Comparing T&D Capacity Options, On a Risk Adjusted … · EESAT_2005_DUA-Eyer.ppt 2 ACKNOWLEDGMENTS...
Transcript of Comparing T&D Capacity Options, On a Risk Adjusted … · EESAT_2005_DUA-Eyer.ppt 2 ACKNOWLEDGMENTS...
Comparing T&D Capacity Options,On a Risk Adjusted Cost Basis
Including Stationary and Transportable DERs
Joe Iannucci and Jim EyerDistributed Utility Associates
(510) 482 [email protected]
for US DOE and Sandia National Laboratories
andThe California Energy Commission
EESAT_2005_DUA-Eyer.ppt 2
ACKNOWLEDGMENTS
• This project is part of the collaboration between the California Energy Commission (CEC) and the Energy Storage Systems Program of the U.S. Department of Energy (DOE/ESS) through Sandia National Laboratories (SNL).
EESAT_2005_DUA-Eyer.ppt 3
Agenda
• Study Purpose
• T&D Planning Uncertainties
• Risk Adjusted Cost Concept and Results
• Merits of DER Transportability
• Conclusions
EESAT_2005_DUA-Eyer.ppt 4
Team
• Joe Iannucci, DER Advocate• Jim Eyer, Senior Analyst• Jim Skeen, Utility Distribution Engineer, P.E.• Dr. Roger Pupp, Economist, Financial Analyst• Dr. Thomas Hoff, Engineering Economist• Susan Horgan, Principal of DUA
• Imre Gyuk (DOE) and John Boyes (Sandia)• Mark Rawson (CEC)
EESAT_2005_DUA-Eyer.ppt 5
Study Purpose
• Develop and try a basic framework to compare risk adjusted cost for T&D capacity options, including DER
– Hypothesis: More optimal cost-of-service is achieved by selecting T&D capacity options using risk adjusted cost.
• Characterize the merits of DER “transportability”
EESAT_2005_DUA-Eyer.ppt 6
Background• Ri$k
– financial exposure that is not certain– forms: additional cost and/or reduced “profit”
• Explicit evaluation of risk allows utility toavoid unattractive outcomesaccept risk, to pursue favorable outcomes
• Utility pricing– revenue requirements obscures actual risk
“distributed risk” -- all customers pay
EESAT_2005_DUA-Eyer.ppt 7
Risk Evaluation
0
20,000
40,000
60,000
80,000
100,000
120,000
140,000
Do Nothing Do Upgrade 600 kW DER 750 kW DER Rent 500 kWDiesel
Rent 500 &250 kW Diesel
Option
Ris
k ($
Yea
r 1)
DER is Undersized
DER Reliability
Project Delay
Utility Response
Utility Lost Revenue
T&D Damage and Repair
Customer Unserved Energy
EESAT_2005_DUA-Eyer.ppt 8
Risk Adjusted Cost Example
0
20,000
40,000
60,000
80,000
100,000
120,000
140,000
Do Nothing Do Upgrade 600 kW DER,$100/kW-year
750 kW DER,$75/kW-year
Rent 500 kWDiesel
Rent 500 &250 kW Diesel
Option
Ris
k-ad
just
ed C
ost (
$ Ye
ar 1
)
Risk
Direct Cost
EESAT_2005_DUA-Eyer.ppt 9
Key T&D Planning Uncertainties
• “Inherent” Peak Load Growth– Drivers: economic conditions & load mix
• Uncertain Block Load Changes – e.g.; strip malls, housing developments
primarily additions• Weather-related Variability
normally design to “extreme” conditions• e.g.; one year in ten
EESAT_2005_DUA-Eyer.ppt 10
Key T&D Planning Uncertainties
• Construction Delays– engineering and/or construction staff shortages– budget shortfalls– “institutional” challenges (e.g., permits)
• Load Shape Change– load mix– energy use pattern
• T&D Equipment Loading History– remaining life / reliability
EESAT_2005_DUA-Eyer.ppt 11
Calculating RiskExpected Value of Possible Future Outcomes
50% chanceload growth < expected
no overload
50% chance load growth > expected
10% overload
Load GrowthUncertainty
45% chanceno overload
5% chance7% overload
45% chance10% overload
5% chance17% overload
End States Cost ($)
$0
$50,000
$170,000
$425,000
Gross, forEnd-State
Probability-Adjusted
$0
$2,500
$31,500
$76,500
$100,000Expected Value (Risk)
TemperatureUncertainty
90% chance temperature <= design
10% overload
10% chance temperature > design
7% overload
10% chance temperature > design
17% overload
90% chance temperature <= design
0% overload
EESAT_2005_DUA-Eyer.ppt 12
The Case• Upgrade 12 MW to 16 MW (+4,000 kW +33%)
– cost: $260/kWadded * 4,000 kW = $1,040,000– “annualized” @ 11% = $114,000/year
• Existing Equipment– remaining life 12 years– value: $39,600/year of remaining life
• Load – previous year peak load 11.7 MW– uncertain load growth
EESAT_2005_DUA-Eyer.ppt 13
Ri$k is Co$t• Cost elements of risk quantified:
– Utility-related• T&D equipment damage -- $39,600/year remaining• event “response” -- assumed $1,000/event• lost revenues -- assumed 14¢/kWh
– Customer-related• cost incurred due to outages -- monetized• assumed $3/kWh of “unserved energy”
NORMALLY reliability indices are “proxy”
All costs evaluated relate to overloading.
EESAT_2005_DUA-Eyer.ppt 14
Cost for Possible Future Outcomes
0
300
600
900
1,200
1,500
1,800
2,100
2,400
2,700
3,000
3,300
0% 5% 10% 15% 20% 25%
Scenario Maximum Overload, % of T&D Equipment Rating
Scce
nario
Tot
al C
ost (
$000
EESAT_2005_DUA-Eyer.ppt 15
Load Growth Uncertainty
0%
5%
10%
15%
20%
25%
30%
0% 5% 10% 15% 20% 25%Overload, % of T&D Equipment Rating
Freq
uenc
y of
Occ
urre
nce
0%
20%
40%
60%
80%
100%
Cum
ulative Probability
EESAT_2005_DUA-Eyer.ppt 16
0
20,000
40,000
60,000
80,000
100,000
120,000
0 250 500 750 1,000 1,250 1,500
DER Capacity (kW)
Risk
-- E
xpec
ted
Valu
e ($
)
DER “Undersizing” RiskDo Nothing Cost
EESAT_2005_DUA-Eyer.ppt 17
DER Cost
0
50,000
100,000
150,000
200,000
250,000
250 500 750 1,000 1,250 1,500DER Capacity (kW)
Ann
ual C
ost (
$)
$75 kW-year
$100 kW-year
$150 kW-year
EESAT_2005_DUA-Eyer.ppt 18
0
20,000
40,000
60,000
80,000
100,000
120,000
0 250 500 750 1,000 1,250 1,500
DER Capacity (kW)
Risk
-- E
xpec
ted
Valu
e ($
)
0
50,000
100,000
150,000
200,000
250,000
250 500 750 1,000 1,250 1,500DER Capacity (kW)
Ann
ual C
ost (
$)
$75 kW-year
$100 kW-year
$150 kW-year
Risk Adjusted Cost Results
75,000
100,000
125,000
150,000
175,000
250 500 750 1,000 1,250 1,500DER Capacity (kW)
Ris
k A
djus
ted
Cos
t -- E
xpec
ted
Valu
e ($
)
Upgrade Risk-adjusted CostDo Nothing DER Cost $150 kW-yearDER Cost $100 kW-yearDER Cost $75 kW-year
EESAT_2005_DUA-Eyer.ppt 19
Important CriteriaLoad Growth Uncertainty
Weather UncertaintyOverloading: magnitude, frequency, durationCustomer Cost Assumed for OutagesExisting T&D Equipment• Capacity “Headroom” Remaining• Type/value• Life Remaining
Budget/Staff Availability Uncertainty
EESAT_2005_DUA-Eyer.ppt 20
DER Transportability Value• Use same capacity several times
different locationsdifferent seasonsdifferent years
• 3x to 5x benefits ($PW) for same kW• Distribution budget optimization
– serve same or more demand (kW) with less $• Fleet effects
– DER reliability (backup units, n+1)– economies-of-scale
EESAT_2005_DUA-Eyer.ppt 21
0
50
100
150
200
250
300
1 2 3 4 5 6 7 8 9 10Year
Ann
ual $
PW
/ kW
Single Year Reliability/PQValue
Single Year Deferral Value
Example: Value Proposition for Transportable MES and DGs
0
50
100
150
200
250
300
1 2 3 4 5 6 7 8 9 10Year
Annu
al $
PW /
kW
0
200
400
600
800
1,000
1,200
1,400
Cumulative $PW
/ kW
Single Year Reliability/PQ Value
Single Year Deferral Value
Cumulative Value ($PW)
EESAT_2005_DUA-Eyer.ppt 22
Conclusions• Transportable DERs can have significantly
enhanced value (relative to stationary).• T&D risk is an important though obscured
element of the DER value proposition.• A rich area for additional research
– “piggy-back” on related developments in T&D planning and engineering
• especially tools, data, “smart” T&D systems
– apply methodology to actual cases