Comments_Sprinkler Lobby Lounge

1
Contractor has fully responsibility to verify the proposed plan which has new sprinkler pipes/points does not have any impact on system pressure drop between zone control valve and new design point of lobby lounge area. All installation works to comply with CP52 requirements. Temperature rating of sprinkler shall be same as the existing. To confirm sprinkle coverage (see the attached mark-up) To submit installation drawings endorsed by contractor’s QP before commencement of any installation work.

description

comments

Transcript of Comments_Sprinkler Lobby Lounge

Page 1: Comments_Sprinkler Lobby Lounge

Contractor has fully responsibility to verify the proposed plan which has new

sprinkler pipes/points does not have any impact on system pressure drop between

zone control valve and new design point of lobby lounge area.

All installation works to comply with CP52 requirements.

Temperature rating of sprinkler shall be same as the existing.

To confirm sprinkle coverage (see the attached mark-up)

To submit installation drawings endorsed by contractor’s QP before commencement

of any installation work.