Community Liaison Group -...

47
Community Liaison Group West & North Joint Meeting 21 February 2019

Transcript of Community Liaison Group -...

Page 1: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Community Liaison Group

West & North Joint Meeting

21 February 2019

Page 2: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

JIM WILLIAMSON

Introduction

Page 3: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Time Item Topic

5.30pm 1 Welcome, introductions, apologies and actions from previous meeting

5.40pm 2 Report from CLG community members

6:10pm 3 Special Guests – Patsy Toop / Thomas Alemis

6.40pm 4 Tea Break

6.55pm 5 Construction update

7.10pm 7 Landscape CLG Workshop Update

7.20pm 6 Questions from CLG members on construction update and landscape workshop update

7.35pm 8 West Gate Tunnel Authority Update

7.50pm 9 Upcoming events for CLG Members to attend

7.55pm 10 Actions arising and close

Page 4: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Report from CLG community members

Page 5: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Patsy Toop

Department of Environment, Land, Water and Planning

Inner West Air QualityCommunity Reference Group

Page 6: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Independent Chair of the Inner West Air Quality Community

Reference Group - Patsy Toop

The Inner West AQ CRG was announced on 26 July 2018 by the

Minister for Energy, Environment and Climate Change and the

Minister for Roads and Road Safety

Purpose: to investigate air quality issues in the inner west of

Melbourne and make recommendation to government on priority

actions to improve air quality

Inner West Air QualityCommunity Reference Group

Page 7: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Inner West Air QualityCommunity Reference Group

Group Membership (15)

Supported

by:

Representatives from local councils

Community member representatives

Independent Chairperson

EPA and other experts

DELWP as Secretariat

The scope of the Inner West AQ

CRG covers the areas of

Maribyrnong, Hobsons Bay, and

Brimbank

Community member

representatives were

recruited by a public

Expression of Interest

process

Page 8: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

The next meeting is scheduled for 25 February 2019 and will

focus on developing a shared baseline understanding of air

quality

Inner West Air QualityCommunity Reference Group

Members identified key areas of interest in relation to air quality

and finalised the Terms of Reference for the CRG

An introductory meeting was held on 10 December 2018

Page 9: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

The initial term of the CRG is 12 months (ends in December

2019)

Meetings will occur approximately every four weeks

Summaries of each meeting are publicly available online at:

https://www.environment.vic.gov.au/sustainability/inner-west-

air-quality-reference-group

Inner West Air QualityCommunity Reference Group

Page 10: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Millers Road and Williamstown Road Corridor Study

Thomas AlemisSenior Traffic and Planning Engineer/Officer

VicRoads

Page 11: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Millers Road and Williamstown Road Corridor Study

led by VicRoads

Page 12: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

How familiar are you with the formation

and role of the corridor study group?

12

Page 13: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

13

Corridor Study Group – work flow & objective

Formation of corridor

study group

Concept solutions

developed by

VicRoads led Group

which consider safety, access

and amenity

Concepts supported

by community and then endorsed

by steering

committee

Solutions presented

for considerati

on and endorsement by the Minister

for Roads

Page 14: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

14

What’s happened so far?

• Meeting 1 – 20 September 2018:

- Establishing context around the formation

of the working group;

- What we have heard so far;

- The study area;

- What does success look like?

• Meeting 2 – 25 October 2018 – Issue

Identification Workshop

- Tapping into the local knowledge of our

members to identify issues along the

corridor.

Meeting 1 - Corridor Study Context

Meeting 2 – “Issue Identification”

Meeting 3 – “Solution Development”

Community consultation

Work behind the scenes, meetings etc.

Recommendation to Minister

Page 15: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

15

What’s next?

• Meeting 3 for the working

group is scheduled for 27

February 2019

• The focus of this meeting will

be to utilise the issues

identified as a basis for

solution development.

http://media.navigatored.com/images/940*637/blueprint.jpg

Page 16: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

16

Questions?

Page 17: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm
Page 18: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Tea break

Page 19: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

CPB JOHN HOLLAND JV

Construction Update

Page 20: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

TUNNEL ZONE

Andrew Shepherd

Construction Manager

Page 21: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

North Yarra Main Sewer

• Community impacts:• Temporary and overnight

lane closures on Somerville Road and Whitehall St

• Permanent parking restrictions on Youell St to be implemented

Page 22: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Northern Portal and Pivot Site

Page 23: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

PORT TO CITY

Jacques le Sueur

Construction Manager

Page 24: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Port to City Precinct – overview

Maribyrnong River

crossings

Footscray Road

preparations

City connections

(E-Gate and F-Gate)

Wurundjeri Way

Page 25: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Maribyrnong River works

• Community impacts:• Maribyrnong Shared Use Path and traffic

changed

• Noise and vibration from piling

Page 26: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Footscray Road

• Community impacts:• Traffic changes including

lane realignment and narrowing

• Tree removal

Page 27: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

WEST ZONE

Charles Fairbairn

Construction Manager

Page 28: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Williamstown Road interchange

Community impacts:

• Local road and ramp closures

• Night works

• Pedestrian and vehicle detours

Page 29: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Fogarty Avenue / The Avenue

• Community impacts:• Temporary closure of Muir Street pedestrian

bridge

• Ongoing closures of Fogarty Ave with traffic detours in place

Page 30: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Millers Road interchange

Page 31: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Beevers Street / Paringa Road

• Beevers Street full road closure for three

days – property access impacts

• Staged closures of Paringa Road -

property access impacts

• Community impacts are largely localised

changed traffic conditions as well as some

increased noise and vibration

Page 32: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

West Gate Freeway – Chambers Road to Grieve Parade

Community impacts:

• Temporary noise wall installation and demolition of existing noise wall

• Traffic detours and increased construction traffic in area

Page 33: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Landscape CLG Workshop Update

Page 34: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Landscaping and open space workshop

• Opportunity for CLG members to engage with landscaping and open space

• Driven from past CLG meeting discussions and actions

• Interactive and hands-on session with expert present

• Early designs and current designs presented

Page 35: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Workshop format

• Welcome and introduction

• Purpose and structure

• Detailed run-through:

• East/City of Melbourne

• Maribyrnong River crossing

• Northern portal and retarding basin

• Harris Street changes

• West through to Kororoit Creek

• Clarification of next steps

• Close

Page 36: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Key takeaways

• Higher interest in urban planning ramifications

and considerations

• Clear desire to show community what

landscaping, urban design and open space will

look like on completion

• Need to explore and better communicate safety

considerations for pedestrians and SUP users

• Explore opportunities to seek feedback through

CLG reps

• Interest in way-finding and heritage signage

• Actions with attendees for review

Page 37: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Next steps

• Come back to CLG members addressing

specific actions from workshop

• Respond with how to assist CLG

members present designs to their

communities/communities

• Continue development of materials for a

public information campaign

Page 38: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Landscape Design – Communications Approach

Key stages:

• CLG Engagement

• Provide insight into design development process

• Overview of stakeholder requirements

• Key opportunities for input

• Community Information Campaign

• Highlight developments from EES to current design

• Focus on local areas of interest

• Link to broader benefits and outcomes

Page 39: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Communications Approach - CLG

CLG Engagement – Q1 2019

• Workshop on 18 Feb 2019

• Insight into design development and

stakeholder engagement to date

• Comments / feedback / areas of interest

• Key opportunities for input

• Close-out of comments and ongoing updates

Page 40: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Communications Approach - Community

• Community information campaign – Q1-3 2019

• Pop-up sessions

• Stakeholder briefings

• Info Centre displays

• Updated materials; Fact Sheets, maps, images

• Digital / online information

• ‘Greening the West’ – tree numbers and locations

• Focus on open space & local areas

• Links to active transport – walking and cycling

Page 41: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Questions from CLG members on construction update

Page 42: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

West Gate Tunnel Authority Update

Peter SammutChief Executive Officer

Page 43: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Premier and Minister visit the Northern Portal Site

Page 44: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Upcoming events for CLG members to

attend

Page 45: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Upcoming Events

• Brooklyn Community Representative Group Open House Forum

• 6 March 2019

Page 46: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

Actions arising and close

Page 47: Community Liaison Group - westgatetunnelproject.vic.gov.auwestgatetunnelproject.vic.gov.au/.../359687/08-Joint-West-and-North-21... · 7.35pm 8 West Gate Tunnel Authority Update 7.50pm

THANK YOU