Community Solar in Oregon · 2019. 11. 5. · EQ Research, LLC Oregon Solar Energy Industries...
Transcript of Community Solar in Oregon · 2019. 11. 5. · EQ Research, LLC Oregon Solar Energy Industries...
Community Solar in OregonDesign and Outlook
October 18, 2019
Charlie Coggeshall
EQ Research, LLC
Oregon Solar Energy Industries Association
Coalition for Community Solar Access
Community Solar – How it Works
SEPA
Program Design - Big Picture
• Legislation passed in 2016 (SB 1547)
• Rules adopted June 2017 (860-088-00100)
• 160+ MW in “initial capacity tier”
• PGE – 93MW; PAC – 63MW; IDP – 3MW
• Projects limited to 25 kW - 3 MW in size
• Project Manager eligibility
• Third-party developers and utilities
Program Implementation: Remaining Timeline
Policy Elements• October 22 - Staff and Stakeholders make case for policy elements at PUC public meeting• October 29 - PUC special meeting to deliberate and decide policy issues
Program Implementation Manual (PIM)• November 18 - A final draft of the PIM is posted for public comment and PUC review• December 3 – Staff present PIM to PUC (opportunity for stakeholder comment)
Program Launch (target)• (September 30 – Project Manager Registration open)• December 4 - Program opens the pre-certification application website• December 16 - Project Managers may start submitting pre-certification applications
Customer Participation
• All customer types eligible, but: • At least 50% of project capacity reserved
for residential and/or small commercial• At least 10% of project capacity reserved
for low-income customers• Min. 20% subscription discount
• Participation options:• Direct ownership• Subscription (minimum 10 years)
• Individual limits:• Cannot exceed avg. annual usage,
and ≤ 40% of project capacity• 2 MW max. for one customer; and
up to 4 MW for “affiliated”
Project Certification Requirements
Pre-Certification
• Project details
• Interconnection documentation (payment submitted for SIS)
• Non-ministerial permits
• Documentation of acquisition approach, proposed marketing materials, low-income strategy, and proposed forms/contracts
Certification
• Minimum 50% subscribed
• At least 5 participants
• Compliance with low-income requirements
• Constructed/inspected
• 6 months to interconnect/operate
Step 1 Step 2 Step 3
Project Manager Registration
• Available now
• Requires ongoing compliance with “standard of conduct”
Maximum of 18 months
Program Administration
• Program Administrator• Energy Solutions (prime) and ETO (sub)• Develops Implementation Manual • Processes pre-cert. and cert. applications
and provides initial review prior to PUC review
• Facilitates data and financial flow
• Low-income Facilitator• Community Energy Project• Reports to the Program Administrator• Liaison/supporter for program to achieve
low-income targets
• Utilities• Apply credits on participant bills• Receives subscription payments from
participants and passes through to PA
Capacity Allocation & Credit Rate (proposed)
Administrative Costs (proposed)
Utility75% of
Tier (MW)General (MW)
Small or Non-
profit or Gov't
(MW)
Rate ($/kWh)
20-yr
Levelized
(2.18% esc.)
PGE 69.86 52.40 17.47 $ 0.11234 $ 0.13895
PAC 48.45 36.34 12.11 $ 0.09770 $ 0.12084
IPC 2.45 1.84 0.61 $ 0.08480 $ 0.10489
Fee Type/Duration Fee
Application Fee ($/kW-DC) $ 5.00
Ongoing Participant Fee ($/kW-DC/month)
*Note – this is not applied to low-income participants
$ 1.50
Interconnection Proposals
Recommendation #1: Streamlined CSP interconnection process• Process
• Eligible CSP requests will be studied separately from traditional serial queue • Interconnection study would limit scope, comparable to Energy Resource (ER)
• Eligibility criteria• The proposed generator, together with all other interconnected and requested
generation in the local area, is less than 100% of minimum daytime load (MDL) • If MDL is not available for the feeder, use 30% of summer peak load
*Based on 30% screening level - Klamath County has about 30 MW of available capacity, with: 2 feeders that could handle a 2-3 MW project; 13 feeders for 1-2 MW; 7 feeders for 361-999 kW; and 7 feeders for <361 kW
Interconnection Proposals
• Recommendation #2: Initial models for cost-sharing between generators
• Recommendation #3: 360 kW or less to meter on the low side of the transformer
• Recommendation #4: RFI for third-party expert interconnection study review services
• Recommendation #5: Enhanced pre-application report for non-profit/public PMs • Can request 5 sites in single request, at no cost
• Recommendation #6: PacifiCorp to provide additional information on the process to address the backlog of interconnection applications (i.e., outside Recommendation #1)
How to stay involved
• Track the PUC Docket: UM 1930
• Review Draft PIM Chapters and provide comments via the Program Administrator’s Stakeholder Engagement Website -https://orcsplaunch.wordpress.com
• Register to become a Project Manager and learn more about program requirements via the Program website - https://www.oregoncsp.org
• Join OSEIA! We have weekly member updates and a Community Solar Committee that meets bi-monthly. https://www.oseia.org/join We have government and non-profit rates.