Contractor has fully responsibility to verify the proposed plan which has new sprinkler pipes/points does not have any impact on system pressure drop between zone control valve and new design point of lobby lounge area. All installation works to comply with CP52 requirements. Temperature rating of sprinkler shall be same as the existing. To confirm sprinkle coverage (see the attached mark-up) To submit installation drawings endorsed by contractor’s QP before commencement of any installation work.
-
Upload
nay-myo-oo -
Category
Documents
-
view
212 -
download
0
description
comments
Transcript of Comments_Sprinkler Lobby Lounge
Contractor has fully responsibility to verify the proposed plan which has new
sprinkler pipes/points does not have any impact on system pressure drop between
zone control valve and new design point of lobby lounge area.
All installation works to comply with CP52 requirements.
Temperature rating of sprinkler shall be same as the existing.
To confirm sprinkle coverage (see the attached mark-up)
To submit installation drawings endorsed by contractor’s QP before commencement