COMMUNITY UPDATE
August 22, 2018
COMMUNITY UPDATEAndrew Neiditz | SOUTH SOUND 911
Steve Dwoskin | CallisonRTKLDavid Chamness| CallisonRTKL
• OUR PROGRESS
• Employee charrettes- May 15 & 16, July 11 & 12
• Initial coordination meetings with City of Tacoma and utilities
• Building systems selection process
• Development of interior layout
• Building form and envelope studies
• Construction estimate updates
SITE LAYOUT
Does not represent final or proposed design. For illustrative purposes only
SOUTH D STREET
PACIFIC AVENUE
SO
UTH
36TH
STR
EE
T
SECURE STAFF PARKING
SOUTH SOUND 911PUBLIC SAFETY
COMMUNICATIONS CENTER72,500 S.F.
LANDSCAPE SECURITY SETBACK
LANDSCAPE SECURITY SETBACK
PUBLIC ENTRANCE
STAFF ENTRANCE
SITE SECTION | WEST – EAST (FROM SOUTH 36TH STREET)
THIRD FLOOR
SECOND FLOOR
GROUND FLOOREMPLOYEE ENTRANCE
PACIFICAVENUE
EMPLOYEE PARKING
82 FEETSTAND-OFF
ZONE50
’ –0”
H
110’ – 0” W
32’ –
0” H
SITE SECTION | SOUTH – NORTH (FROM PACIFIC AVE)
THIRD FLOOR
SECOND FLOOR
GROUND FLOORPUBLIC ENTRANCE COMMUNICATION SYSTEMS
911 COMMUNICATIONS CENTER
305’ – 0” W
50’ –
0” H
GROUND LEVEL
RECORDS
COMMUNICATIONSSYSTEMS
FACILITYSUPPORT
FACILITYSERVICES
EMERGENCYOPERATIONS
CENTER
PUBLICENTRY
TRAININGROOM
SERVICEAREA
LEVEL 2
INFORMATIONSERVICES
911COMMUNICATIONS
SUPPORT
911COMMUNICATIONS
CENTER
LEVEL 3
ADMINISTRATION EXECUTIVE AREA911
COMMUNICATIONSCENTER
(BELOW)
BUILDING FORM
ARCHITECTURAL INSPIRATION
Office Precedents
Material Reference Communications Center Precedent
MASSING VIEW
Puget Sound Hospital (View from South Division Lane and South D Street)
MASSING VIEW
Proposed Building (View from South Division Lane and South D Street)
PACIFIC AVENUE (LOOKING SOUTHWEST)
PACIFIC AVENUE (LOOKING NORTHWEST)
SOUTH D STREET (LOOKING NORTHWEST)
BUILDING COLORS & MATERIALS
Insulated Metal Panels
Precast Concrete IPE Wood Metal Canopy
Metal Railing Vertical Seam Metal Panels
LANDSCAPE PLAN
LANDSCAPE TYPOLOGIES
Forest
Meadow Stormwater Green Roof
Rock Gardnen
DESIGN KICKOFF
DESIGN
CONSTRUCTION
2ND QUARTER2018
3RD QUARTER2018
2ND QUARTER2019
3RDQUARTER2020
BUILDINGCOMMISSIONING
• User Group Charrettes• Equipment Demos• Conceptual Design• Functional Layouts • Site Due Diligence- Survey, Geotech
• Schematic Design• Design Development• Building Agency Coordination• Construction Documentation & Permits• Construction Cost Reviews• End of Phase Presentations to SS911 • Technology Integration
• Set-up• Move-In (soft openings)• Initiate backup improvements
• Schematic Design complete September 2018
• Additional employee charrettes completed
• Construction cost review August 2018
• Policy Board meeting – August 22, 2018
• Community meeting – August 22, 2018
• Bidding and Award- 2ND Quarter 2019• Permitting• Construction
SCHEDULE OVERVIEW
THANK YOU.