Kerstin Robertson
Comparison of the EU’s Sustainable urban mobility plan (SUMP)
and the Swedish planning supportTransport for an attractive city (TRAST)
VTI rapport 844A | Com
parison of the EU’s Sustainable urban m
obility plan and the Swedish planning support Transport for an attractive city
www.vti.se/en/publications
VTI rapport 844APublished 2015
VTI rapport 844A
Comparison of the EU’s
Sustainable urban mobility plan (SUMP)
and the Swedish planning support
Transport for an attractive city (TRAST)
Kerstin Robertson
Diarienummer: 2012/0251-24
Omslagsbilder: Karin Andersson, VTI, Hejdlösa Bilder AB
Tryck: LiU-Tryck, Linköping 2015
VTI rapport 844A
Abstract
The planning support developed in the EU’s Sustainable urban mobility plan (SUMP) and the
Swedish planning support system Transport for an attractive city (TRAST) aims at developing
sustainable transport in cities. Both systems include the formulation of one or more plans and support
for the planning process. This analysis and comparison of SUMP and TRAST is based on the SUMP
Guidelines, the two main TRAST Handbooks and the TRAST Guide. The comparison is structured in
accordance with the SUMP Steps.
This comparison showed that identical or similar areas and requirements are addressed in SUMP and
TRAST regarding the planning process. Both SUMP and TRAST include instructions in the form of
guidelines that must be interpreted and translated into a plan, practical planning and actions by cities.
TRAST, however, also includes handbooks and guides with suggestions, discussions and examples of
measures, actions and policies. TRAST is furthermore developed for integrated implementation with
spatial planning. Implementation of both TRAST and SUMP is supported through projects and
networking, e.g. for facilitating exchange of experiences between cities.
Title: Comparison of the EU’s Sustainable urban mobility plan (SUMP) and the
Swedish planning support Transport for an attractive city (TRAST)
Author: Kerstin Robertson (VTI, www.orcid.org/0000-0003-1041-1981)
Publisher: Swedish National Road and Transport Research Institute (VTI)
www.vti.se
Publication No.: VTI rapport 844A
Published: 2015
Reg. No., VTI: 2012/0251-24
ISSN: 0347-6030
Project: Endurance
Commissioned by: EU/IEE/Swedish Transport Administration
Keywords: SUMP, TRAST, Sustainable urban mobility plan
Language: English
No. of pages: 33
VTI rapport 844A
Referat
Det planeringsstöd som har tagits fram i EU, SUMP (”Sustainable urban mobility plan”), och det
svenska planeringsstödet TRAST (Trafik för attraktiv stad) syftar båda till att stödja utvecklingen av
hållbara transporter i städer. Båda systemen omfattar utveckling av en eller flera planer och
processtöd. Denna analys och jämförelse mellan SUMP och TRAST är baserad på ”SUMP
Guidelines”, de två TRAST-handböckerna och TRAST-guiden. Jämförelsen har strukturerats i
enlighet med de olika stegen i SUMP.
Jämförelsen visade att motsvarande områden och krav tas upp i SUMP och TRAST när det gäller
planeringsprocessen. Både SUMP och TRAST omfattar anvisningar som av städerna måste tolkas och
omsättas till en plan, till praktisk planering och till åtgärder. TRAST-handböckerna omfattar dock
även förslag, diskussion och exempel på åtgärder och policys och TRAST är vidare anpassat för
integrering med övrig stadsplanering. Implementering av både TRAST och SUMP stöds ofta genom
projekt och nätverkande, till exempel för att underlätta utbytet av erfarenheter mellan städer.
Titel: Jämförelse mellan ”Sustainable urban mobility plan” (SUMP) och det
svenska planeringsstödet Trafik för attraktiv stad (TRAST)
Författare: (Kerstin Robertson VTI, www.orcid.org/0000-0003-1041-1981))
Utgivare: VTI, Statens väg och transportforskningsinstitut
www.vti.se
Serie och nr: VTI rapport 844A
Utgivningsår: 2015
VTI:s diarienr: 2012/0251-24
ISSN: 0347-6030
Projektnamn: Endurance
Uppdragsgivare: EU/IEE/Trafikverket
Nyckelord: SUMP, TRAST, Trafikstrategi
Språk: Engelska
Antal sidor: 33
VTI rapport 844A
Preface
This report is developed within the EU project EU-wide establishment of enduring national and
European support networks for sustainable urban mobility (ENDURANCE) which is coordinated by
EPOMM and co-funded by the Intelligent Energy Europe programme of the European Union. The
Swedish participation is also funded by the Swedish Transport Administration.
Linköping, June 2015
Kerstin Robertson
Research Director, Transport and Environment
Project leader
VTI rapport 844A
Quality review
Internal peer review was performed on 15 June 2015 by Tomas Svensson. First author; Kerstin
Robertson has made alterations to the final manuscript of the report. The head of research department
Mattias Viklund examined and approved the report for publication on 24 August 2015. The
conclusions and recommendations expressed are the author’s and do not necessarily reflect VTI’s
opinion as an authority.
Kvalitetsgranskning
Intern peer review har genomförts 15 juni 2015 av Tomas Svensson. Förste författaren; Kerstin
Robertson har genomfört justeringar av slutligt rapportmanus. Avdelningschef Mattias Viklund har
därefter granskat och godkänt publikationen för publicering 24 augusti 2015. De slutsatser och
rekommendationer som uttrycks är författarens egna och speglar inte nödvändigtvis myndigheten
VTI:s uppfattning.
VTI rapport 844A
Table of contents
Summary .................................................................................................................................................9
Sammanfattning ...................................................................................................................................11
1. Introduction .....................................................................................................................................13
1.1. SUMP .........................................................................................................................................13
1.2. TRAST .......................................................................................................................................14
2. Overview and comparison of SUMP and TRAST ........................................................................16
3. Comparison of SUMP activities with the TRAST Handbooks and the TRAST Guide ............19
3.1. SUMP Step 1: Determine your potential for a successful SUMP ..............................................19
3.2. SUMP Step 2: Define the development process and scope of plan ...........................................21
3.3. SUMP Step 3: Analyse the mobility situation and develop scenarios .......................................23
3.4. SUMP Step 4: Develop a common vision ..................................................................................24
3.5. SUMP Step 5: Set priorities and measurable targets..................................................................25
3.6. SUMP Step 6: Develop effective packages of measures ...........................................................26
3.7. SUMP Step 7: Agree on clear responsibilities and allocate funding .........................................27
3.8. SUMP Step 8: Build monitoring and assessment into the plan ..................................................28
3.9. SUMP Step 9: Adopt Sustainable Urban Mobility Plan ............................................................29
3.10. SUMP Step 10: Ensure proper management and communication (when implementing the
plan) ...........................................................................................................................................30
3.11. SUMP Step 11: Learn the lessons ..............................................................................................31
4. Concluding analysis and comparison of SUMP and TRAST ......................................................32
Literature ..............................................................................................................................................33
VTI rapport 844A
VTI rapport 844A 9
Summary
Comparison of the EU’s Sustainable urban mobility plan (SUMP) and the Swedish planning
support Transport for an attractive city (TRAST)
by Kerstin Robertson (VTI)
The planning support developed in the EU’s Sustainable urban mobility plan (SUMP) and the
Swedish planning support system Transport for an attractive city (TRAST) aims at developing
sustainable transport in cities. Both systems include the formulation of one or more plans and support
for the planning process. This analysis and comparison of SUMP and TRAST is based on the SUMP
Guidelines, the two main TRAST Handbooks and the TRAST Guide. The comparison is structured in
accordance with the SUMP Steps.
This comparison showed that identical or similar areas and requirements are addressed in SUMP and
TRAST regarding the planning process. Both SUMP and TRAST include instructions in the form of
guidelines that must be interpreted and translated into a plan, practical planning and actions by cities.
TRAST, however, also includes handbooks and guides with suggestions, discussions and examples of
measures, actions and policies. TRAST is furthermore developed for integrated implementation with
spatial planning. Implementation of both TRAST and SUMP is supported through projects and
networking, e.g. for facilitating exchange of experiences between cities.
VTI rapport 844A 10
VTI rapport 844A 11
Sammanfattning
Jämförelse mellan ”Sustainable urban mobility plan” (SUMP) och det svenska planeringsstödet
Trafik för attraktiv stad (TRAST)
av Kerstin Robertson (VTI)
Det planeringsstöd som har tagits fram i EU, SUMP (”Sustainable urban mobility plan”), och det
svenska planeringsstödet TRAST (Trafik för attraktiv stad) syftar båda till att stödja utvecklingen av
hållbara transporter i städer. Båda systemen omfattar utveckling av en eller flera planer och
processtöd. Denna analys och jämförelse mellan SUMP och TRAST är baserad på ”SUMP
Guidelines”, de två TRAST-handböckerna och TRAST-guiden. Jämförelsen har strukturerats i
enlighet med de olika stegen i SUMP.
Jämförelsen visade att motsvarande områden och krav tas upp i SUMP och TRAST när det gäller
planeringsprocessen. Både SUMP och TRAST omfattar anvisningar som av städerna måste tolkas och
omsättas till en plan, till praktisk planering och till åtgärder. TRAST-handböckerna omfattar dock
även förslag, diskussion och exempel på åtgärder och policys och TRAST är vidare anpassat för
integrering med övrig stadsplanering. Implementering av både TRAST och SUMP stöds ofta genom
projekt och nätverkande, till exempel för att underlätta utbytet av erfarenheter mellan städer.
VTI rapport 844A 12
VTI rapport 844A 13
1. Introduction
The planning support developed in EU, Sustainable urban mobility plan (SUMP), and the Swedish
planning support system Transport for an attractive city (TRAST) are aimed at developing
sustainable transport in cities. Both systems include the formulation of one or more plans and support
for the planning process. Many cities in Sweden have already developed or are developing mobility
plans (e.g. Traffic strategies) based on the TRAST guide. The aim of the present analysis was
therefore to identify similarities and differences between the TRAST and the SUMP guidelines, since
it is necessary to determine whether documents and processes developed according to one system are
applicable in the other.
The comparison of the guidelines were carried out by analysing the instructions in the SUMP
Guideline, the TRAST Handbooks and the TRAST Guide.
1.1. SUMP
The Sustainable urban mobility plan (SUMP) was defined in EU Commission communication COM
(2009) 490 final, entitled “Action Plan on Urban Mobility”. The action plan proposes a programme of
actions to support sustainable urban mobility centred on six themes corresponding to the main
messages that emerged from the Green Paper consultation. Among these six themes, Theme 1
(Promoting integrated policies) includes a total of 13 actions, the first of which is accelerating the
take-up of SUMP:
Themes 1-6 and their component actions in the EU action plan on urban mobility (COM(2009) 490 final)
Theme 1 – Promoting integrated policies Action 1 — Accelerating the take-up of sustainable urban mobility plans
Action 2 — Sustainable urban mobility and regional policy
Action 3 — Transport for healthy urban environments
Theme 2 – Focusing on citizens Action 4 — Platform on passenger rights in urban public transport
Action 5 — Improving accessibility for persons with reduced mobility
Action 6 — Improving travel information
Action 7 — Access to green zones
Action 8 — Campaigns on sustainable mobility behaviour
Action 9 — Energy-efficient driving as part of driving education
Theme 3 – Greening urban transport Action 10 — Research and demonstration projects for lower and zero emission
vehicles
Action 11 — Internet guide on clean and energy-efficient vehicles
Action 12 — Study on urban aspects of the internalisation of external costs
Action 13 — Information exchange on urban pricing schemes
Theme 4 – Strengthening funding Action 14 — Optimising existing funding sources
Action 15 — Analysing the needs for future funding
Theme 5 – Sharing experience and
knowledge
Action 16 — Upgrading data and statistics
Action 17 — Setting up an urban mobility observatory
Action 18 — Contributing to international dialogue and information exchange
Theme 6 – Optimising urban mobility Action 19 — Urban freight transport
Action 20 — Intelligent transport systems (ITS) for urban mobility
In the publication “Guidelines – Developing and implementing a sustainable urban mobility plan”
(www.mobilityplans.eu), SUMP is introduced as a “new planning concept and paradigm” and as a
VTI rapport 844A 14
“strategic plan” that address transport-related challenges in urban areas in a more sustainable and
integrated way. It places particular emphasis on the involvement of citizens and stakeholders and the
coordination of policies between sectors. The overall aim is better quality of life. The guidelines are
intended for urban transport and mobility practitioners and other stakeholders involved in the
development of a sustainable urban mobility plan. Handbooks and tools in specific areas are
continually being developed.
The SUMP guidelines include 11 steps that are subdivided into a total of 32 activities. The guideline
activities has a clear focus on planning process guidelines and does not include guidelines regarding
the content of SUMP, except for the development of scenarios. Each activity is defined briefly (1-1.5
pages) in the guideline document including rationale, aims, tasks, activities, timing and coordination,
and a brief checklist (see SUMP Guidelines).
1.2. TRAST
TRAST comprises a set of Swedish guidelines developed by the Swedish Association of Local
Authorities and Regions (SALAR), the Transport Agency and the Swedish National Board of
Housing, Building and Planning (Boverket), with the aim of supporting integrated planning and the
development of balanced and sustainable urban transport systems and attractive cities. The first edition
was published in 2004, the second edition in 2007 and a third update is under development. The
material includes two main handbooks, a guide and a number of additional background reports and
supporting handbooks that are available at: www.trafikverket.se/Foretag/Planera-och-
utreda/Samhallsplanering/Tatort/Trafik-for-en-attraktiv-stad. One of the handbooks includes
background (facts and information) about activities and measures for urban and transport system
development and the other handbook and the guide aim at supporting the planning process.
The TRAST planning process handbook includes three main sections:
“Attractive city” (Attraktiv stad), where qualities of an attractive city and planning strategies
are defined
“Local planning of travel and transport” (Kommunal planering för resor och transporter), in
which suggestions regarding structural support for local planning can be found
“Local strategies, plans and programmes” (Kommunens arbete med strategi, planer och
program), where planning process support is presented.
The TRAST Guide provides support to municipalities of all sizes that are in the process of
developing a mobility plan. The guide is designed to help create a systematic and lucid working
process and is divided into three phases:
Phase 1. Initiate and get an assignment (Fas 1. Starta arbetet och få ett uppdrag),
Phase 2. Develop a mobility plan (Fas 2. Ta fram en trafikstrategi), and
Phase 3. Implementation and management (Fas 3. Att genomföra och förvalta).
The TRAST Background Handbook is a review that addresses activities and measures and includes
the following sections:
City qualities
Transport planning
Accessibility
Safety and security
Traffic safety
Traffic and environmental effects
Transport systems (including subsections on pedestrian, bicycle, moped, public, rail, car, goods
and emergency traffic).
VTI rapport 844A 15
The planning process recommended in TRAST is structured in three planning stages, of which the
TRAST recommendations can be applied in the first two:
Strategic planning: including spatial planning and the development of one or several mobility
plans (e.g. a Traffic strategy)
Action planning: including for example transport plans and identification of measures
The third stage is Project planning.
VTI rapport 844A 16
2. Overview and comparison of SUMP and TRAST
This overview and comparison of SUMP and TRAST presented in this report is based on the SUMP
Guidelines, the two main TRAST Handbooks and the TRAST Guide. The overview is structured in
accordance with the 13 SUMP steps and corresponding sections in the TRAST Handbook and Guide
have been identified and are presented below. Headings and section subheadings in the TRAST
material are translated to English, and the corresponding Swedish terms and concepts are given in
brackets. A more detailed comparison is done in the next section.
SUMP Step TRAST Planning process handbook
(section)
TRAST Guide (section)
Phase 1: Preparing well
Step 1: Determine your potential
for a successful SUMP
Section: Attractive city (Attraktiv stad)
Section: Local planning of travel and
transport (Kommunal planering för resor och transporter)
Phase 1. Initiate and get an assignment
(Fas 1. Starta arbetet och få ett uppdrag)
Acceptance within the municipality (Avstämning inom kommunen)
Step 2: Define the development
process and scope of plan
Section: Local strategies, plans and
programmes (Kommunens arbete med strategi, planer och program)
- A defined process (En tydlig
process)
Phase 1. Initiate and get an assignment
(Fas 1. Starta arbetet och få ett uppdrag)
Develop an assignment, including schedule
and organisation (Ta fram ett uppdragsförslag inklusive tidsplan och
organisation)
Step 3: Analyse the mobility situation and develop scenarios
Section: Local strategies, plans and
programmes (Kommunens arbete med
strategi, planer och program)
- Current situation
(Nulägesbeskrivning)
- Alternatives and analysis
(Alternativ och analys)
Phase 1. Initiate and get an assignment
(Fas 1. Starta arbetet och få ett uppdrag)
Analyse current plans and programmes (Ta
fram tidigare planer/program/utredningar)
Compile basic data and initiate analysis of
current situation (Ta fram enkla basdata och påbörja en översiktlig nulägesanalys)
Phase 2. Develop a mobility plan
(Fas 2. Ta fram en Trafikstrategi)
Analysis of current situation
(Nulägesanalys)
Develop a common vision, scenarios and
measures (Arbeta fram en vision för
trafiken, skissera olika scenarier och tänkbara åtgärder)
Phase 2: Rational and transparent goal setting
Step 4: Develop a common vision
and engage citizens
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer och
program)
- Vision (Vision)
- Develop wide support
(Förankring)
Phase 2. Develop a mobility plan
(Fas 2. Ta fram en Trafikstrategi)
Political agreement and decision
(Förankra och besluta (politiskt) om
uppdraget)
Develop a common vision, scenarios and measures (Arbeta fram en vision för
trafiken, skissera olika scenarier och
tänkbara åtgärder)
Workshop (Trafikdag/workshop)
VTI rapport 844A 17
SUMP Step TRAST Planning process handbook
(section)
TRAST Guide (section)
Step 5: Set priorities and
measurable targets
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer och
program)
- Targets (Mål)
- Evaluation (Uppföljning)
Phase 2. Develop a mobility plan
(Fas 2. Ta fram en Trafikstrategi)
Set targets (Formulera mål och välj
inriktning)
Gain acceptance for targets (Förankra mål
och inriktning)
Develop an action plan (Förslag till handlingsplan; Skissera genomförandet
(tidsplan och budget)
Step 6: Develop effective packages of measures
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer och
program)
- Choice of alternatives (Val av
alternativ)
- Action planning
(Åtgärdsplanering)
TRAST Background Handbook (TRAST
Handbok: Underlag)
Phase 2. Develop a mobility plan
(Fas 2. Ta fram en Trafikstrategi)
Develop a draft mobility plan (Ta fram ett förslag till trafikstrategi)
Phase 3. Implementation and management
(Fas 3. Att genomföra och förvalta)
Develop packages of measures
(Genomförandeplanering, inkludera åtgärder i verksamhetsplaneringen)
Phase 3: Elaborating the plan
Step 7: Agree on clear
responsibilities and allocate funding
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer och
program)
- A defined process (En tydlig
process)
Phase 1. Initiate and get an assignment
(Fas 1. Starta arbetet och få ett uppdrag)
Define an assignment including schedule
and organisation (Ta fram ett uppdragsförslag inklusive tidsplan och
organisation)
Political agreement and decision (Förankra och besluta (politiskt) om
uppdraget; Kommunicera,
remissbehandla, revidera)
Step 8: Build monitoring and
assessment into the plan
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer och program)
- Evaluation (Uppföljning)
Phase 3. Implementation and management
(Fas 3. Att genomföra och förvalta)
Monitor, assess and communicate (Följ upp och utvärdera, kommunicera
resultaten)
Step 9: Adopt Sustainable Urban Mobility Plan
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer och
program)
- Develop wide support
(Förankring)
Phase 1. Initiate and get an assignment
(Fas 1. Starta arbetet och få ett uppdrag)
Political agreement and decision (Förankra och besluta (politiskt) om
uppdraget)
VTI rapport 844A 18
SUMP Step TRAST Planning process handbook
(section)
TRAST Guide (section)
Phase 4: Implementing the plan
Step 10: Ensure proper
management and communication (when implementing the SUMP)
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer och
program)
- A defined process (En tydlig process)
- Develop wide support
(Förankring)
Phase 2. Develop a mobility plan
(Fas 2. Ta fram en Trafikstrategi)
Communicate, consult and revise
(Kommunicera, remissbehandla, revidera)
Phase 3. Implementation and management
(Fas 3. Att genomföra och förvalta)
Monitor, assess and communicate (Följ upp och utvärdera, kommunicera
resultaten)
Update steering documents (Uppdatera
styrdokument (nuläge, mål, inriktning) och
handlingsplan; Aktualitetsförklara)
Step 11: Learn the lessons Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer och program)
- Evaluation (Uppföljning)
Phase 3. Implementation and management
(Fas 3. Att genomföra och förvalta)
Monitor, assess and communicate (Följ upp och utvärdera, kommunicera
resultaten)
On a general level, identical or similar guidelines are included in both systems. However, the focus in
SUMP is on planning process guidelines, whereas TRAST also includes instructions and suggestions
regarding the development and content of a plan document. The SUMP Guidelines provide very
general support in the form of a checklist, while the more detailed interpretation and implementation
can be defined by the organisation applying the guidelines.
The TRAST material, on the other hand, takes the structure of a handbook, including the TRAST
Guide, with the focus on describing background information, experiences, discussion and suggestions
about how to develop the planning process and the plan, and how to identify measures that may
contribute to developing sustainable urban transport systems.
This difference may reflect the fact that the SUMP guidelines are very recent, whereas the
development of TRAST started over 10 years ago. A more detailed comparison of SUMP Steps 1-11
and the corresponding TRAST guidelines is presented in the next section.
VTI rapport 844A 19
3. Comparison of SUMP activities with the TRAST Handbooks and the TRAST Guide
In this section a step by step comparison on activity level between SUMP and TRAST is presented.
3.1. SUMP Step 1: Determine your potential for a successful SUMP
SUMP Step 1. Determine your potential
for a successful SUMP
TRAST Handbooks TRAST Guide
Activity 1.1: Commit to overall
sustainable mobility principles
Checklist:
Analysis on the extent to which
sustainability principles guide current policies relevant to urban
mobility completed.
Overall commitment to
sustainability principles from key
stakeholders achieved.
Section: Attractive city (Attraktiv stad)
Includes:
- A description and a vision of the
attractive city
- Motivation for the relevance of
attaining a common vision and goals
regarding the development of the city and the traffic system (Visioner och
målbild)
- Presentation and motivation for
agreeing on sustainability principles in municipal planning (Hållbar
utveckling)
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer
och program)
- Vision (Vision)
- Overall commitment (Förankring)
Phase 1. Initiate and get an assignment
(Fas 1. Starta arbetet och få ett uppdrag)
Acceptance within the municipality (Avstämning inom kommunen)
Inventory of visions and goals (Invertera visioner och mål)
Activity 1.2: Assess impact of
regional/national framework
Checklist:
Relevant documents from national and regional level reviewed and
results summarised.
Opportunities and potential problems that might result from
regional and national framework conditions identified.
Section: Attractive city (Attraktiv stad)
Includes:
- Both regional and national
perspectives are important – for
example coordination and cooperation between municipalities
is required (Regionala samband)
- Opportunities and problems (Att
planera för den attraktiva staden; Hinder på vägen)
Section: Local planning of travel and
transport (Kommunal planering för resor och transporter)
- Relate to national and regional
strategies, programmes and goals (Statens intressen I den fysiska
planeringen)
Phase 1. Initiate and get an assignment
(Fas 1. Starta arbetet och få ett uppdrag)
Acceptance within the municipality
(Avstämning inom kommunen)
Includes:
- Inventory of strategies, plans and
programmes
- Development of regional and national
cooperation
Activity 1.3: Conduct self-assessment
Checklist:
Appropriate self-assessment
carried out.
Strengths and weaknesses with
regard to developing a Sustainable Urban Mobility Plan identified.
Results summarised as starting
point to optimise local planning processes.
Section: Attractive city (Attraktiv stad)
Includes:
- Opportunities and problems (Att
planera för den attraktiva staden;
Hinder på vägen)
Phase 1. Initiate and get an assignment
(Fas 1. Starta arbetet och få ett uppdrag)
Acceptance within the municipality
(Avstämning inom kommunen)
Activity 1.4: Review availability of
resources
Section: Local planning of travel and
transport (Kommunal planering för resor och transporter)
Phase 1. Initiate and get an assignment
(Fas 1. Starta arbetet och få ett uppdrag)
VTI rapport 844A 20
SUMP Step 1. Determine your potential
for a successful SUMP
TRAST Handbooks TRAST Guide
Checklist:
Required skills and financial resources for planning process
analysed.
Skills management plan compiled.
Budget for running sustainable urban mobility planning process
politically approved.
Likely budgetary framework for measure implementation assessed.
Includes:
- Municipal goals and budget (Kommunens mål och budget)
Formulate and agree on a project
description (Formulera och förankra en projektbeskrivning)
Includes: Goals, description, political commitment, communication/information,
organisation, schedule, budget/resources and
risk analysis.
Activity 1.5: Define basic timeline
Checklist:
Realistic basic timeline for
sustainable urban mobility planning process and measure
implementation prepared.
Timeline approved by decision makers.
Phase 1. Initiate and get an assignment
(Fas 1. Starta arbetet och få ett uppdrag)
Formulate and agree on a project
description (Formulera och förankra en projektbeskrivning)
Includes: Goals, description, political
commitment, communication/information, organisation, schedule, budget/resources, risk
analysis
Activity 1.6: Identify key actors and
stakeholders
Checklist:
Stakeholder groups identified: Primary stakeholders, key actors,
intermediaries.
Analysis of actor constellations carried out.
Basic stakeholder coordination strategy developed.
Phase 1. Initiate and get an assignment
(Fas 1. Starta arbetet och få ett uppdrag)
Formulate and agree on a project
description (Formulera och förankra en projektbeskrivning)
Includes: Goals, description, political
commitment, communication/information, organisation, schedule, budget/resources, and
risk analysis.
VTI rapport 844A 21
3.2. SUMP Step 2: Define the development process and scope of plan
SUMP Step 2. Define the development
process and scope of plan
TRAST Handbook TRAST Guide
Activity 2.1: Look beyond your own
boundaries and responsibilities
Checklist:
Most appropriate Sustainable Urban Mobility Plan area
identified.
Agreement achieved on geographical coverage.
Agreement achieved on the basic roles and responsibilities of
authorities and politicians.
Planning team created.
Political agreement signed and adopted by all municipal council
Section: Attractive city (Attraktiv stad)
Includes:
- Planning for the attractive city (Att planera för den attraktiva staden;
Hinder på vägen; Hållbar
utveckling)
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer och program)
Includes:
- A defined process (En tydlig
process)
- Vision (Vision)
- Overall commitment (Förankring)
- Goals (Mål)
Phase 1. Initiate and get an assignment
(Fas 1. Starta arbetet och få ett uppdrag)
Formulate and agree on a project
description (Formulera och förankra
en projektbeskrivning)
Includes: Goals, description, political
commitment, communication/information,
organisation, schedule, budget/resources, and risk analysis.
Phase 2. Develop a mobility plan
(Fas 2. Ta fram en Trafikstrategi)
Analysis of current situation
(Nulägesanalys)
Develop a common vision, scenarios
and strategy (Ta fram vision, mål och inriktning)
Activity 2.2: Strive for policy
coordination and an integrated planning
approach
Checklist:
Relevant policy linkages identified (synergies and conflicts).
Initial options for policy integration assessed.
Dialogue established with all concerned actors about integration
possibilities.
Initial prioritisation of integration options decided.
Assessment and prioritisation
specified according to advanced
scenario building results (> Activity 3.2).
Section: Local planning of travel and
transport (Kommunal planering för resor
och transporter)
Includes:
- Strategic planning (Inriktningsplanering)
(which includes the use of scenarios)
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer
och program)
Includes:
- A defined process (En tydlig
process)
- Vision (Vision)
- Overall commitment (Förankring)
Phase 1. Initiate and get an assignment
(Fas 1. Starta arbetet och få ett uppdrag)
Acceptance within the municipality (Avstämning inom kommunen)
Includes: Commitment, coordination, the development of common visions and goals,
and a workshop.
Formulate and agree on a project
description (Formulera och förankra
en projektbeskrivning)
Includes: Goals, description, political
commitment, communication/information,
organisation, schedule, budget/resources, and risk analysis.
Activity 2.3: Plan stakeholder and citizen
involvement
Checklist:
Planning of different involvement strategies finalised.
Communication plan elaborated and approved.
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer
och program)
Includes:
- A defined process (En tydlig
process)
- Commitment (Förankring)
(which includes the development of a communication plan)
Phase 2. Develop a mobility plan
(Fas 2. Ta fram en Trafikstrategi)
Establish commitment for vision,
targets and strategy (Förankra vision, mål och inriktning)
Includes: Consultations, workshops and
dialogue.
VTI rapport 844A 22
SUMP Step 2. Define the development
process and scope of plan
TRAST Handbook TRAST Guide
Activity 2.4: Agree on work plan and management arrangements
Checklist:
Political mandate and support for your plan concluded.
Coordinator of the planning process determined.
Strategy for risk management and quality management devised.
Work plan for your planning process developed and politically
approved.
Section: Local planning of travel and
transport (Kommunal planering för resor och transporter)
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer
och program)
Includes:
- A defined process (En tydlig
process)
Phase 1. Initiate and get an assignment
(Fas 1. Starta arbetet och få ett uppdrag)
Formulate and agree on a project
description (Formulera och förankra en projektbeskrivning)
Includes: Goals, description, political
commitment, communication/information, organisation, schedule, budget/resources, and
risk analysis.
VTI rapport 844A 23
3.3. SUMP Step 3: Analyse the mobility situation and develop scenarios
SUMP Step 3. Analyse the mobility
situation and develop scenarios
TRAST Handbook TRAST Guide
Activity 3.1: Prepare an analysis of
problems and opportunities
Checklist:
Suitable indicators selected to describe the status.
All necessary data made available
by the actors concerned. (If sufficient data is not available, start
with what you have, but draft a plan
on how to close the data gaps.)
Review and analysis concluded.
Baseline scenario developed against which progress can be measured.
Key problems to be addressed by the Sustainable Urban Mobility Plan
prioritised.
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer och program)
- Goals (Mål)
- Current situation (Nulägesbeskrivning)
- Alternatives and analysis (Alternativ
och analys)
Includes: Scenarios
Phase 2. Develop a mobility plan
(Fas 2. Ta fram en Trafikstrategi)
Analysis of current situation (Nulägesanalys)
Develop a vision, goals and
strategy (Ta fram vision, mål och
inriktning)
Activity 3.2.: Develop scenarios
Checklist:
Do-nothing scenario elaborated (qualitatively and quantitatively).
Business-as-usual scenario elaborated (qualitatively and
quantitatively).
Different alternative policy scenarios described (qualitatively
and quantitatively). Choose which
scenario serves the vision in the most efficient and effective way.
Appropriate techniques applied to support the scenario development
and appraisal.
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer och
program)
- Alternatives and analysis (Alternativ och analys)
Includes: Scenarios
VTI rapport 844A 24
3.4. SUMP Step 4: Develop a common vision
SUMP Step 4. Develop a common vision
and engage citizens
TRAST Handbook TRAST Guide
Activity 4.1: Develop a common vision of
mobility and beyond
Checklist:
Vision board established.
First draft of vision developed.
Draft discussed with stakeholders.
Agreement on final draft of vision.
Vision outcomes published in attractive format.
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer och program)
- Vision (Vision)
- Overall commitment (Förankring)
Phase 2. Develop a mobility plan
(Fas 2. Ta fram en Trafikstrategi)
Develop a vision, goals and strategy (Ta fram vision, mål och inriktning)
Establish commitment for vision,
targets and strategy (Förankra vision,
mål och inriktning)
Workshop (Trafikdag/workshop)
Activity 4.2: Actively inform the public
Checklist:
Notes from stakeholder meetings made public.
Attractive information material about vision building and its
outcomes elaborated and
disseminated.
Media involved.
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer
och program)
- Vision (Vision)
- Overall commitment (Förankring)
Includes: Communication plan, methods
for dissemination
Phase 2. Develop a mobility plan
(Fas 2. Ta fram en Trafikstrategi)
Develop a vision, goals and strategy
(Ta fram vision, mål och inriktning)
Establish commitment for vision,
targets and strategy (Förankra vision, mål och inriktning)
Workshop (Trafikdag/workshop)
VTI rapport 844A 25
3.5. SUMP Step 5: Set priorities and measurable targets
SUMP Step 5. Set priorities and
measurable targets
TRAST Handbook TRAST Guide
Activity 5.1: Identify the priorities for
mobility
Checklist:
Vision reviewed to guide the development of the objectives.
Draft objectives developed.
Draft discussed with key
stakeholders.
Final draft of the objectives formalised.
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer och program)
- Vision (Vision)
- Overall commitment (Förankring)
Phase 2. Develop a mobility plan
(Fas 2. Ta fram en Trafikstrategi)
Political agreement and decision
(Förankra och besluta (politiskt) om
uppdraget)
Develop a common vision, scenarios,
and measures (Arbeta fram en vision för
trafiken, skissera olika scenarier och
tänkbara åtgärder)
Workshop (Trafikdag/workshop)
Activity 5.2: Develop SMART targets
Checklist:
Develop a suitable set of locally
relevant targets.
Reality check of objectives (> see
Activity 5.1) completed.
Formal adoption of targets and
trajectories by all stakeholders as part of the action and budget plan
(> Activity 7.2)
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer
och program)
- Targets (Mål)
Phase 2. Develop a mobility plan
(Fas 2. Ta fram en Trafikstrategi)
Set targets (Formulera mål och välj
inriktning)
Gain acceptance for targets (Förankra
mål och inriktning)
Develop an action plan (Förslag till
handlingsplan; Skissera genomförandet (tidsplan och budget)
Includes: Time and budget plan
VTI rapport 844A 26
3.6. SUMP Step 6: Develop effective packages of measures
SUMP Step 6. Develop effective packages
of measures
TRAST Handbook TRAST Guide
Activity 6.1: Identify the most effective
measures
Checklist:
Framework of resources re-assessed.
Options of possible measures defined
and summarised.
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer och program)
- Alternatives and analyses (Alternativ
och analys)
- Choice of alternatives (Val av
alternativ)
- Action planning (Åtgärdsplanering)
TRAST Background Handbook
(TRAST Handbok: Underlag)
Phase 2. Develop a mobility plan
(Fas 2. Ta fram en Trafikstrategi)
Develop an action plan (Ta fram handlingsplan)
Compile the mobility plan
(Sammanställ Trafikstrategin)
Communicate, consult and review
(Kommunicera, remissbehandla och
justera)
Adopt the mobility plan (Anta Trafikstrategin)
Activity 6.2: Learn from others’ experience
Checklist:
Identified interesting places that have
implemented a measure.
Exchange with implementers
established.
Key results summarised.
TRAST Background Handbook
(TRAST Handbok: Underlag)
Phase 2. Develop a mobility plan
(Fas 2. Ta fram en Trafikstrategi)
Develop an action plan (Ta fram handlingsplan)
Compile the mobility plan
(Sammanställ Trafikstrategin)
Communicate, consult and review
(Kommunicera, remissbehandla och
justera)
Activity 6.3: Consider best value for money
Checklist:
Suitable measures (and packages of measures) assessed with an eye to
costs and benefits, as well as value for
money.
Results summarised for discussion on
final measure selection.
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer
och program)
- Action planning (Åtgärdsplanering)
TRAST Background Handbook
(TRAST Handbok: Underlag)
Phase 2. Develop a mobility plan
(Fas 2. Ta fram en Trafikstrategi)
Develop an action plan (Ta fram
handlingsplan)
Compile the mobility plan
(Sammanställ Trafikstrategin)
Communicate, consult and review
(Kommunicera, remissbehandla och justera)
Activity 6.4: Use synergies and create
integrated packages of measures
Checklist:
Effective packages of measures and possible synergies identified.
Packages of measures checked with an eye to integration with land use
planning and other sectoral planning
activities.
Set of packages of measures
selected as input for discussion
on final selection and action and budget plan (> Activity 7.2).
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer och program)
- Action planning (Åtgärdsplanering)
TRAST Background Handbook
(TRAST Handbok: Underlag)
Phase 2. Develop a mobility plan
(Fas 2. Ta fram en Trafikstrategi)
Develop an action plan (Ta fram handlingsplan)
Compile the mobility plan
(Sammanställ Trafikstrategin)
Communicate, consult and review
(Kommunicera, remissbehandla och
justera)
VTI rapport 844A 27
3.7. SUMP Step 7: Agree on clear responsibilities and allocate funding
SUMP Step 7. Agree on clear
responsibilities and allocate funding
TRAST Handbook TRAST Guide
Activity 7.1: Assign responsibilities and
resources
Checklist:
Final set of packages of measures proposed.
Responsibilities and possible funding sources identified.
Discussion with concerned
stakeholders concluded.
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer och program)
- A defined process (En tydlig
process)
Phase 3. Implementation and management
(Fas 3. Att genomföra och förvalta)
Action planning (Genomförandeplanering, påbörja
genomförandet)
Activity 7.2: Prepare an action and budget
plan
Checklist:
Action and budget plan drafted.
Formal agreement from decision
makers and key stakeholders.
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer och program)
- A defined process (En tydlig
process)
Phase 3. Implementation and management
(Fas 3. Att genomföra och förvalta)
Action planning (Genomförandeplanering, påbörja
genomförandet)
VTI rapport 844A 28
3.8. SUMP Step 8: Build monitoring and assessment into the plan
SUMP Step 8. Build monitoring and
assessment into the plan
TRAST Handbook TRAST Guide
Activity 8.1: Arrange for monitoring and
evaluation
Checklist:
Suitable indicators (based on indicators selected in Activity 5.2
Develop SMART targets) selected.
Suitable monitoring and evaluation tools agreed on.
Work plan and responsibilities for data collection and management
agreed.
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer och program)
- Evaluation (Uppföljning)
Phase 3. Implementation and
management
(Fas 3. Att genomföra och förvalta)
Monitor, assess and communicate (Följ upp och utvärdera, kommunicera resultaten)
VTI rapport 844A 29
3.9. SUMP Step 9: Adopt Sustainable Urban Mobility Plan
SUMP Step 9. Adopt Sustainable Urban
Mobility Plan
TRAST Handbook TRAST Guide
Activity 9.1: Check the quality of the plan
Checklist:
Final draft of Sustainable Urban
Mobility Plan compiled.
Internal and stakeholder review
completed.
Final amendments completed.
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer och program)
- A defined process (En tydlig process)
3.3 Develop wide support
Phase 2. Develop a mobility plan
(Fas 2. Ta fram en Trafikstrategi)
Communicate, consult and review
(Kommunicera, remissbehandla och
justera)
Phase 3. Implementation and
management
(Fas 3. Att genomföra och förvalta)
Update steering documents (Uppdatera styrdokumenten, aktualitetsförklara)
Activity 9.2: Adopt the plan
Checklist:
Sustainable Urban Mobility Plan
adopted by elected representatives of pubic body/bodies responsible for
planning.
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer och program)
- A defined process (En tydlig process)
- Commitment (Förankring)
Phase 2. Develop a mobility plan
(Fas 2. Ta fram en Trafikstrategi)
Adopt the mobility plan (Antagande av Trafikstrategin)
Activity 9.3: Create ownership of the plan
Checklist:
Public relations and involvement activities planned and carried out.
Adoption of Sustainable Urban Mobility Plan celebrated with
citizens and stakeholders.
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer
och program)
- A defined process (En tydlig process)
- Commitment (Förankring)
Phase 2. Develop a mobility plan
(Fas 2. Ta fram en Trafikstrategi)
Communicate, consult and review
(Kommunicera, remissbehandla och justera)
VTI rapport 844A 30
3.10. SUMP Step 10: Ensure proper management and communication (when implementing the plan)
SUMP Step 10. Ensure proper management
and communication (when implementing
the plan)
TRAST Handbook TRAST Guide
Activity 10.1: Manage plan implementation
Checklist:
Work plan on management procedures and actor responsibilities agreed on.
Risk contingency plan elaborated.
Reporting formats agreed on.
Phase 3. Implementation and management
(Fas 3. Att genomföra och förvalta)
Action planning (Genomförandeplanering, påbörja genomförandet)
Monitor, assess and communicate (Följ
upp och utvärdera, kommunicera resultaten)
Activity 10.2: Inform and engage citizens
Checklist:
Citizens and stakeholders who are directly affected by measure
implementation involved.
Solutions for mitigation of negative effects during implementation
elaborated.
General public informed about progress of measure implementation.
Phase 3. Implementation and management
(Fas 3. Att genomföra och förvalta)
Monitor, assess and communicate (Följ
upp och utvärdera, kommunicera resultaten)
Activity 10.3: Check progress towards
achieving the objectives
Checklist:
Implementation of measures
continually monitored.
Impacts evaluated at regular intervals.
Evaluation report prepared and published.
Phase 3. Implementation and management
(Fas 3. Att genomföra och förvalta)
Action planning (Genomförandeplanering, påbörja genomförandet)
Monitor, assess and communicate (Följ upp och utvärdera, kommunicera
resultaten)
Update steering documents (Uppdatera styrdokumenten, aktualitetsförklara)
VTI rapport 844A 31
3.11. SUMP Step 11: Learn the lessons
SUMP Step 11. Learn the lessons TRAST Handbook TRAST Guide
Activity 11.1: Update current plan regularly
Checklist:
Necessary amendments in implementation of measures
identified.
Amendments discussed with actors
concerned.
Plan update concluded.
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer
och program)
- Evaluation (Uppföljning)
Phase 3. Implementation and
management
(Fas 3. Att genomföra och förvalta)
Monitor, assess and communicate (Följ upp och utvärdera, kommunicera
resultaten)
Update steering documents (Uppdatera styrdokumenten, aktualitetsförklara)
Activity 11.2: Review achievements –
understand success and failure
Checklist:
Ex-post evaluation of planning process and measure implementation
concluded.
Lessons learnt documented.
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer och program)
- Evaluation (Uppföljning)
Phase 3. Implementation and
management
(Fas 3. Att genomföra och förvalta)
Targets and metrics (Mål och mått)
Includes: Evaluation
Activity 11.3: Identify new challenges for
next SUMP generation
Checklist:
New challenges ahead for urban transport and mobility identified.
Lessons learnt from current planning cycle used for development of next
Sustainable
Urban Mobility Plan.
Section: Local strategies, plans and
programmes
(Kommunens arbete med strategi, planer och program)
- Evaluation (Uppföljning)
Phase 3. Implementation and
management
(Fas 3. Att genomföra och förvalta)
Monitor, assess and communicate (Följ upp och utvärdera, kommunicera resultaten)
Update steering documents (Uppdatera styrdokumenten,
aktualitetsförklara)
This detailed analysis and comparison based on SUMP activity levels revealed that identical or similar
guidelines are included in both systems. SUMP still focuses on planning process guidelines, whereas
TRAST includes instructions and suggestions regarding the development and content of plan documents
even on this more detailed level. The TRAST Background Handbook has no counterpart in SUMP, but
additional support is under development, for example city networks, benchmarking activities and
additional supporting tools.
VTI rapport 844A 32
4. Concluding analysis and comparison of SUMP and TRAST
Both SUMP and TRAST include instructions in the form of guidelines that must be interpreted and
translated into a plan, practical planning and actions by cities. In addition, the TRAST support
includes handbooks and guides with suggestions, discussion and examples of measures, actions and
policies. In both TRAST and SUMP, implementation is supported through projects, for example
facilitating the exchange of experiences between cities.
This comparison showed that identical or similar areas and requirements are addressed in SUMP and
TRAST regarding the planning process. However, the TRAST material also includes a comprehensive
handbook addressing the development of traffic strategies, traffic plans and actions (Table 1). In
conclusion, the TRAST planning support includes all areas included in SUMP.
Table 1. Summary of comparison of SUMP and TRAST.
Type of support SUMP TRAST
Instruction (checklist) for integrated
planning
Guidelines TRAST Handbook: Planning process
TRAST Guide
Design and development of an integrated
planning process
TRAST Handbook: Planning process
TRAST Guide
Development and content of a sustainable
mobility plan
TRAST Handbook: Planning process
TRAST Background Handbook - Facts and
information
TRAST Guide
VTI rapport 844A 33
Literature
SUMP Guidelines – Developing and implementing a sustainable urban mobility plan. Available at
www.mobilityplans.eu.
Transport for an attractive city - an introduction to TRAST, 2014, available at
http://webbutik.skl.se/sv/artiklar/samhallsbyggnad/transport-for-an-attractive-city-an-introduction-to-
trast.html#sthash.uBXHWYfJ.dpuf.
TRAST, 2007, second edition, Trafik för en attraktiv stad (Transport for an attractive city). Handbooks
available at www.trafikverket.se/Foretag/Planera-och-utreda/Samhallsplanering/Tatort/Trafik-for-en-
attraktiv-stad/Rapporter-om-TRAST/. In Swedish.
TRAST-guiden, 2011. Guide available at www.trafikverket.se/Foretag/Planera-och-
utreda/Samhallsplanering/Tatort/Trafik-for-en-attraktiv-stad/Rapporter-om-TRAST/. Also a checklist
is available. In Swedish.
www.vti.se
VTI, Statens väg- och transportforskningsinstitut, är ett oberoende och internationellt framstående forskningsinstitut inom transportsektorn. Huvuduppgiften är att bedriva forskning och utveckling kring infrastruktur, tra� k och transporter. Kvalitetssystemet och miljöledningssystemet är ISO-certi� erat enligt ISO 9001 respektive 14001. Vissa provningsmetoder är dessutom ackrediterade av Swedac. VTI har omkring 200 medarbetare och � nns i Linköping (huvudkontor), Stockholm, Göteborg, Borlänge och Lund.
The Swedish National Road and Transport Research Institute (VTI), is an independent and internationally prominent research institute in the transport sector. Its principal task is to conduct research and development related to infrastructure, traf� c and transport. The institute holds the quality management systems certi� cate ISO 9001 and the environmental management systems certi� cate ISO 14001. Some of its test methods are also certi� ed by Swedac. VTI has about 200 employees and is located in Linköping (head of� ce), Stockholm, Gothenburg, Borlänge and Lund.
HEAD OFFICELINKÖPINGSE-581 95 LINKÖPINGPHONE +46 (0)13-20 40 00
STOCKHOLMBox 55685SE-102 15 STOCKHOLM PHONE +46 (0)8-555 770 20
GOTHENBURGBox 8072SE-402 78 GOTHENBURGPHONE +46 (0)31-750 26 00
BORLÄNGE Box 920SE-781 29 BORLÄNGEPHONE +46 (0)243-44 68 60
LUND Medicon Village ABSE-223 81 LUND PHONE +46 (0)46-540 75 00