Transcript of COMPOSITE ELEVATED WATER STORAGE TANK … · COMPOSITE ELEVATED WATER STORAGE TANK ... • Elevated...
Typical Water Storage Tanks In the Northwest
•• Ground Level Storage ReservoirsGround Level Storage Reservoirs•• StandpipesStandpipes•• Wood Stave TanksWood Stave Tanks•• Elevated Steel Storage ReservoirsElevated Steel Storage Reservoirs•• Elevated Composite ReservoirsElevated Composite Reservoirs
Why Chose Elevated Composite?
• Cost of Steel Has Escalated• Several Contractors Now Construct Composite Tanks
Making the Costs Competitive• All the Storage Volume is Useable• Reduced Maintenance Costs• Multi-use Potential of Space in Pedestal (Office -
Storage)
More Useable Volume
159 Ft159 Ft157 Ft 6 In157 Ft 6 In
2.5 MG2.5 MG
99 Ft99 Ft
0.94 MG0.94 MG
54 Ft54 Ft
104 Ft104 Ft
5555’’--66””
Design Considerations
•• Seismic RequirementsSeismic Requirements•• Air Gap For OverflowAir Gap For Overflow•• Supplemental DisinfectionSupplemental Disinfection•• SamplingSampling•• Circulation of ContentsCirculation of Contents•• SecuritySecurity
Seismic Loading Is A ConsiderationConcrete FoundationConcrete Foundation
Donut 35 Ft Inside Donut 35 Ft Inside 69 Ft Outside69 Ft Outside
What Makes the Tank Competitive
Reinforcing Steel Reinforcing Steel PrePre--assembledassembled
Prefabricated FormsPrefabricated Forms
Where is The Steel Tank Constructed?
Set the Ring Beam SupportsSet the Ring Beam Supports
Rig and Beginning Welding the Rig and Beginning Welding the Cone Portion of the ReservoirCone Portion of the Reservoir
Certified Welding Inspector Should Be Part of Engineering Construction Team
Machine WeldsMachine Welds
Hand WeldsHand Welds
1 1 ¼”¼” PlatePlate
Raising 455,000 Pounds in Under 4 Hours
First Jacking SequenceFirst Jacking Sequence Jacks and Cable AssembliesJacks and Cable Assemblies
Tank Bottom is Prepared for Grouting Voids
22”” Threaded CouplingsThreaded Couplingsat Approximately 8 Ft at Approximately 8 Ft Centers For Grout Centers For Grout
Grout Being Pumped Into Void Between Reservoir ¼” Plate Bottom and Concrete Roof On Pedestal
Grout Flowing into Next Grout Flowing into Next Grouting PortGrouting Port
Inside Components of Reservoir
Access TubeAccess Tube
Overflow PipeOverflow Pipe
AccessAccess LadderLadder
Chlorine Injection Chlorine Injection or Sample Portor Sample Port
Completed Tank
Tank Tank AccessAccess
Center Tube Center Tube AccessAccess
Tank Tank Ventilation Ventilation
LouverLouver
FAA Clearance FAA Clearance LightLight