Company profile March 2013 Byrne Construction
-
Upload
dwaine-byrne -
Category
Documents
-
view
270 -
download
3
Transcript of Company profile March 2013 Byrne Construction
Page 1
Company Profile
Page 2
Business, Administrative & Contact
Information
Business Name: Byrne Construction Pty Ltd Business Type: Civil & Construction Primary Contact,
Dwaine Byrne Mobile: 0404 889 439 Email: [email protected]
Office: 7 Gentle Road
Medina WA 6167
Postal: PO Box 629 Kwinana WA 6167
Contact: Tel 08 9439 6094
Fax 08 9439 3429 Email [email protected]
ABN: 99 105 099 367
Page 3
What we do Concrete supply and placing
Steel fixing
Tilt Panel Construction/Erection
Formwork supply and install
Suspended Slabs
Bridge Construction
Mining Construction
Pre Cast Construction
Pre Cast Yard - 1600m2
Labour Hire
Plant and Machinery Bobcats
Telehandlers
Loaders
Roller and compaction equipment
Vibrating Screeds
Lighting Tower
Compressor
Scaffolding
Boom lifts
Scissors Lifts
Excavators – 22 , 13 , 8 , 6 , 2 & 1.5 Tonne Machines
40 Tonne Rough Terrain Crane / Flat Bed Crane
Concrete & Formwork associated equipment
Water Carts
Page 4
About us
Byrne Construction Pty Ltd is a civil and construction company. It was incorporated in the year of 2003. Dwaine has been in construction for 30 years and has worked on various projects throughout Australia. Dwaine always had hands on approach to work regardless with the position he held.
Our Specialty is concrete and formwork throughout Australia. The projects that we have been involved of the highest standards of quality and safety in the industry and therefore we adopt the approved policies and procedures as our own.
With our vast array of experience behind us we feel we are in a prime position to expand on the services we can provide and the clients we do business with.
Byrne Construction believes that the success of our company
Lies in our people. We thrive on delivering a safe working Environment to every project we endeavor.
Page 5
Our Projects
Page 6
Xstrata Zinc Filter Plant Upgrade Location: Queensland Our Client: IPS Duration: 8 Months The works of this project included;
Placing 1300m3 concrete.
Ring Beam installation.
Zinc Building.
Concrete slabs.
Lead Storage Building.
Transfer stations.
Formwork.
Reinforcing.
Earthworks.
Hadrian Dyno Noble Project
Page 7
Location: Port Hedland, WA Our Client: IPS Duration: 6 months
The works of this project included;
Construction of an explosive plant.
Placing 1000m3 Concrete.
Foundation.
Pedestals.
Slabs.
Earthworks.
Formwork / Reinforcement.
South Perth Apartments Location: Perth, WA Our Client: DAVROB Duration: 1 Year
The works of this project included;
Premium Luxury Apartments.
Placing 1000m3.
Retaining Walls.
Suspended slabs.
Columns.
Lift shafts.
Reinforcement.
Earthworks.
Page 8
Glen Iris / Rathmines Water Tanks Location: Bunbury, WA Our Client: Omega Construction Duration: 8 Months
The works of this project included;
8 Metre high Water Tank.
Placing 800 m3 Concrete.
Concrete Bases.
Concrete Slabs.
Earthworks.
Footings.
Panel formwork.
Fremantle Ports
Location: Fremantle, WA Our Client: Marine & Civil Duration: 3 Months
The works of this project included;
Extension to Wharf.
Precast pile caps.
Placing 500m3 Concrete.
Reinforcement.
Concrete slabs.
Worked in strict tolerances.
Page 9
Gorgon Jetty Pre – Assembly
Location: Henderson, WA Our Client: Leighton’s Duration: 24 months
The works of this project included;
The Gorgon LNG Jetty.
Construction of Caissons.
Formwork installation.
Concrete Placemen.
Labour hire.
Page 10
Gorgon Pipe Rack Ballast Blocks
Location: Medina/ Casting Yard, WA Our Client: Omega Construction Duration: 2 Months
The works of this project included;
Construct 250 pipe supports.
Strict environmental policies.
Worked in strict tolerances.
Pre cast Yard used to manufacture.
Concrete Placement.
Pre fab moulds.
Utah Point Pre Cast Pile Caps
Location: Medina / Casting Yard, WA Our Client: Marine & Civil Duration: 2 Months
The works of this project included; Construct 300 precast piles.
Worked in strict tolerances.
Concrete Placement.
Steel moulds.
Transported to Port Headland.
Pre Cast Yard used to manufacture.
Page 11
Coral Bay –Water Storage Tank
Location: Coral Bay, WA Our Client: DM Civil Duration: 3 Months The works of this project included;
Construction of a radius 5 Metre high Water Tank.
Radius formwork.
Reinforcement.
Concrete Placement.
Page 12
SGA – Southern Gateway Alliance
Location: Perth to Bunbury Our Client: Leighton’s Duration: 18 Months The works of this project included;
Construction of 7 bridges.
Placing 5000 M3 concrete.
Abutments/ Pier columns.
Reinforcement.
Formwork / Earthworks.
Page 13
CSBP/ Ammonium Nitrate Plant Expansion
Location: Kwinana, WA Our Client: Marine & Civil Duration: 24 Months The works of this project included;
Expansion to CSBP Plant.
Placing 10,000 M3 Concrete.
Bases, Pedestals.
Pre Cast Panels.
Large Concrete slabs.
Radius bases.