Columbia County Road Department

51
Columbia County Road Department Department Presentation June, 2013 By David Hill

description

Columbia County Road Department. Department Presentation June, 2013 By David Hill. Columbia County Road Department Presentation: Work Performed Revenues / Expenses Projects Completed / Planned Issues and Needs. Work Performed By County Road Crews. Ditching. Road Grading. - PowerPoint PPT Presentation

Transcript of Columbia County Road Department

Page 1: Columbia County Road Department

Columbia County Road Department

Department PresentationJune, 2013

By David Hill

Page 2: Columbia County Road Department

Columbia County Road Department Presentation:

Work Performed

Revenues / Expenses

Projects Completed / Planned

Issues and Needs

Page 3: Columbia County Road Department

Work Performed By County Road Crews

Page 4: Columbia County Road Department

Ditching

Road Grading

Page 5: Columbia County Road Department

Bridge Repair

Culvert Replacement

Page 6: Columbia County Road Department

Herbicide Application

Page 7: Columbia County Road Department

Chip Seal

39 Miles in 2012

Page 8: Columbia County Road Department

Excavation

Page 9: Columbia County Road Department

Clear Debris From Landslides and

Floods

Page 10: Columbia County Road Department

We Move Snow

and Apply to Icy Roads:

Sand

Anti-Ice Chemical

Page 11: Columbia County Road Department

Storm Damage Removal

Page 12: Columbia County Road Department

Earthquake Preparation and

Recovery

Page 13: Columbia County Road Department

Other Tasks Performed By The Road Department

• Signs and Striping

• Roadside Vegetation

• Pothole Repair

• Paving

• Equipment Repair

• Building Repair

• Regulation and Permitting

Page 14: Columbia County Road Department

Budget and Personnel Numbers

Page 15: Columbia County Road Department

Columbia County Road Department Personnel & Mileage

• EMPLOYEES: Road Maintenance 13 (includes supervisors) Mechanics 2

Signs 1 Office 5

Total 21 (25.5 in 2011)

– COUNTY ROAD MILES: Paved Gravel Total Employees Miles

/Emp– Clatskanie District 79 55 135 3

45– Rainier District 111 43 153 4

38– St. Helens District 147 32 179 4

45*– Vernonia District 52 34 85 2

42

– Total 389 164 553If all the Columbia County Roads were placed end to end they would reach from St. Helens to Reno NV.

* St. Helens crew performs all centerline striping and herbicide application for all districts

Page 16: Columbia County Road Department

Road Department RevenuesYear Motor Vehicle

FeesAggregate Mining Fee

O&C Timber/Levy

Permits Federal STP Fund Exchange

Total Total Adj to 1996 Dollars

95-96 $2,181,988 $312,790 0 $16,971 $193,558 $2,705,307 $2,705,307

96-97 $2,174,958 $447,560 $455,422 $18,157 $178,653 $3,274,750 $3,201,298

97-98 $2,160,605 $445,143 $426,870 $13,206 $198,407 $3,244,231 $3,122,821

98-99 $2,270,155 $341,064 $416,808 $13,683 $188,142 $3,229,852 $3,041,799

99-00 $2,358,619 $421,047 $420,000 $18,597 $222,105 $3,440,368 $3,134,690

00-01 $2,380,647 $329,436 $420,000 $32,504 $229,646 $3,392,233 $3,005,315

01-02 $2,494,885 $324,978 $420,000 $23,166 $233,268 $3,511,187 $3,062,285

02-03 $2,266,730 $306,819 $420,000 $21,428 $246,832 $3,277,565 $2,794,836

03-04 $2,570,434 $270,129 $420,000 $30,258 $239,568 $3,545,682 $2,945,037

04-05 $2,564,061 $385,506 $420,000 $26,605 $265,584 $3,678,709 $2,955,399

05-06 $2,664,546 $396,848 $420,000 $28,740 $250,382 $3,776,498 $2,939,149

06-07 $2,639,899 $334,751 $420,000 $32,457 $276,840 $3,721,678 $2,816,271

07-08 $2,509,933 $339,531 $420,000 $36,174 $340,806 $3,668,198 $2,673,164

08-09 $2,260,613 $264,980 $420,000 $40,171 $310,085 $3,315,662 $2,424,884

09-10 $2,510,874 $298,670 $340,200 $38,303 $323,718 $3,532,428 $2,541,723

10-11 $2,946,734 $336,694 $306,400 $32,499 $372,872 $4,019,000 $2,803,342

11-12 $3,278,527 $314,381 $37,352 $27,843 $493,248 $4,161,651 $2,858,466

12-13 (Est) $3,339,713 $370,613 0 $32,654 $382,982 $4,125,962 $2,800,482

13-14 (Bud) $3,450,000 $360,000 0 $28,000 $385,400 $4,223,000

Page 17: Columbia County Road Department

2012 Revenues

78%

12%

1%

1%

8% Motor Vehicle Fees

Depletion Fees

O&C Timber

Permits

Federal STP$3,278,527

$314,381

$493,248

Total Revenue: $4,125,962

$27,843

$37,352

Page 18: Columbia County Road Department

2

2.5

3

3.5

4

4.5

95-96

96-97

97-98

98-99

99-00

00-01

01-02

02-03

03-04

04-05

05-06

06-07

07-08

08-09

09-10

10-11

11-12

12-13

Mil

lio

ns

Adj Rev Revenues

Road Revenues and Revenues Adjusted for Inflation

Page 19: Columbia County Road Department

County Road Revenues per Mile, FY July 2010 to June 2011

Washington

Columbia

Clatsop

Tillamook

Page 20: Columbia County Road Department

2010-2011 Revenue Per Mile

Higher Revenue Per Mile than Columbia County

Lower Revenue Per Mile than Columbia County

Page 21: Columbia County Road Department

Expense Cost

Personnel Salary (59%) $1,233,845 $2,097,412

Med Insurance (18%) $384,861

PERS (15%) $312,155

SS, W/C, Unemployment (8%) $166,551

Rock $150,000

Asphalt $300,000

Paint (for striping) $130,000

Culvert, Herbicide, Anti-Ice, Signs, Supplies $105,000

Fuel $220,000

Equipment, Parts, Supplies & Repairs $225,000

Utilities, Insurance, Admin, Other $388,000

Bridges (Fishhawk, JP West & Pebble Cr Rds) $383,000*Total $3,998,412

FY 2014 Road Department Budget

* STP Fund Exchange through ODOT

Page 22: Columbia County Road Department

Average Diesel Prices

$1.82

$2.24

$2.94 $2.89

$4.12

$2.46

$3.10

$3.99$4.16

$0.00

$1.00

$2.00

$3.00

$4.00

$5.00

2004 2005 2006 2007 2008 2009 2010 2011 2012

Page 23: Columbia County Road Department

Average Local Rock Prices / Ton

$5.82

$7.25

$8.13 $8.13 $8.25

$9.17 $8.97 $9.06 $8.94

$0.00$1.00$2.00$3.00$4.00$5.00$6.00$7.00$8.00$9.00

$10.00

2004

2005

2006

2007

2008

2009

2010

2011

2012

Page 24: Columbia County Road Department

Average Local Asphalt Prices / Ton

$29.75 $30.31

$34.81

$43.60

$48.00

$54.00

$50.00 $50.00

$54.00

$0.00

$10.00

$20.00

$30.00

$40.00

$50.00

$60.00

2004 2005 2006 2007 2008 2009 2010 2011 2012

Page 25: Columbia County Road Department

Recent Road Projects

Page 26: Columbia County Road Department

Elk Creek Road Reconstruction

Grinding Old Asphalt

Grading

Oil Matte

Page 27: Columbia County Road Department

Canaan Rd Guard Rail

Before

After

Total Cost: $494,000

Grant: $345,000

Page 28: Columbia County Road Department

Nicolai Rd Overlay 2011

Total Cost: $500,000

4.6 Miles

Page 29: Columbia County Road Department

Brinn Rd, Cox Cr

Four Watershed Council Culvert Replacements

Cater Rd, Alder Cr

Cedar Cr Rd, Cedar Cr

Scappoose Vernonia Rd, Elk Cr

Cost: $73,000

Page 30: Columbia County Road Department

Scappoose Vernonia Road

At Milepost 8

.

Repaired in 2011

Total Cost: $465,000

Grant: $390,000

Page 31: Columbia County Road Department

Holbrook Road Washout

Jan 2013

May 2013

Page 32: Columbia County Road Department

Nick Thomas Road

Landslide

Repair and Construction To Start: June 2013

Page 33: Columbia County Road Department

Marshland – Midland Road

Recycled Asphalt Resurfacing

Construction To Start:

July 2013

5000 CY of Asphalt Grindings to be used on Midland District Rd

Page 34: Columbia County Road Department

Marshland District Road Resurfacing Using Asphalt Grindings.

Construction Completed August 2013

Page 35: Columbia County Road Department

Eddings Road Culvert Construction To Start:

August 2013

Page 36: Columbia County Road Department

Eddings Road Culvert Construction Finished September 2013

Page 37: Columbia County Road Department

Scappoose – Vernonia Road Landslide / Heaving

Walker Road Landslide

Construction To Start: August 2013

Page 38: Columbia County Road Department

Hudson Park Bridge and

Fishhawk Creek Bridge

Construction To Start: Summer 2013

Other Bridge Replacement Projects:

• JP West - 2014 - $1,425,000

• Coon Creek - 2014 - $2,915,000

• Pebble Creek - 2016 - $2,693,000

County Bridge Inventory: 93

Total Cost: $921,000

Grant: $820,000

Total Cost: $1,624,000

Grant: $1,477,000

Page 39: Columbia County Road Department

Very Poor

Poor

Fair

Good

Very Good

Preventive Maintenance

Corrective Maintenance

Heavy Resurfacing

Reconstruction

$50 K

$120 K

$200 K

$360 K

10 Yrs 20 Yrs

Pavement Life Cycle

Page 40: Columbia County Road Department

Very Good

Typical Time

Maintenance Strategies

Heavy Resurfacing

Good

Fair

Poor

Very Poor

$200,000 / RM

$200,000 / RM

Heavy Resurfacing

Total Spent on Preventative Maintenance: $150,000 /RM

Total Spent on Heavy Resurfacing: $400,000 / RM

30 Yrs

15 Yrs

Page 41: Columbia County Road Department

Mayger Road

May 25, 2012

Very Poor

Poor

Fair

Good

Very Good

Preventive Maintenance

Corrective Maintenance

Heavy Resurfacing

Reconstruction

$50 K

$120 K

$200 K

$360 K

10 Yrs 20 Yrs

Pavement Life Cycle

Page 42: Columbia County Road Department

Ilmari Road

May 25, 2012

Very Poor

Poor

Fair

Good

Very Good

Preventive Maintenance

Corrective Maintenance

Heavy Resurfacing

Reconstruction

$50 K

$120 K

$200 K

$360 K

10 Yrs 20 Yrs

Pavement Life Cycle

Page 43: Columbia County Road Department

Haven Acres Road

Very Poor

Poor

Fair

Good

Very Good

Preventive Maintenance

Corrective Maintenance

Heavy Resurfacing

Reconstruction

$50 K

$120 K

$200 K

$360 K

10 Yrs 20 Yrs

Pavement Life Cycle

Page 44: Columbia County Road Department

Conyers Creek Road

Very Poor

Poor

Fair

Good

Very Good

Preventive Maintenance

Corrective Maintenance

Heavy Resurfacing

Reconstruction

$50 K

$120 K

$200 K

$360 K

10 Yrs 20 Yrs

Pavement Life Cycle

Page 45: Columbia County Road Department

Tide Creek Road

Very Poor

Poor

Fair

Good

Very Good

Preventive Maintenance

Corrective Maintenance

Heavy Resurfacing

Reconstruction

$50 K

$120 K

$200 K

$360 K

10 Yrs 20 Yrs

Pavement Life Cycle

Page 46: Columbia County Road Department

Lentz Road

Very Poor

Poor

Fair

Good

Very Good

Preventive Maintenance

Corrective Maintenance

Heavy Resurfacing

Reconstruction

$50 K

$120 K

$200 K

$360 K

10 Yrs 20 Yrs

Pavement Life Cycle

Page 47: Columbia County Road Department

Columbia County Roads Department Needs:

• Pavement Preservation – Scappoose Vernonia Rd, Apiary Rd, Mayger Rd, and most other County Roads.

• Port Westward / Hermo Road access / construction / reconstruction

• Gable Road – Bike / Ped / Enhancement, Overlay / Drainage

• Guardrail Construction

• Safety Improvements

State Highway Concerns:

• Hwy 30 Preservation

• Swedetown Overpass

• Bennett Road and Tide Creek Road Intersections

Page 48: Columbia County Road Department

Apiary Culvert Replacement

Page 49: Columbia County Road Department

Apiary Culvert Replacement

Today

Poor Roads, Poor Funding,

But we will work safe, hard, and effective to perform good work …

Page 50: Columbia County Road Department

… and with a smile!

Page 51: Columbia County Road Department

Have a Great Day!