Transcript of Community Services and Health Industry Skills Council Revised Project Timelines January 2014.
Community Services and Health Industry Skills Council
Revised Project Timelines
January 2014
Submitted by December 2015• Review of current content by Dec 2014:- Selected Technicians & Health Support - Dental Assisting - Complementary & Alternative Health - Selected Community Sector Development - Community Sector Coordination - General Community Services- Case Management
• Review of current content by Dec 2015:- Dental Technology and Dental Prosthetics - Individual Client Support- Nutrition/dietetic assistance- Allied Health Assisting- Ambulance- Enrolled/Division 2 Nursing- Remaining Client Services
• Develop Implementation Guides• Provide general advisory role including stakeholder support, enquiries,
presentations, participation on committees, speaking engagements
Timeline: Submitted by Dec 2014
Analyse Feedback(July 2013)
Engage SMEG(August – October 2013)
Finalise Second Draft(November 2013)
Public Consultation(February – April 2014)
Analyse Feedback and Finalise Components
(April 2014)
Preliminary QA(May 2014)
Validation and sign-off by IRG
(June 2014)
Finalise Case for Endorsement(30 June 2014)
External Quality Assurance and editing
(1 July -10 August 2014)
Consultation with State Training Authorities
(September 2014)
Submit for endorsement (to NSSC)
(24 October 2014)
July 2013 – March 2014 April 2014 – June 2014 July 2014 – December 2014
Industry Reference Group (IRG)
Subject Matter Experts (SME)
TPAC
Timeline: Submitted by Dec 2015
Analyse Feedback(July 2014)
Engage SMEG(August – October 2014)
Finalise Second Draft(November 2014)
Public Consultation(27 January – 21 March 2015)
Preliminary QA and Moderation
(27 January – 21 March 2015)
Analyse Feedback and Finalise Components
(April 2015)
Preliminary QA(May 2015)
Validation and sign-off by IRG
(June 2015)
Finalise Case for Endorsement(30 June 2015)
External Quality Assurance and editing
(1 July -10 August 2015)
Consultation with State Training Authorities
(September 2015)
Submit for endorsement (to NSSC)
(24 October 2015)
July 2014 – March 2015 April 2015 – June 2015 July 2015 – December 2015
Industry Reference Group (IRG)
Subject Matter Experts (SME)
TPAC
Timeline: Direct Client Care
Analyse Feedback
(July 2013)
Engage SMEG
(August – October 2013)
Finalise Second Draft
(November 2013)
Public Consultation
(February – April 2014)
Analyse Feedback
(April - July 2014)
Engage SMEG
(August – October 2014)
Finalise Third Draft
(November 2014)
Public Consultation
(27 January – 21 March 2015)
Analyse Feedback and Finalise Components
(April 2015)
Preliminary QA
(May 2015)
Validation and sign-off by IRG
(June 2015)
Finalise Case for Endorsement
(30 June 2015)
External Quality Assurance and
editing
(1 July -10 August 2015)
Consultation with State Training
Authorities
(September 2015)
Submit for endorsement (to
NSSC)
(24 October 2015)
July 2013 – March 2014 April 2014 – March 2015 April 2015 – June 2015 July 2015 – December 2015
Industry Reference Group (IRG)
Subject Matter Experts (SME)
TPAC
Post December 2015The following work will be addressed post December 2015 as part of Continuous Improvement:• Analysis and review low use qualifications (23 qualifications and 150
units) including:- Ancillary Services- Population Health- Cast Technology- Prosthetic/Orthotic Technology - Sleep Technology- Rehabilitation and Assistive Technology - Hyperbaric Technology - Mortuary Theatre Practice- Development/Humanitarian Assistance