Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP Gale Associates, Inc.

Transcript of Commissioning the Air Barrier - ABAA...

Page 1: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Commissioning the Air Barrier

Brian H. Neely, AIA, CDT, BECxP

Gale Associates, Inc.

Page 2: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Air Barrier Association of America (ABAA) is a Registered Provider with The American Institute of

Architects Continuing Education Systems. Credit earned on completion of this program will be

reported to CES Records for AIA members. Certificates of Completion for non-AIA members are

available on request.

This program is registered with the AIA/CES for continuing professional education. As such, it

does not include content that may be deemed or construed to be an approval or endorsement by

the AIA of any material of construction or any method or manner of handling, using, distributing,

or dealing in any material or product.

Page 3: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Brian H. Neely, AIA, CDT, BECxP

Senior Project Manager

[email protected]

800-659-4753

www.galeassociates.com

Page 4: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

What is Building Enclosure Commissioning?

Page 5: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

“The process by which the design and constructed performance of building enclosure materials, components assemblies and systems are validated to meet defined objectives and requirements of the project, as established by the Owner.”

NIBS Guideline 3-2012

Page 6: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

How?

Page 7: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

1. Compare the Design and Construction to:• Owner’s Project Requirements

• Basis of Design

Page 8: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

2. Compare the Design and Construction to:• Control heat, air and vapor flow

• Control water penetration

• Control light and solar radiation

Page 9: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

3. Compare the Design and Construction to:• Monitor and Inspect Construction

Page 10: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

4. Compare the Design and Construction to:• Test and Verify Installed Assemblies

Page 11: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Timeline of Recent Standards Development

Page 12: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Why Now?

Page 13: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

2005ASHRAE Guideline 0, The Commissioning Process

2006NIBS Guideline 3, Exterior Enclosure Technical Requirements

for the Commissioning Process

2012ASTM E2813, Standard Practice for Building Enclosure

Commissioning (BECx)

2012ASTM/NIBS Memorandum of Agreement on Building

Enclosure Commissioning

Page 14: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

2012NIBS Guideline - 3, Building Enclosure Commissioning Process

2013ASHRAE Standard 202, The Commissioning Process for

Buildings and Systems (Joins ASHRAE GL-0)

2014ASTM Standard Guide for Building Enclosure Commissioning

(Replaces NIBS GL-3)

2015-PresentASTM/NIBS BECx Certification and Training Program

Page 15: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Proposed ASTM E2813

Identifies mandatory tests for commissioning projects

Identifies mandatory tests for commissioning projects

• Fundamental

• Enhanced

Note that lab testing is not required but may be beneficial based upon project and wall component types

Page 16: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Proposed ASTM E2813

Page 17: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Proposed ASTM E2813

Page 18: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Mandatory BECx Tests

501.2 (Nozzle Test ) Minimum 3 Times During Construction

Infrared Roof Scan

Flood Testing of Horizontal Waterproofing

Air and Water Infiltration Testing of Opaque Walls

Air and Water Infiltration Testing of Windows (Chamber)

Sealant Inspection Testing

Page 19: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Mandatory Enhanced BECx Tests

Air Barrier Leak Testing

Whole Building Air Test

Dynamic Fan Testing

Page 20: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Why Building Enclosure Commissioning?

Page 21: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Air Leakage Accounts For:

• 40% of a building’s energy consumption (DOE)

• 43% of heat loss (NIST)

• 26% of cooling loss (NIST)

Page 22: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

LEED Version 4:

• BECx 2 points

• References ASHRAE Guidelines 0, 1.1 and NIBS Guideline 3

• Tasks: all fundamental tasks, plus (partial list):

• Review contractor submittals

• Review building operations 10 months after substantial completions

• Develop an ongoing commissioning plan

Page 23: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

State and Municipal Requirements

New York City

California GOA DCAM MSBA

USACE Oregon Montana Washington NY State Bldg Code

North Carolina

Page 24: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Building Enclosure Commissioning Helps to Avoid Common Problems in Building Construction

Water intrusion

Indoor air quality issues

Mold growth

Air infiltration (energy loss and occupant discomfort)

Improves balancing of HVAC equipment

Page 25: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Key Causes of Enclosure Failure

Page 26: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

20th Century Building Enclosures:

• Simple building materials• Limited layers• Trained workforce

Page 27: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Today’s Building Enclosures:

• Complex, new building materials• Multiple layers/configurations• Limited designer/contractor

experience

Page 28: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Reliance on a single water barrier (i.e. sealants)

Page 29: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

New untested building materials

Page 30: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Complex geometries

Page 31: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Repetitiveness of problem details

Page 32: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Repetitiveness of problem details

Page 33: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Lack of technical understanding of moisture intrusion mechanisms

Page 34: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Lack of modeling / review / testing / startup

Page 35: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Lack of coordinated details between construction trades

Insert curtain wall shop drawing

Page 36: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Workmanship

Page 37: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

The Building Enclosure Commissioning Process

Predesign Design Pre-construction

Construction Post-Occupancy

Bidding/procurement

Page 38: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Pre-Design Phase Services

Assist in creation of Owner’s Basis of Design

Review prime architect’s early schematic designs

Identify options for enclosure systems

Page 39: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Wall System Peer Review (BOD)

Page 40: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Wall System Peer Review (BOD)

Page 41: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Design Phase Services

Develop Commissioning Specifications

Peer Review DDsand CDS

Testing Matrix and Commissioning Plan

Standardize approach to design development

Page 42: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Design Requirements

Combinations of building enclosure components are numerous

Building enclosures must perform as a system with all joints, junctures, and penetrations detailed

Design specifications must be clear and coordinated with drawings

All components must work in conjunction with adjoining assemblies

Page 43: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Project Time Line

Conception Completion

High

Low

SchematicDesign

Construction Documents

Shop Drawings

ConstructionPre-Design

Importance of Design Phase Review

Page 44: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Typical Review Table

Page 45: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Design Considerations

Page 46: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Design Considerations

Page 47: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Constructability Concerns

Page 48: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Level of Detail

Page 49: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Level of Detail

Page 50: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Procurement Phase Services

Review and assist with the evaluation of enclosure related subcontractor bids

Attend a Pre-Bid Conference to review the BECx specification with prospective bidders

Assist with the development of addenda

Review and assist with the evaluation of enclosure relatedbidder RFIs

Page 51: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

BE Sub-Bid Evaluations

Substitutions and “Value Engineering” Options

Scheduling, Phasing, and Coordination of Trades

Quality Assurance (QA) and Quality Control (QC) Programs

Qualifications and Exclusions

Page 52: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Pre-Construction Phase Services

Implementation of the BECx Plan

Mock-Up Review and Testing

Update Testing Matrix and Commissioning Plan

Conduct Enclosure coordination meetings

Review Shop Drawings and Submittals

Review Construction Sequencing and Scheduling

Page 53: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

BE Component Coordination Meeting

Review “by others”

Review and coordinate shop drawing details at which various enclosure components interface

Members include architect, owner, BECxA, CM/GC, and sub trades

Review construction sequencing and scheduling

Page 54: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

BE Component Coordination Meeting

Page 55: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

BE Component Coordination Meeting

Page 56: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

BE Component Coordination Meeting

BE Component Coordination Meeting

Page 57: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Shop Drawing Review

Page 58: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Curtain Wall Shop Drawing Review

Page 59: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Curtain Wall Shop Drawing Review

Page 60: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Curtain Wall Shop Drawing Review

Page 61: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Curtain Wall Shop Drawing Review

Page 62: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Roofing Shop Drawing Review

Page 63: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Roofing Shop Drawing Review

Page 64: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Roofing Shop Drawing Review

Page 65: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Roofing Shop Drawing Review

Page 66: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Mock-Up

To be built by on-site trades

Full-scale laboratory testing

To include as many typical details as possible

To be tested for compliance with established standards

Access for modifications to address potential problems

Troubleshoot potential problems

Establishes standard of care for trades

Page 67: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

On-Site Mock-Up

Page 68: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Off-Site Mock-Up

Page 69: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Construction Phase Services

Finalize commissioning plan based on results of mock-up testing

Verify and document field QA/QC programs

Integration of RFIs and change orders to the Commissioning Plan

Provision and follow-up of ongoing deficiency lists

Page 70: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Construction Administration

Attend periodic progress meetings to discuss enclosure construction issues

Document applicable comments/discussions

Address detail modifications due to construction changes

Review and verify ongoing compilations of as-built drawings and conditions to be used for future updates and corrections

Page 71: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Construction Monitoring

Perform periodic on-site observations of contractor’s work

Attend job-site meetings while critical enclosure components are being installed

Summarize observations, concerns, and recommendations in a written report

Witness and verify field tests and field data reports

Review unique interface conditions to verify that they meet the design intent

Confirm that defective conditions are rectified

Page 72: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

System Punch List Inspections

Page 73: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

System Punch List Plan

Page 74: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

System Punch List Elevation

Page 75: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Deficiency Photo Log

Page 76: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Deficiency Tracking Log

Page 77: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Deficiency Tracking Log

Page 78: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Acceptance Phase

Testing

Review as-built drawings (building enclosure)

Final walk through punch list

Final report

Page 79: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Testing

Smoke tests, tracer gas (qualitative)

Chamber tests (quantitative)

Spray nozzle, spray rack leak tests

Infra-red (after enclosure complete or with temp. heat)

Page 80: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

ASTM E 1186, Standard Practice for Air Leakage Detection in Building Enclosures and Air Barrier Systems

Page 81: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

ASTM E 1186-03, Standard Practices for Air Leakage Site Detection in Building Enclosures and Air Barrier Systems

Page 82: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

ASTM E 1186, Standard Practice for Air Leakage Detection in Building Enclosures and Air Barrier Systems

Page 83: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

ASTM D 4541 Standard Test Method for Pull-Off Strength of Coatings – Portable Adhesion Testing

Page 84: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

ASTM C 1193, Standard Guide for Use of Joint Sealants, Method A, Field Applied Sealant Joint Hand Pull Tab

Page 85: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

ASTM C 1153, Standard Practice for Location of Wet Insulation in Roofing Using Infrared Imaging

Page 86: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

ASTM E 779, Standard Test Method for Determining Air Leakage Rate by Fan Pressurization

Page 87: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

ASTM C 1060, Standard Practice for Thermographic Inspection of Insulation Installations in enclosure Cavities of Frame Buildings

Before

Page 88: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

ASTM C 1060, Standard Practice for Thermographic Inspection of Insulation Installations in enclosure Cavities of Frame Buildings

After

Page 89: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Post Commissioning

Maintenance Staff Training

10 month walk-throughWarranty / seasonal evaluation

Review performance with owner / user

Lessons Learned

Post-Occupancy Commissioning

Page 90: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Typical Design/ Construction Issues

Page 91: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Constructability Concerns

Page 92: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Thermal Bridging Issues

Page 93: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Avoid This – Flashing Conflict

Page 94: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Avoid This – Most Common Issue (Leakage/Business Interruption)

Page 95: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Three-Dimensional Sketch

Page 96: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Specifications vs. Drawings

Page 97: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Avoid This – Poor Workmanship

Page 98: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Avoid This – Poor Specification

Page 99: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Atypical Details

Page 100: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Construction Photo

Page 101: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Design Detail

Page 102: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Design Detail

Page 103: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

As-Built Detail

Page 104: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Final Installation Photo

Page 105: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Building Enclosure Consulting Services

Gateway Community College, New Haven, CT

Page 106: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Building Enclosure Commissioning Services

The Jackson Laboratory for Genomic Medicine

Page 107: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Boston University

Building Enclosure Commissioning Services

Page 108: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Building enclosure Commissioning ServicesDivision of Fisheries and Wildlife, Westborough, MA

Building enclosure Commissioning ServicesMassachusetts College of Liberal Arts, North Adams, MA

Building enclosure Commissioning ServicesBoston University, Boston, MA

Building for the Future

Brigham's & Women’s Hospital, Boston, MA

Building enclosure Commissioning

Bridgewater State College, Bridgewater, MA

Westwood Fire StationMedfield Public Safety

Multiple Projects

Building Enclosure Commissioning Services

Page 109: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

Harvard University

Multiple Building Enclosure Commissioning Projects

Gateway Community College,

New Haven, CT

Western CT State University, Danbury, CT

Jackson Laboratory, Farmington CT

Boston University

Emmanuel College, Boston, MA

Harvard University

Dartmouth College, Hanover, NH

University of Vermont

Baltimore Convention Center Hotel, Baltimore,

MD

Institute of Contemporary Art, Boston, MA

UF-607 Innovation Hub Phase II, Gainesville, FL

UF-323A Chemistry/Chemical Biology Building, Gainesville, FL

UF-Weimer Hall, Gainesville, FL

UF-603 CRC Expansion & Renovation, Gainesville, FL

UF-590 VMTH Clinical Simulation Lab Addition, Gainesville, FL

UF-212 Newell Hall Renovation, Gainesville, FL

UF-UAA-34 Student Life Building, Gainesville, FL

FIU Student Academic Support Center, Miami, FL

Y.E. Smith Elementary School, Orlando, FL

UF Data Center East Campus, Gainesville, FL

Orange County Public Schools, Orlando, FL

NC A&T University Student Center, Greensboro, NC

FSU Student Center Renovations & Additions, Fayetteville, NC

Fayetteville State University-Renaissance Hall Student Housing, Fayetteville, NC

Fayetteville State University-New Science & Tech Building, Fayetteville, NC

Duke University West Campus K-4 Residence Hall, Durham, NC

Page 110: Commissioning the Air Barrier - ABAA Conferenceabaaconference.com/wp...Commissioning-the-Air-Barrier_Brian-Neely.pdf · Commissioning the Air Barrier Brian H. Neely, AIA, CDT, BECxP

ThankYou!