx and CO

are given in Table-2 (a).

Page 8: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

TABLE-2 (a)

Predicted 24-Hourly Short Term Maximum Incremental Concentrations

Pollutant Maximum Incremental

Concentration (µµµµg/m3)

(X,Y) coordinates

(m)

Towards Direction

NOx 0.83 (- 200 , 0) W

CO 0.67 (- 100 , 400) NNW

Resultant Concentrations after Implementation of the Project

The maximum incremental GLCs due to the proposed project for NOx and CO are superimposed on

the maximum baseline concentrations recorded during the study period. The cumulative

concentrations (baseline+incremental) after implementation of the project are tabulated below in

Table-2 (b). The predicted ground level concentration isopleths for various parameters during

study period is given in Figure- 1 & 2 respectively.

TABLE-2 (b)

Details of maximum incremental concentration of pollutants on the surroundings

Parameters Baseline Incremental GLC’s,

µg/m3

Resultant GLC’s,

µg/m3

Standard, µg/m3

NOx 24.3 0.83 25.1 80

CO 725 0.67 726 2000

It is seen from the above table, the resultant GLC’s obtained at Project Site are well within the

CPCB standards (dated 18th November, 2009).

Page 9: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

FIG.1

Isopleths Showing Maximum Incremental Ground Level Concentrations of NOx

Page 10: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

FIG.2

Isopleths Showing Maximum Incremental Ground Level Concentrations of CO

MANAGEMENT PLAN

SOURCES MANAGEMENT

• Exhaust from D.G. set of

capacity 250 kVA- 1 nos.

• EPA/CPCB certified DG set conforming to the standards will be

deployed.

• D.G. set will be provided with effective stack height (49.0 m) as per

the norms of CPCB above the roof of the D.G. house.

• Low sulphur content fuel (HSD - Sulphur content 0.05%) will be used.

Page 11: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

• Emission due to vehicular

exhausts especially

congestions during peak

traffic hours.

• Sufficient width of driveways to ensure smooth traffic movements.

• Provisions of fully internalized parking including the parking facilities

for the visitors.

• Guided traffic - ways within the project site.

• Speed humps will be installed for speed restrictions inside the project

area.

WATER ENVIRONMENT:

BASE LINE WATER QUALITY:

Location: Project Site

Date of sampling: 26-27.05.2014

Parameter Results Complete Test as Per IS :10500-1991

Desirable Limit Permissible Limit

Physical Parameter

Colour, Hazen Units <01 < 5 < 25

Odour Unobjectionable Unobjectionable -

Taste Agreeable Agreeable -

Turbidity, NTU 1.3 <5 .0 <10.0

pH value 7.68 6.5 - 8.5 -

Chemical Parameter

Total Hardness as CaCO3,mg/l 664 < 300 mg/l < 600 mg/l

Iron (as Fe),mg/l 0.11 < 0.3 mg/l < 1.0 mg/l

Chloride (as Cl),mg/l 340.8 < 250 mg/l < 1000 mg/l

Residual Free Chlorine, mg/l <0.02 < 0.2 --

Fluoride (as F), mg/l 1.18 < 1.0 < 1.5

Total Dissolved solids, mg/l 1564 < 500 mg/l < 2000 mg/l

Calcium( as Ca), mg/l 147.2 < 75 mg/l < 200 mg/l

Magnesium (as Mg), mg/l 71.0 < 30 mg/l < 100 mg/l

Copper (as Cu), mg/l 0.068 < 0.05 mg/l < 1.5 mg/l

Manganese as Mn 0.009 < 0.1 mg/l < 0.3 mg/l

Sulphate (as SO4), mg/l 244.8 < 200 mg/l < 400 mg/l

Nitrate (as N03), mg/l 10.7 < 45.0 mg/l No relaxation

Phenolic compounds, mg/l <0.001 < 0.001 mg/l < 0.002

Mercury(as Hg), mg/l <0.0001 < 0.001 mg/l No relaxation

Page 12: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

Arsenic (as As), mg/l <0.001 < 0.01 No relaxation

Cyanide(as Cn),mg/l <0.001 < 0.05 No relaxation

Lead( as Pb),mg/l <0.001 < 0.05 No relaxation

Zinc (as Zn),mg/l 0.38 < 5 < 15 mg/l

Chromium (as Cr),mg/l <0.001 < 0.05 No relaxation

Selenium(as Se),mg/l <0.001 < 0.01 No relaxation

Cadmium(as Cd), mg/l 0.005 < 0.01 No relaxation

Aluminum (as Al),mg/l <0.001 < 0.03 mg/l < 0.2 mg/l

Alkalinity(as CaCO3 ),mg/l 460 < 200.0 mg/l < 600 mg/l

Boron (as B) mg/l 0.038 < 1.0 mg/l < 5 mg/l

Anionic detergents(as MBAS),mg/l <0.001 < 0.2 < 1 mg/l

Conductivity uS/cm 2,426 - -

Mineral oil <0.001 <0.01 <0.03

Bacteriological Parameter

Coliform/100 ml, MPN/100 ml Nil - 10.0 (Max)

Escherichia coli/100 ml Absent - Absent

Monitoring report is enclosed as Annexure IV.

CONSTRUCTION PHASE:

SOURCES MANAGEMENT

• Generation of sewerage • Temporary septic tank followed by soaks - pit will be provided.

• Significant water demand

for construction.

• Curing water will be sprayed and after liberal curing all concrete

structures will be covered with gunny bags that will conserve water.

• There will be provision of using polymer dispersion and air entraining

agents to reduce the water demand for construction.

• Un-captured run off from

the site may contaminate

ground water aquifers.

• The rain water entering into the pit will be screened for the removal of

heavy silt and other materials.

• Provisions will be made to ensure the construction vehicles stick to the

access track to prevent mud & dirt being deposited on roads.

• Fence will be constructed around the site to trap sediments whilst

allowing the water to flow through.

• Up - slope water will be diverted with turf and due care will be taken not

to mix mortar in locations that will drain into storm water system.

• Unsanitary conditions • The civil contractor will be employed and will be responsible for site

Page 13: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

during rainy season. sanitation and will be bound by the management to adhere to healthy

level of sanitation.

• There will be no stagnant water at site, as the runoff from the relevant

areas will be systematically drained into the storm water line. There will

be provision of cleaning the storm - water line periodically.

POST CONSTRUCTION PHASE:

Waste water generation and treatment:

The waste water generated from various domestic activities will be to the tune of 262 KLD which

will be treated in the sewage treatment plant of appropriate capacity.

SEWAGE TREATMENT PLAN

STP based on Extended Aeration technology with capacity of 300 KLD will be installed for waste

water treatment. Physico - chemical characteristics of influent and effluent are given as:

Parameters Influent Treated effluent

pH 7.5 - 8.5 7 - 8

Suspended solids 250- 275 mg/l <10 mg/l

BOD 300 - 350 mg/l <5 mg/l

COD 450 - 550 mg/l <60 mg/l

Oil & Grease 8 -10 mg/l <5 mg/l

Coliforms (MPN/ 100 ml) 5-8 x 105 - 107 50 – 500/ less

Page 14: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

SCHEMETIC LAYOUT OF STP:

RAINWATER HARVESTING SCHEME:

Rain Fall Data (last 10 years):

Source: Water Resource Department, Rajasthan

907

646750

377

572 553407 392

805

563

0

200

400

600

800

1000

2012 2011 2010 2009 2008 2007 2006 2005 2004 2003

Ra

infa

ll i

n m

Year

Rainfall Data

annual rainfall standard deviation average

Page 15: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

CALCULATION OF PEAK DISCHARGE:

S.

No

Type of

Structure/ Surface

Area [A]

(sq. m.)

Run off

Coefficient

[C]

Intensity

of rainfall

(m/hour)

Total discharge

[Q]

(m3/hr)

1. Roof top area 8,781.29 0.90 0.06 474.19

2. Plantation/Landscape Area 5,364.07 0.30 0.06 96.55

3. Parking & paved areas 12,154.64 0.75 0.06 546.96

Grand Total (1-3) 26,300.00 1,117.70 say 1,118

VOLUME OF RAIN WATER DRAINAGE

Total Rain Water Flow : 1,118 m3/hr

Considering 15 minutes of peak rainfall,

Runoff volume : 279.5 m3/hr

Volume of each pit : 27 m3 (3 m x 3 m x 3 m)

Total no. of rain water harvesting pits required : Total run-off volume/ volume of each pit

: 279.5/27

: 10.35 say 11 nos.

11 Nos. Rain Water Harvesting pit of size 3 m length x 3 m width x 3 m depth with PVC slotted

pipe upto minimum depth of 35 m.

TOTAL RAIN WATER RECHARGE THROUGH RAINWATER HARVESTING:

S.

No

Type of

Structure/ Surface

Area [A]

(sq. m.)

Run off

Coefficient

[C]

Intensity

of rainfall

(m/annum)

Total discharge [Q]

(m3/annum)

1. Building foot print area 8,781.29 0.90 0.597 4,718.19

2. Landscape Area 5,364.07 0.30 0.597 960.70

3. Parking & paved areas 12,154.64 0.75 0.597 5,442.24

Grand Total (1-3) 26,300.00 11,121.13 m3/annum,

say 11,200 m3/annum

Total Annual Recharge to Ground Water Regime of the area through rainwater harvesting

structure would be 11,200.00 m3/annum.

Page 16: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services EIA coordinator Sunita Mantri

RAIN WATER HARVESTING SCHEME

MITIGATION MEASURES

S. No. Anticipated impacts

1. Daily water demand: 399 KLD

Existing: 350 KLD

Proposed:49 KLD

2. • Daily waste water generation:

KLD

• Surface / ground water

contamination due to untreated

wastewater

4. • Un-captured storm water run

Affordable Group Housing (Expansion)

Projects Pvt .Ltd.

Private Limited, Jaipur

Authorized Signatory

RAIN WATER HARVESTING SCHEME

Anticipated impacts Mitigation measures / Management

KLD • Daily fresh water demand reduced to

KLD existing + 48 KLD proposed)

of Environment Management Plan which will be met

from ground water (Existing Bore well:

• The maximum annual recharge will be to the tune of

11,200.00 cu. m. (Existing: 10,500.00 cu. m.)

harvesting the storm water.

Daily waste water generation: 262

contamination due to untreated

• Domestic waste water will be treated in sewage treatment

plant based on Extended Aeration

capacity of 300 KLD.

• Treated water from STP will be used for flushing (

landscaping & general washing (96

Farmer (70 KLD).

captured storm water run-off. • The runoff from the building terraces, paved areas and

CP&EMP

Authorized Signatory

Mitigation measures / Management

fresh water demand reduced to 227 KLD (179

after implementation

of Environment Management Plan which will be met

Existing Bore well: - 6 no.).

The maximum annual recharge will be to the tune of

(Existing: 10,500.00 cu. m.) by

water will be treated in sewage treatment

Extended Aeration technology with

Treated water from STP will be used for flushing (76 KLD),

96 KLD), Supplied to

The runoff from the building terraces, paved areas and

Page 17: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

• Flooding or logging of storm water

drains

landscape areas will be channelized to the rain water

harvesting structures designed on the peak intensity of

rainfall (60 mm/hr) to accommodate peak surface runoff,

which will avoid the problems of flooding. Details of

existing as well proposed rain – water channels and pit is

given in Utility/ Mosaic Plan (Annexure VI)

• The storm - water drains will be cleaned in the pre-

monsoon phase so that the water logging can be avoided.

LAND ENVIRONMENT:

SOIL MONITORING REPORT

Date of Monitoring: 26-27.05.2014

S. No. Parameter Result

1. pH (10 % slurry) 7.65

2. Conductivity 133 µmhos/cm

3. Moisture Content <1.00 %

4. Total Organic Matter 1.02 %

5. Phosphorous (as P) 42 mg/100gm

6. Nitrogen (as N) 196 mg/100gm

7. Potassium (as K) 68 mg/100gm

8. Sodium (as Na) 1.26 mg/100gm

9. Texture (Clay) 44%

10. Texture (Sand) 30%

11. Texture (Silt) 26%

12. Iron (as Fe) 0.06 mg/kg

13. Chloride (as Cl-) 1.04 mg/100gm

14. Water Holding Capacity 21.6 %

15. Zinc (as Zn) 3.12 mg/kg

16. Copper (as Cu) 0.18 mg/kg

17. Cadmium (as Cd) 0.02 mg/kg

18. Bulk Density 1.30 gm/cc

19. Porosity 42% v/v

20. Pearmability 4.8 Cm/s

21. Alkali Metals 0.28 mg/kg

Page 18: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

22. Lithium < 0.01 mg/kg

23. Boron (as B) 0.06 mg/kg

24. Appearance Light Brown Colour

Soil monitoring report is enclosed as Annexure VI.

CONSTRUCTION PHASE:

SOURCES MANAGEMENT

• Construction waste:

1,498 MT.

• The construction waste will be stacked properly.

• The recyclable waste (metal, wood, etc.) will be sold to the

vendors.

• The inert waste (brick, masonry, concrete, etc. will be used for

road making, filling and for strengthening the approach roads.)

POST CONSTRUCTION PHASE:

The total waste generation in the project will be 1,848 kg/day. The details are tabularized as:

S. No. Bins Particulars Quantity Treatment Disposal

1. Green

(households)

Compostable waste

Kitchen waste

Garden waste

Total: 1230 kg/day

Existing: 624 kg/day

Proposed: 606

kg/day

No in-situ

treatment.

Collected and

stored at

designated

places.

Will be sent to

Jaipur Municipal

Corporation

disposal sites.

2. Dark grey

bins

(households)

Non – biodegradable

waste + recyclable

waste:

Plastics

Metal

Glass

Misc.

Total: 618 kg/day

Existing: 416 kg/day

Proposed: 202

kg/day

No in-situ

treatment.

Collected and

stored at

designated

places.

Will be sent to

Jaipur Municipal

Corporation

disposal sites.

3. Blue

(households)

Paper waste

Paper

Newspaper

Cardboards

Packing material

Not Quantified Efforts to recycle

to the best

possible extent.

Will be collected

on daily basis.

Sold to the

vendors for

recycling.

Page 19: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

NOISE ENVIRONMENT:

NOISE MONITORING REPORT

Date of Monitoring: 26-27.05.2014

S. No. Monitoring time Unit in dB(A)

1. 06.00 53.6

2. 07.00 54.8

3. 08.00 56.9

4. 09.00 57.3

5. 10.00 55.9

6. 11.00 54.3

7. 12.00 53.9

8. 13.00 54.8

9. 14.00 51.9

10. 15.00 53.1

11. 16.00 55.8

12. 17.00 56.4

13. 18.00 54.8

14. 19.00 53.0

15. 20.00 50.7

16. 21.00 47.9

17. 22.00 45.2

18. 23.00 43.6

19. 24.00 42.8

20. 01.00 40.6

21. 02.00 38.6

22. 03.00 41.6

23. 04.00 48.9

24. 05.00 51.4

Leq day dB(A) 54.8

Leq Night dB(A) 46.3

Page 20: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

CONSTRUCTION PHASE:

During construction phase following will be the tentative sources of noise:

Name of Source Noise level at 16 m from

source {dB (A)}

Noise level at 1 m from source

{dB (A)}

Back hoe/Loader 81 105

Dump truck 83 107

Generator Not considered 75 (as prescribed by CPCB)

To understand the combined effect of these noise levels on the nearby community, Custic 3.2

(Lakes Environmental – USEPA approved) scientific model has been used to estimate the noise

levels at different distances from the proposed project. All the major noise generating machineries

like D.G. Sets, Pumps, Trucks, vibrators, drilling machine, etc., are considered in this model. The

noise level at project boundary due to different sources is calculated based on the following

formula:

Lp2 = Lp1 – 20 log (r2 / r1) – Ae1, 2

where, Lp1 and Lp2 are sound levels at points located at distance r1 / r2 from the source and Ae1,2 is

the excess attenuation due to environmental conditions. The resultant noise level is obtained by

adding existing maximum levels to that of predicted level.

The predicted noise levels based on the above analysis at the project boundary considering that

there is no attenuation on account of barriers, will be as follows:

LOCATION MAX.EXISTING MAX. PREDICTED RESULTANT MAX

Project Site 54.2 56 58.2

All values are in dB(A)

From the above, it is clearly seen that there will be no significant impact on the surrounding

community due to noise from the proposed activity.

Further due to natural attenuation effects, by proper green belt development, design / maintenance

of machines, providing PPE’s to workers, etc., the impact on noise levels will be minimal.

Page 21: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

CONSTRUCTION PHASE:

SOURCES MANAGEMENT

Major sources of

noise pollution:

• Vehicular traffic

• Heavy moving

machinery

• Operation of D.G.

sets, etc.

• The construction area will be shielded with help of tarpaulin sheets.

• Complete construction work especially heavy earth work will be done during day

time.

• Traffic planning and management will be made adequate to ensure uninterrupted

traffic movement in the area so as to minimize the noise due to congestion.

• The vehicles will be regularly maintained and optimum use of the same will be

made.

• Moving parts of the machines will be maintained properly so as to avoid metal-

to-metal impact noise.

• The D.G. sets used will be eco - friendly with minimum noise.

• Ear - plugs will be provided to the workers.

POST CONSTRUCTION PHASE:

SOURCES MANAGEMENT

• The source of

noise in the post

construction

phase may be

due to the road

traffic, operation

of D.G. sets.

• EPA/CPCB certified DG sets conforming to the standards for noise will be used.

• D.G. sets will be housed in an inbuilt acoustic enclosure, which will help to contain

the noise within the permissible standards.

• The driveways will have sufficient width so that there is no congestion of vehicles

during peak hours which will lead to increase in the noise levels.

• Adequate parking including provisions of visitors parking.

• Entry & exits will be manned with trained & efficient security to ensure smooth flow

of vehicles.

• There will be less starting and stopping and the vehicles will be speed restricted to

ensure the noise remains within the permissible limits.

• The area will cover 20.40% (5,364.07 sq.m.) area under landscape, which will help

to absorb noise.

Page 22: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

ENERGY:

• The DG sets will be used only in case of power cuts or failure for back up. Low - sulphur -

content fuel (Sulphur content 0.05%) will be used.

• Energy - efficient compact Fluorescent Lamps to be used as these CFL give same illumination

with less wattage compared to GLS Lamps.

• Sodium vapour lights will be used for external lighting.

• Power factor will be maintained around 0.90 and above. All capacitors will be provided with

Harmonic Filters to avoid distortion in Voltage

• to minimize the losses.

• Insulation of exposed walls and roof will be done to minimize heat gains inside the building.

This will help to reduce the air conditioning demand of the buildings.

• About 7.5 KL of hot water requirement of top two floors and villas will be met through solar hot

water generators 30 nos of capacity 250 L each.

Expenditure on Environmental Measures:

S.

No.

Particulars Capital Cost Annual recurring cost

Existing Proposed Existing Proposed

1 Acoustic enclosures & stack attached

to DG sets

2.0 lacs 2.0 lacs

0.50 lacs 0.20 lacs

2 STP 30.0 lacs 20.0 lacs 2.0 lacs 1.0 lacs

3 Rain water harvesting 20.0 lacs 2.0 lacs 2.0 lacs 0.20 lacs

4 Solid waste management 5.0 lacs 2.0 lacs 1.0 lacs 0.20 lacs

5 Pollution monitoring 2.0 lacs 1.0 lacs 0.50 lacs 0.20 lacs

6 Fire fighting & emergency handling 25.0 lacs 5.0 lacs 0.50 lacs 0.20 lacs

7 Green Belt 3.0 lacs 1.0 lacs 0.30 lacs 0.10 lacs

8 Training in the area of environment &

occupational health.

- - - -

Total 87.0 lacs 33.0 lacs 6.8 lacs 2.10 lacs

Page 23: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

BIODIVERSITY

Biodiversity is often taken to refer mainly to the diversity of species, especially where conservation

is under discussion. Biotic component comprises of both plant animal communities which interact

not only within and between them self but also with abiotic i.e. physical and chemical components

of the environment. Generally a biological community is being dependent on the environmental

conditions and resources of its location may change if there are many major changes in the

environment. The number of variables like temperature, humidity, atmospheric conditions, soil,

topography, etc. is responsible for maintaining the homeostasis of the environment and a change

in any one or more of these variables may tend to destabilize the ecosystem. In such cases the

change may be mostly irreversible. Therefore, the need to assess the changes of the animal and

plant resources is primary requisite as these living things determine the environmental healthiness

of any given ecosystem or environment.

Biological impact assessment generally includes listing of plants and animals present at the project

site. The identified species are then checked for their status according to IUCN list of threat

categories viz., endemic, endangered, vulnerable, rare, indeterminate and insufficiently known. In

certain cases it is also considered desirable to conduct vegetation analysis using standard phyto-

sociological methods.

Field studies were undertaken in the month of April 2014. The proposed site and habitats adjacent

to the site were surveyed for flora and fauna species, consequently, little habitat for native species

exists and fauna species composition on-site is very low.

1. SCOPE OF WORK

The biological study of the area has been conducted in order to understand the ecological

status of the existing flora and fauna to generate baseline information and evaluate the

probable impacts on the biological environment.

The present scope of work was undertaken with the following objectives:

• To collect the baseline terrestrial biodiversity status regarding flora and fauna in the

project area.

• To assess the frequency, density, abundance, Importance Value Index (IVI) and

Shannon-Wiener Diversity Index (flora).

Page 24: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

• To evaluate the dominant species of plant and animal. Secondary data also be collected

from the local residents and authenticated list of flora and fauna by the Department of

Forest, Govt. of Rajasthan, Rajasthan.

• To identify the endangered / threatened / scheduled species in the study area (both flora

and fauna). The conservation plan will be given if any wildlife species of schedule I is

present there.

• To mark the wetlands and other ecologically sensitive areas such as national parks/

sanctuaries.

• To provide the conservation plan and suggestion / recommendation for social forestry

green belt / plantation.

• To assess the effect of construction and operation of the project on existing ecology.

On the basis of onsite observations a checklist of flora and fauna was prepared.

2. DESCRIPTION OF THE STUDY AREA

The site is located between latitude 26°50'14.83"N and longitudes 75°37'2.68"E at Bhankrota,

District-Jaipur, Rajasthan. The site is about 21 km from Jaipur towards Ajmer on Jaipur-Ajmer

highway.

3. METHODOLOGY

To achieve the above objectives, study of the area was undertaken at project site. The field

sampling was conducted during the period of April 2014.

FLORAL STUDY

The vegetation sampling was carried out by using the least count quadrate method across

different habitats. The quadrants are useful for quantification of density and abundance of the

vegetation in the study area. The size and number of quadrates needed were determined using

the species area curve (Mishra, 1968) and the running mean method (Kershaw, 1973).

Summarization of previously used methods and recommendations led to the use of more than

often (10x10m) quadrates laid out for sampling the tree stratum and 1x1m quadrates for herbs and

grasses. DBH of trees was also determined. All individuals > 10 cm GBH (Girth at Breast Height)

were included in tree category. However, for examining the shrub species 3x3m sample plots were

laid out.

Page 25: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

The data collected for biodiversity information were quantitatively analyzed for density, frequency,

abundance and Shannon-Wiener Diversity Index. The relative values of frequency, density and

dominance of all the species were summed up to represent Importance Value Index (IVI). The

followings are the formulae to derive frequency, density, abundance, Importance Value Index (IVI)

etc.

Total number of quadrate in which species occurred Frequency = ————————————————————————------ x 100 Total number of quadrate studied Total number of individuals of a species Density = —————————————————---------------------------- Total number of quadrate studied Total number of individuals of species in all quadrate Abundance = ————————————————————————— Total number of quadrate in which species occurred

Total Basal Area Dominance = ————————————————— Total area sampled Frequency of the species Relative Frequency = —————————————— x 100 Total frequency of all species Density of the species Relative Density = ——————————————x 100 Total density of all species Abundance of the species Relative Abundance = —––———————————— x 100 Total abundance of all species

Page 26: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

Dominance of the species Relative Dominance = —––———————————— x 100 Total Dominance of all species Importance Value Index (IVI) = Relative frequency + Relative density +Relative dominance

Shanon – Weaver Index (1948):

The number of species and number of individuals in a community is measure of species

diversity which depends on stability of the habitat. Vegetation of the study area was assess by

determining Shannon – Weaver diversity index (1948)

D = -Σ (ni / n) log2 (ni / n)

ni = Number of individuals of each species in the sample

n = Total number of individuals

Page 27: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

3.1. FLORA :

FLORAL STUDY:

Tree (10 x 10m)

S.

N

o

Specie

s name

Binomial

name

Total

No of

quadrat

e

studied

Total no of

quadrate

in which

species

occurred

Total no of

individual

of species

in all

quadrate

Densi

ty

Relative

Density

Frequenc

y

Relative

Frequenc

y

Basal

area

(m2)

Relative

Dominan

ce

Importanc

e

Value

Index

(IVI)

SWD

Index

H= - ∑ Pi

( lnPi)

1 Neem Azadirachta

indica 25 3 4 0.16 19.048 12 23.077 0.139 34.090 76.2144 -0.31585

2 Babool Acacia

nilotica 25 10 17 0.68 80.952 40 76.923 0.268 65.910 223.7856 -0.17106

0.48691

Shrub (3 x3m)

S.

N

o

Species

name

Binomial

name

Total No

of

quadrate

studied

Total no of

quadrate in

which

species

occurred

Total no of

individual

of species

in all

quadrate

Dens

ity

Relative

Density

Freque

ncy

Relativ

e

Freque

ncy

Abunda

nce

Relativ

e

Abund

ance

Importan

ce

Value

Index

(IVI)

SWD

Index

H= - ∑

Pi

( lnPi)

1

Vilayati

Babool

Prosopis

juliflora 25 7 11 0.44 9.02 28 11.67 1.57 9.52 30.20 -0.231

2

Phog

shrub

Calligonum

polygonoide 25 8 13 0.52 10.66 32 13.33 1.63 9.84 33.83 -0.246

Page 28: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

s

3 Kair

Capparis

decidua 25 9 16 0.64 13.11 36 15.00 1.78 10.77 38.88 -0.265

4

Bui Aerva

tomentosa 25 5 12 0.48 9.84 20 8.33 2.40 14.53 32.70 -0.242

5

Aak Calotropis

procera 25 8 17 0.68 13.93 32 13.33 2.13 12.87 40.14 -0.269

6

Khimp Leptadenia

pyrotechnica 25 6 18 0.72 14.75 24 10.00 3.00 18.17 42.92 -0.278

7

Munja

grass

Saccharum

munja 25 6 11 0.44 9.02 24 10.00 1.83 11.10 30.12 -0.231

8 Ber

Zizyphus

nummularia 25 11 24 0.96 19.67 44 18.33 2.18 13.21 51.22 -0.302

2.063

Herb (1 x 1m)

S.

N

o

Species

name

Binomial

name

Total

No of

quadr

ate

studi

ed

Total no of

quadrate

in which

species

occurred

Total no

of

individual

of

species

in all

quadrate

Densi

ty

Relative

Density

Freque

ncy

Relative

Frequenc

y

Abunda

nce

Relative

Abunda

nce

Importan

ce

Value

Index

(IVI)

SWD

Index

H= - ∑ Pi

( lnPi)

1 Peeli

Doodhak

Launaea

nudicaulis 25 12 28 1.12 8.86 48 11.54 2.33 6.30 26.70 -0.247

2 Satyanasi Argemone

mexicana 25 14 41 1.64 12.97 56 13.46 2.93 7.90 34.34 -0.226

Page 29: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

3 Sarphonk

a

Tephrosia

purpurea 25 9 35 1.4 11.08 36 8.65 3.89 10.50 30.22 -0.227

4 crabgrass

Digitaria

sanguinali

s 25 5 16 0.64 5.06 20 4.81 3.20 8.64 18.51 -0.253

5 Gokharu

herb

Tribulus

terrestris 25 14 43 1.72 13.61 56 13.46 3.07 8.29 35.36 -0.217

6 Bermuda

Grass

Cynodon

dactylon 25 11 46 1.84 14.56 44 10.58 4.18 11.29 36.42 -0.261

7 Motha Cyperus

rotundus 25 12 31 1.24 9.81 48 11.54 2.58 6.97 28.32 -0.191

8 Tawa-

tawa

Euphorbia

hirta 25 5 11 0.44 3.48 20 4.81 2.20 5.94 14.23 -0.155

9 Bitter

cucumber

Citrullus

colocynthi

s 25 4 14 0.56 4.43 16 3.85 3.50 9.45 17.72 -0.142

10 Crowfoot

grass

Eleusine

indica 25 6 19 0.76 6.01 24 5.77 3.17 8.55 20.33 -0.155

11 Cobbler's

Pegs

Bidens

pilosa 25 9 21 0.84 6.65 36 8.65 2.33 6.30 21.60 -0.172

12

Jungli

Tulsi

Ocimum

tenuifloru

m 25 3 11 0.44 3.48 12 2.88 3.67 9.90 16.26 -0.189

2.434

Page 30: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project : Affordable Group Housing (Expansion) CP&EMP

Promoted by : Siddha Infra Projects Pvt .Ltd.

Enkay Enviro Services Private Limited, Jaipur EIA coordinator Sunita Mantri Authorized Signatory

3.2 FAUNA:

FAUNAL STUDY

Primary faunal studies were conducted during study in and around the project site.

The different methods adopted were as follows:

• Physical observation by the survey method conducted in the study area for the faunal

diversity study.

• Secondary data were gathered from the local habitant with the discussion.

• Data collected from the other sources for the complete biological environmental studies.

• Rapid surveys were carried out at the Siddha Aaagan site at Bhankrota, district Jaipur (Raj).

Intensive surveys were conducted at study site, which would be subjected to higher degree

of disturbance by project related activities. Data on the presence/absence of the different

faunal species in the project area was recorded largely based on direct and indirect

evidence such as tracks, spoors, dung and calls. Secondary information sources such as

published information, unpublished reports, personal communication and informal interviews

with villagers were also taken into account for supplementing primary data collected during

field studies. Standard field guides were used for identification of faunal species during the

surveys (Peater, 1980).

• Avifaunal studies (Bird surveys) were conducted at the sampling points marked for intensive

study. While traversing the area, birds were identified either by direct sighting or by calls.

Casual observations were also recorded as and when the team moved through the study

area. Field guide by Ali & Ripley, (1983) was used to identify bird species. Existing

checklists of avian species (Anon., 1998) of the project area was also consulted and

validated.

ENDANGERED/ THREATENED/ENDEMIC ANIMALS

Faunal studies were also conducted during April 2014. During the survey of the study site, no

threatened/ endemic species in and around the study area were observed.

Page 31: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan

Promoted by: Eldeco Infrastructure & Properties Ltd.

Major Features in the Study Area

Feature Name / Status

National Park / Sanctuary Nil

Biosphere Reserve /Tiger Reserve/ Elephant Reserve /any other Reserve

Nil

Habitat for migratory birds Nil

Corridor for animals of Schedule I & II of the Wildlife (Protection) Act, 1972

Nil

REPTILIAN

Particulars

S.

No.

Common name

Binomial name

Family

Schedule

IW(P)A / IUCN

Reptilian 1 Russell's viper Daboia russelii Viperidae IV

2 Garden Lizard/Girgit Calotes versicolor Agamidae LC

3 Common House Gecko Hemidactylus frenatus Gekkonidae LC

4 Yellow-Green House

Gecko

Hemidactylus flaviviridis Agamidae LC

A) AVIS OR AVIFUANA

Site specific avifaunal species observed during the site visit:

S. No. Common Name Binomial Name Family Schedule

IUCN/IW(P)A

1. House sparrow Passer domesticus Passeridae IV

2. Rock Pigeon Columba livia Columbidae IV

3. Common Bulbul Pycnonotus barbatus Pycnonotidae IV

Avifaunal species observed surrounding area of sight during visit:

S. No. Common Name Binomial Name Family Schedule

IUCN/IW(P)A

1. Common Kingfisher Alcedo atthis Alcedinidae IV

2.

Common Myna Acridotheres tristis Sturnidae IV

3.

Indian Robin Saxicoloides fulicatus Muscicapidae IV

4. Crow Pheasant Centropus sinensis Cuculidae IV

5 Rose-Ringed Parakeet Psittacula krameri Psittacidae IV

Page 32: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan

Promoted by: Eldeco Infrastructure & Properties Ltd.

4. Indian Ring Dove Streptopelia decaocto Columbidae IV

5. House crow Corvus splendens Corvidae V

6. Brown Rock Chat Cercomela fusca Muscicapidae IV

7. Oriental Magpie-Robin Copsychus saularis Muscicapidae IV

8. Indian Black Drongo Dicrurus macrocercus Dicruridae IV

E) MAMMALIA

Particulars S. No Common Name Binomial Name Family Schedule

Mammals 1 Mongoose / Neola Herpestes edwardsi Herpestidae IV

2 Five stripped palm squirrel Funambulus pennantii Sciuridae IV

3 Indian Hedgehog Paraechinus micropus Erinaceidae IV

4 Buffalo or Domestic Asian

water buffalo

Bubalus bubalis Bovidae IV

5 Common House rat Rattus rattus Muridae V

6 Indian porcupine Hystrix indica Hystricidae IV

7 Indian field mouse Mus booduga Muridae V

8 Grey Musk Shrew Suncus murinus Soricidae IV

c. Endangered species Not observed during the study period.

d. Endemic species Not observed during the study period .

e. Migratory species Avifaunal species may be migratory.

f. Aquatic fauna NIL

4.0 Green Belt Development

The greenbelt development plan aims at overall improvement in the environmental

conditions of the region. Green belt planning will be done with ecological perspectives

for project. Nature of pollutants, availability of space and dominant wind directions

should be considered. This will help in reducing the concentration of pollutants and will

also be effective in attenuating noise levels.

The plan with a five-fold objective addresses issues such as

� prevention of land degradation due to activities during construction phase;

� enhancing the forest cover for increasing the biodiversity of the region;

� providing aesthetic value to the project area and consequently inviting a

proportionate tourist flux;

� Enhancing the ecological equilibrium of the area;

Page 33: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan

Promoted by: Eldeco Infrastructure & Properties Ltd.

� A large proportion in combating soil erosion.

4.1 Criteria for selection of plant species

Moreover, keeping in view the characteristics of soil, water quality and topography of

the area the following additional aspects should also be considered;

� Fast growing and perennial species;

� Large leaf area index;

� Locally available species which are tolerable to soil and climate of area;

� Low water requirement and heat tolerant;

� Pest resistant species;

� Tolerance to inorganic chemicals;

5.0 Guidelines and Techniques for Greenbelt Development

A detailed survey was conducted with respect to existing, vegetation, types, diversity

and density etc. in the project area for development of greenbelt around project

components. The greenbelt plan has been formulated considering the parameters

such as climate, soil types etc. Greenbelt within and outside the premises will

attenuate dust emission and noise during construction. The greenbelt is also

developed for the efficient use of land and to improve the aesthetic quality of the

environment.

A careful plan of the plantation is necessary for the most efficient and economic

management. The following points should be borne in mind while developing the

greenbelt are:

� Trees growing up to 10 m or above in height with perennial foliage will be

planted around the proposed project.

� Planting of trees will be undertaken in appropriate encircling rows around the

project site.

� Generally fast growing species will be planted. Plant species should be

selected as per the environmental scenario and condition of the proposed

study site.

� Evergreen trees should be planted.

Page 34: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan

Promoted by: Eldeco Infrastructure & Properties Ltd.

� Short growing trees should be allotted at the front and tall at the back for easy

watching and to improve the appearance.

� A good fence is essential. Live fencing is economic and cheap to other kind of

fences. The plants suitable for live fencing should be drought resistant, easy to

propagate from seed, quick growing, have dense foliage, should stand severe

pruning and should be thorny.

The inter-connecting/approach roads to various project components, within the

colonies, working sites will be developed with avenue plantation, at a distance of 2 – 3

m wherever required tree guards shall be installed for protection of these plants.

The shrubs and climbers should be planted even in between the tree spaces.

Farmyard manure should also be applied to the pits of the plants for good survival.

A nursery should be created for supply of saplings, and its maintenance should be

followed. However, the saplings could also be obtained from nurseries being

developed for compensatory afforestation.

5.1 Selection of Plant Species

Keeping in view the climatic conditions, status of soils and vegetation types in and

around the project area the following species of plants have been found suitable for

plantation around the colonies, road sides and various components of the project.

Plants species for greenbelt development are as in Table 1.

In addition to above some flowering plants, shrubs, herbs, and climber plants species

will also be planted for beautification in the project area.

5.2 Spacing and Pit Size

The spacing and pit size would be vary according to the choice of species and

compatibility of various species to grow together in a niche. Small trees would be

planted at a distance of 3 m apart, while broadleaf species would be planted at a

spacing of 5 m. The pit size would be 30 cm x 30 cm x 30 cm for shrubs and herbs

whereas for the broadleaf species the size of 3 x 3 x 3 foot needs to be adopted.

5.3 Fencing and Closure

Page 35: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan

Promoted by: Eldeco Infrastructure & Properties Ltd.

A minimum block plantation would be undertaken by providing barbed wire fencing

including watch and ward for assuring protection from biotic interference.

5.4 Plantation Guard and Protection from Fire

Protection of plantation is greatest challenge from villagers and their cattle damage

the plantations before they are established. Hence protection of plantation is of

paramount importance and guards should be arranged for two to three years. Most of

the plants shall be guarded against fire, mainly in the summer season.

5.5 Suggested plants

Table 1: Following listed species are suggested to develop greenbelt around the project site:

S.No Type of Plants (Common name) Botanical name

1. Ashok Polyalthia longifolia

2. Shisham Dalbergia sissoo

3 Ardu Ailanthus excelsa

4 Kachnar Bauhinia variegata

5 Gulmohar Delonix regia

6 Neem Azadirachta indica

7 Satani Alstonia scholaris

8 Kadam Anthosephalus cadamba

9 Bottle Brush Callistemon citrinus

10 Palas Butea monosperma

11 Date Palm Phoenix sylvestris

12 Fan palm/ Bismarckia Palm Bismarck Palm

13 Sago Palm Cycas revolute

14 Jacaranda Jacaranda cuspidifolia

15 Royal Palm Roystonea regia

16 Amaltas Cassia fistula

Shrub

S.No. Common Name Botanical Name

1 Thunja Thuja occidentalis

2 Croton Codiaeum variegatum

3 Chandni Gardenia florida

Page 36: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan

Promoted by: Eldeco Infrastructure & Properties Ltd.

4 Rubber plant Ficus elastica

5 Arocraria Arocraria sp.

6 Snake plant Sansevieria trifasciata

7 Chandni Tabernaemontana divaricata

8 Bougainvillea Bougainvillea glabra

9 Fire bush Hamelia patens

Herbs

S.No. Common Name Botanical Name

1 Genda Tagetes patula

2 Rose Rosa macdub

3 Crown Daisy Garland chrysanthemum

4 Flox Phlox subulata

5 Moss rose Portulaca grandiflora

5.6 Post Plantation Care

� When the soil is dry below the surface of the mulch, it is time to water.

� Keep the soil moist but not soaked;

� Overwatering causes leaves to turn yellow or fall off.

� Water in trees at least once a week, barring rain, and more frequently during

hot weather.

� Continue until mid-fall, tapering off for lower temperatures that require less-

frequent watering.

� Other follow-up care may include minor pruning of branches damaged

during the planting process.

� Prune sparingly immediately after planting and wait to begin necessary

corrective pruning until after a full season of growth in the new location.

� Tree guard should be around the saplings until the plant reaching at mature

stage.

� Fertilizers and pesticides/insecticides should be given proper time.

6.0 IMPACT OF PROJECT ACTIVITIES ON BIODIVERSITY

DIRECT, INDIRECT AND CUMULATIVE IMPACT ON FLORA

Page 37: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan

Promoted by: Eldeco Infrastructure & Properties Ltd.

� Direct Impact

� Clearing of project site for construction activities – The project site is a waste rocky

land with sparse growth of trees and spiny shrub which are commonly distributed

throughout and none of rare, endangered or threatened or endemic species was

observed during survey / reported. Therefore no impact on biodiversity is

envisaged.

� Indirect Impact

� Construction activity is likely to affect the movement of the animal

� Increase in noise may affect the feeding, breeding and movement of animals.

Felling of trees may affect the avifauna

� Likely settling of dust to be generated by movement of vehicles and running of

crusher for construction activities on leaves may results in to stunted growth of

vegetation and may also affect the capacity of production.

� Large numbers of labour population will influx the area during construction phase.

The major threat to surrounding flora is through collection of fuel wood by labour for

cooking purposes and thereby loss of trees.

� Dumping of huge quantity of excavated earth material may lead to loss of flora in

the project area

� The soil erosion due to natural and anthropogenic activities may cause major threat

to survival of vegetation.

� Cumulative Impact

� Indirect and cumulative impacts are associated with various construction activities

such as clearing of vegetation for establishment of various project units, movement

of vehicles, construction equipments & machineries etc, interferences due to influx

of labours etc.

� The loss of land for various project unit will also not adversity affect the fauna as

similar habitat is present throughout the project immediate influenced area.

Therefore, impact due to loss of habitat for birds, reptiles and mammals of the

project area is not expected.

� Impacts on surrounding fauna due to movement of vehicles, machinery,

equipments and work force may slightly interfere in animal movements. As most of

the domestic animals Cows, Buffaloes, Goats, Sheep’s and Donkeys are guided &

Page 38: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan

Promoted by: Eldeco Infrastructure & Properties Ltd.

controlled by the owners/caretakers and hence any causality in terms of killing or

accident are not expected.

� Intermittent settlements any adverse impacts on wildlife are ruled out.

7.0 EFFECTIVE REMOVAL OF POLLUTANTS

(1) Plants grow under conditions of adequate nutritional supply (for healthy and

better growth),

(2) Absence of water stress (to maintain openness of stomatal apertures and form

of epidermal structures),

(3) Well-exposed to atmospheric conditions of light and breeze ( i.e. away from

engineering structures hindering free flow of air) to maintain free interaction

with gases.

� Characters of plants including shapes of crowns considered necessary for effecting

absorption of pollutant gases and removal of dust particles are as follows:

1) Tolerance towards pollutants in question, at concentrations, that are not

too high( to be instantaneously lethal)

2) Longer duration of foliage,

3) Freely exposed foliage , through

• Adequate height of crown,

• Openness of foliage in canopy,

• Big leaves( long and broad laminar surfaces),

• Large number of stomatal apertures,

• Stomata well- exposed ( in level with the general epidermal surface)

7.1 REMOVAL OF SUSPENDED PARTICULATE MATTER

1) Height and spread of crown,

2) Leaves supported on firm petioles,

3) Abundance of surfaces on bark and foliage, through

• Roughness of bark,

• Epidermal outgrowth on petioles,

Page 39: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan

Promoted by: Eldeco Infrastructure & Properties Ltd.

• Abundance of auxiliary hairs,

• Hairs or scales on laminar surfaces,

• Stomata protected (by wax, arches/rings, hairs etc.)

The plant species should be capable of sorption of dust pollutants and barrier of noise

pollution. Combined deficiency of a variety of species will be contributed to reach the

goals of restrict the pollution.

8.0 MITIGATION OF IMPACT: The mitigation measures of biological impacts are aimed

at (in order of preference):

i) Avoid impact,

ii) Minimize impact,

iii) Rectify impact,

iv) Compensate for impact.

Setting aside or exclusion of critically important areas, compensatory afforestation,

creation of green belts, rehabilitation of species or individuals are basic actions taken

for mitigation of impact. While creating green belt and undertaking the afforestation

works, it is required to plant indigenous/local plants and as for as possible exotics

should not be introduced. The cost of eco-restoration of the site should be included in

the project cost. This is desirable on two counts:

i) It ensures allocation of fund for undertaking the rehabilitation of the area

during and also after the project period is over.

ii) It also acts as deterrent in selection of site for the project by bringing in the

cost of eco-restoration which can be enormous in cases where activities are

proposed on a critical ecosystems.

9.0 RECOMMENDATION

At present the project site is a barren waste land with sparse growth of herbs and

shrub and few trees

� Construction activities will be restricted to day hours only.

Page 40: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan

Promoted by: Eldeco Infrastructure & Properties Ltd.

� Poaching of animals by labourers will be strictly prohibited. It may be

ensured by the contractors that no hunting is practiced at the site by any

of the workers.

� Ward and watch for the animal movement in and around the project area

during construction phase will be provided.

� Environment and Wildlife Conservation awareness program will be

organized for both work force and surrounding villages.

� All the vehicles delivering materials to the site shall be covered to avoid

spillage of material.

� Approach road used by vehicles shall be kept clean and clear of dust.

� All earth work shall be protected to minimize dust generation.

� All crusher used in construction shall confirm to relative dust emission

devises.

� All vehicles equipment machinery used in construction shall be fitted by exhaust

silencers.

� Equipments should be maintained regularly and sound proof gadgets should be

used.

� Cutting of trees should be strictly prohibited in the area for other construction

work.

� Provision of proper fencing to the plantation area.

� Watchman should be provided to care of plantation for 3-5 years

10.0 CONCLUSION

The present study is with the objective to minimize adverse environmental impacts as

discussed. The study covers all possible environmental issues involved in the project

and the necessary mitigation measures. It was observed that diversity of trees were

low while the shrub and herbs were in quite better in diverse condition which can be

sustain by the cultivation of native and local species in post construction phase.

Faunal diversity of the site was also low but avifaunal diversity of the site is much

better than the other faunal diversity. Therefore, we can say that the biological

diversity of the study site not much more impacted by the present proposed

infrastructure development and the sustainable environment scenario can be retained

Page 41: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan

Promoted by: Eldeco Infrastructure & Properties Ltd.

by the proper landscaping. Taking appropriate mitigation measures for the

sustainable environment at the site and the surrounding area is our sole

responsibility.

SOCIO ECONOMIC ENVIRONMENT

OBJECTIVES

The broad objectives of the socio-economic impact assessment are:-

1. To study the socio-economic status of the people living in the study area.

2. To assess the impact on socio-economic environment due to the project

concerned.

3. To evaluate the community development measures proposed to be taken up

by the Project Proponent, if any.

4. To suggest community development measures that needs to be taken for

the study area with stakeholder engagement.

The studies carried out are descriptive and exploratory in nature.

The information analyzed for the project has been collected from various secondary

sources, which has been supported by the extensive site visits and field

observations.

SAMPLING METHOD

The studies are conducted on a target sample; and references are drawn on the basis

of survey.

A target sample of 10 people is interviewed selected on the basis of non probability

sampling with access to the nearest habitation to the extent possible.

The proposed group housing project promoted by Siddha Infra Project Limited, in

village Thikariya & Bagru Khurd, Tehsil Sangner, District Jaipur. There are 5

habituations of respective 5 villages in the Study area of 2.0 km. periphery. There are

also few scattered houses and development Schemes within 2.0 km. periphery of

respective 5 villages.

Page 42: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan

Promoted by: Eldeco Infrastructure & Properties Ltd.

Habitation and Human settlement

The habitations of developing urbanization Thikariya, Bagru Khurd, Harchandpur at Deoliya,

Rampurawas Deoliya and Balmukundpura villages are in vicinity. There are several plotted

development scheme in the vicinity.

Population

The total population of the study area (2.0 km. periphery) is approx. 6,324. There are 895

households as per the Census of India, 2011 and approx. 7 members per household. The

proposed project falls in village Thikariya and Bagru Khurd. Details are given in the Table 0.1:-

Table 0.1: Population Composition of Study Area

*Sources: Census of India, 2011

Gender Distribution

Out of the total population, 50.90% are male and 49.10% are female in the study area. As

according to the above mentioned table, the gender ratio of the study area is approx 964 per

thousand male. The gender ratio of the study area is very pleasent as it compared to the

district Jaipur (910) and state Rajsthan (928). It is tabulated below:-

Table 0.2: Gender Ratio of the Study Area

Census of India, 2011

Sl. No. Name TRU Households Population Male Females

1. Bagru Khurd Rural 194 1438 725 713

2. Balmukundpura @

Nada Rural 96 684 348 336

3. Harchandpura @

Deoliya Rural 177 1490 760 730

4. Rampurawas Deoliya Rural 83 484 254 230

5. Thikariya Rural 345 2238 1137 1101

Total 895 6334 3224 3110

Sl. No. Location Gender Ratio

1. Gender Ratio of the Study Area 964

2. Gender Ratio in the Children (0-6 Age Group) of Study Area 905

3. Gender Ratio of District Jaipur 910

4. Gender Ratio of Rajsthan State 928

5. Gender Ratio of India 943

Page 43: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan

Promoted by: Eldeco Infrastructure & Properties Ltd.

Literacy Profile

An average literacy rate of the study area as per census 2011 is 63.09%. The male

literacy with respect to the male population is 58.76% and the female literacy with

respect to the female population is 41.24%. The literacy gap between male & female is

approx. 17.52%. There are 36.91% people in our study area is illiterate. In the study

area of the project the literacy is as reflected from the following table:-

Table 0.3: Literacy Profile of the Study Area

*Sources: Census of India, 2011

Occupation

Occupational structure of the workforce indicates the economic activity of the region. The

occupational patterns include cultivators, agricultural labourers, and household industry

workers. The work participation rate of the study area is 28.97% in which males are 75.69%

63.09

36.91

58.76

37.4741.24

62.53

Literate Illiterate

Literacy Profile of the Stuey Area

Total Male Female

Sl. No. Name Literates

Total Male Female

1. Bagru Khurd 847 495 352

2. Balmukundpura @ Nada 343 209 134

3. Harchandpura @ Deoliya 934 576 358

4. Rampurawas Deoliya 334 200 134

5. Thikariya 1538 868 670

Total 3996 2348 1648

Page 44: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Enkay Enviro Services Private Limited EIA coordinator

Project: ELDECO Eden Park (Expansion)

Promoted by: Eldeco Infrastructure & Properties Ltd.

and females are 24.31%. The employment rate in the 2.0 Km

marginal workers and non workers are as follows:

� The Main workers constitute

whether as female worker’s participation is

� The Marginal workers constitute

workers of 58.70%.

� The Non Workers constitute

women 59.31% in the no

Table 0.4

S.

No

Name of the

Village

Main Workers

Total Males

1. Bagru Khurd 316 295

2. Balmukundpura

@ Nada 165 152

3. Harchandpura

@ Deoliya 425 327

4. Rampurawas

Deoliya 127 103

0

10

20

30

40

50

60

70

80

90

Total Worker Non

OCCUPATIONAL STRUCTURE OF THE PEOPLE IN THE STUDY AREA

Private Limited, Jaipur

Conceptual Plan and Environmental Management Plan

Eldeco Infrastructure & Properties Ltd.

The employment rate in the 2.0 Km. periphery for main workers,

marginal workers and non workers are as follows:

The Main workers constitute 79.95% in which male worker’s participation is

whether as female worker’s participation is 15.68%.

The Marginal workers constitute 20.05% with the male workers of 41.30

The Non Workers constitute 71.03%; and there is distribution of men

% in the non working population.

Table 0.4: Occupational Structure of the Study Area

Main Workers Marginal Workers

Males Female Total Males Female Total

21 58 24 34 1064

13 114 8 106 405

98 16 15 1 1049

24 46 10 36 311

Non-worker Main Worker Marginal Worker

OCCUPATIONAL STRUCTURE OF THE PEOPLE IN THE STUDY AREA

Conceptual Plan and Environmental Management Plan

periphery for main workers,

% in which male worker’s participation is 84.32%

41.30% and female

%; and there is distribution of men 40.79% and

: Occupational Structure of the Study Area

Non Workers

Males Female

406 658

188 217

418 631

141 170

Marginal Worker

OCCUPATIONAL STRUCTURE OF THE PEOPLE IN THE STUDY AREA

Total

Male

Female

Page 45: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan

Promoted by: Eldeco Infrastructure & Properties Ltd.

5. Thikariya 434 360 74 134 95 39 1670 682 988

Total 1467 1237 230 368 152 216 4499 1835 2664

*Sources: Census of India, 2011

SOCIAL INFRASTRUCTURE AVAILABLE

Infrastructure Profile of the study area (1 k.m.)

*Table as provided by the building & construction manual

Note:

DWF: Drinking Water Facility C : Canal P : Phone

Tp : Tap L : Lake B : Bus

W : Well S :Spring RS : Railway Service

T : Tank O : Others NW : Navigable Waterways

TW : Tube Well PO : Post Office CB : Commercial Bank

HP : Hand Pump TO : Telegraph Office CoB : Co-operative

Bank

R : River PT : Post & Telegraph Offices

a) Educational Facilities

For the educational point of view our study area is rich. There are a lot number of educational

institutions are running around the project site. Siddha School in the Siddha Compound,

Government Upper Primary School, Bagru Khurd, 2.02 km. (SE), Government Primary

School, Thikariya, 1.4 km. (NNE), Rajsthan Dental College and Hospital, 0.53 km. (NW),

Manipal University, 1.20 km. (NNW), Parasrampuria Gem International School, 2.41 km.

(NNE), Government Senior Secondary School, Kalwara, 4.63 km. (SE) exist from the project

site.

Village DWF

Tp W T T

W

H

P

R C L S O P

O

T

O

PT P B RS NW CB CoB

1.0 km Y Y Y Y Y Y N N N N N N N N Y Y N N N N

Page 46: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan

Promoted by: Eldeco Infrastructure & Properties Ltd.

b) Medical Facilities

There are also medical facilities exist on the project site. Rajsthan Dental College and

Hospital 0.80 km. (NW), Radha Govind Nursing Home, Kalwara, 4.79 km. (SSE) and

Rukmini Devi Memorial Hospital, Kalwara 4.98 km. (SSE) from the site.

c) Place of Worship

Following place of worship have been observed near the site:- Thakur ji Ka Temple,

1.61 km. (ENE), Shri 1008 Chandraprabhu Digambar Jain Mandir, 2.23 km. (NNE), Bad

ke Balaji Mandir, 2.79 km. (NE) and Shri Ram Chandra Mission Ashram, 3.37 km. (ENE).

d) Others

In the Siddha campus, Siddha School for the children of worker and Siddha Community

Center is available. There are first Aid Fox is available and experienced medical doctor is

visiting regularly.

Page 47: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan

Promoted by: Eldeco Infrastructure & Properties Ltd.

Socio Economic Observations

� The major occupations in the area involve private jobs and small retailing.

� The children were observed to be with malnutrition in the village Thikariya, Bagru

Khurd, Balmukundpura and Rampurawas @ Deoliya.

� There are working women in the study area equally as the male workers.

� Girl child education is predominantly promoted in the region and is good.

� Personal hygiene and awareness of cleanliness is good.

� Public toilets are missing in public places.

� Animal health care, mainly cattle, improves and keeps up the human health care.

� Government run healths programmes are organized in the villages falling in the study

are.

� Electricity supply is available.

� Television and FM radio is the medium of mass communication.

SOCIO ECONOMIC IMPACT

CHANGES IN COMMUNITY DEMOGRAPHICS:-

S.

no.

Existing variables/

situations of Socio-

economic Issues :

Predict (adverse/ favorable) impacts

(reasons for variations & bias of

representative data).

Mitigation measures. In

numbers.

1 Habitation in the Buffer

Zone: The existing

habitation in the

The proposed project will fulfill the

housing requirements of approximately

2019 people. The housing requirements

Regular Eco club activities

will be organized for various

environment protection and

Page 48: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan

Promoted by: Eldeco Infrastructure & Properties Ltd.

villages Thikariya 1.78

km. (NE), Bagru Khurd

1.24 km. (SE),

Harchandpur @

Deoliya 1.57 km.

(WSW), Rampurawas

@ Deoliya 1.24 km.

(NW) and

Balmukundpura 1.71

km. (NNW) are rural

with pucca and semi-

pacca houses.

of urbanizing city of Jaipur will be

fulfilled with sustainable and inclusive

growth. The proposed project will

contribute to reduce the housing

shortage in the State, especially in

EWS/LIG categories. It will also lead to

temporary influx of approx. 200 workers

during the construction phase (peak)

and approx 25 people post operation.

This may lead to the locality

development and further. The project

will create supporting businesses, post

construction commercial activity &

indirect employment.

awareness activities

amongst the existing

residents from Thikariya,

Bagru Khurd, Harchandpur

@ Deoliya, Rampurawas

@ Deoliya and

Balmukundpura and

students of nearby

government schools, and

the incoming society of

residents in the proposed

project.

EMPLOYMENT IMPACT

S.no

.

Existing variables/

situations of Socio-

economic Issues :

Predict (adverse/ favorable) impacts

(reasons for variations & bias of

representative data).

Mitigation measures. In

numbers.

2 The existing

inhabitants in the

study area are

primarily either

engaged in the

Industrial Jobs or

private petty jobs.

Direct, (Local), Employment

Generation.

A minimum of approx. Rs. 1.19# crore

of direct money incomes could be

generated by the local people in the

region through the construction

activities.

Post construction phase: Towards

administration and staff approx. 25

Jobs.

Further, employing local

residents helps to maintain

the demographic profile of

the neighboring villages.

A proper direction given to

the villagers would help route

the savings for growth.

Page 49: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan

Promoted by: Eldeco Infrastructure & Properties Ltd.

3 Indirect

Employment

The secondary

employment activities

in the study area

include local labour

(daily basis), head

loading, and dairy

etc.

The security and administration will

generate post construction

opportunities. Indirect employment

Approx. 50 will also be generated

through the potential residents posing

demand of helpers, (for household

activities).

Construction materials will be

procured locally. Thus there

is a possibility of generation

of local trading opportunities,

though temporary in the

operation phase of the

project.

#: Proposed manpower [200] * [199] (Calculated at the minimum wage rate per day

of semi-skilled, Raj.) = 39,800 * 300 (approx. working days) = Rs. 1,19,40,000/-

GROWTH OF POSITIVE EXTERNALITIES

S.no. Existing variables /

situations of Socio-

economic Issues :

Predict (adverse/ favorable)

impacts (reasons for variations

& bias of representative data).

Mitigation measures. In

numbers.

4 The local markets are in

Thikariya 1.78 km. (NE),

Bagru Khurd 1.24 km. (SE)

& Mahapura 5.5 km. (ENE)

and small unorganized

markets around the main

roads.

In Thikariya, Bagru Khurd and

Mahapura, for example demand

for communication facilities, (for

each apartment), super markets

for convenience (staples, impulse

& emergency) goods is estimated

to increase.

Considering the proposed

region as rural and semi

urban, hence the mixed

income group of all the

apartments would create

the demand for all

construction related and

petty shops in the

surrounding for electrical,

mechanical, carpentry,

black smithy, and plumbing

thereby developing

positive externalities.

GROUP HOUSING V/S INDEPENDENT HOUSES

S.no. Existing Predict (adverse/ favorable) impacts Mitigation measures.

Page 50: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan

Promoted by: Eldeco Infrastructure & Properties Ltd.

variables/situations of

Socio-economic Issues :

(reasons for variations & bias of

representative data).

In numbers.

5 India subsists 15% of the

world population in 2.5%

of the worlds land area.

Hence with rising

population affects a

growing need of

accommodation. Group

housing provide vertical

structures and fulfills

housing requirement on a

single piece of land

whereas independent

housing expands

horizontally thereby

occupying more land,

(which further meets the

crisis of shortage of land

and rising land prices).

Growing vertical than horizontal will not

put the burden of rising prices of land on

the society :-

Considering the same piece of land

area:

Number of apartments provided by the

proposed project = 411 flats

Number of houses provided by the

independent houses = 50 approx.

(Calculated on the similar built up area

as of flats)

Further, it is analyzed that, owning an

independent house is more expensive

option than owning an apartment with

common amenities, thus resulting in

lesser number of persons entering the

independent housing market.

Proposed group

housing structures

aims at not putting the

burden of water and

sanitation on society

through its Rain water

harvesting structures

and Sewage treatment

plants.

HEALTH & RELATED IMPACTS:

S.

no.

Existing

variables/situations of

Socio-economic Issues :

Predict (adverse/ favorable)

impacts (reasons for

variations & bias of

representative data).

Mitigation measures. In

numbers.

6 Site Security

The site location is around open

vacant plots with low density

population.

Construction phase site specific

security shall be managed

Adequate security

arrangement will be made to

ensure that the local

inhabitants and the stray cattle

are not exposed to the

Page 51: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan

Promoted by: Eldeco Infrastructure & Properties Ltd.

accordingly. potentials injury during

construction activities.

7 Health impacts – on

mental, physical, and

social well being.

The proposed project will not

adversely impact the mental,

physical and social well being.

Expectations in Fair pay,

employee care, social

responsibility commitments

etc. will be timely met.

Greivance redressal

mechanism will be made to

handle complaints from the

study area.

8. Loss/ gain of health &

fitness in short term (>1)

or long term (<1):

The deterioration in health &

fitness of the habitation will be

negligble for a temporary phase

during construciton activities.

Regular health camps to trace

the develeopments and control

any ill-consequences during

construction activities.

9. Loss/gain of view by study

area inhabitants:

The project is located in midst of

scattered housing and vacant

lands.

Plantation & landscaping will

be done, Cleanliness will be

maintained in and around the

group housing premises during

construction and post

consrtruction phases.

10. Loss/gain of culture and

religion: It is clearly stated

in as per the Human

Rights, that the obligation

of States is to promote

universal respect for, and

observance of, culture &

religion.

The proposed project will follow

universal respect for, and

observance and protection of,

human rights and fundamental

freedoms for all.

The proposed project

expansion will promote neither

selective, nor relative, but

universal respect through

contribution in various

festivities, equal observance

and protection among

employees and societies at

large in all community activities

and social responsibility.

Page 52: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan

Promoted by: Eldeco Infrastructure & Properties Ltd.

TERTIARY IMPACTS

S.

No

.

Existing variables/

situations of Socio-

economic Issues :

Predict (adverse/ favorable)

impacts (reasons for variations &

bias of representative data).

Mitigation measures. In

numbers.

11 Economic benefits to

immediate community

and public revenue.

If the proposed group housing

project operationalizes, it is

expected to appreciate the land

prices of the LIG/MIG housing and

petty shops in the vicinity (in 2.0

k.m. vicinity).

The project after its

commencement and

operation will generate

revenue for government,

as registry, stamp duty and

House tax, to Jaipur

Development Authority.

12 Quality of Life The proposed project will provide

housing to approximately 2019

people in the project. This is a huge

society development itself. This is

descent housing in which the

residents will enjoy all facilities and

amenities of a civilized society with

adequate STP, parking and 24

hours electricity and Lower

maintenance cost.

Every measure will be

done to avoid

inconvenience of the

people and maintained

their safety and security.

13. Gain of leisure, peace

and serenity

The inner city congestions reveal

that residents in inner core of the

city have concerns regarding

housings posing a challenge with

the rising population.

The proposed project will

provide comfortable

housing for those willing to

move out of inner city.

14 CSR Benefits The proposed project aims to

contribute to sustainable community

development in the concerned

areas of Health, Employment,

Sanitation & facilities, and Women

empowerment.

An action plan is with

monetary allocation is

given below :

Page 53: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan

Promoted by: Eldeco Infrastructure & Properties Ltd.

Corporate Social Responsibility

The proposed project is commited towards CSR with respect to its applicability with, The

Companies Act 2013.

S.

No.

Activities Capital Cost (Rs. in Lacs)

First

Year

Second

Year

Third

Year

Fourth

Year

Fifth

Year

1. Health camps at the nearest Government

Hospital.

Health camps will be organized by a

Certified government/private doctor and

medical practitioner including treatment and

medicine distribution drive. Following major

health issues has been observed in the

study area:-

Malnutrition,

Sun-burn disease,

Dental decay & checkup

In addition following activities will be done

in the village Thikariya and Bagru Khurd.

Typhoid and Hepatitis B Vaccination Camp.

Women awareness programme on health.

Eye patient will be identified in the village

and cataract surgery will be done in the eye

camp organized by Siddha Infra Private

Limited.

5.0 4.0 3.0 2.0 2.0

2. Regular Eco club activities:-

Establishment of a Eco- Club and

organization of various environment

protection and awareness activities

amongst the existing residents of Thikariya

1.78 km. (NE), Bagru Khurd 1.24 km. (SE)

and the students of Government Upper

Primary School Bagru Khurd 2.0 km. (SE),

3.0 3.0 2.0 2.0 2.0

Page 54: CONCEPTUAL PLAN AND ENVIRONMENTAL MANAGEMENT PLAN · 2014-09-11 · Project : Affordable Group Housing (Expansion) ... Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Enkay Enviro Services Private Limited, Jaipur EIA coordinator

Project: ELDECO Eden Park (Expansion) Conceptual Plan and Environmental Management Plan

Promoted by: Eldeco Infrastructure & Properties Ltd.

Government Primary School, Thikariya 1.4

km. (NNE), and the student of Siddha

School in Siddha Compound with the

incoming society of residents in the

proposed project.

3. Facilities development in education /sports/

Installation of fans /Desktop computer

every year in the Government Upper

Primary School Bagru Khurd and

Government Primary School Thikariya.

3.0 2.0 2.0 2.0 1.0

4. Women Empowerment through self –

earning & sustainable Self Help group in

the village Bagru Khurd and Thikariya.

Women of these villages will be trained in

embroidery, stitching, bag-making, crotia &

macramé.

3.0 2.0 2.0 2.0 1.0

5. Erection, fittings and maintenance of

Rainwater storage structures and modular

toilets for Girls and Boys in the following

locations in the study area :

Upper Primary School Bagru Khurd,

Government Primary School School,

Thikariya,

5.0 2.0 2.0 ---- ----

Total 19.0 13.0 11.0 8.0 6.0

Capital Cost : Rs. 57.00 Lacs.

***************