Compensatory Mitigation SUMMER2015

17
Compensatory Mitigation For Utility-Scale Solar Energy Projects

Transcript of Compensatory Mitigation SUMMER2015

Page 1: Compensatory Mitigation SUMMER2015

Compensatory MitigationFor Utility-Scale Solar Energy

Projects

Page 2: Compensatory Mitigation SUMMER2015

2

STEPS Background on Compensatory Mitigation

alleviate loss that cannot be addressed on-site, by restoring anticipated loss off-site.

acquired, restored, and/or preserved offsite to offset the unavoidable impacts

“in-kind” mitigationAvoid

Minimize

Rectify

Reduce

Compensatory Mitigation

(CEQ, 1979)

Page 3: Compensatory Mitigation SUMMER2015

3

Different Solar Technologies and Impacts

Power towers

Parabolic trough

Solar photovoltaic

Crescent Dunes Solar Energy Project

Ivanpah Solar Electric Generating System

Silver State North

Genesis Solar Power Project

Silver State SouthStatus: Initial Construction

Harry AllenStatus: Approved Comment and Review Period

Page 4: Compensatory Mitigation SUMMER2015

4

The United States 2000-2010

(DOE, 2012)

Page 5: Compensatory Mitigation SUMMER2015

5

Mandatory Growth

National Environmental Policy Act of 1969 (NEPA) Congressional mandates Executive Orders 13212 Executive Orders 13514 DOI Secretarial Order 3285SA1

“take appropriate actions, tothe extent consistent with applicable law, to expedite projects that will increase the production, transmission, or conservation of energy.”

“Encourage … development of renewable energy …while protecting and enhancing the nation’s water, wildlife, and other natural resources; to identify appropriate areas for generation …on public lands to ensure the most environmentally responsible development…”

Page 6: Compensatory Mitigation SUMMER2015

6

BLM SEZ’s

Programmatic Environmental Impact Statement for Solar Energy Development in Six Southwestern States2012

Page 7: Compensatory Mitigation SUMMER2015

7

Methods and Materials The Bureau of Land Management (BLM)

www.blm.gov/wo/st/en.html The California Energy Commission (CEC)

www.energy.ca.gov/ Biological opinion is the document that states the opinion of the Service as to whether or not the Federal action is likely to jeopardize the continued existence of listed species or result in the destruction or adverse modification of critical habitat.

Environmental Impact Statement (EIS), a document that describes the consequences of the proposed project on the environment.

Record of Decision(ROD) document with the final decision on the project specifications, required avoidance and minimization measures, and required compensatory mitigation

Right-of- Way Lease/Grant (ROW) specifies final stipulations on project design, and mitigation requirements.

Page 8: Compensatory Mitigation SUMMER2015

8

How Data Was Kept 30 documents were reviewed for

the 6 projects.

An Excel file was kept with all document titles and webpages that were reviewed.

Which documents contained the accurate information?

30

Page 9: Compensatory Mitigation SUMMER2015

9

Need for Utility-Scale Solar Development and Data on Compensatory Mitigation Costs

Main goal of solar energy program for utility-scale solar energy development on BLM-administered lands :

– is to create a standardized and streamlined authorization process (BLM and DOE 2012).

“…to ensure consistent application of measures to mitigate the potential adverse impacts of such development.” (BLM and DOE 2012)

“CONSISTENT APPLICATION”

GOAL=

Page 10: Compensatory Mitigation SUMMER2015

10

ResultsProject Total

AcresTotal MW

Total Compensatory Mitigation Costs¹

Approx. Cost Per Acre

Approx. Cost Per MW

Crescent Dunes Nevada 2010

1620 110 $200,000 $123 $1,818

Silver State North Nevada 2010

600 50 $509,400² $849 $10,188

Silver State South Nevada 2014

2427 250 $7,277,600 $2,998 $29,110

Harry AllenNevada 2015

594 112 $2,234,708 $3,762 $19,952

GenesisCalifornia 2010

4640 250 $5,329,106 - $5,352,306 $1,148 - $1,153

$21,316 - $21,409

IvanpahCalifornia 2010

3471 370 $29,547,635 $8,512 $79,858

Average Approx. Cost

$2,898 $27,040

Page 11: Compensatory Mitigation SUMMER2015

11

How do the numbers compare?

Findings suggest: Unrelated to the amount of acres acquired for the project footprint

Harry Allen Solar594 acres

$3,762/acre

$19,952/MW

Only of

Only of

Silver State North600 acres

$10,188/MW

$849/acre 19%

51%

Page 12: Compensatory Mitigation SUMMER2015

12

How do the numbers compare?

12

Findings suggest: Compensatory mitigation costs are un-related to the type of solar technology used.

Ivanpah

$8,512/acre

$79,858/MW

Only of

Crescent Dunes

$1,818/MW

$123/acre 1.45%

2.28%

Power Tower in 2010

Only of

Page 13: Compensatory Mitigation SUMMER2015

13

How do the numbers compare?

13

The findings from this study suggest that compensatory mitigation costs are inconsistent within states and from state to state. The findings suggest that compensatory mitigation costs are inconsistent no matter if the same animal/ plant species is effected.

Ivanpah

$8,512/acre

$79,858/MW

Only of

Only of

Genesis

$21,409/MW

$1,153/acre 13%

26%

California in 2010

Dessert Tortoise fees $910/acre

300% of land

Only of

Only of 40% of land

$500/acre 55%

13%1750 of 4640

10,413 of 3,471

Page 14: Compensatory Mitigation SUMMER2015

How do the numbers compare?

This finding from the combined six projects suggests that compensatory mitigation prices go up as the MW output goes up (with exception to Crescent Dunes).

14

Ivanpah Solar Electric Generating System370 MW $19,858

Silver State South 250 MW $29,110/MW

Genesis Solar Power Project250 MW $21,409/MW

Harry Allen Solar112 MW $19,952/MW

Crescent Dunes 110 MW $1,818/MW

Silver State North 50 MW $10,188/MW

Page 15: Compensatory Mitigation SUMMER2015

15

Missing data.What’s next? Any real rules set in place for the actual costs of compensatory mitigation? Where do the numbers come from? Many projects were approved in the same year, so why are the variations so

large? Is the government properly managing our land?

More research needs to be done.

The BLM has approved 33 projects since 2010, so there is a chance that some of those facilities can fill in gaps in price.

A standard put in place for compensatory mitigation costs. The research needs to be complete to be sure the compensatory mitigation

process is fair.

Any

?

Page 16: Compensatory Mitigation SUMMER2015

16

References

CEQ (Council on Environmental Quality), 1979. CEQ Regulation 1508-- Terminology and Index. Available at: https://ceq.doe.gov/nepa/regs/ceq/1508.htm

BLM, 2011. Crescent Dunes Final Environmental Impact Statement FES-10-57, N-86292, DOI-BLM-NVB020-2009-0104-EIS, Appendix E: BLM Wildlife Mitigation and Monitoring Plan. BLM Battle Mountain District, Tonanah, Nevada. Available at: http://www.blm.gov/style/medialib/blm/nv/field_offices/battle_mountain_field/blm_information/nepa/crescent_dunes_solar.Par.86958.File.dat/Appendix%20E.pdf.

NFWS (National Fish and Wildlife), 2010. Biological Opinion for the Silver State Solar Project File No. 84320-2010-F-0208,Fish and Wildlife Office, Las Vegas, Nevada. Available at: http://www.blm.gov/style/medialib/blm/nv/field_offices/las_vegas_field_office/energy/nextlight_-_other/NextLight_BO.Par.54027.File.dat/NextLight_Silver_State_Solar_BO%20.pdf

Page 17: Compensatory Mitigation SUMMER2015

17

Questions?BARBARA NEAL

[email protected] STATE

UNIVERSITY