Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes,...

20
Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes, Principal Project Manager Office of Everglades Policy and Coordination Big Cypress Basin Board Meeting February 17, 2012

Transcript of Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes,...

Page 1: Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes, Principal Project Manager Office of Everglades Policy and.

Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project

Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project

Janet Starnes, Principal Project ManagerOffice of Everglades Policy and CoordinationJanet Starnes, Principal Project ManagerOffice of Everglades Policy and Coordination

Big Cypress Basin Board MeetingFebruary 17, 2012

Page 2: Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes, Principal Project Manager Office of Everglades Policy and.

Picayune Strand RestorationProject Background, Issues and NeedsPicayune Strand RestorationProject Background, Issues and Needs

279 miles of roads and 48 miles of canals constructed on 55,000 acres by private developer in late ’60s

Resulted in over-drainage of northern and southern Golden Gate Estates

Caused extreme flows to estuaries, affecting salinity and marine habitat

Resulted in drier conditions inland Expansion of invasive plant

species such as Cabbage Palm and Brazilian Pepper

Loss of Cypress forests Plant species changed, quality

of animal habitat declined

Page 3: Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes, Principal Project Manager Office of Everglades Policy and.

Historic FlowwaysHistoric Flowways

Major Flowway

Minor Flowway

I-75

Page 4: Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes, Principal Project Manager Office of Everglades Policy and.

Missing Piece of the PuzzleMissing Piece of the Puzzle

Collier Seminole

State Park Everglade

s National

Park

Big Cypress National Preserve

Urban Developmen

t

Southern Golden Gate

Estates

Rookery Bay

National EstuarineResearch Preserve

Fakahatchee Strand State Preserve

Picayune Strand State Forrest

Florida Panther National Wildlife Refuge

10,000 Islands

National Wildlife Refuge

Restores ecological connectivity between publicly owned lands

Page 5: Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes, Principal Project Manager Office of Everglades Policy and.

Alternatives ConsideredAlternatives Considered

20+ alternatives initially formulated Three alternatives warranted further

evaluation Alternative #6 Alternative #12 Alternative #3D

“No Action” alternative also considered

Page 6: Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes, Principal Project Manager Office of Everglades Policy and.

U.S 41

6L Boundary

Restoration Plan Restoration Plan

3 Spreader Canals

3 Pump Stations

Canal Plugs

Primary Roads

Secondary Roads

Private Lands Boundaries

Berm

N

I-75

Management Roads

810 cfs

2650 cfsPrivate Lands Boundary

POI Boundary

MILLE

R C

AN

AL

FAK

A U

NIO

NC

AN

AL

MER

RIT

T C

AN

AL

PR

AIR

IE C

AN

AL

1250 cfs

U.S. 41 Drainage Enhancement

Tie-Back

Levee

Elements

Page 7: Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes, Principal Project Manager Office of Everglades Policy and.

Summary of BenefitsSummary of Benefits

Restores freshwater flows to estuaries

Restores upland/wetland habitat in watershed

Restores pre-drainage watershed flow pattern to a sheet flow condition

Increases groundwater levels

Restores habitat for endangered/threatened species (Florida panther, woodstork, etc.)

Provides for better fire management

Page 8: Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes, Principal Project Manager Office of Everglades Policy and.

Picayune Strand - Phase 1Picayune Strand - Phase 1 Seven miles of

Prairie Canal filled 65 miles of

roadway removed 17 culverts

constructed to restore natural sheet flow

More than 13,000 acres of restored and enhanced habitat

U. S. Army Corps of Engineers constructing remaining features

Page 9: Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes, Principal Project Manager Office of Everglades Policy and.

Prairie Canal Plugging – Phase IPrairie Canal Plugging – Phase I

One year after plugging of Prairie Canal

Page 10: Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes, Principal Project Manager Office of Everglades Policy and.

Phase I - Road Removal

Extent of vegetation removal and road degrading

Natural regeneration two years after degrading

Page 11: Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes, Principal Project Manager Office of Everglades Policy and.

Prairie Canal Plugging – Phase IPrairie Canal Plugging – Phase I

January 2009

Summer 2008

Page 12: Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes, Principal Project Manager Office of Everglades Policy and.

Merritt Pump StationMerritt Pump Station

810 cubic feet per second capacity

Smallest of the three PSRP pump stations

Located approximately two miles south of I-75

Page 13: Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes, Principal Project Manager Office of Everglades Policy and.

Merritt Pump Station (Cont.)

October 2010

September 2011

Page 14: Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes, Principal Project Manager Office of Everglades Policy and.

Phase II - Road RemovalPhase II - Road Removal

Area of construction is from the eastern bank of the Faka Union Canal to the western bank of the Merritt Canal

Degrade ~95 miles of roads

Page 15: Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes, Principal Project Manager Office of Everglades Policy and.

Phase II – Road RemovalPhase II – Road Removal

Example of Degraded Road

Page 16: Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes, Principal Project Manager Office of Everglades Policy and.

Faka Union Pump StationFaka Union Pump Station

2625 cubic feet per second capacity

Largest of the three PSRP pump stations

Located approximately three miles south of I-75

Page 17: Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes, Principal Project Manager Office of Everglades Policy and.

Faka Union Pump Station (cont.)Faka Union Pump Station (cont.)

Faka Union Pump Station Foundation

January 2012

Page 18: Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes, Principal Project Manager Office of Everglades Policy and.

Phase III - Road RemovalPhase III - Road Removal

Area of construction is from the eastern bank of the Miller Canal to the western bank of the Faka Union Canal

Degrade ~100 miles of roads

Page 19: Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes, Principal Project Manager Office of Everglades Policy and.

Remaining Work To Be ContractedRemaining Work To Be Contracted

Miller Pump Station and Phase IV Road Removal Construction scheduled to begin in Fall 2013 Three year construction time frame Includes protection features for “Private Lands”

Protection Features Port of the Islands - Construction scheduled to

begin in Fall 2013 6Ls/US41 - Construction scheduled to begin in

Fall 2015

Page 20: Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes, Principal Project Manager Office of Everglades Policy and.

Questions?Questions?