Complete Well Design

download Complete Well Design

of 18

Transcript of Complete Well Design

  • 8/3/2019 Complete Well Design

    1/18

    ContentsExecutive summary ......................................................................... 2

    1. Rig selection ........................................................................... 2

    2. Pore pressure and fracture pressure. ......................................... 4

    3. Problems that could be encountered during drilling in differentformations. ..................................................................................... 5

    4. Casing scheme ........................................................................ 6

    5. Mud types. Mud programme ..................................................... 7

    6. Functions of cement. Cement programme .................................. 9

    7. Maximum hook load .............................................................. 10

    8. Safety while drilling ............................................................... 11

    9. Well completion .................................................................... 12

    Conclusion .................................................................................... 13

    Appendix A. Molly field pressure profile, mud weights and casing stringsdepths ......................................................................................... 14

    Appendix B. Hook load calculation ................................................... 15

    Appendix C. BOP stack working pressure calculation .......................... 16

    Appendix D. Downhole completion design ......................................... 17

    References.................................................................................... 18

    Bibliography .................................................................................. 18

  • 8/3/2019 Complete Well Design

    2/18

    2 | P a g e

    Executive summary

    This report provides a brief description of main steps of well planning

    process through the example of an exploratory well in the Molly field in

    the North Sea. The main steps include: rig selection, study of pore

    pressures, fracture pressures and lithology, construction of casing design,

    mud and cement programme, completion design and design of well

    control system.

    1. Rig selectionThere are many criteria that should be taken into account when selecting

    a proper marine rig. This is the list of main criteria:

    1. Water depth rating2. Derrick and substructure capacity3. Physical rig size and weight4. Deck load capacity5. Stability in rough weather6. Duration of drilling programme7. Rig rating features, i.e. horsepower, pipe handling capabilities,

    mud mixing capacity

    8. Exploratory vs. development drilling9. Availability and cost

    Water depth rating is usually considered as most important selection

    criteria for offshore rigs. For this reason, the selection process of suitable

    rig to drill a well in Molly field should be considered in accordance with

    this main factor.

    Generally, Mobile Offshore Drilling Units are divided into two categories:

    floaters and bottom supported. Floaters are located on top of the water

    surface or slightly below it. This group includes two types of drilling rigs -

    semisubmersibles and drill ships. Bottom-supported rigs, on the other

    hand, are contacting the bottom of the sea and are supported by it.

  • 8/3/2019 Complete Well Design

    3/18

    3 | P a g e

    Most widely used type of marine drilling units is a jackup rig. The largest

    jackup rigs are able to drill in locations with water depths up to 400 feet,

    while the maximum well depth is around 30,000 feet. (Baker 2001) Deep

    platforms are capable of drilling wells in water depths up to 1000 ft, but

    their usage is economically justified only for long-term development

    drilling. (Adams and Charrier 1985) Semisubmersible rigs are specially

    designed vessels for offshore petroleum industry, therefore operation

    costs are generally much higher due to large amounts of initial

    investment required.

    Implementation of a jackup rig for drilling a well in Molly field would be

    economically most efficient alternative. The water depth of 160 ft is in

    the range of operation of most jackup rigs, thus there is no necessity to

    use floating units that are capable to operate in deeper waters. Operation

    costs of a jackup rig are much lower and they are more easily available

    on the market. From the shallow water depth it can be assumed that

    Molly field is located not far from the shore, therefore there is no need to

    utilize a drillship capable of carrying large amounts of equipment and

    materials required for drilling.

  • 8/3/2019 Complete Well Design

    4/18

    4 | P a g e

    2. Pore pressure and fracture pressure.Pore pressure.

    Formation pressure is one of the most important factors that influences

    well design and drilling operations. If formation pressure is not correctly

    estimated, it can lead to variety of drilling problems, for instance

    blowouts, lost circulation, hole instability, stuck pipe and excessive costs.

    However, in zones of abnormal pressures it can be very challenging to

    predict formation pressures accurately.

    Knowledge of formation pressures is the basis of the whole well planning

    process, thus not enough attention paid to formation pressure evaluation

    can cause in the other stages of well planning being inadequate.

    To predict formation pressure several methods can be implemented. They

    can be categorized in three groups:

    1.Areal analysis from seismic data

    2. Offset well correlationa. log analysisb. drilling parameter evaluationc. production or test data

    3. real-time evaluationa. qualitativeb. quantitative (Adams and Charrier 1985)

    Fracture pressure

    Reliable information on fracture pressure gradient is essential to avoid

    problems with lost circulation and selecting a proper casing seat depth. It

    becomes even more valuable when drilling in zones of low permeability,

    since it is necessary to propagate hydraulic fracturing to increase well

    productivity.

  • 8/3/2019 Complete Well Design

    5/18

    5 | P a g e

    While there are numerous theoretical and field developed equations of

    determining the fracture pressure gradient, none of the theoretical

    methods can consider all characteristics of the rock formations. For this

    reason, testing each new casing seat for fracture pressure to determine

    accurate fracture pressure gradient is very common in the field.

    Leak-off test is the most widely used direct method for identifying

    fracture pressures.

    These two parameters are the basis for further well design process,

    particularly casing design, as well as planning the drilling mud

    programme. Mud weight should always be kept in the window between

    pore pressures and fracture pressures of all formations that mud is

    affecting. The casing is run to isolate the weaker formations, to use

    heavier muds to drill lower formations. These two factors are very

    important for the safety of drilling process.

    3. Problems that could be encountered duringdrilling in different formations.

    Different hazards occur while drilling in different rock formations. Shales

    and sandstone formations, which are present in the Molly field have

    specific properties that could cause a number of problems that are

    discussed further. Most of them can be avoided by implementation of

    proper mud control programme.

    Lost Circulation

    In porous sandstone, gravel formations, vugular limestones or any rock

    formation that has faulted, fissured and jointed zones, high permeability

    results in drilling fluid flowing into the formations rather than circulating

    back up the hole.

  • 8/3/2019 Complete Well Design

    6/18

    6 | P a g e

    Heaving shale problems

    Some shale layers demonstrate high adsorption of water. The reason for

    that is the presence of hydratable clays in the formation. It can lead to

    the clays swelling and sloughing into the hole and result in further drilling

    problems, such as pipe sticking, hole bridging and excessive build-up of

    solids in the mud.

    The most effective way to deal with this problem is to utilize an inhibitive

    mud, which will reduce the hydration rate of the clays.

    4. Casing schemeThe casing scheme is based on the consideration of formation and

    fracture gradients. However, there are other geological factors that

    should be taken into account during selection of casing seat depths.

    In the given well there is a number of formations that should be

    considered. The surface casing is lowered to 5640 ft below RKB to ensure

    that Paleocene lower sands that could contain fresh waters are covered

    prior further drilling. It isolates Paleocene middle shales, clays and light

    sandstones that could cause heaving and sloughing problems. It also

    provides support for the BOP stack.

    The production casing is run from the bottom up to the casing hanger on

    the surface. It isolates the possible hydrocarbon bearing zone and gives

    support to weak and hydratable Jurassic and Triassic formations.

    TVD of casing seat, ft Hole size Casing size, OD

    984 33" 30"

    5640 17 1/2" 13 3/8"

    10240 12 1/4" 9 5/8"

    Table 1. Casing scheme

  • 8/3/2019 Complete Well Design

    7/18

    7 | P a g e

    5. Mud types. Mud programmeThere is a large variety of drilling fluids currently exploited in the

    industry. Generally, they can be divided into three categories: water, oil

    and in some cases gas based fluids. These categories can be subdivided

    depending on the different additives used to change the density or

    chemical and physical properties of mud.

    Water based fluids

    Water is the main component and is the continuous phase of the fluid.

    Water based muds can be categorized into four groups depending on the

    presence or absence of inhibitor and dispersant additives.

    Non-dispersed and non-inhibited muds.

    Very simple CMC Gel or Spud Gel mud systems, though could be used in

    drilling only very unreactive formations.

    Dispersed and non-inhibited muds.

    Simple clay-based systems. However, because of the problems while

    drilling in reactive clay is not commonly used in oil industry.

    Dispersed and inhibited systems.

    Fresh or sea water based muds made through addition of lime or

    gypsum. High level of calcium ions in the solution assists in prevention

    borehole instability, clay heaving and sloughing.

    Non-dispersed and inhibited systems.

    Very widely used mud type, especially in highly reactive clay formations

    and while drilling though salt layers. The mechanism of inhibition varies

    depending on the inhibition agent.

  • 8/3/2019 Complete Well Design

    8/18

    8 | P a g e

    Oil based fluids

    These muds contain oil as their main component and continuous phase.

    Water can be added to the mixture as discontinuous phase, in that case it

    is called invert emulsion.

    It is beneficial to use this type of mud in water sensitive formations, such

    as production zones and shales, since oil doesn't hydrate the shales. They

    are also useful in drilling complex geometry wells due to their high

    lubricity characteristics. Corrosion resistance, stuck pipe prevention,

    contamination are some other factors that make oil based muds relatively

    cost effective.

    Environmental problems related to the usage of oil based muds led to

    development of biodegradable synthetic oil muds. These muds are very

    expensive and should be considered only in situations where it is

    impossible to drill using water based muds.

    TVD, ft Hole size Casing

    size

    Mud type Mud weight,

    ppg

    984 33" 30" Sea water/bentonite 10

    5640 17 1/2" 13 3/8" Sea water/bentonite 12

    Water based mud with inhibition additives is used to prevent clay

    hydration and sloughing

    10240 12 1/4" 9 5/8" Oil based mud* 13

    *Oil based mud is used to reduce formation damage in the potential

    reservoir formations and to avoid clay hydration

    Table 2. Mud programme

    Mud weight graph is provided in Appendix A.

  • 8/3/2019 Complete Well Design

    9/18

    9 | P a g e

    6. Functions of cement. Cement programmeCement is used for four main reasons:

    1.Provides zonal isolation2.Sustains axial load of casing string3.Protects from the corrosive influence of fluids and offers casing

    support.

    4.Supports the boreholeCementing of the surface casing string will be conducted up to the

    surface, since it is providing support to the next string.

    Main objectives of this cementing stage are: 1) to provide zonal isolation

    of weak formations, i.e. heaving shales, weak sandstones and water

    bearing formations; 2) Provide good casing shoe for further drilling with

    higher mud density.

    A spacer should be run between mud and cement to act as a buffer to

    prevent contamination of cement slurry from mud. It also helps in

    providing good mud removal and cement bond. The amount of spacer

    needed should provide enough annular depth to ensure that no contact

    between cement and mud is possible, since mud and cement are

    incompatible fluids and contamination could lead to channelling or pre-

    mature setting of cement inside the casing

    For economical reasons two types of cement slurries will be used: lower

    density extended cement slurry for non-critical parts, from 4500 ft up to

    the surface, and a higher density cement slurry with better compressive

    strength for isolating formations with possible water migration -

    Paleocene water sands, 4500 ft-5640 ft.

    Cementing of the production casing string will be conductedwith

    the same class G cement with high density that provides good

    compressive strength and has fluid loss control additives to avoid

    dehydration of the cement filtrate to permeable formations. Top of

    cement is run only up to the "Piper" sandstones with a safety margin of

  • 8/3/2019 Complete Well Design

    10/18

    10 | P a g e

    500 ft additional annular length. Accordingly, the top of cement will be at

    7000 ft point. Thus, the critical possible hydrocarbon bearing formations

    and zones of possible water migration are cased and cemented.

    Cementing the production string up to the top should be avoided due to

    risk of possible trapped annular pressure. This pressures can represent a

    large hazard for casing and tubing. In addition, it is beneficial from the

    financial point of view to use smaller amounts of cement.

    In this casing section gas migration control additives like latex polymers

    should be included in the slurry to prevent gas trapping in the cement

    during its thickening period, as it can largely reduce cement's physical

    characteristics. Also it is essential to have proper centralisation in this

    section to aid in proper mud filter cake removal to get a good cement

    bond to casing and formation.

    7. Maximum hook loadThe two main loads that have the strongest impact on derrick structure

    are the longest drill string configuration and the longest casing string

    used. Usually, in most of the modern medium to deep wells the casing

    string is much heavier than the drill string. To make an estimate of

    derrick capacity weights of both strings will be calculated.

    Drill string buoyant weight calculation

    Common practice recommends avoiding putting ordinary drill pipes under

    compression, since they are only designed to work under tension. For this

    reason, it is important to make sure that the total weight of Bottom-hole

    assembly in mud is higher than the maximum required weight on bit, so

    that the point of zero stress will always be lower than drill pipe to BHA

    connection. In practice, it is suggested to decrease the weight on bit

    value even further, to less than 85% of the BHA weight. (Rabia)

  • 8/3/2019 Complete Well Design

    11/18

    11 | P a g e

    In the calculation presented in Appendix B it is shown that the total drill

    string weight in mud is equal to lbs. With an additional 150 000

    lbs allowance for over pull during tripping operations the maximum hook

    load equals to 384 715 lbs.

    The total buoyant weight of production casing is

    Therefore, the maximum load on the derrick structure is

    imposed by casing string and is equal to

    8. Safety while drillingBlowouts

    Blowouts are the most hazardous problem in drilling operations. They

    occur when hydrostatic pressure of mud column becomes lower than

    formation pressure. It is obvious that adequate mud weight is the main

    method to control this risk, although excessively rapid withdrawal of the

    drill string is also commonly overseen as the cause of blowouts. This

    phenomenon is described as pipe suction and depends on the speed ofpulling, mud viscosity and gel strength, and hole-pipe clearance.

    Therefore, it is important to keep the mud viscosity as low as possible.

    For this reason deflocculants are added to the drilling fluid. Velocity of

    drill string retraction is also a big concern and must be always kept in

    adequate ranges.

    However, it is not always possible to predict all regions of abnormal

    pressures, so blowouts happening is inevitable in drilling industry. That is

    why second barrier in safety deals with mitigation of this risk, through

    implementation of a proper well control system. The key equipment used

    for this is the blowout prevention stack. They are designed to stop the

    flow of fluid through the drill pipes or annulus.

    The pressure that impacts the BOP stack is calculated in appendix C and

    it is equal to 3848 psi. From the BOP pressure ratings available on the

  • 8/3/2019 Complete Well Design

    12/18

    12 | P a g e

    market (Burgoyne et al. 1986), we can assume that a 5000 psi working

    pressure stack would be suitable for this well.

    9. Well completionSince the well drilled has two possible hydrocarbon bearing zones, it is

    essential to provide isolation of this zones from each other. This function

    is served by packers, which also provide means for downhole tubing

    anchoring and casing protection.

    For safety reasons, to prevent uncontrollable release of hydrocarbons it is

    required to install a safety valve, which acts as a second barrier in well

    control system.

    To support and secure the tubing string it is necessary to install a tubing

    hanger.

    Two zones of perforation require installing of selective production

    equipment, which will assist in producing only from particular zone, while

    shutting off the other. This function is served by sliding sleeves, that are

    placed on both perforations.

    Installing of hydraulic set packers requires pressure differential between

    tubing and annulus. For this reason it is necessary to set the plug in the

    nipple. Nipple can be used in many other applications, such as sealing

    and locking of different downhole equipment.

    Depending on the needs of well operation, there is a variety completionaccessories: chemical injection mandrel - provides ability to inject

    chemicals in various applications, e.g. cleaning the well from the scale

    and paraffins.

    Downhole completion design is provided in Appendix D.

    Automatic shutdown system provides another safety barrier to control

    different types of blowouts.

  • 8/3/2019 Complete Well Design

    13/18

    13 | P a g e

    List of installed equipment

    1. Tubing Hanger2. Chemical Injection Mandrel3. Gauge Mandrel with the P/T gauge4. TRSSSV5. Sliding sleeve6. Packers7. Nipple8. Automatic shutdown system

    Conclusion

    All stages of well design process that were described show closeinterconnection between each other. For example, adequate mudprogramme or casing design influences every later stage of the designprocess.

    Word count: 2493

  • 8/3/2019 Complete Well Design

    14/18

    14 | P a g e

    Appendix A. Molly field pressure profile, mud weights and casing strings depths

    -12000

    -10000

    -8000

    -6000

    -4000

    -2000

    0

    8 9 10 11 12 13 14 15 16 17 18

    Depth,

    ft

    Equivalent mud density, ppg

    Pore pressure

    Fracture gradient

    Trip margin

    Safety margin

    Mud density

    Conductor

    Surface

    Production

  • 8/3/2019 Complete Well Design

    15/18

    15 | P a g e

    Appendix B. Hook load calculation

    To calculate the weight of drill collars it is necessary to estimate the

    maximum required weight on bit, to ensure that weight on bit will always

    remain 15% lower than the total weight of drill collars. In the table of

    ranges of bit weights and rotary speeds recommended by manufacturers

    (Burgoyne et al. 1986) it is suggested to use WOB not more than 6200

    lb/in of bit diameter for drill bits, to drill in hard limestones and

    dolomites. So, required WOB is

    ,

    after applying the safety factor and buoyancy factor the required weight

    of drill collars is

    Rabia (198 recommends using drill collars to drill hole sections.

    To determine the number of drill collars and their weight, we should

    divide the total required weight of DC in mud by its nominal weight per

    foot and the length of one drill collar:

    .

    The total weight of 24 drill collars is

    while

    the total length is

    The drill string is consisting of 5" OD drill pipes with nominal weight of

    lbs/ft. Thus, the ( )

    ( )

  • 8/3/2019 Complete Well Design

    16/18

    16 | P a g e

    Appendix C. BOP stack working pressure calculation

    The pressure that the BOP stack must withstand is equal to the between

    the formation pressure and the gas hydrostatic pressure:

    Therefore, these parameters should be calculated:

    As a result,

    This calculation should be used for a worst case scenario, only for shallow

    depth wells. Usually, operator's experience suggests using 80% design

    factor: (Adams and Charrier 1985)

  • 8/3/2019 Complete Well Design

    17/18

    17 | P a g e

    Appendix D. Downhole completion design

  • 8/3/2019 Complete Well Design

    18/18

    18 | P a g e

    References

    ADAMS, N.J., CARRIER, T., 1985. Drilling engineering. A complete wellplanning approach. Tulsa, OK: PennWell publishing company.

    BAKER, R., 2001.A primer of oilwell drilling: a basic text of oil and gasdrilling. 6th ed. Austin, TX: University of Texas at Austin.

    BOURGOYNE, A. T. JR., et al., 1986.Applied drilling engineering.Richardson, TX: First Printing, Society of Petroleum Engineers.

    RABIA, H., 1985. Oilwell drilling engineering: principles and practice.London: Graham and Trotman.

    Bibliography

    ECONOMIDES, M. J., et al., 1998. Petroleum well construction. Hoboken,NJ: John Wiley & Sons.

    GATLIN, C., 1960. Petroleum engineering. Drilling and well completions.Englewood Cliffs, NJ: Prentice-Hall, Inc.

    HEAVY OIL SCIENCE CENTRE, 2011. Drilling problems and drillingoperations. [online]. Heavy oil science centre. Available from:http://www.lloydminsterheavyoil.com/drilling.htm [Accessed 19November 2011].

    SERENE ENERGY, 2010. BHA weight & weight-on-bit. [online]. Aberdeen:

    Serene Energy. Available from: http://www.sereneenergy.org/BHA-Weight-and-Weight-on-Bit.php [Accessed 1 December 2011].