Commissioning process and sign off - Home - SSEG Municipal ... · –Electrical installation CoC...
Transcript of Commissioning process and sign off - Home - SSEG Municipal ... · –Electrical installation CoC...
Commissioning process and sign off
2
Agenda
1. Is commissioning necessary?
2. Commissioning part of application process
3. Responsibilities and liabilities
4. High level commissioning and sign off process
5. Commissioning tests
Commissioning process and sign off
Is commissioning necessary?
• Oxford definition of commissioning:
“Bring (something newly produced) into working
condition”
• Solar Photovoltaic (PV) systems are
– New products
– Unique in design; Based on functionality and
constraints
– Has various integration challenges
3
Is commissioning necessary?
• The client wants a safe (legal), well working system
• Supplier wants to honour their warrantee(s)
• Most installers wants to build and protect their reputation
• The network operator wants to protect the network, the
user(s) and community
Proper commissioning and reporting will help to
address some of the above mentioned requirements.
4
Commissioning part of the application1. Application process to install SSEG
Figure 1: Summary of City of Tshwane’s Small Scale Embedded Generation application and approval process
INTERNAL TO MUNICIPALITY
PROCESS FOR THE CUSTOMER
AMEU Standard Document –
SSEG Commissioning Report
Optional commissioning tests
OPTIONAL TECHNICAL TEST SHEET for the small scale embedded generation
installations
Disclaimer: From a technical point of view the NRS097-2-1 test certificate covers these issues quite
thoroughly, so there are no safety concerns that REQUIRE the municipalities to do such tests as
described below. Municipalities may perform such tests on selected (few) installations for additional
comfort on safety aspects.
Project name:
Commissioning Test: ✓
Comments/Results
1. Anti-islanding test: (multi-meter required) With the system running (main breaker closed and SSEG producing power), OPEN the main breaker to the SSEG installation.
- Does the SSEG activate anti-islanding mode? Measure the voltage at the AC output terminals of the SSEG or at the connection point to the AC mains board.
YES/NO
…….……..V
2. SSEG Re-connection test 1: (stop watch required) With the main breaker OPEN and the SSEG in island mode, reconnect the mains (close main breaker). Measure the time the SSEG takes to reconnect to the network/grid.
……………….s
3. SSEG Re-connection test 2: (stop watch required) Take note of the reconnection time in test 2. With the main breaker OPEN and the SSEG OFF, CLOSE the main breaker. In 10 seconds or before the SSEG can reconnect to the grid, open the main breaker. Does the SSEG activate anti-islanding and disconnect from the grid?
YES/NO
4. Inspection of labels: Client side: Check that there are labels on the distribution board clearly indicating the SSEG infeed and point of connection(s). Check that there are labels on the outside of the distribution board Network/Grid Side: Check that there are labels on the feeder and substation, clearly indicating that there is SSEG present on this installation.
Responsibility and Liability Assignment
8
Task/Process Customer Installer Municipality
Quote/Proposal for SSEG
systemApproves Responsible N/A
Quality of products and
installation; NRS 097-2-1,
SANS 10142-1 & 1-X
ApprovesResponsible
and LiableN/A
Do design of system by
competent person ApprovesResponsible
and Liable
Define
component
person
Municipal application done
for SSEGLiable Facilitate Approves
Network Capacity
investigation and allocation;
NRS 097-2-3
N/A Facilitate Responsible
Costs for network
upgrade/meter changes (if applicable)
Approves
and
Responsible
N/AProvide cost
implications
Responsibility and Liability Assignment
9
Task/Process Customer Installer Municipality
Cost for additional network
charges (if applicable)
Approves
and
Responsible
N/AProvide cost
implications
Install correct meter or do
network upgrade (if applicable)N/A Facilitate Responsible
Procure and install EG
systemApproves
Responsible
and LiableN/A
Ensure installation is done
according to requirements(SANS -, NRS series, International
best practice, By Laws and other.)
N/AResponsible
and Liable
Provide
requirements
and
Approves
Commission EG system Approves:
Functions
Responsible
and Liable
Approves:
Safety
Responsibility and Liability Assignment
10
Task/Process Customer Installer Municipality
Provide required documentsApproves
Responsible
and Liable
Check and
Approves
Register EG system on
databaseN/A Facilitate Responsible
Ensure to uphold
arrangements set out in the
SSEG contract between
customer and municipality.
Liable N/AProvides
contract
Maintenance of SSEG
system Responsible Optional N/A
Resolve/exchange faulty
equipment (under warrantee or
not)
Approves Responsible Approve
Areas in green: PV GreenCard serve as QA
High level commissioning and sign off process
1. Solar PV system needs to be designed by installer and
signed off by Pr. Engineer or Pr. Technician Eng.
2. Installation realised under a qualified & registered
electrician.
3. Electrician provides CoC (Certificate of compliance) for
installation
4. Installer provides a signed off as-built drawing to client
after system works as specified
5. Small Scale Embedded Generator (SSEG) Contract to
be signed
6. Installer to provide AMEU commissioning report and
required attachments.
11
Commissioning and sign off process:
Important for Municipalities• Declaration by ECSA registered person
1. EG installation complies with relevant sections for
NRS 097-2-1 and NRS 097-2-3
2. Loss of mains protection (Anti-Islanding) has been
checked to be functional
3. Safety labels have been fitted according to
NRS 097-2-1
12
Commissioning and sign off process:
Important for Municipalities• Declaration by ECSA registered person
4. The SSEG installation complies with the relevant
sections of SANS 10142-1 and other relevant SANS
5. The SSEG installation complies with licensing
requirements of NERSA
6. Reverse power blocking protection system (grid limiting)
installed and commissioned (Not recommended due to
potential revenue loss and safety concerns)
13
Sign Off Highlights
1. Installer/ Supplier/ Customer confirms that
Municipal SSEG is possible
2. Customer SIGNS OFF quote; Provided by
Installer/ Supplier with optional pre design
3. Supplier/ Installer applies on behalf of the customer for Solar PV
SSEG grid interconnection
4. Municipality gives a SIGNED OFF (pre) approval letter with
specific requirements
5. Solar PV SSEG is installed.
6. Solar PV SSEG is commissioned by Reg. Electrician; Optional: Municipality attend
commissioning
7. SIGN OFF
- Pr. Eng. as-builtdesign and
-Registered electrician CoC
8. Installer/Customer provides the relevant and
requested documents (including SIGNED
contract) to the local municipality
9. (If applicable) Municipality upgrade
supply connection and/or change meter
10. Municipality gives a SIGNED OFF confirmation of
documents received (final approval letter). Register
SSEG
11. System needs to be decommisioned: SIGNED OFF CoC by electrician and decommision report
done by installer/customer
12. Provide Municipality with decomissioning
notice
14
- Commissioning tests -
15
Preparation
Site visit and attending commissioning tests could be
required to
• Verify information from application documents
• Confirm safe integration and operation of SSEG
Prior to site visit
• Prepare documentation
– Application documents
– Customer/Installer details
– Address and location of site
– Diagram of local network
16
Preparation
Prior to site visit (cont.)
• PPE, tools and access keys
– PPE for working with electricity and (if required) on heights
– Tools to open distribution boards
– Access keys
– Electrical tester (Clamp on tester to measure current)
– Stop watch
– General electrical tools
• Arrangements for access and testing
– Ideally a week before site visit
– Indicate what you would like to do (could take 60min per tie in point)
– Request a competent person for executing tests at the SSEG
– Arrange security clearance/access (if required)
17
Site Visit
During site visit
1. Verify details of the customer and installer
18
Site Visit
During site visit
1. Verify details of customer and installer
2. Verify the SSEG system details
19
Site Visit
During site visit
1. Verify details of customer and installer
2. Verify the SSEG system details
3. Make sure relevant documents are provided
– Inverter type test according to NRS 097-2-1 done by accredited 3rd party
test house
– Electrical installation CoC done according to SANS 10142-1 (and
10142-1-X when published)
– Final signed as-built single line diagram (SLD) to be provided
– Supplemental EG contract signed with network operator
20
Site Visit
21
Commissioning Tests - Disclaimer
Disclaimer:
• From a technical point of view the NRS097-2-1 test certificate
covers these issues quite thoroughly, so there are no safety
concerns that REQUIRE the municipalities to do such tests as
described here.
• Municipalities may perform such tests on selected (few) installations
for additional comfort on safety aspects.
• NB! - Municipal employees may supply the testers but is not allowed
to operate on electrical installations that is not part of their scope. It’s
the facility owners responsibility to delegate this function to capable
people of their choice who will be responsible & liable for testing.
Especially for testing at the SSEG main breaker; Option B.
22
Commissioning Tests
Testing Point
• Determine at which circuit breaker measurements will be taken
23
Commissioning Tests
Testing Point
• Option A
• Pros: Assurance about anti-islanding of SSEG, irrespective of the
wiring of the SSEG.
– Cons: Operation could be interrupted, current measurement
includes other loads.
• Option B
• Pros: Operations will not be influenced, current measurements
mainly represents SSEG operation current.
– Cons: Need to ensure that the SSEG is correctly integrated into
the relevant distribution circuit. Testing needs to be executed by
competent SSEG operator/facility owners.
24
Commissioning Tests
• Step 0 – Measure voltage and current of breaker
Voltage measurement between a phase and neutral; 237.8V
25
Commissioning Tests
• Step 0 – Measure voltage and current of breaker
Current measurement of a phase: 4.4A
26
Commissioning Tests
• Step 1 – Test for Anti-Islanding
This test is to ensure that the SSEG will not produce electricity and
feedback into the grid during a power outage.
– Step 1.1 Check to see that SSEG is operating, connected and
producing power
– Step 1.2 While the SSEG is operating and producing power,
switch off the chosen breaker.
– Step 1.3 Measure the voltage and current on the load side
(SSEG or bottom side) of the breaker. Write down the voltage
value in the commissioning form.
27
Commissioning Tests
• Step 1 – Test for Anti-Islanding
Voltage measurement between a phase and neutral: 0.0V
28
Commissioning Tests
• Step 1 – Test for Anti-Islanding
Current measurement of a phase: 0.0A
29
Commissioning Tests
• Step 1 – Test for Anti-Islanding
Current and voltage measurement of a phase: 0.0A and 0.0V
30
Commissioning Tests
• Step 1 – Test for Anti-Islanding
– Step 1.4 (If possible) Check to see if inverter indicated
disconnection to the grid and/or operation discontinued.
Inverter Display – Utility supply OFF
31
Commissioning Tests
• Step 1 – Test for Anti-Islanding
– Step 1.5 – If there is no voltage measured on the SSEG side of
the breaker, then it can be accepted that the SSEG activated
anti-islanding mode. Indicate Yes on the commissioning form
above the measured voltage.
32
Commissioning Tests
• Step 2 – Test reconnection time
This test is to see if the inverter adheres to the NRS 097-2-1
reconnection requirement. A stop watch will be needed.
– Step 2.1 After step 1, close the chosen breaker and start timing.
– Step 2.2 Once the SSEG starts producing power (either
indicated on the inverter display or being able to measure
current for Option B), stop the timer and record the value on the
commissioning form. The minimum value should be at least 60s.
33
Commissioning Tests
• Step 2 – Test reconnection time
Inverter Display – Utility supply ON
34
Commissioning Tests
• Step 3 – Reconnection “Dummy test”
This test is to see if the SSEG will start to operate after being exposed
to the utility supply for a short while.
– Step 3.1 Switch the SSEG system off by opening the breaker.
– Step 3.2 Close the chosen breaker for only 10 seconds,
– Step 3.3 Switch the SSEG system off again (Open the breaker).
35
Commissioning Tests
• Step 3 – Reconnection “Dummy test”
– Step 3.3 If the SSEG system stays off after 60 seconds the
SSEG is disconnected from the grid and Anti-Islanding mode has
activated. Record the latter on the commissioning form.
36
Labels Inspection
• Step 4 – Inspection of labels
– Step 4.1 Check to see if the SSEG installation is indicated at the
main AC distribution board.
– Step 4.2 Check to see if the SLD is installed, indicating where
and how the SSEG is interconnected.
– Step 4.3 Check to see if safe operations and/or emergency
isolation instructions are provided (Optional).
37
Labels Inspection
• Step 4 – Inspection of labels
– Step 4.4 Check to see if there is an installed label indicating an
installed SSEG at the point of Supply (Meter box) and preferable
also at the relevant transformer.
38
Extra Considerations
• It would be ideal if power quality measurements could be
done for a few weeks prior and post to the
commissioning (mainly >100kWp).– The existing power quality issues can be quantified
– The effect of embedded generation can be identified
– Provides a better understanding of how EG can influence the grid
• Operation of SSEG systems using a combination of solar PV
SSEG, batteries and/or generators (Hybrid systems) need to
be clearly explained and demonstrated.
• Generators with synchronisation capabilities needs to adhere
to the NRS 097-2-1 requirements and also documented.
39
Extra Considerations
• The first test could take a while if there is multiple tie in
points.
• The single line diagram (SLD) needs to be checked and
verified before commencing with any tests
• One official could be checking the number, size, serial
numbers of the inverters, while the other do the tests.
40