Community Development

Department

PINE LAKES PARKWAY NORTH ROADWAY IMPROVEMENTS

Page 2: Community Development Department PINE LAKES PARKWAY NORTH ROADWAY IMPROVEMENTS.

Community Development

Department

PINE LAKES PARKWAY NORTH ROADWAY IMPROVEMENTS

• Project Summary• Increase safety of roadway: Similar improvements that were completed along

the southern portion of Pine Lakes Parkway. • Increase super elevation of curves.• Add paved shoulders along both sides of roadway.• Add left turn lanes onto Brushwood and Brookside Lanes.

• Provide continuous multi-use path along roadway.• Installation of street lights.• Convert existing overhead utilities to underground.

• Status• 2007 - City Council approved a Work Order for the Design of the Project.• 2011 - City Council approved Change Order for additional design work.• 2011 – City Council approves Capital Improvement Plan for construction of

project in FY12.• 2011 - Design Complete: Currently under review by City and Utility

Companies.

Page 3: Community Development Department PINE LAKES PARKWAY NORTH ROADWAY IMPROVEMENTS.

Community Development

Department

UNDERGROUND CONVERSION HISTORY

• 2007• 12/18/2007 City Council approved the FPL conversion of overhead lines to

underground in conjunction with the Belle Terre 4-Laning Project. • City received a $255,355.00 credit contingent upon the completion of an

additional 1-mile of conversion.• Pine Lakes Parkway was identified and agreed to by FPL as the additional

contiguous1-mile segment.

Page 4: Community Development Department PINE LAKES PARKWAY NORTH ROADWAY IMPROVEMENTS.

Community Development

Department

UNDERGROUND UTILITIES

Segment 1: Underground Utilities installed as part of new roadway alignment – Belle Terre 4-Laning Project

Segment 2: Underground Utilities converted to underground as part of Belle Terre 4-Laning Project

Segment 3: Proposed segment to meet 3-mile conversion in order to receive cost reduction.Work to be completed as part of Pine Lakes Parkway Roadway Improvement Project

Page 5: Community Development Department PINE LAKES PARKWAY NORTH ROADWAY IMPROVEMENTS.

Community Development

Department

UNDERGROUND CONVERSION OPTIONS

• Option One – Approve Agreements• Approve agreements in amount of $309,623.00 and proceed with Pine Lakes

Parkway North Roadway Improvements Project.• Deadline to issue payment and execute FPL Agreements is 12/28/2011.

• Option Two – Do Not Approve Agreements• Do not convert existing utilities.

• Will require repayment of $255,355.00 credit received for conversion of existing utilities as part of Belle Terre 4-Laning Project.

• Will require redesign of multi-use path due to conflicts with existing utility poles.

• Forfeit of a $242,984.00 credit for the conversion of the Pine Lakes FPL Utilities.