Compliance Report w.r.t. Environmental Clearance granted ...

26

Transcript of Compliance Report w.r.t. Environmental Clearance granted ...

Page 1: Compliance Report w.r.t. Environmental Clearance granted ...
Page 2: Compliance Report w.r.t. Environmental Clearance granted ...

1

Compliance Report w.r.t. Environmental Clearance granted by SLEIAA Raipur

(October-2017 to March-2018)

Letter No- 4021/SEIAACG/EC/BASTAR/285 dated 27.11.2015

Sr. No. COMPLIANCE CONDITION COMPLIANCE STATUS

PART A – SPECIFIC CONDITIONS

FACILITIES FOR LABOURERS DURING CONSTRUCTION:

i) Construction camp and temporary labour sheds shall be

located away from the construction site. Construction camps

shall be provided for construction personnel to avoid

indiscriminate settlement of construction workers and

labourers.

Construction workers and labourers are

belong to nearby villages, no separate

construction camp and temporary labour

sheds are constructed at site. Also note that

some skilled labours and construction

workers are residing in rented

accommodation at nearby villages (i.e.

Chokawada, Nagarnar & Dhanpunji

villages).

ii) Provision of drinking water, waste water disposal, solid

waste management and primary health facilities shall be

ensured for labour camps. Proper sanitation facilities shall

be provided at the construction site to prevent health related

problem. Domestic as well as sanitary wastes from

construction camps shall be cleared regularly. Provision

shall be made for mobile toilets. The safe disposal of waste

water and solid wastes generated during construction phase

shall be ensured.

No any construction camps and temporary

sheds are constructed at site, hence not

applicable.

iii) Waste usage during construction shall be optimized to avoid

any wastage. Complied.

The waste accumulation is minimum and

construction debris is optimized to avoid any

wastage.

iv) Adequate safety measures shall be adopted to construction

workers. Complied.

Personnel protective equipment (PPEs) have

been procured and allotted to labour force.

PPEs mobilization have been ensured and

audit on PPE quality done to ensure safety to

the construction workers and details of the

same has already been submitted.

v) All the labourers to be engaged for construction works shall

be screened for health and adequately treated before issue of

work permits. The contractor shall ensure periodic health

check-up of construction workers. A first aid room shall be

provided in the project both during construction and

operation of the project.

Complied.

Periodic health check-up of construction

workers is being carried out by Contractor

regularly. First aid room is already available

at project site.

vi) Provision shall be made for the supply of kerosene or

cooking gas / pressure cooker to the labourers during

construction phase.

No any construction camps and temporary

sheds are at site, the provision for supply of

kerosene, etc may not be applicable.

ENVIRONMENTAL MANAGEMENT DURING CONSTRUCTION:

i) As far as practicable, re-use of debris of demolished existing

building / houses / structures at existing site is recommended

with a special care for handling and disposal of asbestos

waste, if any. Rest of waste is to be disposed at the sanitary

landfill disposal site.

It is totally new construction project and no

demolition done. Also ensure that no use of

any asbestos materials at site, hence not

applicable.

Page 3: Compliance Report w.r.t. Environmental Clearance granted ...

2

ii) The asbestos waste, from demolition debris, if any, shall be

separated and shall be disposed at Common Hazardous

Wastes, Treatment and Disposal Facility.

Project is not using any asbestos wastes,

hence not applicable.

iii) Appropriate measures like adequate drainage, embankment

consolidation and slope stabilization shall be taken along the

roads to avoid soil erosion. Top soil (20 Cm) of the borrow pit

sites shall be conserved and restored after completion of

excavation. All the top soil excavated during construction

activities shall be stored for use in horticulture / landscape

development within the project site. Proper erosion control

and sediment control measures shall be adopted.

Care taken to conserve the top soil by

stacking at nearby area which is used again

as top filling material for the area under

Garden / Horticulture. Proper grading

along with turfing ensured to avoid soil

erosion.

iv) Earth material generated from excavation shall be reused to

the maximum possible extent as filling material during site

development. The construction debris and surplus excavated

material shall be disposed off by mechanical transport in

suitable pre-identified dumping areas to avoid land

degradation and water logging due to indiscriminate dumping.

Dumping areas shall be biologically reclaimed through topsoil

cover and plantation.

Complied.

Earth material generated out of excavation

is used extensively for filling up during site

development. Construction debris and

surplus earth used for road formation etc.

and no waste surplus material is dumped

outside. Where ever required top soil cover

is restored by using excavated top layer of

soil. Approximately 80% of the excavated

earth material is used in filling and rest

used in road formation.

v) A soil erosion and sedimentation control plan shall be

prepared prior to construction. The soil erosion, sedimentation

control and storm water practices shall be incorporated

depending upon the site characteristics to control soil erosion

and loss of top soil during construction.

Complied.

Suitable measures are being practiced as

per proposed construction plan. However,

site is being leveled with gentle gradation

and no soil erosion envisaged. Storm water

drainage system designed through

underground Hume pipe network to avoid

soil erosion.

vi) Disposal of muck including excavated material during

construction phase shall not create any adverse effects on the

neighboring communities and disposed off taking the

necessary precautions for general safety and health aspects.

The existing soil is not slushy in nature and

no possibility of muck generation at site as

steel shuttering for roof casting done to

avoid accumulation of muck.

vii) Low sulphur diesel type diesel generator sets should be used

during construction phase. Diesel generator sets during

construction phase shall have acoustic enclosures and shall

confirm to Environment (Protection) Rules, 1986 prescribed

for air and noise emission standards. No diesel generator sets

shall be used during operation phase.

No DG sets are being used.

viii) All vehicles/equipments deployed during construction phase

shall be ensure in good working condition and shall conform

to applicable air and noise emission standards. These shall be

operated only during non-peaking hours.

Complied.

ix) Ambient noise levels shall conform to residential standards

both during day and night. Incremental pollution loads on the

ambient and noise quality shall be closely monitored during

construction phase. Adequate measures shall be provided to

maintain ambient air quality and noise levels during

construction phase, so as to conform to the stipulated

standards by CPCB/CECB. Fortnightly monitoring of air

quality (RPM, SO2 and NOX) shall be done.

Complied.

Area is located away from the residential

zone. Also monitoring is being carried out

by Regional Office of Chhattisgarh

Environment Conservation Board time to

time and monitored data/results is available

with them.

x) The protective equipment such as earplugs etc. shall be

provided to construction personnel exposed to high noise

levels. Stationary construction equipment generating noise

Complied.

Site is located away from inhabited area

and silence zone. All works including

Page 4: Compliance Report w.r.t. Environmental Clearance granted ...

3

shall be placed away from inhabited areas and silence zone.

Construction activities carried out near residential area shall

be scheduled to daytime only. Only limited necessary

construction shall be done during night time. No unloading of

construction materials shall be done at night. Vehicular noise

and use of horn shall be controlled through enforcement of

laws and public awareness. Use of pressure horns shall be

strictly prohibited. To reduce noise level, the roads shall be

designed to have more rows of plantation.

unloading ensured in the day time only.

Provision of roadside plantation taken up.

xi) Construction spoils, including bituminous material and other

hazardous material including oil from construction equipment

must not be allowed to contaminate water courses and the

dumpsites for such material must be secured so that they shall

not leach into the ground. If necessary, oil trap shall be

installed where heavy machineries are deployed.

No such spoils generated during

construction. However, care being taken

not to spoil the environment.

xii) Proper and prior planning, sequencing and scheduling of all

major construction activities shall be done. Truck carrying

soil, sand and other construction material shall be duly

covered to prevent spillage and dust emission. Adequate dust

emission. Regular water sprinkling for dust suppression shall

be ensured.

Complied.

Work taken up by following construction

planning schedule. Trucks carrying

construction materials are ensured that

these are properly covered to prevent

spillage of dust emission.

xiii) Use of Ready- Mix concrete is recommended for this project.

Water demand during construction shall be reduced by using

pre-mix concrete, curing agents and other best materials.

Complied.

Batching plant (Ready Mix Concrete) is

being used for concreting with admixture to

reduce water demand.

xiv) Accumulation / stagnation of water shall avoid ensuring vector

control. No accumulation / stagnation of water as

site is levelled ground with a gradual slope.

xv) Regular supervision of the above and other measures shall be

in place all through the construction phase so as to avoid

disturbance to the surroundings.

Project ensured supervision through

experienced engineers from contractors.

SELECTION OF MATERIALS FOR BETTER ENERGY EFFICIENCY:

i) Use of fly ash-based bricks / blocks / tiles / products shall be

ensured. Blended and cement with fly ash shall be used. The

provision of Ministry of Environment and Forests,

Government of India latest Notification regarding use of Fly

ash must be complied with. Appropriate usage of other

industrial wastes shall also be explored. Soil borrow area

should be filled up with ash with proper compaction and

covered with topsoil kept separately. Fly ash / pond ash shall

be used for low lying area filling (if available). In

embankment / road construction etc. fly ash shall be utilized as

per the guidelines of Ministry of Environment and Forests,

Government of India / Central Pollution Control Board /

Indian Road Congress etc. concerning authorities. The use of

perforated brick / hollow blocks / fly ash based lightweight

aerated concrete etc. shall also be ensured so as to reduce load

on natural resources.

No fly ash is generated at site and nearby

area and hence no usage of fly ash bricks at

site. However, provision of AAC perforated

blocks are proposed to be used to reduce

load on natural resources.

ii) Construction shall conform to the requirements of local

seismic regulations. The project proponent shall obtain

permission for the plans and designs including structural

design, standard, safety, adequacy of firefighting equipments,

protection measures for lightning and specifications of all

construction works from concerned authority.

Complied.

Project site comes under seismic zone II

and structures are designed based on BIS

norms. Approval including provision for

structural design/standard, safety

firefighting along with lighting and other

specification obtained from Town and

Country Planning Department and copy of

Page 5: Compliance Report w.r.t. Environmental Clearance granted ...

4

the same is enclosed as Annexure-1.

iii) Reduce the use of glazed surface as per National Building

Code 2005. Use of glass in various building may be reduced

upto 40% to reduce the electric consumption and load on air

conditioning. If necessary, use of high quality double glass

with special reflective coating in windows. Roof of the various

building shall meet prescriptive requirement as per Energy

Conservation Building Code by using appropriate thermal

insulation material to fulfill requirement. Opaque wall shall

meet prescriptive requirement as per Energy Conservation

Building Code which is proposed to be mandatory for all air-

conditioned space while it is inspirational for non-air-

conditioned space by use of appropriate thermal insulation

material to fulfill requirement.

Complied.

Being a normal residential complex no

glazed façade is used. However, for

windows of standard size only glazing done

which is approximately 5% of the exposed

surface. Roof tops provided with crazy

ceramic tilling for better thermal insulation.

iv) Use of energy efficient construction materials to achieve the

desired thermal comforts shall be incorporated. The desired

level of roof assembling ‘U’ factor for the top roof shall not

exceed 0.4 Watt/sq.m/degree centigrade with appropriate

modifications of specifications and building technologies. The

provisions of National Building Code 2005 shall be strictly

followed.

Complied.

Roof insulation done with provision of

crazy ceramic tile for better energy

efficiency.

v) Modern electrical power transmission & distribution system

shall be installed. Complied.

Modern modular MCC, Microprocessor

based distribution is being used.

vi) Street lighting shall be energy efficient. Total energy

requirement of the campus should be assessed and at-least

30% of that shall be met by solar energy. Solar operated Light

Emitting Diode (LED) or Compact Fluorescent Lamps (CFL)

shall be provided in street lighting and public / common

places. High intensity, high mast lights to be installed at

intersections, parking areas, vehicle stops and major

pedestrian movement areas as per the specifications and

guidelines prescribed by Bureau of Indian Standards. Solar

water heater shall be provided for hostel and other public /

common places.

Complied.

SCADA based substation, automatic street

lighting and underground cable to

individual building blocks are envisaged.

LED street lighting system is being adopted

at site, to conserve energy high mast lights

to be used.

vii) Extensive network of cellular phones and landlines shall be

provided. The telephone and electric cables shall be laid in the

same corridor. Adequate vertical and horizontal separation

between telephone and electric cable shall be maintained.

Complied.

Network infrastructure for data & voice is

envisaged. Common cable trenches are

envisaged for laying communication &

power cable across complex.

viii) Reduce hard paving–onsite (open area surrounding building

premises) and / or provide shade on hard paved surfaces to

minimize heat island effect and imperviousness of the site.

Complied.

Hard paving is limited and ample greenery

is being provided. Imperviousness of

surrounding area is avoided by not

providing hard surface below paving.

ix) All air-conditioned buildings (if any) shall follow the norms

proposed in the ECBC regulations framed by Bureau of

Energy Efficiency. Use of chillers shall be CFC & HCFC free.

Complied.

Split types air-conditioners are provided at

Studio-1 & Studio-2 Apartments and using

free CFC & HCFC refrigerants i.e. R22 etc.

as per ECBC norms.

WATER BODY CONSERVATION:

i) Improvement or rehabilitation of existing natural streams,

channels / nallas falling within premises (if any) shall be

carried out without disturbing the ecological habitat.

Complied.

No any natural streams, channels / nallas

are falling within premises, hence not

applicable.

Page 6: Compliance Report w.r.t. Environmental Clearance granted ...

5

ii) No untreated / treated waste water shall be discharged in the

any water bodies under any circumstances. Complied.

iii) All the construction and preparatory activities shall be carried

out during dry season only. Complied

WATER SUPPLY:

i) The water treatment plant shall be provided for treatment of

water. Appropriate arrangement shall be made for treatment

and reuse of backwash water (if any).

Complied.

Treated water is being supplied to colony

from main plant and water treatment plant

is under construction.

ii) Project proponent shall provide adequate measuring

arrangement at the inlet point of water uptake and at the

discharge point for the measurement of water utilized in

different categories to monitor the daily water consumption.

Measuring arrangement of effluent generated shall also be

provided.

Water measuring devices shall be fixed at

inlet as well as outlet points for

measurement of water utilized. Such

arrangement shall be ensured for

measurement of effluent also.

iii) Water saving practices such as usage of water saving devices /

fixtures, low flow flushing systems, sensor-based fixtures,

auto control walls, pressure reducing devices etc. shall be

adopted.

Complied.

Low flow flushing system, motorized based

fixtures in pumping arrangement for

underground tank and overhead tank, auto

controlled valves pressure reducing devices

envisaged.

GREENING PROGRAMME:

i) Lay out of proposed building and roads etc. shall be made in

such a way that it shall cause minimum disturbance to

compensate the habitat loss of trees for site cleaning. The

project proponent must obtain permission for tree cutting from

competent authority as per prevailing Acts / Rules. Plantation

along the side of the roads and in open spaces shall be

developed to act as sink of air pollutants. Adequate plantation

programme of trees shall be completed in the construction

stage. The plantation programme shall be drawn to confirm

the natural climate conditions. The plantation shall consist of

mixture of available indigenous, fast growing and sturdy

species of trees, shrubs and herbs. Preferential plantation of

flowering trees with less timber and fruit value shall be carried

out. Plantation shall be done in open spaces available within

the premises. Minimum 33% area shall be covered into green

area.

Complied.

Plantation around roads and open spaces

are envisaged and being followed at site.

Various tree species as Gulmohar,

Jakranda, Neem, Mango, Palm etc. are

being planted. Green area percentage

maintained as per norms. Proposed

greenbelt layout plan is enclosed as

Annexure-2.

SEWAGE MANAGEMENT:

i) Sewage Treatment Plant based on FAB technology shall be

installed. Sewage collection system of adequate capacity to

convey the sewage during peak hours shall be laid to collect

and convey the sewage from various buildings. The

augmentation of Sewage Collection System, Sewage-Pumping

System (if any) and Sewage Treatment Plant shall be ensured

before completion of the building.

Complied.

2 Nos. STPs (200 KLD Capacity of each) is

under construction and status of the same is

enclosed as Annexure-3.

Currently sewage is routed through septic /

soak pits and same will be treated in

proposed STP just after commissioning and

will be utilized for horticulture purpose.

RAIN WATER HARVESTING SCHEME:

i) Project Proponent shall prepare Rain Water Harvesting

Schemes in consultation with Central Ground Water Authority

and Project Proponent shall ensure implementation of Rain

Water Harvesting schemes accordingly.

Complied.

Proposed rain water harvesting scheme is

already submitted to Central Ground Water

Board / Authority and copy of the same is

Page 7: Compliance Report w.r.t. Environmental Clearance granted ...

6

enclosed as Annexure-4.

ii) Rainwater from open spaces shall collect and reuse for

landscaping and other purposes. Rooftop rainwater harvesting

shall be adopted for the building. Every building shall have

rainwater harvesting facilities. The storm water flowing in

roadside drain shall also be recycled and reused to maintain

the vegetation and discharged into natural water bodies.

Before reaching the surface runoff, pretreatment must be done

to remove suspended matter and oil & grease.

Complied.

Proposed rain water harvesting scheme

including 52 numbers of recharge pits is

already submitted to Central Ground Water

Board / Authority for further approval

(Please Refer Annexure-4).

iii) Net imperviousness of the site shall not exceed the

imperviousness factor as prescribed by National Building

Code of India, Bureau of Indian Standards, 2005.

Complied.

National Building Code of India, BIS, 2005

specification is being followed to ensure

restriction of net imperviousness.

TRANSPORT MANAGEMENT:

i) Dedicated pedestrian paths shall be provided along the roads.

Appropriate access shall be provided for physically challenged

people in the pedestrian paths.

Complied.

Foot paths are envisaged and followed at

site. Access for physically challenged people

maintained with ramps etc.

ii) Traffic congestion near the entry and exit points from the

roads adjoining the project site must be avoided. The design of

service roads and the entry and exit from the building shall

conform to the norms & standards prescribed by the National

Highways Authority of India / State Public Works

Department.

Multiple gates for entry and exit envisaged

to ensure removal of congestion.

iii) Permeable (porous) paving in the parking areas, and walkways

& patio areas shall be used to control surface water runoff by

allowing storm water to infiltrate the soil and return to ground

water.

Complied.

Porous paving ensured at site, sand under

layer is being used.

iv) The road drainage shall be designed to enable quick runoff of

surface water and prevent water logging. The road level shall

be kept at least 0.5 to 1.0 meter above the observed high flood

level. The guidelines on Urban Drainage, IRC: SP-50 shall be

followed. On the both sides of all roads, well-lit and smooth

surfaced footpaths shall be provided. The hoardings shall be

strictly prohibited along the roads.

Complied.

Proper drainage systems were considered to

prevent water logging and adequate road

levels are designed.

v) All bungalows shall be provided with car parking and two-

wheeler parking areas. Adequate provision shall be made to

cater the parking needs. Parking spaces standards as given in

‘Manual on Norms and Standards for Environmental

Clearance of Large Construction Projects’ issued by Ministry

of Environment & Forests, Government of India shall be

adapted.

Complied.

Adequate space for car and two wheelers

parking is already provided to cater the

parking and ensure that it is as per the

norms of Large Construction Project.

OTHERS:

i) All mandatory approvals and permissions as required shall be

obtained. Complied.

ii) Unskilled construction labourers shall be recruited from the

local areas. Construction materials shall be procured locally as

far as possible.

Complied.

Unskilled construction labourers are being

recruited locally as per the policy of State

Government and construction materials is

also being procured locally subject to their

availability.

iii) Provision shall be made for the integration of solar water

heating system. Complied.

Solar water heating systems are already

Page 8: Compliance Report w.r.t. Environmental Clearance granted ...

7

provided.

iv) Provision of vermi-composting for the biodegradable solid

wastes as well as the large amount of biomass that shall be

available from the tree plantation shall be made.

Solid waste management system through

segregation of waste and composting in pits

using culture is envisaged.

v) The ground water shall not be abstracted without prior

permission from the competent authority in the project area. Complied.

Indravati river water is being used during

construction.

vi) Adequate roadside drains shall be provided along the road to

facilitate its better maintenance and increase in the life of the

carriageway, which shall avoid soil erosion and land

degradation due to water stagnation. The roadside drains shall

be provided on both sides of the road. Longitudinal and cross

drainage system shall be regularly maintained. Adequate new

drainage works and cross drainage structures shall be provided

for smooth passage of runoff. Filling of existing natural

drainage courses shall be strictly avoided. Suitable drainage at

construction site and camp shall be provided to eliminate the

formation of stagnant water pools.

All such drainage arrangement and

planning done keeping in view of proper

discharge of water and to avoid stagnation.

vii) Regular supervision of the above and other measures for

monitoring shall be in place all through the construction

phase, so as to avoid disturbance to the surroundings.

Complied.

viii) Under the provisions of Environment (Protection) Act, 1986,

legal action shall be initiated, if the construction of the project

has been started without obtaining Environmental Clearance.

Complied.

I OPERATION PHASE:

SEWAGE TREATMENT PLANT:

i) An independent expert shall certify the installation of the

Sewage Treatment Plant (STP) and report in this regard shall

be submitted to SEIAA, Chhattisgarh before the project is

commissioned. Project proponent shall operate and maintain

the sewage collection/conveyance system, sewage pumping

system and sewage treatment system regularly to ensure the

treated effluent quality within the standards prescribed by

Ministry of Environment and Forests, Government of India or

prescribed by Chhattisgarh Environment Conservation Board

(which ever stringent). All the effluent treatment system shall

be kept in good running conditions all the time and failure (if

any), shall be immediately rectified without delay, otherwise,

same alternate arrangement shall be made for storage of

untreated sewage until the control measures are rectified to

achieve the desired efficiency. Project proponent shall install

separate electric metering arrangement with time totalizer for

the running of pollution control systems. The record (logbook)

of power & chemical consumption for running the pollution

control systems shall be maintained.

Complied.

2 Nos. STPs (200 KLD Capacity of each) is

under construction.

Currently sewage is routed through septic /

soak pits and same will be treated in

proposed STP just after commissioning and

will be utilized for horticulture purpose.

ii) Properly treated and disinfected sewage shall be utilized in

flushing the toilets/gardening purpose/make up water in air

conditioning systems etc. No treated/untreated effluent shall

be discharged outside the premises under any circumstances.

Zero discharge condition shall be maintained all the time.

Necessary measures shall be made to mitigate the odour

problems from Sewage Treatment Plant (STP).

Complied.

2 Nos. STPs (200 KLD Capacity of each) is

under construction.

Currently sewage is routed through septic /

soak pits and same will be treated in

proposed STP just after commissioning and

will be utilized for horticulture purpose.

Page 9: Compliance Report w.r.t. Environmental Clearance granted ...

8

ENSURE ENERGY EFFICIENCY:

i) Power requirement shall be 3546 KVA through Chhattisgarh

State Electricity Board. Complied.

Power requirement is proposed & shall be

met from Chhattisgarh State Electricity

Board.

ii) The buildings shall have adequate distance among them to

allow movement of fresh air and passage of natural light, air

and ventilation.

Complied.

Ventilation, natural light and air ensured

through planned location of the buildings

as approved by Town & Country Planning

Department.

iii) During maintenance, energy efficient electric light fittings &

lamps – low power ballasts, low consumption high power

luminaries, lux level limiters & timers for street lighting shall

be provided. Used LEDs and CFLs / TFLs shall be properly

collected and disposed off/sent for recycling as per the

prevailing guidelines/rules of the regulatory authority to avoid

mercury or other contamination. A report on the energy

conservation measures confirming to energy conservation

norms finalized by Bureau of Energy Efficiency shall be

prepared incorporating details about building materials &

technology, ‘R’ value & ‘U’ factors etc.

Complied.

SCADA based substation, automatic street

lighting and underground cable to

individual building blocks are envisaged.

LED street lighting system is being adopted

at site, to conserve energy high mast lights

to be used.

MUNICIPAL SOLID WASTE/OTHER WASTES:

i) Two-chambered container (one for recyclable wastes and

other for all organic and compostable) shall be placed at

appropriate distance on the roadside and inside the building.

Covered dustbins / garbage collector in convenient places to

collect the municipal solid wastes shall be provided. Modern

trunks capable of using hydraulic lifting as well as safe

covered garbage containers shall be provided for

transportation.

Point Noted & to be complied.

ii) The proponent must develop the Solid Wastes Segregation,

Collection, Handling, Transportation and Disposal Scheme

ensuring safe and Scientific segregation, collection, handling,

transportation and disposal of organic and inorganic portion.

The organic waste is to be composed / Vermi composted at the

composed plant. The sludge generated from Sewage

Treatment Plant (after drying) shall be used as manure for

gardening purpose. Dry solid waste and recycling of all

recyclable wastes such as newspaper, aluminum cans, glass

bottles, iron scrap and plastics etc. shall be ensured. All

municipal solid wastes shall be segregated, collected,

transported, treated and disposed as per provisions of the

Municipal Solid Wastes (Management and Handling) Rules,

2000 (As amended).

Point Noted & to be complied.

iii) Public awareness programmes of benefit of living a clean and

healthy life by proper management of solid wastes shall be

organized regularly.

Complied.

iv) All hazardous wastes (if any) shall be segregated, collected,

transported, treated and disposed as per provisions of the

Hazardous Materials (Management handling and Tran

boundary Movement) Rules, 2008.

No generation of Hazardous wastes, hence

not applicable.

v) The use of hand gloves, shoes and safety dress for all waste

collectors and sorters shall be enforced. Complied.

Page 10: Compliance Report w.r.t. Environmental Clearance granted ...

9

vi) Recycling of all recyclable wastes such as newspaper,

aluminium cans, glass bottles, iron scrap and plastics etc. shall

be encouraged through private participation.

Complied.

vii) Necessary measures shall be made to mitigate the odour

problems from solid wastes processing plant. No solid waste processing plant at proposed

site, hence not applicable.

OTHERS:

i) Noise shall be controlled to ensure that it does not exceed the

prescribed standards. During nighttime the noise level

measured at the boundary of the building shall be restricted to

the permissible levels to comply with the prevalent

regulations.

Complied.

ii) Weep holes in the compound wall shall be provided to ensure

natural drainage of rainwater in the catchments area during the

monsoon period.

Complied.

iii) The ground water level and its quality shall be monitored

regularly in consultation with Central Ground Water

Authority.

Complied.

Ground water quality and water level

monitoring is being carried out and status

of the same is enclosed as Annexure-5.

PART B – GENERAL CONDITIONS

i) After approval of the competent authority appropriate

firefighting system shall be adapted.

Complied.

Approval granted from Town & Country

Planning Department (Please Refer

Annexure-1).

ii) The Environmental safeguards and mitigation measures

contained in the application shall be implemented in letter and

spirit.

Point Noted & to be complied.

iii) All the conditions, liabilities and legal provisions contained in

the Environmental Clearance shall be equally applicable to the

successor management of the project in the event of the

project proponent transferring the ownership, maintenance of

management of the project to any other entity.

Point Noted.

iv) The project proponent shall make financial provision in the

total budget of the project for implementation of the above-

mentioned conditions and for suggested environmental

safeguard measures. The funds earmarked for the

environmental protection measures shall not be diverted for

other purpose.

Point Noted.

v) Six monthly monitoring reports shall be submitted to the

SEIAA, Chhattisgarh; Regional Office, Ministry of

Environment and Forests, Government of India, Bhopal and

Chhattisgarh Environment Conservation Board, Raipur, who

shall be monitoring the implementation of environmental

safeguards, shall be given full cooperation, facilities and

documents / data by the project proponents during their

inspection. A complete set of all the documents shall submit to

State Level Environmental Impact Assessment Authority,

Complied.

Six-Monthly EC Compliance Report

including last year covering period from

June, 2017 to November, 2017 has already

been submitted on 12.01.2018 vide our

Letter No. NMDC/NISP/EC-

RESIDENTIAL COMPLEX/2018/208.

Page 11: Compliance Report w.r.t. Environmental Clearance granted ...

10

Chhattisgarh.

vi) The responsibility of implementation of environmental

safeguards rests fully on the project proponent. Project

proponent shall establish an environmental management cell

to carryout functions relating to environmental management

under the supervision of senior executive, directly reporting to

the head of organization.

Complied.

An Environmental Management Cell is

already established to carryout functions

relating to environmental management and

copy of the same is enclosed as Annexure-6.

vii) In the case of any change (S) in the scope of the project, the

project shall require a fresh appraisal by the SEIAA.

Point Noted.

viii) The issuance of this letter does not convey any property rights

in either real or personal property, or any exclusive privileges,

nor does it authorize any injury to private property or any

invasion of personal rights, nor any infringement of Central,

State or Local laws or regulations.

Point Noted.

ix) All other statutory clearances from Chief Controller of

Explosives, Fire Department, Civil Aviation Department,

Forest Conservation Act, 1980 and Wildlife (Protection) Act,

1972 etc. shall be obtained, as applicable by project

proponent. Project proponent shall obtain statutory clearances

/ licenses / permissions from concerned Central Government /

State Government Departments, Boards, Bodies and

Corporations etc. Project proponent shall follow direction

issued by Central Government / State Government, Central

Pollution Control Board / Chhattisgarh Environment

Conservation Board from time to time regarding control of

water & air pollution and for environmental conservation.

Town & Country Planning Department has

already been granted permission for

Structural Building Approval including

Fire. Other permissions such as Civil

Aviation, Forest Conservation etc. are not

applicable for this project.

x) The State Level Environmental Impact Authority,

Chhattisgarh reserves the right to amend the above conditions

and add additional safeguard measures subsequently, if found

necessary, and to take action including revoking of the

environment clearance under the provisions of the

Environmental (Protection) Act. 1986, to ensure effective

implementation of the suggested safeguard measures in a

time-bound and satisfactory manner.

Point Noted.

xi) The project proponent shall advertise in at least two local

newspapers widely circulated in the region around the project,

one of which shall be in the vernacular language of the locality

concerned within seven days from the date of this clearance

latter, informing that the project have been accorded

environmental clearance and copies of clearance letter are

available with the Chhattisgarh Environment Conservation

Board and may also seen at Website of the Ministry of

Chhattisgarh, Forests and Climate Change, Government of

Complied.

Page 12: Compliance Report w.r.t. Environmental Clearance granted ...

11

India at www.envfor.nic.in and website of SEIAA,

Chhattisgarh at www.seiaacg.org.

xii) A copy of the clearance letter shall be sent by the proponent to

concerned Panchayat, Zila Parisad / Municipal Corporation,

urban local body and the Local NGO, if any from whom

suggestions / representations, if any, received while processing

the proposal. The clearance letter shall also be put on the

website of the Company by the proponent.

Complied

xiii) Any appeal against this environmental clearance shall lie with

the National Green Tribunal, if preferred, within a period of

30 days as prescribed under section 16 of the National Green

Tribunal Act, 2010.

Point Noted.

Page 13: Compliance Report w.r.t. Environmental Clearance granted ...

ANNEXURE-1: STRUCTURAL BUILDING PLAN APPROVAL FROM TOWN & COUNTRY PLANNING DEPARTMENT

Page 14: Compliance Report w.r.t. Environmental Clearance granted ...

ANNEXURE-1: STRUCTURAL BUILDING PLAN APPROVAL FROM TOWN & COUNTRY PLANNING DEPARTMENT

Page 15: Compliance Report w.r.t. Environmental Clearance granted ...

ANNEXURE-1: STRUCTURAL BUILDING PLAN APPROVAL FROM TOWN & COUNTRY PLANNING DEPARTMENT

Page 16: Compliance Report w.r.t. Environmental Clearance granted ...

ANNEXURE-1: STRUCTURAL BUILDING PLAN APPROVAL FROM TOWN & COUNTRY PLANNING DEPARTMENT

Page 17: Compliance Report w.r.t. Environmental Clearance granted ...

ANNEXURE-1: STRUCTURAL BUILDING PLAN APPROVAL FROM TOWN & COUNTRY PLANNING DEPARTMENT

Page 18: Compliance Report w.r.t. Environmental Clearance granted ...

ANNEXURE-2: LAYOUT PLAN OF GREENBELT DEVELOPMENT

Page 19: Compliance Report w.r.t. Environmental Clearance granted ...

ANNEXURE-3: STATUS OF PROPOSED SEWAGE TREATMENT PLANT

PROPOSED WASTE WATER GENERATION & SEWAGE TREATMENT PLANT

Figure 1: Water Balance Diagram for non-rainy season

NOTE: CONSIDERED @100% FLUSHING & @80% FRESH WATER AGAINST @95% AS ADVISED BY HONORABLE SEAC COMMITTEE

Recycled Water

FRESH WATER (1307 KLD)

HORTICULTURE (170 KLD)

@ 80%

1785 KLD FLUSHING (740 KLD)

@ 100%

170 KLD

Waste water

740 KLD

WASTE WATER GENERATED (1785 KLD)

STP CAPACITY 2150 KLD

875 KLD TO EXTERNAL

Page 20: Compliance Report w.r.t. Environmental Clearance granted ...

ANNEXURE-3: STATUS OF PROPOSED SEWAGE TREATMENT PLANT

Figure 2: Water Balance Diagram for rainy season

NOTE: CONSIDERED @100% FLUSHING & @80% FRESH WATER AGAINST @95% AS ADVISED BY HONORABLE SEAC COMMITTEE Wastewater Generation & Treatment It is expected that 1785 KLD of wastewater shall be generated from project site during operation phase. Wastewater will be treated in the STP provided within the complex generating 1785 KLD of recoverable water from STP which will be recycled within the project but 875 KLD during non- rainy season and 1045 KLD during rainy season extra water will be discharge through external line. SEWAGE TREATMENT TECHNOLOGY FAB TECHNOLOGY Sewerage System An external sewage network shall collect the sewage from all units, and flow by gravity to the proposed sewage treatment plant. 20% extra STP capacity is taken so as to take load of housing during operational. Following are the benefits of providing the Sewage Treatment Plant in the present circumstances:

Recycled Water

FRESH WATER (1307 KLD)

WASTE WATER GENERATED (1785 KLD)

STP CAPACITY 2150 KLD @ 80%

1785 KLD

FLUSHING (740 KLD)

@ 100%

Waste water

740 KLD

1045 KLD TO EXTERNAL

Page 21: Compliance Report w.r.t. Environmental Clearance granted ...

ANNEXURE-3: STATUS OF PROPOSED SEWAGE TREATMENT PLANT

Reduced net daily water requirements, source for Horticultural purposes by utilization of the treated waste water. Reduced dependence on the public utilities for water supply and sewerage systems. Sludge generated from the Sewage Treatment Plant shall be rich in organic content and

an excellent fertilizer for horticultural purposes. a. Waste water Details

(a) Daily load : 2150 KLD (b) Duration of flow to STP : 24 hours (c) Temperature : Maximum 32oC (d) pH : 7 to 9.5 (e) Colour : Mild (f) T.S.S. (mg/l) : 100-400 mg/l (g) BOD (mg/l) : 200-300 mg/l (h) COD (mg/l) : 500-700 mg/l

b. Final discharge characteristics

(a) pH : 6.5 to 7.5 (b) Oil & Grease : <10 mg/l (c) B.O.D. : <20 mg/l (d) C.O.D. : <100 mg/l (e) Total Suspended Solids : <10 mg/l

c. Treatment Technology The technology is based on attached growth aerobic treatment followed by clarification by a tube settler. Lime will be dosed in for suppression of foaming tendencies. The clarified water will be filtered in a pressure sand filter after dosing of coagulant (alum) for removal of unsettled suspended impurities. This water will be passed through an activated carbon filter for removal of organics. The filtered water from ACF is then chlorinated & stored in the flushing tank. The attached growth fluidized aerobic bed reactor (FAB) process combines the biological processes of attached & suspended growth. It combines submerged fixed film with extended aeration for treatment of the waste water. The waste water after screening is collected in an equalization tank. The equalization tank is required for preventing surges in flow & facilitating equalization of characteristics over the entire quantity of effluent in a given time. A provision for pre-aeration is made in the equalization tank in order to ensure mixing & to prevent the sewage from going septic. The equalized sewage is then pumped into the FAB reactor for biological processing. The water enters the bottom of the reactor & flows up through the fixed film media which grossly enhances the hydraulic retention time & provides a large surface area for growth of biological micro – organisms. The FAB reactor is aerated by fine pore sub – surface diffusers which provide the oxygen for organic removal. The synthetic media floats on the water & the air agitation ensures good water to micro-organism contact. The FAB treatment is an attached growth type biological treatment process where in, the majority of biological activity takes place on the surface of the PVC media. Continuous aeration ensures aerobic activity on the surface of the media. Micro – organisms attach themselves on the media & grow into dense films of a viscous jelly like nature. Waste

Page 22: Compliance Report w.r.t. Environmental Clearance granted ...

ANNEXURE-3: STATUS OF PROPOSED SEWAGE TREATMENT PLANT

water passes over this film with dissolved organics passing into the bio-film due to concentration gradients within the film. Suspended particles & colloid may get retained on this sticky surface where they are decomposed into soluble products. Oxygen from the aeration process in the waste water provides oxygen for the aerobic reactions at the bio-film surface. Waste products from the metabolic processes diffuse outward & get carried away by the waste water or air currents through the voids of the media. The aerated effluent passes into a tube deck settler for clarification. The theory of gravity tube settler system is that the carrier fluid maintains laminar flow in the settling media at specified maximum viscosity. These two parameters of a carrier fluid, flowing through a hydraulic configuration, will determine the velocity gradients of the flow, the height of boundary layer at the inclined surface and the residence time within the media. The carrier fluid must be viscous Newtonian, exhibiting a Reynolds number of less than 1000 and preferably, a number under 400. The laminar flow, through the inclined tubes, will produce velocity gradients sufficiently large to form an adequate boundary layer, where the velocity of fluid approaches zero. Boundary layers are necessary in functioning tube settlers, to allow suspended solids to separate from the viscous carrier fluid. Under gravitational forces, they will settle to the hydraulic surface of the tube and subsequently from the clarifier media. Since the tubes are inclined at 60 degrees, solids settled on the tubes are continually discharged down. This downward rolling action increases particle contact and hence further agglomeration, which increases the sludge settle ability. Studies show that these agglomerated sludge particles can have a settling rate in excess of ten times the settling rate of the individual floc particles in the influent. These heavy agglomerated masses quickly slide down the 60 degree inclined tube and settle at the bottom of the tank. At the bottom of the Tube deck, where the sludge leaves the Tube surface, the larger agglomerated captures smaller particles in the upcoming stream. This solid contact phenomenon greatly enhances the capture efficiency. Stages of Treatment: The treatment process consists of the following stages:

Equalization Bio- Degradation Clarification & Settling Filtration

Page 23: Compliance Report w.r.t. Environmental Clearance granted ...

ANNEXURE-3: STATUS OF PROPOSED SEWAGE TREATMENT PLANT

Figure 3: Schematic Diagram of STP

Sewer System The alignment and slope of the sewer line will follow the road network, drains or natural ground surface and will be connected to the trunk sewers. The discharge point will be a treatment plant, a pumping station, a water course or an intercepting sewer. Pumping stations would be provided at places where the natural slope of the terrain is insufficient to permit gravity flow or the cost of excavation is uneconomical to do the same.

Page 24: Compliance Report w.r.t. Environmental Clearance granted ...

ANNEXURE-3: STATUS OF PROPOSED SEWAGE TREATMENT PLANT

Page 25: Compliance Report w.r.t. Environmental Clearance granted ...

ANNEXURE-4: PROPOSED RAIN WATER HARVESTING STRUCTURES / RECHARGING STRUCTURES

RAIN WATER HARVESTING The storm water disposal system for the premises shall be self-sufficient to avoid any collection/stagnation and flooding of water. The amount of storm water run-off depends upon many factors such as intensity and duration of precipitation, characteristics of the tributary area and the time required for such flow to reach the drains. The drains shall be located near the carriage way along either side of the roads. Taking the advantage of road camber, the rainfall run off from roads shall flow towards the drains. Storm water from various blocks shall be connected to adjacent drain by a pipe through catch basins. The water table becomes more than 25 m in future, rainwater harvesting can be carried out. Therefore, it has been calculated to provide 4 rainwater harvesting pits at selected locations, which will catch the maximum run-off from the area. 1) Since the existing topography is congenial to surface disposal, a network of storm water

pipe drains is planned adjacent to roads. All building roof water will be brought down through rain water pipes.

2) Proposed storm water system consists of pipe drain, catch basins and seepage pits at

regular intervals for rain water harvesting and ground water recharging. 3) For basement parking, the rainwater from ramps will be collected in the basement storm

water storage tank. This water will be pumped out to the nearest external storm water drain.

4) Annual rainfall of 731mm/yr shall be considered for designing the storm water drainage

system. Peak hourly rainfall has been considered as 25 mm/hr. The recharge pit of 2.5mx5mx4m is constructed for recharging the water. Inside the recharge pit, a recharge bore is constructed having 300 mm diameter and 30 m depth. The bottom of the recharge structure will be kept 4 m above this level. At the bottom of the recharge well, a filter media is provided to avoid choking of the recharge bore. Design specifications of the rain water harvesting plan are as follows:

Catchments/roofs would be accessible for regular cleaning. The roof will have smooth, hard and dense surface which is less likely to be damaged allowing release of material into the water. Roof painting has been avoided since most paints contain toxic substances and may peel off. All gutter ends will be fitted with a wire mesh screen and a first flush device would be installed. Most of the debris carried by the water from the rooftop like leaves, plastic bags and paper pieces will get arrested by the mesh at the terrace outlet and to prevent contamination by ensuring that the runoff from the first 10-20 minutes of rainfall is flushed off. No sewage or wastewater would be admitted into the system.

No wastewater from areas likely to have oil, grease, or other pollutants has been connected to the system. Calculations for storm water load Roof-top area = Ground Coverage = 418512.01 m2

Page 26: Compliance Report w.r.t. Environmental Clearance granted ...

ANNEXURE-4: PROPOSED RAIN WATER HARVESTING STRUCTURES / RECHARGING STRUCTURES

Green Area = 33980.17 m2 Paved Area = Total Plot Area – (Roof-top Area + Green Area)

= 491603.25– (418512.01 + 33980.17) = 39111.07m2 Runoff Load Roof-top Area = 418512.01 × 0.025 × 0.95 = 9939.66 m3/hr Green Area = 33980.17 × 0.025 × 0.1 = 84.95 m3/hr Paved Area = 39111.07 × 0.025 × 0.75 = 733.33 m3/hr Total Runoff Load = ( 9939.66 + 84.95 + 733.33 ) m3/hr = 10757.94 m3/hr Taking 15 minutes Retention Time, Total volume of storm water = 10757.94 /4 = 2689.48 m3 Taking the effective size of a Recharge pit 2.5mx5mx4m respectively, Volume of a single Recharge pit = L x B x H = 2.5 x 5 x 4 = 50 m3 Hence No. of pits required = 2689.48/50 = 53.78 or say 54 Pits.

Figure-1: Rain Water Harvesting Structures